CN111140248A - Bias tunnel structure applying prestress to pilot tunnel and construction method thereof - Google Patents

Bias tunnel structure applying prestress to pilot tunnel and construction method thereof Download PDF

Info

Publication number
CN111140248A
CN111140248A CN202010057586.0A CN202010057586A CN111140248A CN 111140248 A CN111140248 A CN 111140248A CN 202010057586 A CN202010057586 A CN 202010057586A CN 111140248 A CN111140248 A CN 111140248A
Authority
CN
China
Prior art keywords
tunnel
prestressed
pilot tunnel
anchor cable
pilot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010057586.0A
Other languages
Chinese (zh)
Other versions
CN111140248B (en
Inventor
杨建民
舒东利
王磊
朱麟晨
张涵
何聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN202010057586.0A priority Critical patent/CN111140248B/en
Publication of CN111140248A publication Critical patent/CN111140248A/en
Application granted granted Critical
Publication of CN111140248B publication Critical patent/CN111140248B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Inorganic Chemistry (AREA)
  • Chemical & Material Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a bias tunnel structure applying prestress to a pilot tunnel and a construction method thereof, wherein the bias tunnel structure comprises a tunnel and a frame beam fixed on the surface of a slope, a prestressed anchor cable is connected between the pilot tunnel and the frame beam of the tunnel, and the construction method comprises the following steps: drilling a hole from the ground surface of the bias low-side slope to the pilot tunnel to be excavated; constructing a frame beam on the surface of the side slope, excavating a pilot tunnel, placing a prestressed anchor cable into a drill hole, anchoring one end of the prestressed anchor cable on the frame beam, applying prestress to the prestressed anchor cable, and then fixing the other end of the prestressed anchor cable on the hole wall of the pilot tunnel to form active reinforcement for the biased low-side slope. The invention applies the prestressed anchor cable between the pilot tunnel and the side slope earth surface, can form active reinforcement to the mountain side slope, and carries out tunnel expanding excavation construction after the reinforcement is finished, so as to ensure the excavation safety and the side slope stability of the whole large-section tunnel.

Description

Bias tunnel structure applying prestress to pilot tunnel and construction method thereof
Technical Field
The invention relates to the technical field of tunnel engineering, in particular to a bias tunnel structure applying prestress to a pilot tunnel and a construction method thereof.
Background
When the tunnel enters a hole in a bias terrain, diseases such as slope slippage collapse, sinking crack deformation in the hole and the like are easy to occur, and particularly, the stability of a mountain is more difficult to ensure for a large-section tunnel, so that great difficulty is brought to engineering construction. The existing commonly used bias tunnel reinforcement measures mainly comprise surface grouting, anchoring piles, surface mortar anchor rods, back pressure low mountain side surface and the like, and prestress anchor cables can be applied from the surface, but in the traditional technology, anchor cables are applied outside tunnel excavation contour lines, surface reinforcement is not directly connected with in-hole construction, and a technical scheme for reinforcing the surface and the in-hole together is not provided, so that the traditional reinforcement measures have the defects of large engineering quantity and unobvious reinforcement effect.
Disclosure of Invention
The invention aims to: aiming at the problems in the prior art, the bias tunnel structure applying prestress to the pilot tunnel and the construction method thereof are provided.
In order to achieve the purpose, the invention adopts the technical scheme that:
a bias tunnel structure applying prestress to a pilot tunnel comprises a tunnel and a frame beam fixed on the surface of a slope, wherein a prestressed anchor cable is connected between the pilot tunnel of the tunnel and the frame beam.
According to the bias tunnel structure with the pilot tunnel applying prestress, the prestressed anchor cables are connected between the pilot tunnel and the surface of the slope, so that active reinforcement can be formed on the mountain slope, and tunnel expanding excavation construction is performed after reinforcement is completed, so that the excavation safety and the slope stability of the whole large-section tunnel are guaranteed. And the frame beam is firmly fixed on the surface of the side slope by applying prestress, so that the problem of infirm surface structure in the past is avoided, and the effective reinforcement can be formed on the surface of the side slope.
As a preferable scheme of the invention, the prestress of the prestressed anchor cable is greater than or equal to 5 tons.
As a preferable aspect of the present invention, the prestressed anchor cable includes a steel pipe and a tendon disposed in the steel pipe, and the steel pipe is filled with cement slurry.
As a preferable mode of the present invention, one end of the prestressed anchor cable is anchored to the frame beam, and the other end thereof is fixed to the wall of the pilot tunnel.
As the preferred scheme of the invention, the frame beam is a reinforced concrete frame structure.
As a preferable aspect of the present invention, the frame beam is provided at a bias low side of the slope.
The invention also discloses a construction method of the bias tunnel structure applying prestress to the pilot tunnel, which comprises the following steps:
the method comprises the following steps: drilling a hole from the ground surface of the bias low-side slope to the pilot tunnel to be excavated;
step two: constructing a frame beam on the surface of the side slope, excavating the pilot tunnel, placing a prestressed anchor cable into the drilling hole, anchoring one end of the prestressed anchor cable on the frame beam, applying prestress to the prestressed anchor cable, and then fixing the other end of the prestressed anchor cable on the hole wall of the pilot tunnel to form active reinforcement for the biased low side slope.
The method is characterized in that a prestressed anchor cable is applied between a pilot tunnel and the surface of a side slope, active reinforcement can be formed on the side slope of the mountain, and tunnel expanding excavation construction is performed after reinforcement is completed, so that the excavation safety and the side slope stability of the whole large-section tunnel are ensured; the frame beam is firmly fixed on the surface of the side slope by applying prestress, so that the problem of infirm surface structure in the past is avoided, and effective reinforcement can be formed on the surface of the side slope.
As a preferred embodiment of the present invention, the second step comprises:
s21: drilling a steel perforated pipe into the borehole to the profile of the pilot tunnel, and constructing a frame beam on the surface of the side slope;
s22: excavating the pilot tunnel, after the steel flower pipes are exposed, putting a reinforcing bar bundle into the steel flower pipes and extending out of the surface of the side slope;
s23: and anchoring and connecting one end of the steel bar bundle with the frame beam, applying prestress to the steel bar bundle, and injecting slurry into the steel perforated pipe for consolidation.
As a preferable aspect of the present invention, the prestress is greater than or equal to 5 tons.
In summary, due to the adoption of the technical scheme, the invention has the beneficial effects that:
1. the invention applies the prestressed anchor cable between the pilot tunnel and the side slope earth surface, can form active reinforcement to the mountain side slope, and carries out tunnel expanding excavation construction after the reinforcement is finished, so as to ensure the excavation safety and the side slope stability of the whole large-section tunnel.
2. The frame beam is firmly fixed on the surface of the side slope by applying prestress, so that the problem of infirm structure of the surface in the past is avoided, and the effective reinforcement can be formed on the surface of the side slope.
Drawings
FIG. 1 is a schematic structural diagram of a biased tunnel structure with a pre-stressed leading via according to the present invention.
Icon: 1-slope earth surface, 2-frame beam, 3-prestressed anchor cable, 4-tunnel and 41-pilot tunnel.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings.
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Example 1
As shown in fig. 1, a biased tunnel structure with a prestressed force applied to a pilot tunnel comprises a tunnel 4 and a reinforced concrete frame beam 2 fixed on the surface 1 of a slope, wherein the frame beam 2 is arranged at the biased low side of the slope, a prestressed anchor cable 3 is connected between a pilot tunnel 41 of the tunnel 4 and the frame beam 2, one end of the prestressed anchor cable 3 is anchored on the frame beam 2, the other end of the prestressed anchor cable is fixed on the wall of the pilot tunnel 41, and the prestressed anchor cable 3 has a prestressed force greater than or equal to 5 tons. The prestressed anchor cable 3 comprises a steel pipe and a steel bar bundle positioned in the steel pipe, and cement paste is filled in the steel pipe.
Example 2
As shown in fig. 1, a construction method of a biased tunnel structure in which a pilot tunnel applies prestress includes the following steps:
the method comprises the following steps: drilling a hole from the ground surface 1 of the bias low-side slope to a pilot tunnel 41 to be excavated;
step two: drilling a steel perforated pipe into the borehole until the profile of the pilot tunnel 41 is formed, and constructing a reinforced concrete frame beam 2 on the side slope ground surface 1;
step three: excavating the pilot tunnel 41, after the steel perforated pipes are exposed, putting a steel bar bundle into the steel perforated pipes and extending out of the surface 1 of the side slope;
step four: and (3) firmly anchoring and fixing one end of the reinforcing bar bundle and the frame beam 2 by using high-strength reinforced concrete, applying prestress of more than or equal to 5 tons to the reinforcing bar bundle, and then injecting slurry into the steel perforated pipe for consolidation.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (9)

