CN110847325A - Construction process of sewage pipe network in villages and towns by horizontal directional drilling - Google Patents
Construction process of sewage pipe network in villages and towns by horizontal directional drilling Download PDFInfo
- Publication number
- CN110847325A CN110847325A CN201911271295.5A CN201911271295A CN110847325A CN 110847325 A CN110847325 A CN 110847325A CN 201911271295 A CN201911271295 A CN 201911271295A CN 110847325 A CN110847325 A CN 110847325A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- drilling
- hole
- pore
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 34
- 238000005553 drilling Methods 0.000 title claims abstract description 31
- 238000010276 construction Methods 0.000 title claims abstract description 24
- 239000010865 sewage Substances 0.000 title claims abstract description 14
- 239000011148 porous material Substances 0.000 claims abstract description 24
- 239000002689 soil Substances 0.000 claims abstract description 17
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 17
- 238000004140 cleaning Methods 0.000 claims abstract description 10
- 230000002787 reinforcement Effects 0.000 claims abstract description 5
- 238000002844 melting Methods 0.000 claims abstract description 4
- 230000008018 melting Effects 0.000 claims abstract description 4
- 238000003466 welding Methods 0.000 claims abstract description 4
- 239000007788 liquid Substances 0.000 claims description 15
- HEMHJVSKTPXQMS-UHFFFAOYSA-M Sodium hydroxide Chemical compound [OH-].[Na+] HEMHJVSKTPXQMS-UHFFFAOYSA-M 0.000 claims description 9
- 239000012530 fluid Substances 0.000 claims description 9
- 239000004568 cement Substances 0.000 claims description 6
- 239000000440 bentonite Substances 0.000 claims description 3
- 229910000278 bentonite Inorganic materials 0.000 claims description 3
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 claims description 3
- 235000019353 potassium silicate Nutrition 0.000 claims description 3
- 235000011121 sodium hydroxide Nutrition 0.000 claims description 3
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 claims description 3
- 101150054854 POU1F1 gene Proteins 0.000 description 2
- 102000001999 Transcription Factor Pit-1 Human genes 0.000 description 2
- 108010040742 Transcription Factor Pit-1 Proteins 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000002002 slurry Substances 0.000 description 2
- 239000004927 clay Substances 0.000 description 1
- 238000001125 extrusion Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/06—Methods of, or installations for, laying sewer pipes
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices or the like
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/04—Directional drilling
- E21B7/046—Directional drilling horizontal drilling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/28—Enlarging drilled holes, e.g. by counterboring
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- Physics & Mathematics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Mechanical Engineering (AREA)
- Health & Medical Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Earth Drilling (AREA)
Abstract
The invention relates to a construction process of a sewage pipe network in a village and a town by using a horizontal directional drill, which comprises the following steps: 1) determining a pore canal formed by an inclined line segment, a curve segment and a horizontal straight line segment of the track segment of the directional pore; 2) drilling a guide hole by using an arrow-type small drill bit, drilling a drill rod from the ground, controlling the direction and the depth of the drill bit, and drilling into an accurate positioning guide hole; 3) then, reversely expanding the soil back by using the guide hole, and only crushing the undisturbed soil in the designed hole diameter during expanding the soil back; 4) finally, cleaning out soil in the pore channel by utilizing hole cleaning equipment to form a pore channel for installing the pipe; 5) welding a pipeline: the pipeline is made of PE pipes and is welded in a hot melting mode; 6) after the pipeline is connected, the pipeline is uniformly and stably pulled, and clean water is injected into the pipeline from the tail of the pipeline in the pulling construction process, so that the self weight of the pipeline is increased, and the pipeline is prevented from floating upwards; 7) after the pipeline is pulled through, in order to avoid the collapse of the pavement, the construction is carried out in time by adopting an in-hole grouting reinforcement method. The process method improves the surface smoothness of the drilled hole and ensures the strength of the constructed pavement.
Description
Technical Field
The invention relates to a construction process of a sewage pipe network in a village and a town by using a horizontal directional drill, belonging to the field of sewage pipe networks.
Background
In the sewage pipe network construction process, according to the directional construction process, in the dragging process of the pipeline, the pipeline is always suspended at the upper part of the pore canal because the pipeline is hollow and the specific gravity is smaller than the specific gravity of the slurry, so that the dragging force is overlarge or the elevation deviation exceeds the standard requirement. In addition, the soil in the construction area is silty clay, underground water is abundant, and the problems of road surface collapse and the like caused by pore canal collapse and the like are easily caused.
Disclosure of Invention
The technical problem to be solved by the invention is to provide a construction process of a horizontal directional drill in a sewage pipe network in villages and towns, and the process method improves the surface smoothness of a drill hole and ensures the strength of a constructed road surface.
In order to solve the above problems, the specific technical scheme of the invention is as follows: a construction process of a sewage pipe network in a village and a town by using a horizontal directional drill comprises the following steps:
1) determining a pore canal formed by an inclined line segment, a curve segment and a horizontal straight line segment of the track segment of the directional pore;
2) drilling a guide hole by using an arrow-type small drill bit with the outer diameter slightly larger than that of the drill rod, drilling the drill rod from the ground, receiving a message sent by a transmitter in the underground drill bit by a ground instrument, controlling the direction and the depth of the drill bit, and drilling the drill bit into an accurate positioning guide hole;
3) then, reversely expanding the soil back by using the guide hole, and only crushing the undisturbed soil in the designed hole diameter during expanding the soil back;
4) finally, cleaning out soil in the pore channel by utilizing hole cleaning equipment to form a pore channel for installing the pipe;
5) welding a pipeline: the pipeline is made of PE pipes and is welded in a hot melting mode;
6) after the pipeline is connected, the pipeline is uniformly and stably pulled, and clean water is injected into the pipeline from the tail of the pipeline in the pulling construction process, so that the self weight of the pipeline is increased, and the pipeline is prevented from floating upwards;
7) after the pipeline is pulled through, in order to avoid the collapse of the pavement, the construction is carried out in time by adopting an in-hole grouting reinforcement method.
In the processes of drilling the guide hole and back reaming in the step 2) and the step 3), drilling fluid is added, and the components of the drilling fluid comprise, by weight, 20% of bentonite, 1% of commercially available drilling fluid, 0.4% of caustic soda and the balance of water.
The grouting component in the step 7) consists of a liquid A and a liquid B, wherein the liquid A: liquid B = 3: 1; the solution A consists of water and cement, and the weight part ratio of the water to the cement is 0.75-1.5: 1; the liquid B comprises 35-40% of water glass, 2-3% of retarder and the balance of water.
The two sides of the pore passage are provided with downward inclined sections, the outer end part of the inclined section at the inlet is provided with a working pit (1), the outer end part of the inclined section at the outlet is provided with a receiving pit, and the depths of the working pit and the receiving pit are less than the depth of the horizontal section; the horizontal section in the middle of the pore canal is provided with a plurality of pressure relief pits.
The construction process of the horizontal directional drill in the sewage pipe network in villages and towns adopts the process, the pore is finally formed, the inner wall is smooth, the pipeline is convenient to drag in, and the installation work is completed.
Drawings
Fig. 1 is a schematic view of the drilling construction of the present application.
Fig. 2 is a schematic view of back-reaming drilling construction according to the present application.
Fig. 3 is a schematic diagram of the construction of the pore canal mud cleaning of the application.
Fig. 4 is a schematic diagram of pipeline dragging installation construction according to the application.
Detailed Description
A construction process of a sewage pipe network in a village and a town by using a horizontal directional drill comprises the following steps:
1) as shown in fig. 1, determining a directional hole trajectory line segment, wherein the directional hole trajectory line segment comprises an inclined line segment, a curved line segment and a horizontal straight line segment to form a hole channel;
2) drilling a guide hole by using an arrow-type small drill bit with the outer diameter slightly larger than that of the drill rod, drilling the drill rod from the ground, receiving a message sent by a transmitter in the underground drill bit by a ground instrument, controlling the direction and the depth of the drill bit, and drilling the drill bit into an accurate positioning guide hole;
3) then, the guide hole is utilized to reversely expand back, and only the undisturbed soil in the designed hole diameter is crushed during expanding back, as shown in figure 2;
4) finally, cleaning out soil in the pore channel by utilizing hole cleaning equipment to form a pore channel for installing the pipe, as shown in figure 3;
5) welding a pipeline: the pipeline is made of PE pipes and is welded in a hot melting mode;
6) after the pipeline is connected, the pipeline is uniformly and stably pulled, as shown in fig. 4, in the dragging construction process, clear water is injected into the pipeline from the tail of the pipeline, the self weight of the pipeline is increased, and the pipeline is prevented from floating upwards;
7) after the pipeline is pulled through, in order to avoid the collapse of the pavement, the construction is carried out in time by adopting an in-hole grouting reinforcement method.
In the processes of drilling the guide hole and back reaming in the step 2) and the step 3), drilling fluid is added, and the components of the drilling fluid comprise, by weight, 20% of bentonite, 1% of commercially available drilling fluid, 0.4% of caustic soda and the balance of water. When the original soil in the hole is crushed by reaming, the soil in the hole is stirred to form plastic slurry, and a smooth layer of wall protection mud skin is formed on the hole wall by means of extrusion of machines and tools during hole cleaning so as to balance the rock fixing pressure in the hole channel and finally form a stable and smooth pipe installing channel.
The grouting component in the step 7) consists of a liquid A and a liquid B, wherein the liquid A: liquid B = 3: 1; the solution A consists of water and cement, and the weight part ratio of the water to the cement is 0.75-1.5: 1; the liquid B comprises 35-40% of water glass, 2-3% of retarder and the balance of water. The grouting component can realize rapid pipeline reinforcement and avoid road surface collapse.
The two sides of the pore passage are provided with downward inclined sections, the outer end part of the inclined section at the inlet is provided with a working pit 1, the outer end part of the inclined section at the outlet is provided with a receiving pit 2, and the depths of the working pit 1 and the receiving pit 2 are smaller than the depth of the horizontal section; a plurality of pressure relief pits 3 are arranged at the horizontal section in the middle of the pore channel.
Claims (4)
1. A construction process of a sewage pipe network in a village and a town by using a horizontal directional drill is characterized by comprising the following steps:
1) determining a pore canal formed by an inclined line segment, a curve segment and a horizontal straight line segment of the track segment of the directional pore;
2) drilling a guide hole by using an arrow-type small drill bit with the outer diameter slightly larger than that of the drill rod, drilling the drill rod from the ground, receiving a message sent by a transmitter in the underground drill bit by a ground instrument, controlling the direction and the depth of the drill bit, and drilling the drill bit into an accurate positioning guide hole;
3) then, reversely expanding the soil back by using the guide hole, and only crushing the undisturbed soil in the designed hole diameter during expanding the soil back;
4) finally, cleaning out soil in the pore channel by utilizing hole cleaning equipment to form a pore channel for installing the pipe;
5) welding a pipeline: the pipeline is made of PE pipes and is welded in a hot melting mode;
6) after the pipeline is connected, the pipeline is uniformly and stably pulled, and clean water is injected into the pipeline from the tail of the pipeline in the pulling construction process, so that the self weight of the pipeline is increased, and the pipeline is prevented from floating upwards;
7) after the pipeline is pulled through, in order to avoid the collapse of the pavement, the construction is carried out in time by adopting an in-hole grouting reinforcement method.
2. The process of claim 1, wherein the horizontal directional drilling is carried out in a sewage pipe network in villages and towns, and the process comprises the following steps: in the processes of drilling the guide hole and back reaming in the step 2) and the step 3), drilling fluid is added, and the components of the drilling fluid comprise, by weight, 20% of bentonite, 1% of commercially available drilling fluid, 0.4% of caustic soda and the balance of water.
3. The process of claim 1, wherein the horizontal directional drilling is carried out in a sewage pipe network in villages and towns, and the process comprises the following steps: the grouting component in the step 7) consists of a liquid A and a liquid B, wherein the liquid A: liquid B = 3: 1; the solution A consists of water and cement, and the weight part ratio of the water to the cement is 0.75-1.5: 1; the liquid B comprises 35-40% of water glass, 2-3% of retarder and the balance of water.
4. The process of claim 1, wherein the horizontal directional drilling is carried out in a sewage pipe network in villages and towns, and the process comprises the following steps: the two sides of the pore passage are provided with downward inclined sections, the outer end part of the inclined section at the inlet is provided with a working pit (1), the outer end part of the inclined section at the outlet is provided with a receiving pit (2), and the depths of the working pit (1) and the receiving pit (2) are smaller than the depth of the horizontal section; a plurality of pressure relief pits (3) are arranged at the horizontal section in the middle of the pore channel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911271295.5A CN110847325A (en) | 2019-12-12 | 2019-12-12 | Construction process of sewage pipe network in villages and towns by horizontal directional drilling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911271295.5A CN110847325A (en) | 2019-12-12 | 2019-12-12 | Construction process of sewage pipe network in villages and towns by horizontal directional drilling |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110847325A true CN110847325A (en) | 2020-02-28 |
Family
ID=69608786
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911271295.5A Pending CN110847325A (en) | 2019-12-12 | 2019-12-12 | Construction process of sewage pipe network in villages and towns by horizontal directional drilling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110847325A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112145791A (en) * | 2020-08-12 | 2020-12-29 | 中国二十冶集团有限公司 | Method for horizontally dragging and laying pipeline |
CN112282022A (en) * | 2020-09-15 | 2021-01-29 | 北京建工土木工程有限公司 | Method for quickly constructing rain sewage inspection well on existing road |
CN113236857A (en) * | 2021-03-24 | 2021-08-10 | 北京恩菲环保股份有限公司 | Pipeline connection method for preventing pulling-out leakage during directional drilling construction |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101457853A (en) * | 2008-11-20 | 2009-06-17 | 江苏广宇建设集团有限公司 | Non-digging tube-pulling construction method |
CN102061933A (en) * | 2010-12-13 | 2011-05-18 | 山西晋城无烟煤矿业集团有限责任公司 | Long drilling positioning construction process |
RU2429403C1 (en) * | 2010-03-09 | 2011-09-20 | Федеральное государственное автономное образовательное учреждение высшего профессионального образования Сибирский федеральный университет (СФУ) | Installation for trenchless replacement of underground pipelines |
CN102434716A (en) * | 2011-09-26 | 2012-05-02 | 武汉地网非开挖科技有限公司 | Flexible pipe assisted type pipeline returning method |
-
2019
- 2019-12-12 CN CN201911271295.5A patent/CN110847325A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101457853A (en) * | 2008-11-20 | 2009-06-17 | 江苏广宇建设集团有限公司 | Non-digging tube-pulling construction method |
RU2429403C1 (en) * | 2010-03-09 | 2011-09-20 | Федеральное государственное автономное образовательное учреждение высшего профессионального образования Сибирский федеральный университет (СФУ) | Installation for trenchless replacement of underground pipelines |
CN102061933A (en) * | 2010-12-13 | 2011-05-18 | 山西晋城无烟煤矿业集团有限责任公司 | Long drilling positioning construction process |
CN102434716A (en) * | 2011-09-26 | 2012-05-02 | 武汉地网非开挖科技有限公司 | Flexible pipe assisted type pipeline returning method |
Non-Patent Citations (1)
Title |
---|
乌效鸣等: "《钻井液与岩土工程浆材》", 31 July 2014 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112145791A (en) * | 2020-08-12 | 2020-12-29 | 中国二十冶集团有限公司 | Method for horizontally dragging and laying pipeline |
CN112282022A (en) * | 2020-09-15 | 2021-01-29 | 北京建工土木工程有限公司 | Method for quickly constructing rain sewage inspection well on existing road |
CN113236857A (en) * | 2021-03-24 | 2021-08-10 | 北京恩菲环保股份有限公司 | Pipeline connection method for preventing pulling-out leakage during directional drilling construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110847325A (en) | Construction process of sewage pipe network in villages and towns by horizontal directional drilling | |
CN108678130A (en) | A kind of non-digging drag pipe construction method | |
CN101122130B (en) | Construction method of drilling follow casting pile used for building or bridge foundation | |
CN103075179A (en) | Entitative coal seam gas drainage drilling hole double-pipe drainage method | |
CN105649012A (en) | Construction method for bored pile of subway station enclosure structure of upper-soft lower-hard ground | |
CN107747312B (en) | Method for drilling and grouting construction of gravel stratum | |
CN107687176B (en) | Polyethylene pipe non-excavation construction method | |
CN110145230A (en) | A kind of horizontal directional drilling trombone slide method | |
CN103122632A (en) | Construction method for drilling hole and casting pile in plastic flow stratum or karst cave stratum | |
CN103603342A (en) | Construction method of ultra-long bored concrete pile with large-diameter casing combination | |
BRPI0611197A2 (en) | Apparatus and method for directing an open-ended conductive tube into the ground and well bottom assembly | |
CN104929136A (en) | Urban complex underground obstacle working condition occlusive pile enclosure construction method | |
CN212175815U (en) | Deep foundation pit supporting structure | |
CN204941351U (en) | A kind of pile foundation construction removes underground obstacle drill bit | |
CN103031847B (en) | Reducing overlap joint combined type orifice pipe grouting method | |
CN111535742A (en) | Low-resistance directional drilling and crossing construction method for PE pipeline | |
CN111236387B (en) | Construction method for connecting newly-built sewage pipe with existing sewage pipe | |
CN106837382A (en) | A kind of subway tunnel country rock pre grouting from the surface reinforcement process | |
CN105134069A (en) | Technology for constructing gas vertical shaft penetrating strong water-rich rock stratum through anti-well method | |
CN116291471A (en) | Construction method and tunneling equipment for large-diameter vertical shaft of upper soft and lower hard stratum | |
CN105401572A (en) | Construction technique for environment-friendly cast-in-situ bored pile provided with wall protecting tube | |
CN203757177U (en) | Mud sand sludge area manual pipe jacking construction device | |
CN104213882A (en) | Coalbed methane horizontal well PE screen pipe well completion method and device | |
CN102828692A (en) | Pneumatic drilling method for casing pipe type spiral drilling machine | |
CN115653497A (en) | Laying construction process for horizontal directional drill crossing pipeline |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200228 |
|
RJ01 | Rejection of invention patent application after publication |