CN111335941B - 露天矿斜溜槽放矿疏堵和设备转移的一种方法 - Google Patents
露天矿斜溜槽放矿疏堵和设备转移的一种方法 Download PDFInfo
- Publication number
- CN111335941B CN111335941B CN202010141246.6A CN202010141246A CN111335941B CN 111335941 B CN111335941 B CN 111335941B CN 202010141246 A CN202010141246 A CN 202010141246A CN 111335941 B CN111335941 B CN 111335941B
- Authority
- CN
- China
- Prior art keywords
- scraper
- rope
- inclined chute
- slope
- dredging
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F13/00—Transport specially adapted to underground conditions
- E21F13/04—Transport of mined material in gravity inclines; in staple or inclined shafts
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66D—CAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
- B66D1/00—Rope, cable, or chain winding mechanisms; Capstans
- B66D1/28—Other constructional details
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66D—CAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
- B66D1/00—Rope, cable, or chain winding mechanisms; Capstans
- B66D1/60—Rope, cable, or chain winding mechanisms; Capstans adapted for special purposes
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F13/00—Transport specially adapted to underground conditions
- E21F13/006—Equipment transport systems
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66D—CAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
- B66D2700/00—Capstans, winches or hoists
- B66D2700/01—Winches, capstans or pivots
- B66D2700/0125—Motor operated winches
Abstract
露天矿斜溜槽放矿疏堵和设备转移的一种方法。利用坡底、坡顶支架,在斜溜槽上方适宜位置,架设一条索道绳,形成纵贯全局的悬空通道;利用电耙导向平台、移位绞车、定位组件移动电耙耙斗到堵塞位置,即可进行往复耙矿作业并疏通堵塞;中小型采掘、装运机械,可利用移位绞车辅助提升,以溜槽为通道,转移到坡顶生产场地或下放到坡底。
Description
技术领域:
本申请属矿山技术领域。
技术背景:
山坡露天斜溜槽放矿,正在成为许多陡帮开采矿山的明智选择;这种开拓方式是将上部开采矿石用斜溜槽直接溜放到坡底装运场地,能减少运输功,节省汽车数量,节约基建道路开拓费用,最重要的是减少采场外布置运输线路的土地压占和破坏;但是,露天斜溜槽放矿存在一个很重要的安全隐患,那就是溜槽疏堵作业难度大、危险性大,疏堵不及时,会形成堵塞积压矿堆,一旦堵塞体崩塌倾泻,对下部工业场地就会造成极大冲击破坏;本发明旨在采用一种安全、便捷的方法,进行经常性的、及时的疏堵作业,避免酿成安全事故;同时,疏堵系统又能兼用于采场设备转移。
发明内容:
整个疏堵系统的设施布置如图1所示;系统的主体是:利用坡底支架1和坡顶支架10,在斜溜槽上方适宜位置,架设一条索道绳(钢丝绳)4,形成纵贯全局的悬空通道;图1中A表示电耙导向平台,其作用是将电耙绞车引到侧翼安全位置,以避开斜溜槽放矿的正面的滚石冲击破坏;图1 中B表示电耙定位组件,其由索道滑轮17、配重物18和电耙滑轮19三部分组成;移位绞车11通过转向滑轮9和移位绳8拉动定位组件沿索道绳移动就位,转向滑轮9固定在索道绳适宜部位,定位组件下行则靠重力作用;电耙耙斗20的尾绳5(空载绳)绕过电耙滑轮19悬吊耙斗,并跟随定位组件移动;当定位组件移动到处理疏堵位置时,移位绞车11锁死,电耙滑轮 19实现定位,电耙即可开始往复耙矿作业,疏通堵塞。
图2、图3中,电耙导向平台由电耙导向轮13、后托轮12、前托轮 14和安装支架组成;两个导向轮13分别用于电耙的尾绳5(空载绳)和首绳6(重载绳)的平面导向,将电耙绞车引到侧翼安全位置;四个前托轮 14用于电耙作业端尾绳和首绳的限位与导向,因为作业端的尾绳和首绳经常需要上行绕道高位滑轮,故设置上下双托轮;后托轮12用于电耙牵引端尾绳和首绳的限位,只设置下托轮即可;两个导向轮13的平面位置是可调的,应使牵引端尾绳和首绳的水平间距和上下高差适应电耙的重载卷筒和空载卷筒,同样要使作业端尾绳和首绳的相互位置适应定位组件;图3中电耙绞车16要离开导向轮13适宜距离,以保障安全和适宜绳偏角。
图4中,电耙滑轮(电耙原配滑轮)19吊装在配重物18上;配重物18的质量要适宜定位组件的上下移动和电耙作业;索道滑轮17的绳道要设置防滑脱机制。
可以用振荡器、冲击器、转轮之类机械代替电耙疏堵,此时,只需将电耙耙斗更换即可;也可以完全取消电耙,将自带电源和升降装置的振荡器之类机械直接悬吊在配重物18下面,遥控升降疏堵。
