CN110725208A - 一种墩顶叠合梁无支架架设的施工方法 - Google Patents
一种墩顶叠合梁无支架架设的施工方法 Download PDFInfo
- Publication number
- CN110725208A CN110725208A CN201910875239.6A CN201910875239A CN110725208A CN 110725208 A CN110725208 A CN 110725208A CN 201910875239 A CN201910875239 A CN 201910875239A CN 110725208 A CN110725208 A CN 110725208A
- Authority
- CN
- China
- Prior art keywords
- section steel
- crane
- section
- erecting
- steel beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种墩顶叠合梁无支架架设的施工方法,先是利用履带吊拼装主塔墩顶的0#节段钢梁及桥面板,然后继续用履带吊在0#节段钢梁上拼装第一台架梁吊机并调试取证,接着用第一台架梁吊机吊装架设0#节段钢梁左右两端的1#节段钢梁并张拉斜拉索;第一台架梁吊机向0#节段钢梁一端的1#节段钢梁走行到位并锚固,然后在0#节段钢梁另一端的1#节段钢梁上吊装第二台架梁吊机构件并拼装;第二台架梁吊机调试取证后完成墩顶梁段架设。本发明具有能在没有墩旁支架辅助的情况下完成墩顶三节段叠合梁的架设、不需要投入墩旁支架及顶推相关设备以节省临时钢结构和机械设备的投入、工程进度快、施工难度小、成本投入较小、更绿色环保的优点。
Description
技术领域
本发明涉及大桥施工方法,尤其是涉及一种在不设置墩旁支架的情况下架设墩顶三节段(包括一节段0号块和两节段1号块)叠合梁的施工方法。
背景技术
随着我国经济的迅速发展,桥梁技术的进步,在我国江河湖面上修建的大跨度桥梁也随之增多,尤其是斜拉桥因为其美观、经济而应用广泛。叠合梁斜拉桥用钢量少,逐渐成为了斜拉桥上部结构的主流。
主塔墩顶三节段作为斜拉桥上部结构架设的起始端,架梁吊机需要依托其才能形成双悬臂正常架设。传统的施工工法为在主塔墩旁设置落地支架作为0号和1号节段的施工平台,采用吊机进行墩顶三节段叠合梁的架设,纵横向顶推到设计位置;然后分别在两个1号节段上拼装架梁吊机,地进行后续双悬臂架设施工。此法需要提前投入墩旁支架以及顶推相关设备,费用投入较高。因此需要研究一种节省支架和设备投入的新型施工方法。
发明内容
本发明的目的在于提供一种无需设置墩旁支架架设墩顶三节段叠合梁的施工方法,即在没有墩旁支架辅助的情况下完成墩顶三节段叠合梁的架设,以节省临时钢结构和机械设备的投入。
本发明的目的是这样实现的:
一种墩顶叠合梁无支架架设的施工方法,特征是:具体步骤如下:
A、钢梁和桥面板在工厂加工完成后运输至施工现场,用履带吊进行墩顶的0#节段钢梁架设,调整好标高和平面位置后,施工临时锚固;在0#节段钢梁上吊装0#节段桥面板,并浇筑相邻两块0#节段桥面板之间的湿接缝;
B、利用履带吊在0#节段钢梁上拼装第一台架梁吊机,拼装完成后锚固于0#节段钢梁上,调试取证;
C、利用拼装好的第一台架梁吊机分别在0#节段钢梁的左右两端各架设一个1#节段钢梁,并在两个1#节段钢梁上铺设1#节段桥面板,并浇筑相邻两块1#节段桥面板之间的湿接缝,张拉斜拉索;
D、第一台架梁吊机向一侧的1#节段钢梁走行至设计位置并锚固,利用第一台架梁吊机起吊第二台架梁吊机构件,在另一侧的1#节段钢梁上设计位置拼装第二台架梁吊机;
E、第二台架梁吊机调试取证,两台架梁吊机对称拼装剩余叠合梁,墩顶梁端架设完成。
本发明先是利用履带吊拼装主塔墩顶的0#节段钢梁及桥面板,然后继续用履带吊在0#节段钢梁上拼装第一台架梁吊机并调试取证,接着用第一台架梁吊机吊装架设0#节段钢梁左右两端的1#节段钢梁并张拉斜拉索;第一台架梁吊机向0#节段钢梁一端的1#节段钢梁走行到位并锚固,然后在0#节段钢梁另一端的1#节段钢梁上吊装第二台架梁吊机构件并拼装;第二台架梁吊机调试取证后完成墩顶梁段架设。
本发明具有能在没有墩旁支架辅助的情况下完成墩顶三节段叠合梁的架设、不需要投入墩旁支架及顶推相关设备以节省临时钢结构和机械设备的投入、工程进度快、施工难度小、成本投入较小、更绿色环保的优点。
附图说明
图1为本发明的施工步骤A示意图;
图2为本发明的施工步骤B示意图;
图3为本发明的施工步骤C示意图;
图4为本发明的施工步骤D示意图;
图5为本发明的施工步骤E示意图。
具体实施方式
下面结合实施例对本发明作进一步详细说明。
一种墩顶叠合梁无支架架设的施工方法,具体步骤如下:
A、钢梁和桥面板在工厂加工完成后运输至施工现场,用350t履带吊1进行墩顶0#节段钢梁2架设,地面标高+2.000m,梁面标高48.010m,采用72m主臂进行吊装作业;分别将0#节段钢梁2的纵梁、横梁、小纵梁以及稳流板吊装至设计位置并用高强螺栓连接;0#节段钢梁2安装好并调整好标高和平面位置后,施工临时锚固;在0#节段钢梁2上吊装0#节段桥面板3,并浇筑相邻两块0#节段桥面板3之间的湿接缝;
B、利用350t履带吊1在0#节段钢梁2上拼装第一台架梁吊机4,采用散件拼装;拼装完成后锚固于0#节段钢梁2上,调试取证;
C、利用拼装好的第一台架梁吊机4分别在0#节段钢梁2的左右两端分别架设1#节段钢梁5、1#节段钢梁6,并在1#节段钢梁5、1#节段钢梁6上铺设1#节段桥面板3,浇筑相邻两块两个1#节段面板3之间的湿接缝,张拉斜拉索7,即:第一台架梁吊机先在0#节段钢梁2的左侧吊装1#节段钢梁5,第一台架梁吊机回转180°在0#节段钢梁2的右侧再吊装1#节段钢梁6,在1#节段钢梁5、1#节段钢梁6上铺设1#节段桥面板3;第一次对称张拉斜拉索7,施工浇筑相邻两块1#节段面板3之间的湿接缝,待湿接缝达到设计强度,第二次张拉斜拉索7;
D、第一台架梁吊机4向左侧的1#节段钢梁5走行至设计位置并锚固,利用第一台架梁吊机4起吊第二台架梁吊机8构件,在右侧的1#节段钢梁6上设计位置拼装第二台架梁吊机8;
E、第二台架梁吊机8调试取证,第一台架梁吊机4、第二台架梁吊机8对称拼装剩余叠合梁,墩顶梁端架设完成。
Claims (1)
1.一种墩顶叠合梁无支架架设的施工方法,其特征在于:具体步骤如下:
A、钢梁和桥面板在工厂加工完成后运输至施工现场,用履带吊进行墩顶的0#节段钢梁架设,调整好标高和平面位置后,施工临时锚固;在0#节段钢梁上吊装0#节段桥面板,并浇筑相邻两块0#节段桥面板之间的湿接缝;
B、利用履带吊在0#节段钢梁上拼装第一台架梁吊机,拼装完成后锚固于0#节段钢梁上,调试取证;
C、利用拼装好的第一台架梁吊机分别在0#节段钢梁的左右两端各架设一个1#节段钢梁,并在两个1#节段钢梁上铺设1#节段桥面板,并浇筑相邻两块1#节段桥面板之间的湿接缝,张拉斜拉索;
D、第一台架梁吊机向一侧的1#节段钢梁走行至设计位置并锚固,利用第一台架梁吊机起吊第二台架梁吊机构件,在另一侧的1#节段钢梁上设计位置拼装第二台架梁吊机;
E、第二台架梁吊机调试取证,两台架梁吊机对称拼装剩余叠合梁,墩顶梁端架设完成。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910875239.6A CN110725208A (zh) | 2019-09-17 | 2019-09-17 | 一种墩顶叠合梁无支架架设的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910875239.6A CN110725208A (zh) | 2019-09-17 | 2019-09-17 | 一种墩顶叠合梁无支架架设的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110725208A true CN110725208A (zh) | 2020-01-24 |
Family
ID=69219038
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910875239.6A Pending CN110725208A (zh) | 2019-09-17 | 2019-09-17 | 一种墩顶叠合梁无支架架设的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110725208A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112695649A (zh) * | 2020-12-18 | 2021-04-23 | 中铁大桥局集团有限公司 | 一种滩地大跨度斜拉桥钢桁梁整节段对称双悬臂架设方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2693492A1 (fr) * | 1992-07-10 | 1994-01-14 | Dumez | Pont haubanné et son procédé de réalisation. |
CN103437300A (zh) * | 2013-07-11 | 2013-12-11 | 中铁大桥局股份有限公司 | 墩顶钢梁无墩旁托架架设双悬臂的施工方法 |
CN104594201A (zh) * | 2014-12-16 | 2015-05-06 | 中铁大桥局集团有限公司 | 一种利用单侧墩旁托架架设墩顶钢梁的方法 |
CN104652283A (zh) * | 2015-01-09 | 2015-05-27 | 中铁港航局集团有限公司 | 斜拉桥钢主梁架梁吊机对称拼装的异步拼装施工方法 |
CN108149560A (zh) * | 2017-12-25 | 2018-06-12 | 中交路桥华南工程有限公司 | 叠合梁节段及其现场拼装方法 |
WO2018133045A1 (zh) * | 2017-01-20 | 2018-07-26 | 中国铁建大桥工程局集团有限公司 | 一种自锚式悬索桥安装方法 |
CN109972517A (zh) * | 2017-12-27 | 2019-07-05 | 中交第二航务工程局有限公司 | 一种钢混结合梁斜拉桥主梁的施工方法 |
-
2019
- 2019-09-17 CN CN201910875239.6A patent/CN110725208A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2693492A1 (fr) * | 1992-07-10 | 1994-01-14 | Dumez | Pont haubanné et son procédé de réalisation. |
CN103437300A (zh) * | 2013-07-11 | 2013-12-11 | 中铁大桥局股份有限公司 | 墩顶钢梁无墩旁托架架设双悬臂的施工方法 |
CN104594201A (zh) * | 2014-12-16 | 2015-05-06 | 中铁大桥局集团有限公司 | 一种利用单侧墩旁托架架设墩顶钢梁的方法 |
CN104652283A (zh) * | 2015-01-09 | 2015-05-27 | 中铁港航局集团有限公司 | 斜拉桥钢主梁架梁吊机对称拼装的异步拼装施工方法 |
WO2018133045A1 (zh) * | 2017-01-20 | 2018-07-26 | 中国铁建大桥工程局集团有限公司 | 一种自锚式悬索桥安装方法 |
CN108149560A (zh) * | 2017-12-25 | 2018-06-12 | 中交路桥华南工程有限公司 | 叠合梁节段及其现场拼装方法 |
CN109972517A (zh) * | 2017-12-27 | 2019-07-05 | 中交第二航务工程局有限公司 | 一种钢混结合梁斜拉桥主梁的施工方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112695649A (zh) * | 2020-12-18 | 2021-04-23 | 中铁大桥局集团有限公司 | 一种滩地大跨度斜拉桥钢桁梁整节段对称双悬臂架设方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108330842B (zh) | 一种大跨度钢混组合梁架设施工的架桥机及施工方法 | |
CN110042769B (zh) | 一种组合梁斜拉桥辅助跨全悬臂拼装施工方法 | |
CN102154988B (zh) | 大跨度钢箱叠拱桥先梁后拱的施工方法 | |
KR20140084107A (ko) | 셀프-런칭 이동식 비계공법 | |
CN111254836A (zh) | 山区大跨径钢混组合梁现场拼装及架桥机架设施工方法 | |
CN110042768A (zh) | 一种组合梁斜拉桥主梁双节段循环施工方法 | |
CN110700103B (zh) | 一种连续性组合梁施工方法 | |
CN103882812A (zh) | 斜拉索桥中跨主梁的施工方法 | |
CN113638304B (zh) | 混凝土梁式桥隐盖梁结构体系及其施工方法 | |
CN106939553A (zh) | 一种钢桥面和钢箱拱肋安装方法 | |
WO2024148715A1 (zh) | 一种连续钢桁梁桥的架设方法 | |
CN114892552A (zh) | 一种箱梁式桥梁改造施工方法 | |
CN109629449B (zh) | 一种钢箱拱桥拱脚钢混结合段安装定位支架及对位方法 | |
CN110820519A (zh) | 一种便于快速施工的隧间拱桥及其施工方法 | |
CN112144413B (zh) | 一种山区钢混组合梁整跨原位拼装架设方法 | |
CN112160246B (zh) | 组合梁安装方法 | |
CN110725208A (zh) | 一种墩顶叠合梁无支架架设的施工方法 | |
CN112458879A (zh) | 一种栓焊混连的分段预制装配式组合梁及其施工方法 | |
CN104775363A (zh) | 上塔柱钢筋节段的组拼方法 | |
CN111851307A (zh) | 一种大跨径预制装配式波形腹板组合箱梁运架施工方法 | |
CN111877169A (zh) | 一种无支架无大型吊机架设陆地重型端横梁的施工方法 | |
CN109371859A (zh) | 一种加固大跨箱梁桥的内置桁架拱结构及其施工方法 | |
CN105088962A (zh) | 一种波形钢腹板部件的整体吊装方法 | |
CN212611918U (zh) | 一种钢板梁的连接结构 | |
CN211472128U (zh) | 一种连续性组合梁 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20200124 |