1. The bias tunnel structure applying prestress to the pilot tunnel is characterized by comprising a tunnel (4) and a frame beam (2) fixed on a slope ground surface (1), wherein a prestress anchor cable (3) is connected between a pilot tunnel (41) of the tunnel (4) and the frame beam (2).
2. A biased tunnel construction prestressed by means of a pilot tunnel according to claim 1, characterized in that the prestress of said prestressed anchorage cables (3) is greater than or equal to 5 tons.
3. The biased tunnel structure prestressed by means of pilot tunnel according to claim 1, wherein said prestressed anchorage cable (3) comprises a steel pipe and a tendon placed in said steel pipe, and said steel pipe is filled with cement slurry.
4. A biased tunnel construction prestressed by a pilot tunnel according to claim 1, characterized in that said prestressed anchorage cables (3) are anchored at one end to said frame girders (2) and at the other end to the wall of said pilot tunnel (41).
5. A biased tunnel construction with prestressed leading-hole according to any one of claims 1-4, characterized in that said frame beams (2) are reinforced concrete frame structures.
6. A biased tunnel construction with pre-stressing leading tunnels according to any of claims 1-4, characterized in that the frame beams (2) are arranged on the biased low side of the slope.
7. A method for constructing a biased tunnel structure prestressed by a pilot tunnel according to any one of claims 1 to 6, comprising the steps of:
the method comprises the following steps: drilling a hole from the bias low side slope earth surface (1) into a pilot tunnel (41) to be excavated;
step two: constructing a frame beam (2) on the side slope earth surface (1), excavating the pilot tunnel (41), placing a prestressed anchor cable (3) into the drilled hole, anchoring one end of the prestressed anchor cable (3) on the frame beam (2), applying prestress on the prestressed anchor cable (3), and then fixedly connecting the other end of the prestressed anchor cable (3) on the hole wall of the pilot tunnel (41).
8. The method of constructing a biased tunnel structure with a prestressed structure according to claim 7, wherein said second step comprises:
s21: drilling a steel perforated pipe into the borehole until the profile of the pilot tunnel (41) is formed, and constructing a frame beam (2) on the side slope ground surface (1);
s22: excavating the pilot tunnel (41), after the steel flower pipes are exposed, putting reinforcing steel bundles into the steel flower pipes and extending out of the surface (1) of the side slope;
s23: and (3) anchoring and connecting one end of the steel bar bundle with the frame beam (2), applying prestress to the steel bar bundle, and injecting slurry into the steel perforated pipe for consolidation.
9. The method of constructing a biased tunnel structure in which a pilot tunnel is prestressed according to claim 7 or 8, wherein the prestress is 5 tons or more.
CN202010057586.0A 2020-01-17 2020-01-17 Bias tunnel structure with prestress applied to pilot tunnel and construction method of bias tunnel structure Active CN111140248B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010057586.0A CN111140248B (en) 2020-01-17 2020-01-17 Bias tunnel structure with prestress applied to pilot tunnel and construction method of bias tunnel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010057586.0A CN111140248B (en) 2020-01-17 2020-01-17 Bias tunnel structure with prestress applied to pilot tunnel and construction method of bias tunnel structure

Publications (2)

Publication Number Publication Date
CN111140248A true CN111140248A (en) 2020-05-12
CN111140248B CN111140248B (en) 2024-05-07

Family

ID=70525980

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010057586.0A Active CN111140248B (en) 2020-01-17 2020-01-17 Bias tunnel structure with prestress applied to pilot tunnel and construction method of bias tunnel structure

Country Status (1)

Country Link
CN (1) CN111140248B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112065469A (en) * 2020-09-23 2020-12-11 中铁工程装备集团有限公司 Underground large-span space structure and construction method thereof
CN113605934A (en) * 2021-07-28 2021-11-05 中铁十八局集团有限公司 Reinforced structure for preventing tunnel uphill from slipping down and construction method thereof
CN114991807A (en) * 2022-05-16 2022-09-02 中国矿业大学(北京) Tunnel entrance and exit slope coupling double-compensation construction method

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2708610A1 (en) * 2002-02-25 2003-08-25 United Lock-Block Ltd. Arched structures and method for the construction of same
CN102155232A (en) * 2011-04-02 2011-08-17 中铁二院工程集团有限责任公司 Construction method of large-span asymmetrical double-arch railway tunnel under terrain bias pressure condition
CN104389628A (en) * 2014-11-21 2015-03-04 山西省交通科学研究院 Landslide section tunnel reinforcing device and reinforcing construction method
CN104775428A (en) * 2015-04-23 2015-07-15 万军利 Compound-type prestressed anchor cable structure and construction method thereof
CN106996299A (en) * 2017-05-25 2017-08-01 中铁局集团厦门建设工程有限公司 Control the steel floral tube pile retaining structure and its construction method of tunnel biased deformation
CN107143358A (en) * 2017-06-28 2017-09-08 山东省地质矿产勘查开发局八0水文地质工程地质大队(山东省地矿工程勘察院) Opposite-pulling anchor cable structure for controlling tunnel bias deformation and construction method thereof
CN109440787A (en) * 2018-11-12 2019-03-08 中国电建集团华东勘测设计研究院有限公司 The structure and method of engineering slope and underground chamber excavation and support simultaneously in a kind of Toppling Deformation rock mass
CN110258536A (en) * 2019-06-19 2019-09-20 山东省地质矿产勘查开发局八0一水文地质工程地质大队(山东省地矿工程勘察院) Opposite-pulling anchor cable structure for reducing bias load and construction method
CN110374633A (en) * 2019-07-19 2019-10-25 中铁隧道集团二处有限公司 The Portal Section Construction method of Tunnel Passing loose media
CN110453693A (en) * 2019-03-02 2019-11-15 华北水利水电大学 It is a kind of using adit formula to the treatment schemes of anchor
CN211598676U (en) * 2020-01-17 2020-09-29 中铁二院工程集团有限责任公司 Bias tunnel structure with pilot tunnel applying prestress

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2708610A1 (en) * 2002-02-25 2003-08-25 United Lock-Block Ltd. Arched structures and method for the construction of same
CN102155232A (en) * 2011-04-02 2011-08-17 中铁二院工程集团有限责任公司 Construction method of large-span asymmetrical double-arch railway tunnel under terrain bias pressure condition
CN104389628A (en) * 2014-11-21 2015-03-04 山西省交通科学研究院 Landslide section tunnel reinforcing device and reinforcing construction method
CN104775428A (en) * 2015-04-23 2015-07-15 万军利 Compound-type prestressed anchor cable structure and construction method thereof
CN106996299A (en) * 2017-05-25 2017-08-01 中铁局集团厦门建设工程有限公司 Control the steel floral tube pile retaining structure and its construction method of tunnel biased deformation
CN107143358A (en) * 2017-06-28 2017-09-08 山东省地质矿产勘查开发局八0水文地质工程地质大队(山东省地矿工程勘察院) Opposite-pulling anchor cable structure for controlling tunnel bias deformation and construction method thereof
CN109440787A (en) * 2018-11-12 2019-03-08 中国电建集团华东勘测设计研究院有限公司 The structure and method of engineering slope and underground chamber excavation and support simultaneously in a kind of Toppling Deformation rock mass
CN110453693A (en) * 2019-03-02 2019-11-15 华北水利水电大学 It is a kind of using adit formula to the treatment schemes of anchor
CN110258536A (en) * 2019-06-19 2019-09-20 山东省地质矿产勘查开发局八0一水文地质工程地质大队(山东省地矿工程勘察院) Opposite-pulling anchor cable structure for reducing bias load and construction method
CN110374633A (en) * 2019-07-19 2019-10-25 中铁隧道集团二处有限公司 The Portal Section Construction method of Tunnel Passing loose media
CN211598676U (en) * 2020-01-17 2020-09-29 中铁二院工程集团有限责任公司 Bias tunnel structure with pilot tunnel applying prestress

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周围;: "软弱围岩条件下的浅埋隧道施工探讨", 交通世界, no. 07, 9 April 2018 (2018-04-09) *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112065469A (en) * 2020-09-23 2020-12-11 中铁工程装备集团有限公司 Underground large-span space structure and construction method thereof
CN112065469B (en) * 2020-09-23 2022-09-16 中铁工程装备集团有限公司 Underground large-span space structure and construction method thereof
CN113605934A (en) * 2021-07-28 2021-11-05 中铁十八局集团有限公司 Reinforced structure for preventing tunnel uphill from slipping down and construction method thereof
CN114991807A (en) * 2022-05-16 2022-09-02 中国矿业大学(北京) Tunnel entrance and exit slope coupling double-compensation construction method
CN114991807B (en) * 2022-05-16 2023-08-18 中国矿业大学(北京) Tunnel entrance and exit side slope coupling double-compensation construction method

Also Published As

Publication number Publication date
CN111140248B (en) 2024-05-07

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN111140248A (en) Bias tunnel structure applying prestress to pilot tunnel and construction method thereof
CN112196582B (en) Method for controlling severe deformation of strong-earthquake deep-buried soft rock stratum tunnel
CN108412519A (en) The slight large deformation single-track tunnel suspension device of highlands soft rock and construction method
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN109930609A (en) A kind of campshed composite supporting construction and its construction method for upper-soft lower-hard ground
EA031926B1 (en) Method for forming a pillar part and reinforcing adjacently constructed parallel tunnels with reinforcing rods
CN106050240A (en) Stability control method for mountainous area weak surrounding rock small-distance tunnel mid-adjacent rock
CN113309132A (en) Construction method based on steel trestle bridge anchoring pile
CN211598676U (en) Bias tunnel structure with pilot tunnel applying prestress
CN110820762A (en) Construction method of stiff-core curtain pile and retaining wall pile anchor combined supporting structure
CN110210069A (en) Tunnel advanced support System Design method and tunnel advanced support design method
CN109898521A (en) A kind of anchored pile supporting and construction method for foundation pit external corner
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
CN206599785U (en) A kind of campshed anchor draws cement earth pile diaphragm wall supporting construction
CN108914945A (en) A kind of deep basal pit pile for prestressed pipe, prestress anchorage cable combined supporting construction method
CN114483081A (en) Construction method of deflection-preventing structure of curved middle wall of multi-arch tunnel under terrain bias pressure
CN104863613B (en) Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method
CN101368388B (en) Anchor pipe skeleton support method
CN105840209B (en) Construction method for controlling deformation of anchor pile in tunnel body section
CN105370306B (en) The massif tunnel excavation construction method of vertical pre-reinforcement processing
CN206942780U (en) A kind of tunnel cross mouth advance support structure
CN214497537U (en) Double-row pile supporting system
CN211395698U (en) Stiff core curtain pile and dado stake anchor combined supporting construction
CN114135315A (en) Advanced stress release construction method for severe large-deformation tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant