CN110747898A - Basement waterproof construction method - Google Patents

Basement waterproof construction method Download PDF

Info

Publication number
CN110747898A
CN110747898A CN201911012636.7A CN201911012636A CN110747898A CN 110747898 A CN110747898 A CN 110747898A CN 201911012636 A CN201911012636 A CN 201911012636A CN 110747898 A CN110747898 A CN 110747898A
Authority
CN
China
Prior art keywords
concrete cushion
basement
permanent wall
layer
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911012636.7A
Other languages
Chinese (zh)
Inventor
陈春荣
席新雅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI ORIENTAL YUHONG WATERPROOF ENGINEERING Co Ltd
Shanghai Oriental Rainbow Waterproof Technology Co Ltd
Original Assignee
SHANGHAI ORIENTAL YUHONG WATERPROOF ENGINEERING Co Ltd
Shanghai Oriental Rainbow Waterproof Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI ORIENTAL YUHONG WATERPROOF ENGINEERING Co Ltd, Shanghai Oriental Rainbow Waterproof Technology Co Ltd filed Critical SHANGHAI ORIENTAL YUHONG WATERPROOF ENGINEERING Co Ltd
Priority to CN201911012636.7A priority Critical patent/CN110747898A/en
Publication of CN110747898A publication Critical patent/CN110747898A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/665Sheets or foils impervious to water and water vapor

Abstract

The invention discloses a basement waterproof construction method, which comprises the following steps: 1) excavating a soil layer according to the designed elevation and combining with a field enclosing structure to form a basement pit structure with a slope on the side wall, and tamping; 2) paving a first concrete cushion layer at the bottom of the pit structure; 3) building a permanent wall at the edge of the concrete cushion; 4) filling backfill between the permanent wall and the side wall of the pit structure; 5) pouring a second concrete cushion layer on the upper part of the backfill according to the elevation requirement, so that the second concrete cushion layer is connected with the permanent wall and is level to the height; 6) paving self-adhesive film waterproof rolls on the surfaces of the first concrete cushion, the permanent wall and the second concrete cushion; 7) and pouring a structural bottom plate on the self-adhesive film waterproof coiled material. Providing reliable waterproof quality for the basement structure.

Description

Basement waterproof construction method
Technical Field
The invention belongs to the field of basement waterproof buildings, and particularly relates to a basement waterproof construction method.
Background
At present, the existing technologies of basement waterproofing methods are all universal, only the key points of the abiding of construction are shown, and no further targeted treatment method or construction process can be provided. In a construction project, when special geographic conditions or construction foundations are met, on-site conditions, construction experience of professionals, construction cases at home and abroad and argumentations of experts are often combined to conduct discussion to confirm a construction method, but the referential of most of the schemes of the special argumentations is not very large. If the inherent and favorable construction method which can be directly used is established for key and difficult parts in the common characteristics of the same type of basement waterproof structures, the cost is greatly reduced, and the quality and the controllability are improved.
Therefore, it is necessary to develop a basement waterproofing construction method to provide a basement structure with reliable waterproofing quality.
Disclosure of Invention
The invention aims to provide a basement waterproof construction method, which aims at key and difficult parts in common characteristics of basement waterproof structures of the same class to establish an inherent and favorable construction method capable of being directly used, reduce the cost and improve the construction quality and controllability.
In order to achieve the purpose, the invention provides a basement waterproof construction method, which comprises the following steps:
1) excavating a soil layer according to the designed elevation and combining with a field enclosing structure to form a basement pit structure with a slope on the side wall, and tamping;
2) laying a first concrete cushion layer at the bottom of the pit structure;
3) building a permanent wall at the edge of the concrete cushion;
4) filling backfill between the permanent walls and the side walls of the pit structure;
5) pouring a second concrete cushion layer on the upper part of the backfill soil according to the elevation requirement, so that the second concrete cushion layer is connected with the permanent wall and is level to the height;
6) paving self-adhesive film waterproof rolls on the surfaces of the first concrete cushion, the permanent wall and the second concrete cushion;
7) and pouring a structural bottom plate on the self-adhesive film waterproof coiled material.
Preferably, the step 3) is followed by: and paving a leveling layer on the inner wall of the permanent wall, wherein the leveling layer is a cement mortar layer, and the thickness of the leveling layer is 10-30 mm.
Preferably, the height of the permanent wall is equal to the sum of the structure thickness at the lowest design level and the net height of the side wall of the basement.
Preferably, the step 4) includes:
4.1) arranging an anti-overturning supporting structure at the inner side of the permanent wall;
4.2) filling backfill in layers;
4.3) waiting for natural sedimentation or adopting manual compaction after the filling is finished.
Preferably, the supporting structure is a scaffold or a tie bar.
Preferably, the backfill soil is pseudo-ginseng soil or dioctahsoil.
Preferably, the step 6) includes:
6.1) performing base layer cleaning on the surfaces of the first concrete cushion layer, the permanent wall and the second concrete cushion layer;
and 6.2) paving the self-adhesive film waterproof roll material by adopting a pre-paving and anti-sticking method, wherein a lap joint is formed between two adjacent self-adhesive film waterproof roll materials.
Preferably, the step 6) further comprises:
the lap joint of the self-adhesive film waterproof coiled material is provided with a fixing nail for fixing, or
And installing a weldable fixing sheet on the permanent wall, and welding the self-adhesive film waterproof coiled material on the weldable fixing sheet for fixing.
Preferably, the step 7) includes:
7.1) binding steel bars at the upper part of the first concrete cushion and the lower part of a construction joint of the permanent wall, and welding a water stop steel plate at the construction joint;
7.2) pouring the structural bottom plate at the upper part of the first concrete cushion layer and the lower part of the construction joint of the permanent wall;
7.3) binding steel bars on the upper parts of the construction joints of the permanent wall and the second concrete cushion;
7.4) carrying out inner formwork supporting treatment on the permanent wall;
7.5) pouring the upper part of the construction joint of the permanent wall and the structural bottom plate at the upper part of the second concrete cushion.
Preferably, the strength grade of the first concrete cushion layer and the second concrete cushion layer is not less than C15, and the thickness of the first concrete cushion layer and the second concrete cushion layer is at least 100 mm.
The invention has the beneficial effects that: by combining the characteristics of the self-adhesive film waterproof coiled material with the waterproof construction method, a structural joint is established for the waterproof of the special-shaped structure of the basement and the construction of structural concrete; a special-shaped structure waterproof construction method of a basement cushion part is built in a targeted manner; construction processes of waterproofing, civil engineering and the like of special-shaped structural parts are combed; outputting a processing mode when the cushion layer part has a special-shaped structure; aiming at key and difficult parts in the common characteristics of the same type of basement waterproof structures, an inherent and favorable construction method which can be directly used is established, the cost is reduced, and the construction quality and controllability are improved.
Additional features and advantages of the invention will be set forth in the detailed description which follows.
Drawings
The above and other objects, features and advantages of the present invention will become more apparent by describing in more detail exemplary embodiments thereof with reference to the attached drawings, in which like reference numerals generally represent like parts throughout.
Fig. 1 is a schematic view showing a waterproofing structure of a basement waterproofing construction method according to an embodiment of the present invention.
Fig. 2 shows a coil lap joint schematic diagram of a basement waterproofing construction method according to an embodiment of the invention.
Fig. 3 shows a coil fixing diagram of a basement waterproofing construction method according to an embodiment of the present invention.
Description of the reference numerals
1. A soil layer; 2. backfilling; 3. constructing a joint; 4. a first concrete cushion; 5. a structural floor; 6. a water stop steel plate; 7. a permanent wall; 8. self-adhesive film waterproof roll; 9. leveling layer; 10. a second concrete cushion; 11. a lap joint; 12. and (5) fixing the nail.
Detailed Description
Preferred embodiments of the present invention will be described in more detail below. While the following describes preferred embodiments of the present invention, it should be understood that the present invention may be embodied in various forms and should not be limited by the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the invention to those skilled in the art.
The basement waterproof construction method comprises the following steps:
1) excavating a soil layer according to the designed elevation and combining with a field enclosing structure to form a basement pit structure with a slope on the side wall, and tamping;
2) paving a first concrete cushion layer at the bottom of the pit structure;
3) building a permanent wall at the edge of the concrete cushion;
4) filling backfill between the permanent wall and the side wall of the pit structure;
5) pouring a second concrete cushion layer on the upper part of the backfill according to the elevation requirement, so that the second concrete cushion layer is connected with the permanent wall and is level to the height;
6) paving self-adhesive film waterproof rolls on the surfaces of the first concrete cushion, the permanent wall and the second concrete cushion;
7) and pouring a structural bottom plate on the self-adhesive film waterproof coiled material.
Specifically, by combining the characteristics of the self-adhesive film waterproof coiled material with the waterproof construction method, a structural joint is established for the waterproofing of the special-shaped structure of the basement and the construction of structural concrete; a special-shaped structure waterproof construction method of a basement cushion part is built in a targeted manner; construction processes of waterproofing, civil engineering and the like of special-shaped structural parts are combed; outputting a processing mode when the cushion layer part has a special-shaped structure; aiming at key and difficult parts in the common characteristics of the same type of basement waterproof structures, an inherent and favorable construction method which can be directly used is established, the cost is reduced, and the construction quality and controllability are improved.
Preferably, step 3) is followed by: and paving a leveling layer on the inner wall of the permanent wall, wherein the leveling layer is a cement mortar layer, and the thickness of the leveling layer is 10-30 mm.
Preferably, the height of the permanent wall is equal to the sum of the structural thickness at the lowest design elevation and the clear height of the side wall of the basement.
Preferably, step 4) comprises:
4.1) arranging an anti-overturning supporting structure at the inner side of the permanent wall;
4.2) filling backfill in layers;
4.3) waiting for natural sedimentation or adopting manual compaction after the filling is finished.
Preferably, the supporting structure is a scaffold or a tie bar.
Preferably, the backfill soil is pseudo-ginseng soil or dioctahsoil.
Preferably, step 6) comprises:
6.1) carrying out base layer cleaning on the surfaces of the first concrete cushion layer, the permanent wall and the second concrete cushion layer;
6.2) paving the self-adhesive film waterproof coiled material by adopting a pre-paving and anti-sticking method, and forming lap joint between two adjacent self-adhesive film waterproof coiled materials.
Preferably, step 6) further comprises:
the lap joint of the self-adhesive film waterproof coiled material is provided with a fixing nail for fixing, or
And installing a weldable fixing sheet on the permanent wall, and welding the self-adhesive film waterproof coiled material on the weldable fixing sheet for fixing.
Preferably, step 7) comprises:
7.1) binding steel bars at the upper part of the first concrete cushion and the lower part of a construction joint of the permanent wall, and welding a water stop steel plate at the construction joint;
7.2) pouring structural bottom plates at the upper part of the first concrete cushion layer and the lower part of the construction joint of the permanent wall;
7.3) binding steel bars on the upper part of the construction joint of the permanent wall and the upper part of the second concrete cushion;
7.4) carrying out inner formwork supporting treatment on the permanent wall;
7.5) pouring the structural bottom plate on the upper part of the construction joint of the permanent wall and the upper part of the second concrete cushion.
Specifically, when the steel bars are bound at the side walls, hard puncture of coiled materials at the side walls is avoided as much as possible; when the water-stopping steel plate is welded at the construction joint, proper protective measures are adopted for welding slag, and the damage to the high-polymer waterproof layer is avoided.
Preferably, the strength grade of the first concrete cushion layer and the second concrete cushion layer is not less than C15, and the thickness is at least 100 mm.
Examples
Fig. 1 is a schematic view showing a waterproofing structure of a basement waterproofing construction method according to the present embodiment; fig. 2 is a schematic diagram illustrating a roll lap joint of the basement waterproofing construction method according to the present embodiment; fig. 3 is a coil fixing diagram illustrating a waterproof construction method for a basement according to the embodiment.
As shown in fig. 1 to 3, the basement waterproofing construction method comprises the following steps:
(1) according to the design elevation, combining with a field enclosing structure, carrying out soil layer 1 excavation, combining the soil layer 1 excavation elevation with the lowest structure elevation requirement and the lowest second-layer structure elevation requirement, and carrying out certain slope relief treatment between the two layers according to the requirement to form a basement pit structure;
(2) tamping soil layers at the bottom and the side wall of the pit structure;
(3) performing construction treatment on the first concrete cushion 4 at the lower part of the structural layer at the lowest elevation according to the requirements of relevant specifications, wherein the strength grade of the first concrete cushion 4 is not less than C15, and the thickness of the first concrete cushion 4 is not less than 100mm (if the thickness of the first concrete cushion is not less than 150mm in a soft soil layer);
(4) building a permanent wall 7 at the position of the first concrete cushion 4 at the lowest elevation according to the requirement of the indoor space size, wherein the height of the permanent wall 7 is equal to the sum of the structural thickness at the lowest elevation and the net height of the side wall of the basement, and the permanent wall 7 can be built in two parts or can be built together;
(5) constructing a cement mortar leveling layer 9 with the thickness of 20mm on the inner wall and the top surface of the permanent wall 7 so as to paste the waterproof coiled material;
(6) according to the requirements, backfill soil 2 is filled between the outer side of the permanent wall 7 and the side wall of the pit structure, and a certain overturn-preventing treatment measure, such as scaffold steel pipe inclined support, is required to be adopted at the inner side of the permanent wall 7 during backfilling because the permanent wall 7 has a certain height, and the tie treatment between the outer side enclosing structure and the permanent wall can also be utilized during building of the permanent wall, and is similar to tie bars in brick walls;
(7) according to the requirement, gaps between the side walls of the layered backfill pit structure and the permanent walls 7 are filled with the backfill soil 2, wherein pseudo-ginseng soil or twenty-eight soil is adopted;
(8) after the backfill 2 is settled to a certain degree or is compacted manually to a certain degree, a second concrete cushion 10 is poured according to the elevation requirement;
(9) after the strength of the concrete cushion layer meets the requirement, performing base layer cleaning on the surfaces of the leveling layer 9 on the surfaces of the first concrete cushion layer 4 and the permanent wall 7 and the surface of the second concrete cushion layer 10;
(10) the paving construction of the macromolecule self-adhesive film waterproof coiled material 8 is carried out on the surfaces of the three parts, the material is carried out by adopting a pre-paving and reverse-adhering method, so that the smooth surface (namely the surface without the adhesive layer surface or the fine sand surface) of the material is only required to be directly contacted with the surface of the base layer; in order to prevent the permanent wall 7 from sliding downwards and ensure that the permanent wall and the vertical surface can have better fitting degree, fixing nails 12 are added on the inner layer surface of the overlapping edge 11 or a weldable fixing sheet is firstly constructed on the surface of the permanent wall vertical surface (arranged in a quincunx shape, the distance is not more than 1 meter) and then the smooth surface of a coiled material is welded on the weldable fixing sheet for proper fixing treatment;
(11) binding steel bars on the upper portion of the first concrete cushion 4 and the lower portion of the construction joint 3 of the permanent wall 7, and welding a water stop steel plate 6 at the construction joint 3, wherein when the steel bars are bound at the permanent wall 7, hard puncture of coiled materials at the permanent wall 7 is avoided as much as possible; when the water stop steel plate 6 is welded at the construction joint 3, appropriate protective measures are adopted for corresponding welding slag to avoid damage to the self-adhesive film waterproof coiled material 8;
(12) pouring a structural bottom plate 5 at the upper part of the first concrete cushion 4 and the lower part of the construction joint 3 of the permanent wall 7;
(13) steel bars on the upper parts of the construction joints 3 of the permanent wall 7 and the upper part of the second concrete cushion 10 are bound (whether the steel bars are bound together or not can be carried out according to the actual situation on site, and the steel bars on the upper parts of the construction joints of the permanent wall are bound generally firstly);
(14) carrying out inner formwork supporting treatment on the permanent wall 7;
(15) and pouring the upper part of the construction joint 3 of the permanent wall 7 and the structural bottom plate 5 at the upper part of the second concrete cushion 10 (whether the two are poured together or the structural bottom plate at the upper part of the construction joint of the permanent wall is poured firstly and then the structural bottom plate at the upper part of the second concrete cushion is poured, which is determined according to the actual situation on site).
Having described embodiments of the present invention, the foregoing description is intended to be exemplary, not exhaustive, and not limited to the embodiments disclosed. Many modifications and variations will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments.

Claims (10)

1. A basement waterproof construction method is characterized by comprising the following steps:
1) excavating a soil layer according to the designed elevation and combining with a field enclosing structure to form a basement pit structure with a slope on the side wall, and tamping;
2) laying a first concrete cushion layer at the bottom of the pit structure;
3) building a permanent wall at the edge of the concrete cushion;
4) filling backfill between the permanent walls and the side walls of the pit structure;
5) pouring a second concrete cushion layer on the upper part of the backfill soil according to the elevation requirement, so that the second concrete cushion layer is connected with the permanent wall and is level to the height;
6) paving self-adhesive film waterproof rolls on the surfaces of the first concrete cushion, the permanent wall and the second concrete cushion;
7) and pouring a structural bottom plate on the self-adhesive film waterproof coiled material.
2. The basement waterproofing construction method according to claim 1 further comprising, after the step 3): and paving a leveling layer on the inner wall of the permanent wall, wherein the leveling layer is a cement mortar layer, and the thickness of the leveling layer is 10-30 mm.
3. The basement waterproofing method according to claim 1 wherein the height of the permanent wall is equal to the sum of the structural thickness at the lowest design level and the clear height of the basement side wall.
4. The basement waterproofing construction method according to claim 1, wherein the step 4) includes:
4.1) arranging an anti-overturning supporting structure at the inner side of the permanent wall;
4.2) filling backfill in layers;
4.3) waiting for natural sedimentation or adopting manual compaction after the filling is finished.
5. The basement waterproofing construction method according to claim 4, wherein the support structure is a scaffold or tie bars.
6. The basement waterproofing construction method according to claim 1, wherein the backfill soil is pseudo-ginseng soil or dioctahas soil.
7. The basement waterproofing construction method according to claim 1, wherein the step 6) includes:
6.1) performing base layer cleaning on the surfaces of the first concrete cushion layer, the permanent wall and the second concrete cushion layer;
and 6.2) paving the self-adhesive film waterproof roll material by adopting a pre-paving and anti-sticking method, wherein a lap joint is formed between two adjacent self-adhesive film waterproof roll materials.
8. The basement waterproofing construction method according to claim 7, wherein the step 6) further comprises:
the lap joint of the self-adhesive film waterproof coiled material is provided with a fixing nail for fixing, or
And installing a weldable fixing sheet on the permanent wall, and welding the self-adhesive film waterproof coiled material on the weldable fixing sheet for fixing.
9. The basement waterproofing construction method according to claim 1, wherein the step 7) includes:
7.1) binding steel bars at the upper part of the first concrete cushion and the lower part of a construction joint of the permanent wall, and welding a water stop steel plate at the construction joint;
7.2) pouring the structural bottom plate at the upper part of the first concrete cushion layer and the lower part of the construction joint of the permanent wall;
7.3) binding steel bars on the upper parts of the construction joints of the permanent wall and the second concrete cushion;
7.4) carrying out inner formwork supporting treatment on the permanent wall;
7.5) pouring the upper part of the construction joint of the permanent wall and the structural bottom plate at the upper part of the second concrete cushion.
10. The waterproof construction method for the basement according to claim 1, wherein the strength grade of the first concrete cushion and the strength grade of the second concrete cushion are not less than C15, and the thickness of the first concrete cushion and the second concrete cushion is at least 100 mm.
CN201911012636.7A 2019-10-23 2019-10-23 Basement waterproof construction method Pending CN110747898A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911012636.7A CN110747898A (en) 2019-10-23 2019-10-23 Basement waterproof construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911012636.7A CN110747898A (en) 2019-10-23 2019-10-23 Basement waterproof construction method

Publications (1)

Publication Number Publication Date
CN110747898A true CN110747898A (en) 2020-02-04

Family

ID=69279540

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911012636.7A Pending CN110747898A (en) 2019-10-23 2019-10-23 Basement waterproof construction method

Country Status (1)

Country Link
CN (1) CN110747898A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482176A (en) * 2021-07-29 2021-10-08 青岛海发置业有限公司 Waterproof and anti-pulling-crack damage structure for outer vertical surface of deep foundation pit structure and construction method thereof
CN113653104A (en) * 2021-08-25 2021-11-16 中国建筑第八工程局有限公司 Waterproof structure at underground wall and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101914927A (en) * 2010-06-22 2010-12-15 中国建筑第二工程局有限公司 Waterproof system for basement bottom board and wall surface and construction method thereof
CN105714849A (en) * 2016-01-29 2016-06-29 中国华冶科工集团有限公司 Reverse construction method for adjacent high and low floors (bays) of basement
CN207079638U (en) * 2017-08-04 2018-03-09 上海建工七建集团有限公司 The waterproof construction of gravity dam retaining wall retaining design high-low bay sole plate
CN207620013U (en) * 2017-11-30 2018-07-17 上海东方雨虹防水技术有限责任公司 The waterproof construction at side wall position at a kind of basement permanent protection wall
CN207775945U (en) * 2017-12-05 2018-08-28 北京东方雨虹防水技术股份有限公司 A kind of bridging arrangement of Novel underground room bottom plate and side wall difference waterproof material
CN108661088A (en) * 2017-03-29 2018-10-16 中天建设集团有限公司 A kind of permanent drainage and step-down anti-floating construction method of basement
CN208907231U (en) * 2018-07-17 2019-05-28 浙江广厦建设职业技术学院 A kind of architectural engineering seepage in underground area waterproof construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101914927A (en) * 2010-06-22 2010-12-15 中国建筑第二工程局有限公司 Waterproof system for basement bottom board and wall surface and construction method thereof
CN105714849A (en) * 2016-01-29 2016-06-29 中国华冶科工集团有限公司 Reverse construction method for adjacent high and low floors (bays) of basement
CN108661088A (en) * 2017-03-29 2018-10-16 中天建设集团有限公司 A kind of permanent drainage and step-down anti-floating construction method of basement
CN207079638U (en) * 2017-08-04 2018-03-09 上海建工七建集团有限公司 The waterproof construction of gravity dam retaining wall retaining design high-low bay sole plate
CN207620013U (en) * 2017-11-30 2018-07-17 上海东方雨虹防水技术有限责任公司 The waterproof construction at side wall position at a kind of basement permanent protection wall
CN207775945U (en) * 2017-12-05 2018-08-28 北京东方雨虹防水技术股份有限公司 A kind of bridging arrangement of Novel underground room bottom plate and side wall difference waterproof material
CN208907231U (en) * 2018-07-17 2019-05-28 浙江广厦建设职业技术学院 A kind of architectural engineering seepage in underground area waterproof construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482176A (en) * 2021-07-29 2021-10-08 青岛海发置业有限公司 Waterproof and anti-pulling-crack damage structure for outer vertical surface of deep foundation pit structure and construction method thereof
CN113653104A (en) * 2021-08-25 2021-11-16 中国建筑第八工程局有限公司 Waterproof structure at underground wall and construction method thereof

Similar Documents

Publication Publication Date Title
CN110747899B (en) Basement waterproof construction method
CN105178357B (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN105862873A (en) Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit
CN113152882A (en) Mixed construction method for basement exterior wall formwork and hot-laid waterproof coiled material
CN106759439B (en) Tower crane foundation for foundation pit and construction method thereof
CN208933989U (en) A kind of tower-crane foundation structure
CN109235493A (en) Basement beam slab is backbreak and short formwork construction method in a kind of contrary sequence method
CN102653946A (en) Waterproof construction method for setting rubber waterstop at bottom of reinforced concrete raft foundation
CN110747898A (en) Basement waterproof construction method
CN104975614B (en) Shaped steel combination formula single side formwork strengthening construction engineering method
CN111042569A (en) Construction method for additionally building linear accelerator machine room in limited space of basement of hospital
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN113697640A (en) Finished hoistway of integrally assembled elevator added in existing multi-story building and construction method
CA2892704C (en) Reinforced blockwork construction method
CN107905609A (en) Underground people's air defense construction method
CN115387393A (en) Post-cast strip pre-sealing quick construction method
CN204645093U (en) Poured band of outer wall of basement advanced processing constructs
CN109667278B (en) Anti-cracking and anti-seepage construction method for arranging tower crane foundation under independent foundation of underground garage
CN212223970U (en) Prefabricated apron post-cast strip stagnant water temporary enclosed construction
RU2671019C1 (en) Method of establishing a standard foundation using ribbed slabs of ceilings (coverings)
CN210288465U (en) Assembled retaining wall post-cast strip plugging member
CN206768879U (en) A kind of poured band of outer wall of basement structure
CN214090002U (en) Basement outer wall post-cast strip is enclosed construction in advance
CN111501832B (en) Two-in-one underground pipe gallery construction method and two-in-one underground pipe gallery structure
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200204

RJ01 Rejection of invention patent application after publication