这套系统的斜溜槽要修建成适宜宽度,底板要平整光滑;中小型采掘、装运机械,可利用移位绞车辅助提升,以斜溜槽作为通道,转移到坡顶生产场地或者下放到坡底;设备转移作业前,应先将斜溜槽放空,再用不带耙齿的刮板类清障器具代替电耙耙斗,清理斜溜槽底板,去除浮渣,然后再牵引转移设备;大型机械需拆解吊运或牵引转运。
附图说明:
图1是系统整体布置的侧面示意图,图中标注符号的意义是:
1——坡底支架, 2——防护坝, 3——矿堆,
4——索道绳, 5——电耙尾绳, 6——电耙首绳,
7——斜溜槽, 8——移位绳, 9——转向滑轮,
10——坡顶支架, 11——移位绞车。 A、B——局部明细图标注。
图2是图1中A标示的局部明细图的放大图,图中标注符号的意义是:
5——电耙尾绳, 6——电耙首绳, 12——后托轮,
13——导向轮, 14——前托轮, 15——防护网,
C——俯视标注。
图3是图2中C标示的俯视图,图中标注符号的意义是:
12——后托轮, 13——导向轮, 14——前托轮,
16——电耙绞车。
图4是图1中B标示的局部明细图的放大图,图中标注符号的意义是:
4——索道绳, 5——电耙尾绳, 6——电耙首绳,
8——移位绳, 17——索道滑轮, 18——配重物,
19——电耙滑轮, 20——电耙耙斗。
具体实施方法:
架空索道绳的规格、涨紧度和悬空高度要适宜;斜溜槽的坡度要适宜,本例推荐斜溜槽坡度42°±3°;空闲工况时,电耙耙斗宜吊起悬挂在斜溜槽中间位置或者易堵塞位置,备用状态不得妨碍溜槽放矿;电耙耙斗移动时,宜吊起悬空,利用电耙尾绳和首绳的控制收放使耙斗悬空移动,以不防碍放矿并保护耙斗免遭矿渣埋没;普通电耙绞车卷筒的容绳量可能不满足斜溜槽长度,应改装卷筒,或者用其他适宜的双筒绞车(卷扬)代替电耙绞车;普通电耙采场作业的有效长度一般不大于60米,但疏堵作业是分段进行,每个部位疏堵不需要耙动这么长距离,因此,溜槽长度大小一般不会防碍疏堵作业;如果斜溜槽长度过大,而又经常需要多部位疏堵时,可以设置两级或者三级疏堵;方法是在斜溜槽上方再架设次级导向平台,导向平台侧翼安全位置增设次级电耙绞车、次级移位绞车,在索道绳上增设次级转向滑轮和次级定位组件;这样就形成了相互独立的多级疏堵系统,索道绳仍可共用;次级疏堵系统的重点注意事项是:导向平台必须高度适宜,不得防碍斜溜槽放矿和设备转移通道。
Claims (1)
1.一种露天矿斜溜槽放矿疏堵和设备转移的方法,其主要技术特征是:斜溜槽要修建成适宜宽度,底板要平整光滑,斜溜槽坡度42°±3°;利用坡底支架(1)和坡顶支架(10),在斜溜槽上方适宜位置,架设一条索道绳(4),形成纵贯全局的悬空通道,架空索道绳的规格、涨紧度和悬空高度要适宜;移位绞车(11)通过转向滑轮(9)和移位绳(8)拉动定位组件沿索道绳移动就位;电耙耙斗(20)的尾绳(5)绕过电耙滑轮(19)悬吊耙斗,并跟随定位组件移动;当定位组件移动到处理疏堵位置时,移位绞车(11)锁死,电耙滑轮(19)实现定位,电耙即可开始往复耙矿作业,疏通堵塞;空闲工况时,电耙耙斗吊起悬挂在斜溜槽中间位置或者易堵塞位置,备用状态不得妨碍溜槽放矿;电耙耙斗移动时,吊起悬空,利用电耙尾绳和首绳的控制收放使耙斗悬空移动,以不防碍放矿并保护耙斗免遭矿渣埋没;利用电耙导向平台将电耙绞车引到侧翼安全和适宜作业的位置;如果斜溜槽长度过大,而又经常需要多部位疏堵时,设置两级或者三级疏堵系统;中小型采掘、装运机械,利用移位绞车辅助提升,以溜槽为通道,转移到坡顶生产场地或下放到坡底。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010141246.6A CN111335941B (zh) | 2020-03-04 | 2020-03-04 | 露天矿斜溜槽放矿疏堵和设备转移的一种方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010141246.6A CN111335941B (zh) | 2020-03-04 | 2020-03-04 | 露天矿斜溜槽放矿疏堵和设备转移的一种方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111335941A CN111335941A (zh) | 2020-06-26 |
CN111335941B true CN111335941B (zh) | 2022-06-17 |
Family
ID=71179910
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010141246.6A Active CN111335941B (zh) | 2020-03-04 | 2020-03-04 | 露天矿斜溜槽放矿疏堵和设备转移的一种方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111335941B (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112374181B (zh) * | 2020-12-09 | 2022-03-29 | 河南跃薪时代新能源科技有限公司 | 一种露天矿山开采运输装置 |
CN112849790B (zh) * | 2020-12-31 | 2022-08-02 | 四川发展天瑞矿业有限公司 | 矿仓专用机械清仓装置及清仓方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1260525A1 (ru) * | 1984-11-27 | 1986-09-30 | Всесоюзный Ордена Ленина Проектно-Изыскательский И Научно-Исследовательский Институт "Гидропроект" Им.С.Я.Жука | Породоспуск с гидравлической разгрузкой |
RU2215147C2 (ru) * | 2001-10-22 | 2003-10-27 | Южно-Российский государственный технический университет | Способ отработки наклонных рудных залежей |
CN104085662A (zh) * | 2014-07-08 | 2014-10-08 | 李劼 | 一种胶带输送机转载点的防堵溜槽装置 |
CN107503751A (zh) * | 2017-08-17 | 2017-12-22 | 广西大学 | 一种露天采石场放矿用溜槽及露天采石场开采方法 |
CN208882670U (zh) * | 2018-09-27 | 2019-05-21 | 中国矿业大学 | 露天煤矿移动式端帮运输溜槽 |
CN110409529A (zh) * | 2019-07-08 | 2019-11-05 | 天津矿山工程有限公司 | 一种溜槽及边坡清表装置及其使用方法 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104196536B (zh) * | 2014-08-12 | 2016-03-30 | 广东安元矿业勘察设计有限公司 | 倾斜矿体留矿法开采的集中出矿方法 |
-
2020
- 2020-03-04 CN CN202010141246.6A patent/CN111335941B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1260525A1 (ru) * | 1984-11-27 | 1986-09-30 | Всесоюзный Ордена Ленина Проектно-Изыскательский И Научно-Исследовательский Институт "Гидропроект" Им.С.Я.Жука | Породоспуск с гидравлической разгрузкой |
RU2215147C2 (ru) * | 2001-10-22 | 2003-10-27 | Южно-Российский государственный технический университет | Способ отработки наклонных рудных залежей |
CN104085662A (zh) * | 2014-07-08 | 2014-10-08 | 李劼 | 一种胶带输送机转载点的防堵溜槽装置 |
CN107503751A (zh) * | 2017-08-17 | 2017-12-22 | 广西大学 | 一种露天采石场放矿用溜槽及露天采石场开采方法 |
CN208882670U (zh) * | 2018-09-27 | 2019-05-21 | 中国矿业大学 | 露天煤矿移动式端帮运输溜槽 |
CN110409529A (zh) * | 2019-07-08 | 2019-11-05 | 天津矿山工程有限公司 | 一种溜槽及边坡清表装置及其使用方法 |
Also Published As
Publication number | Publication date |
---|---|
CN111335941A (zh) | 2020-06-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
RU2396394C1 (ru) | Вскрышной агрегат | |
CN111335941B (zh) | 露天矿斜溜槽放矿疏堵和设备转移的一种方法 | |
RU2456454C1 (ru) | Экскавационно-транспортирующий комплекс | |
CN106638272B (zh) | 一种用于跨胶带运输机的自移式行车桥 | |
CN107237649A (zh) | 小断面长陡坡斜井运输系统及施工方法 | |
CN105736045A (zh) | 一种控制采空区底板突水的袋式充填系统及其充填方法 | |
CN106149782B (zh) | 一种大跨度移动组合式索道悬挂铲挖抓吊牵引搬运系统 | |
CN202703579U (zh) | 大坡度斜井有轨运输施工装置 | |
CN110106867A (zh) | 铁路车站线间人工挖孔桩施工方法 | |
US10647521B2 (en) | Transfer bridge for coarse bulk materials | |
CN107559027B (zh) | 一种轨道式装车机 | |
CN217001927U (zh) | 一种用于煤矿大倾角综采工作面的防滚矸装置 | |
WO2019060948A1 (en) | ROPE CONVEYOR SYSTEM | |
AU627737B2 (en) | Working equipment for earth working, in particular a shovel loader, suspended from a vehicle | |
CN113137234A (zh) | 露天煤矿坑底自移式内排土场提升运煤系统 | |
WO2006024097A1 (en) | Haulage system for pit mining | |
RU2039280C1 (ru) | Выемочно-погрузочный комплекс для открытых горных работ | |
CN220334633U (zh) | 一种框架式人工挖孔桩提升架 | |
CN218844310U (zh) | 一种煤矿用掘锚一体机 | |
CN216077209U (zh) | 小断面长缓斜洞双向开挖多台卷扬机分级接力运输装置 | |
RU2815246C1 (ru) | Контурное горное сооружение для выемки и транспортировки подготовленного рудного массива со дна карьера | |
CN218290324U (zh) | 一种综采工作面巷道超前支架搬运装置 | |
CN214143720U (zh) | 一种组合式整平装置 | |
CN210419037U (zh) | 挡土墙片石运输装置 | |
CN210238519U (zh) | 一种水下抛石夯平装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |