CN111127244A - Three-dimensional intelligent auxiliary evaluation system and method for power transmission and transformation project - Google Patents
Three-dimensional intelligent auxiliary evaluation system and method for power transmission and transformation project Download PDFInfo
- Publication number
- CN111127244A CN111127244A CN201811295811.3A CN201811295811A CN111127244A CN 111127244 A CN111127244 A CN 111127244A CN 201811295811 A CN201811295811 A CN 201811295811A CN 111127244 A CN111127244 A CN 111127244A
- Authority
- CN
- China
- Prior art keywords
- review
- dimensional
- design
- model
- evaluation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000009466 transformation Effects 0.000 title claims abstract description 31
- 230000005540 biological transmission Effects 0.000 title claims abstract description 22
- 238000000034 method Methods 0.000 title claims abstract description 13
- 238000011156 evaluation Methods 0.000 title claims description 52
- 238000012552 review Methods 0.000 claims abstract description 126
- 238000013461 design Methods 0.000 claims abstract description 76
- 238000013480 data collection Methods 0.000 claims abstract description 4
- 238000012795 verification Methods 0.000 claims description 26
- 238000007405 data analysis Methods 0.000 claims description 6
- 238000005259 measurement Methods 0.000 claims description 4
- 238000009877 rendering Methods 0.000 claims description 4
- 230000000007 visual effect Effects 0.000 claims description 3
- 238000007726 management method Methods 0.000 abstract description 14
- 238000010276 construction Methods 0.000 abstract description 4
- 238000013523 data management Methods 0.000 abstract description 3
- 238000011161 development Methods 0.000 abstract description 3
- 238000012550 audit Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012854 evaluation process Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0639—Performance analysis of employees; Performance analysis of enterprise or organisation operations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
- G06T17/05—Geographic models
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T19/00—Manipulating 3D models or images for computer graphics
- G06T19/003—Navigation within 3D models or images
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T19/00—Manipulating 3D models or images for computer graphics
- G06T19/20—Editing of 3D images, e.g. changing shapes or colours, aligning objects or positioning parts
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T2210/00—Indexing scheme for image generation or computer graphics
- G06T2210/04—Architectural design, interior design
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T2210/00—Indexing scheme for image generation or computer graphics
- G06T2210/62—Semi-transparency
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T2219/00—Indexing scheme for manipulating 3D models or images for computer graphics
- G06T2219/20—Indexing scheme for editing of 3D models
- G06T2219/2016—Rotation, translation, scaling
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Physics & Mathematics (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Software Systems (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Computer Graphics (AREA)
- Educational Administration (AREA)
- Development Economics (AREA)
- Game Theory and Decision Science (AREA)
- Remote Sensing (AREA)
- Geometry (AREA)
- Health & Medical Sciences (AREA)
- Computer Hardware Design (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Radar, Positioning & Navigation (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a three-dimensional intelligent auxiliary review system and a method for a power transmission and transformation project, wherein the system comprises the following parts: the system comprises a two-dimensional review system for design data reporting and closing-up review and a three-dimensional review system for three-dimensional process review, wherein the two-dimensional review system uses a Webster platform and comprises management modules for review plan management, review data collection, pre-review, formal review, closing-up review and the like, and the three-dimensional review system is composed of a three-dimensional review module and a plurality of review clients. The system integrally improves the engineering data management capacity, creates a power transmission and transformation engineering three-dimensional design review authoritative management mode, and provides strong data support for the orderly development of engineering construction.
Description
Technical Field
The invention belongs to the field of power systems, and mainly relates to a three-dimensional intelligent auxiliary evaluation system and method for power transmission and transformation engineering.
Background
In 7 months in 2018, the national grid company sends the opinion about the comprehensive application of the three-dimensional design of the power transmission and transformation project and the construction of the project data center of the national grid company, the goals of the three-dimensional design and the digital construction of the project are definitely provided in the opinion, the national grid company newly builds the three-dimensional design of the power transmission and transformation project of 35KV and above in the next half year in 2018, and before 2020, the three-dimensional design, the three-dimensional review and the three-dimensional transfer are realized on the whole. Under the background that the national network strongly pushes the three-dimensional design, the existing engineering design review auxiliary business management system is a two-dimensional system, and the utilization rate is low because the existing engineering design review auxiliary business management system cannot visually review the three-dimensional design. It is necessary to develop a three-dimensional review system suitable for the current transmission and transformation project.
Disclosure of Invention
In order to solve the above problems, the present invention aims to provide a three-dimensional intelligent auxiliary review system and method for power transmission and transformation engineering, which implement three-dimensional data management and application, such as three-dimensional design model parameter data intelligent retrieval and query, three-dimensional design result display and model verification, safe distance measurement and verification, etc., according to the present three-dimensional display technology.
In order to achieve the purpose, the invention is realized by the following technical scheme:
the utility model provides a supplementary system of reviewing of three-dimensional intelligence of power transmission and transformation engineering which characterized in that, includes following part: the system comprises a two-dimensional review system for design data reporting and closing-up review and a three-dimensional review system for three-dimensional process review, wherein the two-dimensional review system uses a Webster platform and comprises management modules for review plan management, review data collection, pre-review, formal review, closing-up review and the like, and the three-dimensional review system is composed of a three-dimensional review module and a plurality of review clients.
Furthermore, the three-dimensional review module is provided with a three-dimensional model web end and comprises a three-dimensional design model viewing module, so that the functions of visual display, viewing of a spatial arrangement scheme, flight viewing, roaming, model zooming, rendering, model rotation, perspective viewing, full-screen display and holographic space retrieval of an engineering three-dimensional design model component can be realized, and the basic operation viewing of a review expert on the model is assisted.
Furthermore, the evaluation client comprises a data analysis module for a three-dimensional GIM result model and an IFC civil engineering model of the power transformation project, a preview module for online preview of the models and a verification module for automatic verification of the three-dimensional design safety clearance of the power transformation project, and a plurality of evaluation clients are connected together by using a local area network built by a three-dimensional mobile evaluation server, a power modem and router hardware equipment.
Further, the data analysis module analyzes and verifies the three-dimensional design results submitted by the design units, including the GIM file and the IFC format file, establishes a set of relatively complete verification models of the three-dimensional design results, such as data formats, coordinate systems, measurement units, modeling requirements, hierarchy division, color matching principles, codes, three-dimensional design models, attribute definitions and the like, and automatically generates a verification report. And an accurate and complete data source is provided for realizing the functions of three-dimensional evaluation intelligent auxiliary evaluation and the like.
Furthermore, the preview module displays and browses a spatial arrangement scheme, flies and browses, roams, zooms, renders, rotates the model, looks through, displays in a full screen mode, and searches the holographic space of the engineering three-dimensional design model component in a three-dimensional model mode at the client.
Furthermore, the verification module utilizes a three-dimensional preliminary design result verification model to form a parameterized review index, realizes the automatic verification of the safety clear distance of the power transformation project and forms a corresponding verification report.
The invention also discloses a three-dimensional intelligent auxiliary review method for the power transmission and transformation project, which is characterized by comprising the following specific steps of:
firstly, according to a review plan issued by a system, a design unit uploads three-dimensional design data, and a management unit reports the three-dimensional design data to the system after reviewing; the administrator distributes the project and appoints the review expert in the system; and the central leader and the review experts view the model and related design data in the system.
Secondly, the manager makes and issues a formal review meeting notice through the engineering design review platform; before the formal review meeting, the review responsible person synchronously downloads all three-dimensional design data of the items to be reviewed by using the three-dimensional mobile review server in the intranet environment.
And thirdly, under the environment of the external network, a temporary local area network is built by utilizing hardware equipment such as a three-dimensional mobile review server, a power modem, a router and the like.
And fourthly, the evaluation expert accesses the three-dimensional mobile evaluation server by using the three-dimensional evaluation client installed on the local server to carry out on-site three-dimensional evaluation.
Has the advantages that:
the three-dimensional intelligent auxiliary evaluation system takes a power transmission and transformation project design evaluation management system and 8 three-dimensional design standard specifications of national network companies as a basis, three-dimensional design data is uniformly handed over and managed in a centralized way through development of evaluation plan arrangement and evaluation project distribution work, and the purpose of standardized and intelligent evaluation management of design results is realized by applying brand-new three-dimensional technical means and methods. The engineering data management capacity is integrally improved, a power transmission and transformation engineering three-dimensional design review authoritative management mode is created, and strong data support is provided for the orderly development of engineering construction.
Drawings
FIG. 1: the invention relates to an architecture diagram of a three-dimensional evaluation system in a three-dimensional intelligent auxiliary evaluation system.
Detailed Description
The invention is further explained below with reference to the drawings and examples.
A three-dimensional intelligent auxiliary review system for power transmission and transformation projects comprises the following parts: the system comprises a two-dimensional review system for design data reporting and closing-up review and a three-dimensional review system for three-dimensional process review, wherein the two-dimensional review system uses a Webster platform and comprises management modules for review plan management, review data collection, pre-review, formal review, closing-up review and the like, and the three-dimensional review system is composed of a three-dimensional review module and a review client.
The three-dimensional review module is provided with a three-dimensional model web end and comprises a three-dimensional design model viewing module, so that the functions of visual display, viewing space arrangement scheme, flight viewing, roaming, model zooming, rendering, model rotation, perspective viewing, full-screen display and holographic space retrieval of an engineering three-dimensional design model component can be realized, and a review expert is assisted in basic operation viewing of the model.
The evaluation client comprises a data analysis module for a three-dimensional GIM result model and an IFC civil engineering model of the power transformation project, a preview module for online preview of the models and a verification module for automatic verification of the three-dimensional design safety clearance of the power transformation project.
The data analysis module analyzes and verifies the three-dimensional design results submitted by the design units, including the GIM file and the IFC format file, establishes a set of relatively complete verification models of the three-dimensional design results, such as data formats, coordinate systems, measurement units, modeling requirements, hierarchy division, color matching principles, codes, three-dimensional design models, attribute definitions and the like, and automatically generates verification reports. And an accurate and complete data source is provided for realizing the functions of three-dimensional evaluation intelligent auxiliary evaluation and the like.
The preview module displays and browses a spatial arrangement scheme, flies and browses, roams, zooms, renders, rotates, looks through, displays in a full screen mode and searches a holographic space of an engineering three-dimensional design model component on a client side in a three-dimensional model mode.
The verification module utilizes a three-dimensional preliminary design result verification model to form a parameterized review index, realizes automatic verification of the safety clear distance of the power transformation project and forms a corresponding verification report.
The three-dimensional intelligent auxiliary evaluation method for the power transmission and transformation project, which uses the evaluation system, comprises the following specific steps:
firstly, according to a review plan issued by a system, a design unit uploads three-dimensional design data, and a management unit reports the three-dimensional design data to the system after reviewing; the administrator distributes the project and appoints the review expert in the system; and the central leader and the review experts view the model and related design data in the system.
Secondly, the manager makes and issues a formal review meeting notice through the engineering design review platform; before the formal review meeting, the review responsible person synchronously downloads all three-dimensional design data of the items to be reviewed by using the three-dimensional mobile review server in the intranet environment.
And thirdly, under the environment of the external network, a temporary local area network is built by utilizing hardware equipment such as a three-dimensional mobile review server, a power modem, a router and the like.
And fourthly, the evaluation expert accesses the three-dimensional mobile evaluation server by using the three-dimensional evaluation client installed on the local server to carry out on-site three-dimensional evaluation.
When the evaluation system is used, the evaluation system is mainly divided into the following 10 service steps according to the evaluation process and the user right service process:
(1) the provincial company issues a review task, and the central leader or full-time is responsible for importing the monthly review plan into the system and controlling the plan to be released and maintained. The central leader completes the assignment work of each project review responsible person and each professional review expert;
(2) the design unit is responsible for uploading project design data to the system, and after the data are declared, the system can complete the project data only when supporting the data return;
(3) the basic unit (power supply company) declares the design data; at this time, the design quality review service starts;
(4) each professional expert utilizes a three-dimensional review module and a review client to carry out formal review and fill in pre-review comments through an engineering design auxiliary review platform (a two-dimensional review system); the evaluation experts and evaluation responsible persons can grade the design, and the center leader can adjust the grade at any time;
(5) and after the pre-review passes, sending a formal review meeting notice, and holding the formal review meeting. In the formal review conference, intelligent review is carried out by utilizing a three-dimensional review client; and the evaluation expert realizes the operations of inquiring the design materials and the like on the system and realizes the artificial auxiliary evaluation. After meeting, the evaluation expert/responsible person can upload the official evaluation meeting data to the system, and the basic unit can check the official evaluation meeting data; the evaluation experts and the evaluation responsible persons can grade the design, and the center leader can adjust the score at any time;
(6) after the formal review passes, the design unit is responsible for uploading the item closing-in data to the system, and the system can upload the closing-in data only when the pre-review passes;
(7) the basic unit is responsible for reporting and closing up the audit of the data;
(8) each professional expert is responsible for auditing the closing-in data, and after the closing-in data is approved, the system retains the data of the two versions of the submission version and the approval version; the evaluation experts and the evaluation responsible persons can grade the design, and the center leader can adjust the score at any time;
(9) each professional review expert fills in review opinions, and the review responsible person gathers the review opinions and uploads the document sending review opinion data to the system;
(10) the central leader can adjust the scoring, and the scoring is finished and the results are filed.
Claims (7)
1. The utility model provides a supplementary system of reviewing of three-dimensional intelligence of power transmission and transformation engineering which characterized in that, includes following part: the system comprises a two-dimensional review system for design data reporting and closing-up review and a three-dimensional review system for three-dimensional process review, wherein the two-dimensional review system uses a Webster platform and comprises management modules for review plan management, review data collection, pre-review, formal review, closing-up review and the like, and the three-dimensional review system is composed of a three-dimensional review module and a plurality of review clients.
2. The three-dimensional intelligent auxiliary review system for the power transmission and transformation project of claim 1, wherein the three-dimensional review module has a three-dimensional model web end and comprises a three-dimensional design model viewing module, and the three-dimensional design model viewing module can achieve functions of visual display, viewing space arrangement scheme, flight viewing, roaming, model zooming, rendering, model rotation, perspective viewing, full screen display and holographic space retrieval of a three-dimensional design model component of the project, and assists review experts in viewing basic operations of the model.
3. The three-dimensional intelligent auxiliary evaluation system for the power transmission and transformation project according to claim 1, wherein the evaluation client comprises a data analysis module for a three-dimensional GIM result model and an IFC civil engineering model of the power transformation project, a preview module for online previewing of the models and a verification module for automatic verification of the three-dimensional design safety clearance of the power transformation project, and a plurality of evaluation clients are connected together through a local area network built by a three-dimensional mobile evaluation server, a power modem and router hardware equipment.
4. The three-dimensional intelligent auxiliary evaluation system for power transmission and transformation projects according to claim 3, wherein the data analysis module analyzes and verifies three-dimensional design results submitted by a design unit, including GIM files and IFC format files, establishes a set of relatively complete verification models of three-dimensional design result data formats, coordinate systems, measurement units, modeling requirements, hierarchy division, color matching principles, coding, three-dimensional design models, attribute definition and the like, and automatically generates a verification report.
5. The three-dimensional intelligent auxiliary review system for power transmission and transformation engineering according to claim 3, wherein the preview module displays and browses spatial arrangement schemes, flight browsing, roaming, model scaling, rendering, model rotation, perspective viewing, full screen display, and holographic space retrieval of engineering three-dimensional design model components at the client side in a three-dimensional model manner.
6. The three-dimensional intelligent auxiliary evaluation system for power transmission and transformation projects according to claim 3, wherein the verification module utilizes a three-dimensional preliminary design result verification model to form a parameterized evaluation index, realize automatic verification of safety clearance of the power transformation projects and form a corresponding verification report.
7. A three-dimensional intelligent auxiliary review method for power transmission and transformation projects, which uses the three-dimensional intelligent auxiliary review system of any one of claims 1 to 6, and is characterized by comprising the following specific steps:
firstly, according to a review plan issued by a system, a design unit uploads three-dimensional design data, and a management unit reports the three-dimensional design data to the system after reviewing; the administrator distributes the project and appoints the review expert in the system; the central leader and the review expert look over the model and the related design data in the system;
secondly, the manager makes and issues a formal review meeting notice through the engineering design review platform; before a formal review conference, a review responsible person synchronously downloads all three-dimensional design data of the item to be reviewed in an intranet environment by using a three-dimensional mobile review server;
thirdly, under the environment of the external network, a temporary local area network is built by utilizing hardware equipment such as a three-dimensional mobile review server, a power modem, a router and the like;
and fourthly, the evaluation expert accesses the three-dimensional mobile evaluation server by using the three-dimensional evaluation client installed on the local server to carry out on-site three-dimensional evaluation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811295811.3A CN111127244A (en) | 2018-11-01 | 2018-11-01 | Three-dimensional intelligent auxiliary evaluation system and method for power transmission and transformation project |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811295811.3A CN111127244A (en) | 2018-11-01 | 2018-11-01 | Three-dimensional intelligent auxiliary evaluation system and method for power transmission and transformation project |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111127244A true CN111127244A (en) | 2020-05-08 |
Family
ID=70494983
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811295811.3A Pending CN111127244A (en) | 2018-11-01 | 2018-11-01 | Three-dimensional intelligent auxiliary evaluation system and method for power transmission and transformation project |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111127244A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111754198A (en) * | 2020-06-28 | 2020-10-09 | 山东智源电力设计咨询有限公司 | Digital processing method and system for power transmission and transformation project |
CN111950921A (en) * | 2020-08-20 | 2020-11-17 | 江苏杰瑞信息科技有限公司 | Multi-person collaborative review method based on offline networking environment |
CN111985774A (en) * | 2020-07-17 | 2020-11-24 | 东南大学 | Automatic three-dimensional interactive inspection system and method for regulating control gauge |
CN112434364A (en) * | 2020-11-26 | 2021-03-02 | 上海市城市建设设计研究总院(集团)有限公司 | IFC-based construction project early-stage digital delivery and review system and method |
CN112766674A (en) * | 2021-01-08 | 2021-05-07 | 国网安徽省电力有限公司 | Transformer substation technical improvement major repair project intelligent review system based on three-dimensional GIS |
CN113128883A (en) * | 2021-04-23 | 2021-07-16 | 广东电网有限责任公司 | GIM file automatic scoring method, device and storage medium |
CN113627003A (en) * | 2021-07-31 | 2021-11-09 | 国网福建省电力有限公司 | Digital auxiliary review method and system based on power transmission and transformation model technology |
CN113627004A (en) * | 2021-07-31 | 2021-11-09 | 国网福建省电力有限公司 | Evaluation method and system for power transmission and transformation three-dimensional model design |
CN113792436A (en) * | 2021-09-17 | 2021-12-14 | 国网福建省电力有限公司 | Power transmission and transformation project design review system and method based on GIM model |
CN115545680A (en) * | 2022-11-29 | 2022-12-30 | 广州嘉为科技有限公司 | Online review collaboration method and device and storage medium |
-
2018
- 2018-11-01 CN CN201811295811.3A patent/CN111127244A/en active Pending
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111754198A (en) * | 2020-06-28 | 2020-10-09 | 山东智源电力设计咨询有限公司 | Digital processing method and system for power transmission and transformation project |
CN111985774A (en) * | 2020-07-17 | 2020-11-24 | 东南大学 | Automatic three-dimensional interactive inspection system and method for regulating control gauge |
CN111950921A (en) * | 2020-08-20 | 2020-11-17 | 江苏杰瑞信息科技有限公司 | Multi-person collaborative review method based on offline networking environment |
CN111950921B (en) * | 2020-08-20 | 2023-12-12 | 江苏杰瑞信息科技有限公司 | Multi-person collaborative review method based on offline networking environment |
CN112434364B (en) * | 2020-11-26 | 2023-01-20 | 上海市城市建设设计研究总院(集团)有限公司 | IFC-based building project early-stage digital delivery and evaluation system and method |
CN112434364A (en) * | 2020-11-26 | 2021-03-02 | 上海市城市建设设计研究总院(集团)有限公司 | IFC-based construction project early-stage digital delivery and review system and method |
CN112766674A (en) * | 2021-01-08 | 2021-05-07 | 国网安徽省电力有限公司 | Transformer substation technical improvement major repair project intelligent review system based on three-dimensional GIS |
CN112766674B (en) * | 2021-01-08 | 2023-12-15 | 国网安徽省电力有限公司 | Intelligent evaluation system for technical improvement overhaul project of transformer substation based on three-dimensional GIS |
CN113128883A (en) * | 2021-04-23 | 2021-07-16 | 广东电网有限责任公司 | GIM file automatic scoring method, device and storage medium |
CN113627003A (en) * | 2021-07-31 | 2021-11-09 | 国网福建省电力有限公司 | Digital auxiliary review method and system based on power transmission and transformation model technology |
CN113627004B (en) * | 2021-07-31 | 2023-07-28 | 国网福建省电力有限公司 | Evaluation method and system for three-dimensional model design of power transmission and transformation |
CN113627004A (en) * | 2021-07-31 | 2021-11-09 | 国网福建省电力有限公司 | Evaluation method and system for power transmission and transformation three-dimensional model design |
CN113627003B (en) * | 2021-07-31 | 2023-12-22 | 国网福建省电力有限公司 | Digital auxiliary review method and system based on power transmission and transformation model technology |
CN113792436A (en) * | 2021-09-17 | 2021-12-14 | 国网福建省电力有限公司 | Power transmission and transformation project design review system and method based on GIM model |
CN115545680A (en) * | 2022-11-29 | 2022-12-30 | 广州嘉为科技有限公司 | Online review collaboration method and device and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111127244A (en) | Three-dimensional intelligent auxiliary evaluation system and method for power transmission and transformation project | |
CN107622355B (en) | Digital management system and method for project group construction process | |
CN114386774B (en) | CPIM-based three-dimensional visual full-life-cycle management platform for coal preparation plant | |
CN112036766B (en) | Gridding distribution network service management method, gridding distribution network service management device, computer equipment and storage medium | |
CN112232761B (en) | Infrastructure application system and method | |
US20100324748A1 (en) | Building Optimization Platform And Web-Based Invoicing System | |
CN105574652A (en) | Planning big data management and control system of smart power distribution network and method | |
CN104866952A (en) | Three-dimensional digital management implementation method for hydropower station engineering project | |
CN111178680B (en) | Wind power plant engineering quality overall process management system, method and equipment | |
CN104504485A (en) | Integrative power system relay protection setting calculation method | |
CN105469188A (en) | Distribution network planning data online intelligent analysis system and distribution network planning data online intelligent analysis method | |
CN109657816A (en) | A kind of online check method of substation equipment monitoring information table | |
CN102968699A (en) | Power network planning collection data platform | |
CN111651818A (en) | BIM model rapid change method | |
CN111666619A (en) | BIM technology-based substation engineering implementation field digital management system | |
CN106355256A (en) | Multivariate visualization overhaul management system | |
CN110503321A (en) | General contract of civil engineering project management system | |
CN107239885A (en) | A kind of electricity power engineering towards supplier digitizes handover resource management system | |
CN114372594A (en) | Distributed power supply comprehensive analysis and safety management and control system | |
CN104881739A (en) | Marketing and distribution data consistency verification method based on IEC61970-61968 CIM standard | |
BE1030747A1 (en) | INTELLIGENT HANDOVER PROCEDURE FOR ENGINEERING FOR FOUR ELECTRICAL/ELECTRONIC SYSTEMS BASED ON A BIM PLATFORM | |
CN113807660A (en) | High-standard farmland construction information management system | |
CN202650332U (en) | Virtual simulation training system of distributed transformer substation based on province, prefecture and county level networks | |
CN111652467B (en) | Table box repair whole process management method based on worksheet management | |
Jing et al. | Development of BIM-Sensor integrated platform for MEP piping maintenance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20200508 |
|
WD01 | Invention patent application deemed withdrawn after publication |