CN110805304A - 混凝土梁的加固构造施工方法 - Google Patents

混凝土梁的加固构造施工方法 Download PDF

Info

Publication number
CN110805304A
CN110805304A CN201911131199.0A CN201911131199A CN110805304A CN 110805304 A CN110805304 A CN 110805304A CN 201911131199 A CN201911131199 A CN 201911131199A CN 110805304 A CN110805304 A CN 110805304A
Authority
CN
China
Prior art keywords
concrete
steel plate
concrete beam
expansive
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201911131199.0A
Other languages
English (en)
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201911131199.0A priority Critical patent/CN110805304A/zh
Publication of CN110805304A publication Critical patent/CN110805304A/zh
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • E04G2021/127Circular prestressing of, e.g. columns, tanks, domes

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种混凝土梁的加固构造施工方法,其特征是混凝土梁下面设置膨胀混凝土,膨胀混凝土强度比混凝土梁混凝土强度高一个强度等级,膨胀混凝土上部设置预应力钢筋,膨胀混凝土内设置混凝土墩,膨胀混凝土下面设置折形钢板,折形钢板插入混凝土柱的凹槽内;承压钢板焊接在混凝土柱或混凝土梁的钢筋上,承压钢板外侧设置锚具。本发明力学性能好,承载能力强。

Description

混凝土梁的加固构造施工方法
技术领域
本发明涉及一种混凝土梁的加固结构施工方法,适用于建筑领域。
背景技术
混凝土梁出现承载力不够的情况下要进行加固,通常会采用混凝土加固或者钢板加固,单纯采用混凝土加固时,加固部分的混凝土往往很难与原有混凝土形成整体;而采用钢板加固时,往往因钢板刚度远大于混凝土刚度,在相同变形下承力会较小,钢板参与协同承载的能力有限。为了解决这些问题,可以采用预应力方式来提升协同承载能力。同时出于使用功能原因,加固部分的混凝土高度有限,对钢板施加预应力时,有可能对加固部分的混凝土造成破坏。如何在钢板施加预应力时不致引起混凝土破坏且能有效地提升加固后混凝土梁的承载力是工程人员面临的课题。
发明内容
本发明是提供一种混凝土梁的加固结构施工方法,解决传统加固结构整体承载能力不好的问题。
本发明在单向预应力施加下容易因混凝土单方向受力过大而出现裂缝,混凝土出现裂缝后预应力效果会差强人意。钢板箍施加竖向预应力,水平预应力钢筋张拉时施加水平预应力,两者交替进行对提升预应力效果会有很大的好处。
混凝土梁下面设置膨胀混凝土,膨胀混凝土强度比混凝土梁混凝土强度高一个强度等级,膨胀混凝土上部设置预应力钢筋,预应力钢筋离混凝土梁底部距离为25~35mm,预应力钢筋直径为25~28mm,膨胀混凝土内设置混凝土墩,混凝土墩沿膨胀混凝土跨度方向设置间距为0.6~0.8m。
混凝土墩通过植筋与混凝土梁连接,每个混凝土墩的植筋数量为 4根,植筋直径为25~28mm。膨胀混凝土下面设置折形钢板,折形钢板插入混凝土柱的凹槽内。为了增加结构的抗震性能,避免梁柱节点因刚度过大而承载过大,对梁柱节点部位刚度进行削弱,混凝土梁与混凝土柱部位交接部位设置钢渣粒,这里混凝土梁与混凝土柱部位交接部位是指混凝土梁底标高以下与混凝土柱部位交接位置,钢渣粒粒径为5~20mm。混凝土柱内侧和外侧均设置钢渣粒,钢渣粒设置长度范围为1/5混凝土柱长度,钢渣粒设置高度范围为100~150mm,外侧钢渣粒外面设置承压钢板,承压钢板焊接在混凝土柱或混凝土梁的钢筋上,承压钢板外侧设置锚具。
承载力计算公式采用如下:F=αM+βN+ρL,其中F为总承载力,α为钢板承载力参与系数,M为钢板承载力,β为膨胀混凝土承载力参与系数,N为膨胀混凝土承载力,膨胀混凝土承载力计算时以凹处高度作为计算高度,ρ为原混凝土梁承载力参与系数,L为原混凝土梁承载力。
钢板承载力参与系数主要与预应力施加情况和混凝土梁跨度、混凝土墩设置间距密切相关;膨胀混凝土承载力参与系数主要与预应力施加情况和混凝土梁跨度、混凝土墩设置间距相关,原混凝土梁承载力参与系数与预应力施加情况和混凝土梁跨度、混凝土墩设置间距相关。预应力施加工艺采用方案二,对不同情况下承载力参与系数进行计算机仿真分析,提出了表1,当混凝土梁跨度或混凝土墩设置间距位于表1范围内,可采用插值方法确定承载力参与系数。当混凝土梁跨度大于12m或小于6m时采用12m所对应的数值,当混凝土梁跨度小于6m时采用6m所对应的数值。混凝土墩设置间距为0.6~0.8m,这个间距可以使承载力参与度处于合理范围内。
表1不同情况下承载力参与系数
Figure BDA0002278339690000021
施工步骤包括:
(1)剥离混凝土梁保护层,将混凝土梁下表面凿毛;
(2)钻设混凝土梁的预埋孔,预埋孔直径为27~30mm,预埋孔内插入植筋,预埋孔与植筋之间空隙注入环氧树脂;
(3)钻设混凝土柱的预应力钢筋预埋孔,钻设混凝土柱埋设折形钢板的凹槽;
(4)凿除混凝土柱与混凝土梁交接部位的混凝土,留置钢渣粒预埋孔;
(5)凿除设置承压钢板部位的混凝土柱或混凝土梁混凝土保护层,裸露出混凝土柱或混凝土梁的钢筋;
(6)在钢渣粒预埋孔安装钢渣粒,然后在混凝土柱或混凝土梁的裸露钢筋上焊接承压钢板;
(7)在预应力钢筋预埋孔内安装预应力钢筋;
(8)支设混凝土墩模板,然后浇筑混凝土;
(9)待混凝土墩的混凝土强度达到设计强度25%后支设膨胀混凝土模板,膨胀混凝土底模板采用折形钢板,侧模采用木模,木模每隔 1~1.2m设置膨胀混凝土浇筑孔,膨胀混凝土浇筑孔设置在侧模,木模每隔2~2.5m设置排气孔,排气孔设置在侧模;
(10)浇筑膨胀混凝土;
(11)安装钢板箍;
(12)安装预应力钢筋;
(13)张拉钢板箍或预应力钢筋;张拉工艺采用如下:1、对钢板箍施加初始应力,初始应力为控制应力的10%,施加时间为12min;对预应力钢筋施加初始应力,初始应力为控制应力的10%,施加时间为8min;2、对钢板箍施加预应力,预应力为控制应力的50%,施加时间为5min;对预应力钢筋施加预应力,预应力为控制应力的50%,施加时间为5min;3、对钢板箍施加预应力,预应力为控制应力的 105%,施加时间为12min;对预应力钢筋施加预应力,预应力为控制应力的105%,施加时间为8min。
(14)采用锚具对预应力钢筋进行锚固,钢板箍张拉完毕后用锚定钢板进行焊接锚固。
本发明力学性能好,承载力高。
附图说明
图1为混凝土梁的加固结构示意图。
1、折形钢板,2、钢板箍,3、膨胀混凝土,4、混凝土墩,5、预应力钢筋,6、钢渣粒,7、承压钢板,8、锚具,9、混凝土梁,10、混凝土柱。
具体实施方式
以下结合附图对本实施例进行详细描述。
加固结构采用折形结构,折形结构在钢板箍2部位凸出,避免因钢板箍2张拉时出现混凝土承压不够而开裂。另外,折形结构在钢板箍2部位凸出部位设置混凝土墩4形成多个支承点,弯矩包络图比普通混凝土梁9的弯矩图要合理很多,混凝土梁9的最大弯矩会降低较大。折形结构弯矩包络图和普通混凝土梁弯矩包络图对比显示折形结构随长度变化的弯矩会平缓很多,表2为加固混凝土用材相同情况下的最大弯矩的对比情况,表中显示折形结构比普通混凝土梁最大弯矩减少率降低较大。
表2加固混凝土用材相同情况下的最大弯矩的对比情况
Figure BDA0002278339690000051
混凝土梁9下面设置膨胀混凝土3,膨胀混凝土3强度比混凝土梁9混凝土强度高一个强度等级,膨胀混凝土3上部设置预应力钢筋 5,预应力钢筋5离混凝土梁9底部距离为25~35mm,预应力钢筋5 直径为25~28mm,膨胀混凝土3内设置混凝土墩4,混凝土墩4沿膨胀混凝土跨度方向设置间距为0.6~0.8m。
混凝土墩4通过植筋与混凝土梁9连接,每个混凝土墩4的植筋数量为4根,植筋直径为25~28mm。膨胀混凝土3下面设置折形钢板1,折形钢板1插入混凝土柱10的凹槽内。为了增加结构的抗震性能,避免梁柱节点因刚度过大而承载过大,对梁柱节点部位刚度进行削弱,混凝土梁9与混凝土柱10部位交接部位设置钢渣粒6,钢渣粒6粒径为5~20mm。混凝土柱10内侧和外侧均设置钢渣粒6,钢渣粒6设置长度范围为1/5混凝土柱10长度,钢渣粒6设置高度范围为100~150mm,外侧钢渣粒6外面设置承压钢板7,承压钢板7 焊接在混凝土柱10或混凝土梁9的钢筋上,承压钢板7外侧设置锚具8。
根据大量计算机仿真分析数据,对不同方案预应力施加方式进行了对比,
第一种方案为:1、对钢板箍2施加初始应力,初始应力为控制应力的10%,施加时间为12min;对预应力钢筋5施加初始应力,初始应力为控制应力的10%,施加时间为8min;2、对钢板箍2施加预应力,预应力为控制应力的105%,施加时间为15min;对预应力钢筋5施加预应力,预应力为控制应力的105%,施加时间为12min。
第二种方案为:1、对钢板箍2施加初始应力,初始应力为控制应力的10%,施加时间为12min;对预应力钢筋5施加初始应力,初始应力为控制应力的10%,施加时间为8min;2、对钢板箍2施加预应力,预应力为控制应力的50%,施加时间为5min;对预应力钢筋5 施加预应力,预应力为控制应力的50%,施加时间为5min;3、对钢板箍2施加预应力,预应力为控制应力的105%,施加时间为12min;对预应力钢筋5施加预应力,预应力为控制应力的105%,施加时间为8min。
第三种方案为:1、对钢板箍2施加初始应力,初始应力为控制应力的10%,施加时间为12min;对预应力钢筋5施加初始应力,初始应力为控制应力的10%,施加时间为8min;2、对钢板箍2施加预应力,预应力为控制应力的30%,施加时间为5min;对预应力钢筋5 施加预应力,预应力为控制应力的30%,施加时间为5min;3、对钢板箍2施加预应力,预应力为控制应力的60%,施加时间为5min;对预应力钢筋5施加预应力,预应力为控制应力的60%,施加时间为 5min;4、对钢板箍2施加预应力,预应力为控制应力的105%,施加时间为12min;对预应力钢筋5施加预应力,预应力为控制应力的 105%,施加时间为8min。
第四种方案为:1、对钢板箍2施加初始应力,初始应力为控制应力的20%,施加时间为12min;对预应力钢筋5施加初始应力,初始应力为控制应力的10%,施加时间为8min;2、对钢板箍2施加预应力,预应力为控制应力的60%,施加时间为5min;对预应力钢筋5 施加预应力,预应力为控制应力的50%,施加时间为5min;3、对钢板箍2施加预应力,预应力为控制应力的105%,施加时间为12min;对预应力钢筋5施加预应力,预应力为控制应力的105%,施加时间为8min。
表3不同预应力方案的钢板承载力参与系数情况
Figure BDA0002278339690000071
Figure BDA0002278339690000081
不同预应力方案的钢板承载力参与系数情况如表3所示,表中表明方案二和方案三钢板承载力参与度高,说明分段预应力加压还是很有必要。而方案四所采用的不均匀加压显然对钢板承载力参与度有削弱作用,进一步说明了采用水平预应力和竖向预应力交叉施加的工艺使钢板与混凝土协同受力能力有所提升。方案二和方案三钢板承载力参与度相差不大,为了简化工序,选择方案二作为预应力施加方案。
施工步骤包括:
(1)剥离混凝土梁9保护层,将混凝土梁9下表面凿毛;
(2)钻设混凝土梁9的预埋孔,预埋孔直径为27~30mm,预埋孔内插入植筋,预埋孔与植筋之间空隙注入环氧树脂;
(3)钻设混凝土柱10的预应力钢筋5预埋孔,钻设混凝土柱10 埋设折形钢板1的凹槽;
(4)凿除混凝土柱10与混凝土梁9交接部位的混凝土,留置钢渣粒6预埋孔;
(5)凿除设置承压钢板7部位的混凝土柱10或混凝土梁9混凝土保护层,裸露出混凝土柱10或混凝土梁9的钢筋;
(6)在钢渣粒6预埋孔安装钢渣粒6,然后在混凝土柱10或混凝土梁9的裸露钢筋上焊接承压钢板7;
(7)在预应力钢筋5预埋孔内安装预应力钢筋5;
(8)支设混凝土墩4模板,然后浇筑混凝土;
(9)待混凝土墩4的混凝土强度达到设计强度25%后支设膨胀混凝土3模板,膨胀混凝土3底模板采用折形钢板1,侧模采用木模,木模每隔1~1.2m设置膨胀混凝土3浇筑孔,膨胀混凝土3浇筑孔设置在侧模,木模每隔2~2.5m设置排气孔,排气孔设置在侧模;
(10)浇筑膨胀混凝土3;
(11)安装钢板箍2;
(12)安装预应力钢筋5;
(13)张拉钢板箍2或预应力钢筋5;张拉工艺采用如下:1、对钢板箍2施加初始应力,初始应力为控制应力的10%,施加时间为 12min;对预应力钢筋5施加初始应力,初始应力为控制应力的10%,施加时间为8min;2、对钢板箍2施加预应力,预应力为控制应力的50%,施加时间为5min;对预应力钢筋5施加预应力,预应力为控制应力的50%,施加时间为5min;3、对钢板箍2施加预应力,预应力为控制应力的105%,施加时间为12min;对预应力钢筋5施加预应力,预应力为控制应力的105%,施加时间为8min。
(14)采用锚具8对预应力钢筋5进行锚固,钢板箍2张拉完毕后用锚定钢板进行焊接锚固。

Claims (1)

1.一种混凝土梁的加固构造施工方法,其特征是混凝土梁下面设置膨胀混凝土,膨胀混凝土强度比混凝土梁混凝土强度高一个强度等级,膨胀混凝土上部设置预应力钢筋,预应力钢筋离混凝土梁底部距离为25~35mm,预应力钢筋直径为25~28mm,膨胀混凝土内设置混凝土墩,混凝土墩沿膨胀混凝土跨度方向设置间距为0.6~0.8m;
混凝土墩通过植筋与混凝土梁连接,每个混凝土墩的植筋数量为4根,植筋直径为25~28mm;膨胀混凝土下面设置折形钢板,折形钢板插入混凝土柱的凹槽内;承压钢板焊接在混凝土柱或混凝土梁的钢筋上,承压钢板外侧设置锚具;
混凝土梁与混凝土柱部位交接部位设置钢渣粒,钢渣粒粒径为5~20mm;混凝土柱内侧和外侧均设置钢渣粒,钢渣粒设置长度范围为1/5混凝土柱长度,钢渣粒设置高度范围为100~150mm,外侧钢渣粒外面设置承压钢板;
施工步骤包括:
(1)剥离混凝土梁保护层,将混凝土梁下表面凿毛;
(2)钻设混凝土梁的预埋孔,预埋孔直径为27~30mm,预埋孔内插入植筋,预留孔与植筋之间空隙注入环氧树脂;
(3)钻设混凝土柱的预应力钢筋预埋孔,钻设混凝土柱埋设折形钢板的凹槽;
(4)凿除混凝土柱与混凝土梁交接部位的混凝土,留置钢渣粒预留孔;
(5)凿除设置承压钢板部位的混凝土柱或混凝土梁混凝土保护层,裸露出混凝土柱或混凝土梁的钢筋;
(6)在钢渣粒预留孔安装钢渣粒,然后在混凝土柱或混凝土梁的裸露钢筋上焊接承压钢板;
(7)在预应力钢筋预埋孔内安装预应力钢筋;
(8)支设混凝土墩模板,然后浇筑混凝土;
(9)待混凝土墩的混凝土强度达到设计强度25%后支设膨胀混凝土模板,膨胀混凝土底模板采用折形钢板,侧模采用木模,木模每隔1~1.2m设置膨胀混凝土浇筑孔,膨胀混凝土浇筑孔设置在侧模,木模每隔2~2.5m设置排气孔,排气孔设置在侧模;
(10)浇筑膨胀混凝土;
(11)安装钢板箍;
(12)安装预应力钢筋;
(13)张拉钢板箍或预应力钢筋;
(14)采用锚具对预应力钢筋进行锚固,钢板箍张拉完毕后用锚定钢板进行焊接锚固;
承载力计算公式采用如下:F=αM+βN+ρL,其中F为总承载力,α为钢板承载力参与系数,M为钢板承载力,β为膨胀混凝土承载力参与系数,N为膨胀混凝土承载力,膨胀混凝土承载力计算时以凹处高度作为计算高度,ρ为原混凝土梁承载力参与系数,L为原混凝土梁承载力;
不同情况下承载力参与系数可根据表1采用,当混凝土梁跨度或混凝土墩设置间距位于表1范围内,可采用插值方法确定承载力参与系数;当混凝土梁跨度大于12m或小于6m时采用12m所对应的数值,当混凝土梁跨度小于6m时采用6m所对应的数值;表1不同情况下承载力参与系数
Figure FDA0002278339680000031
CN201911131199.0A 2017-09-12 2017-09-12 混凝土梁的加固构造施工方法 Withdrawn CN110805304A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911131199.0A CN110805304A (zh) 2017-09-12 2017-09-12 混凝土梁的加固构造施工方法

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710818168.7A CN107630564B (zh) 2017-09-12 2017-09-12 一种混凝土梁的加固结构施工方法
CN201911131199.0A CN110805304A (zh) 2017-09-12 2017-09-12 混凝土梁的加固构造施工方法

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201710818168.7A Division CN107630564B (zh) 2017-09-12 2017-09-12 一种混凝土梁的加固结构施工方法

Publications (1)

Publication Number Publication Date
CN110805304A true CN110805304A (zh) 2020-02-18

Family

ID=61101179

Family Applications (3)

Application Number Title Priority Date Filing Date
CN201911133918.2A Withdrawn CN110836023A (zh) 2017-09-12 2017-09-12 一种混凝土梁的加固施工方法
CN201911131199.0A Withdrawn CN110805304A (zh) 2017-09-12 2017-09-12 混凝土梁的加固构造施工方法
CN201710818168.7A Active CN107630564B (zh) 2017-09-12 2017-09-12 一种混凝土梁的加固结构施工方法

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201911133918.2A Withdrawn CN110836023A (zh) 2017-09-12 2017-09-12 一种混凝土梁的加固施工方法

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201710818168.7A Active CN107630564B (zh) 2017-09-12 2017-09-12 一种混凝土梁的加固结构施工方法

Country Status (1)

Country Link
CN (3) CN110836023A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863708A (zh) * 2021-10-15 2021-12-31 河北雄安荣乌高速公路有限公司 一种混凝土梁跨的加固方法
CN114753668A (zh) * 2022-04-14 2022-07-15 江苏海洋大学 一种无粘结预应力钢丝绳加固砖砌体墙的施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103233431A (zh) * 2013-04-15 2013-08-07 南京联众建设工程技术有限公司 一种加固型涵洞
CN105625743A (zh) * 2016-02-24 2016-06-01 朱奎 带次梁的混凝土主梁加固结构
CN205369972U (zh) * 2016-01-15 2016-07-06 镇江中谊抗震科技股份有限公司 钢筋混凝土梁加固结构
CN105781139A (zh) * 2016-03-02 2016-07-20 叶香雄 承载力不够的楼板加固方法
CN106437193A (zh) * 2016-11-10 2017-02-22 叶香菲 大高度砖混房屋加固结构

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09273318A (ja) * 1996-04-04 1997-10-21 Fujita Corp 既存の鉄筋コンクリート、もしくは鉄骨鉄筋コンクリート構造物における柱・梁接合部の耐震補強構造
JP4027517B2 (ja) * 1998-10-28 2007-12-26 三菱化学株式会社 構造物の補強方法
KR100605387B1 (ko) * 2004-04-19 2006-07-31 (주)영광산업개발 콘크리트구조물 보강재 고정용 스틸와이어의 정착장치구
KR20060095149A (ko) * 2005-02-28 2006-08-31 이선구 임시 긴장 공법을 이용한 사하중/활하중 합성구조 시스템
CN201297042Y (zh) * 2008-11-14 2009-08-26 李延和 加固混凝土梁的体外预应力结构
CN101781936B (zh) * 2009-12-10 2012-10-03 中国建筑科学研究院 一种采用预应力碳纤维板加固梁的方法及装置
CN101994398B (zh) * 2010-10-15 2012-05-23 方远建设集团股份有限公司 混凝土结构钢板-frp复合加固方法
CN102182326B (zh) * 2011-04-02 2012-06-27 武汉大学 一种用于混凝土受弯构件的加固方法
CN203669406U (zh) * 2014-01-08 2014-06-25 周磊 一种增设预应力混凝土板加固结构

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103233431A (zh) * 2013-04-15 2013-08-07 南京联众建设工程技术有限公司 一种加固型涵洞
CN205369972U (zh) * 2016-01-15 2016-07-06 镇江中谊抗震科技股份有限公司 钢筋混凝土梁加固结构
CN105625743A (zh) * 2016-02-24 2016-06-01 朱奎 带次梁的混凝土主梁加固结构
CN105781139A (zh) * 2016-03-02 2016-07-20 叶香雄 承载力不够的楼板加固方法
CN106437193A (zh) * 2016-11-10 2017-02-22 叶香菲 大高度砖混房屋加固结构

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863708A (zh) * 2021-10-15 2021-12-31 河北雄安荣乌高速公路有限公司 一种混凝土梁跨的加固方法
CN114753668A (zh) * 2022-04-14 2022-07-15 江苏海洋大学 一种无粘结预应力钢丝绳加固砖砌体墙的施工方法

Also Published As

Publication number Publication date
CN107630564B (zh) 2020-04-10
CN107630564A (zh) 2018-01-26
CN110836023A (zh) 2020-02-25

Similar Documents

Publication Publication Date Title
CN100447338C (zh) 软土地基多孔双悬臂拱形桥结构及其施工方法
JP2013518199A (ja) 鋼合成桁橋の施工方法{ConstructionMethodofSteelCompositeGirderBridge}
JP4992042B2 (ja) プレキャスト横梁およびそれを用いた橋脚
CN104120647A (zh) 适合快速施工的节段拼装混凝土框架桥墩系统及施工方法
JP4281567B2 (ja) 既設橋脚基礎の補強構造および既設橋脚基礎の補強方法
KR100676627B1 (ko) 슬래브―기둥 접합부의 전단보강체 및 이를 이용한전단보강구조
CN107630564B (zh) 一种混凝土梁的加固结构施工方法
CN112982432A (zh) 一种预应力混凝土基坑支护结构及施工方法
JP2010281033A (ja) 組積造壁の補強工法及び組積造構造物。
KR101086643B1 (ko) 다수개의 강선을 인장부의 전단면에 배치한 프리스트레스트콘크리트거더
JP2006316495A (ja) 橋脚基礎構造とその施工方法
JP7028728B2 (ja) 基礎杭と基礎スラブの接合構造
KR20120100052A (ko) 유압잭을 이용한 측방유동교각 보정방법 및 세굴 보강구조
JP5528217B2 (ja) 橋台の補強方法
JP2010281034A (ja) 組積造壁の補強構造、及び組積造構造物
JP5165546B2 (ja) 橋梁用支保工の設置工法
CN103850259A (zh) 基坑支护体系的压顶梁标高处的水平内支撑及其施工方法
KR101131631B1 (ko) 다수개의 강선을 인장부의 전단면에 배치한 프리스트레스트콘크리트거더를 이용한 조립식교량시공방법
JP6886811B2 (ja) 基礎構造及び基礎構造の構築方法
EP2400063B1 (de) Gründungssystem
CN201095721Y (zh) 软土地基多孔双悬臂拱形桥结构
JP4219746B2 (ja) 軽量盛土構造体およびその施工方法
JP4215659B2 (ja) 鉄筋コンクリート部材の補強方法
KR101131629B1 (ko) 다수개의 강선을 인장부의 전단면에 배치한 프리스트레스트콘크리트거더의 제작방법
CN207032275U (zh) 一种内嵌式桁架外挑混凝土承台

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20200218