CN110705837A - Visual engineering construction management system and construction method thereof - Google Patents

Visual engineering construction management system and construction method thereof Download PDF

Info

Publication number
CN110705837A
CN110705837A CN201910859257.5A CN201910859257A CN110705837A CN 110705837 A CN110705837 A CN 110705837A CN 201910859257 A CN201910859257 A CN 201910859257A CN 110705837 A CN110705837 A CN 110705837A
Authority
CN
China
Prior art keywords
database
engineering
project
construction
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910859257.5A
Other languages
Chinese (zh)
Inventor
廖建新
虎永辉
马树清
张勇
李新淼
肖子豪
郭金涛
詹健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges Projects Development Co Ltd CTG
Original Assignee
China Three Gorges Projects Development Co Ltd CTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges Projects Development Co Ltd CTG filed Critical China Three Gorges Projects Development Co Ltd CTG
Priority to CN201910859257.5A priority Critical patent/CN110705837A/en
Publication of CN110705837A publication Critical patent/CN110705837A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/21Design, administration or maintenance of databases
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/26Visual data mining; Browsing structured data
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Databases & Information Systems (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • General Engineering & Computer Science (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The construction method of the visual engineering construction management system comprises a project engineering quantity database, a visual engineering construction management system and a visual engineering construction management system, wherein the project engineering quantity database is generated by inputting engineering design parameter conditions approved by project establishment and is used for constructing an engineering 3D model; completing the project quantity database, and recording and forming by project construction units according to actual construction completion conditions; a project amount audit database; a project progress database; a construction design support database; monitoring a database; submitting the data to a database; a material supply database; and the display equipment is used for intuitively displaying the data of each database in the engineering 3D model by using a chart, a line or different colors after the data of each database is processed by a computer to form a visual management interface. The invention effectively avoids the situation that workers of other departments and posts can not deeply know the actual situation of the field engineering construction except the personnel directly responsible for the engineering project construction, and solves various problems in the traditional engineering construction management.

Description

Visual engineering construction management system and construction method thereof
Technical Field
The invention belongs to the field of engineering construction management, and particularly relates to a visual engineering construction management system and a construction method thereof.
Background
In the current engineering construction management work, the investors are affected by different work division, and besides the personnel directly responsible for engineering project construction, the workers of other departments and posts do not know the actual situation of the field engineering construction deeply. If the person who is directly responsible for the engineering project construction leaves the management post, the continued manager can not deeply solve the whole engineering project construction, so that the engineering acceleration progress meets the contract requirement under the condition that the progress is delayed due to the management work of the aspects of the progress, the fund payment, the data submission, the design field technical support, the material supply and the like of the engineering project construction, and the problems of excessive fund payment in the current period, incomplete submission of acceptance data of the engineering project construction of the part for completing the fund payment, design field technical support delayed annual plan, unnecessary driving events for completing the engineering project construction according to the period, disorder of normal fund raising plan and the like are caused. Therefore, a large amount of manpower and material resources are needed to supplement and perfect related procedure data again in the later-stage completion of project acceptance, excess project construction fund deduction, excess project construction fund interest, and increased project investment caused by the fact that project construction units move to other uses after purchasing materials, and finally a series of problems that project acceptance, project investment increase, project construction investing credit influence and the like are affected due to the fact that fund acceptance exceeds the contract amount and are difficult to deduct can occur.
Disclosure of Invention
In order to solve the technical problems, the invention provides a visual engineering construction management system and a construction method thereof, which realize the functions of full-period visual management and full-person supervision of engineering construction. The situation that workers at other departments and posts can not deeply know the actual situation of the field engineering construction except the personnel directly responsible for the engineering project construction is effectively avoided, and various problems in the traditional engineering construction management are solved.
The technical scheme adopted by the invention is as follows:
visual engineering construction management system includes:
the project engineering quantity database is input and generated according to project setting approved engineering design parameter conditions and is used for constructing an engineering 3D model;
completing the project quantity database, and recording and forming by project construction units according to actual construction completion conditions;
the project amount auditing database is generated after the third-party project supervision unit and the project investor complete the project amount database 3 in sequence;
the project progress database is generated by inputting after a project supplier decomposes according to a project construction plan and an annual construction plan, and is used for controlling the project investment cost and checking project construction units and design units;
the construction design support database is generated by inputting design data provided by a design unit stage in a dynamic engineering design project;
the monitoring database is generated by recording engineering quality and safety monitoring data after field acquisition;
the data submitting database is used for recording and generating important field record data and engineering construction management control charts of various inspections and acceptance in the project construction process completed by a project construction unit;
the material supply database comprises material materials which are acquired by a project supplier according to a progress plan and delivered to project construction units for project construction, and the material materials are input and generated by project investors according to the receiving conditions of the project construction units;
the financial payment database is used for financial staff to determine whether to pay construction cost of project construction units according to a finished engineering quantity database, an engineering quantity auditing database, a data submitting database and engineering progress database data according to construction contract agreement and cost composition;
the project approximate calculation database comprises total investment calculated by a project supplier after comprehensively considering the project scale, the construction period and the market price expansion factor;
the engineering construction management control chart is generated by forming the data to be filed in the operation process of each component into a uniform format according to the requirements of project investors;
and the display equipment is used for intuitively displaying the data of each database in the engineering 3D model by using a chart, a line or different colors after the data of each database is processed by a computer to form a visual management interface.
The system also comprises an input device and an output device, and the input device and the output device are used for printing or exporting the engineering construction management control chart generated according to the data recorded in each database.
The engineering 3D model, the project engineering quantity database, the finished engineering quantity database, the engineering quantity auditing database, the financial payment database, the engineering progress database, the construction design support database, the monitoring database, the data submission database, the material supply database, the engineering approximate calculation database and the engineering construction management control chart can be independently matched with a display device, an input device, an output device and a computer to realize visual engineering construction management; or compiling all the components into a system and realizing visual engineering construction management based on the cooperation of display equipment, input equipment, output equipment and a computer.
The construction design support database, the data submission database, the material supply database and the project approximate calculation database are decomposed according to a progress plan in the project progress database, and then a relation is established corresponding to the project quantity completed in the project quantity database, so that project engineering construction management is completed according to the plan.
Aiming at the construction of large-scale dynamically designed engineering projects, a construction design support database is added, and the construction design field support service work is concretized, quantized and visualized through the mutual correlation of the construction design support database, an engineering progress database, an engineering quantity auditing database and a financial payment database, so that the construction design field support service work and the field engineering project construction completion condition are closely correlated in the construction management of the engineering projects, the design technical service work check is facilitated, and the design service fee is prevented from exceeding the budget.
A project budget database can be added to facilitate project investment expenditure control, and the visualization of the total fund use condition of a project is beneficial to fund control and overall management of investment fund payment and financing.
The construction method of the visual engineering construction management system comprises the following steps:
s1, construction of an engineering 3D model: establishing an engineering 3D model consistent with an engineering construction project on a computer through a display device, an input device and an output device by utilizing a project engineering quantity database;
s2, database construction: according to the requirements of engineering construction management, a finished engineering quantity database, an engineering quantity auditing database, a financial payment database, an engineering progress database, a construction design support database, a monitoring database, a data submission database, a material supply database, an engineering approximate calculation database and an engineering construction management control chart are established on a computer through display equipment, input equipment and output equipment;
s3, establishing a relation between the database and the engineering 3D model: after the construction of the engineering quantity database, the engineering quantity auditing database, the financial payment database, the engineering progress database, the construction design support database, the monitoring database, the data submission database, the material supply database, the engineering approximate calculation database and the engineering construction management control chart is completed, the engineering quantity auditing database and the engineering construction management control chart are correlated with the engineering 3D model, so that the data of each database can be smoothly reflected and expressed on the engineering 3D model by different colors or lines;
s4, visualization management: and after the data of each database is reflected and expressed on the engineering 3D model in different colors or lines, displaying the engineering 3D model on display equipment to realize data visualization, and timely adjusting or correcting engineering construction management aiming at the data displayed on the display equipment.
The invention discloses a visual engineering construction management system and a construction method thereof, and the technical effects are as follows:
1: the engineering 3D model is established by utilizing the design workload database through the computer, and the data of the finished engineering workload database, the financial payment database, the engineering workload auditing database, the progress plan database, the engineering progress database and the material supply database are reflected on the engineering 3D model after being processed by the computer, so that the visual management of the engineering construction such as the completion progress of the field engineering, the completion of the engineering workload, the capital expenditure, the support of the field design technology and the like is realized.
: the method solves the problem that other managers except the site specific responsible person cannot master the conditions of engineering construction progress, fund payment, data submission, material consumption and the like completely or not know in the original engineering construction management work, realizes the effect of monitoring the whole engineering construction period visual management by the visual engineering construction management method, and is particularly suitable for large-scale engineering construction management which is approved for construction and needs dynamic design in construction.
: the engineering construction management system is particularly suitable for large-scale engineering construction management needing dynamic design, visual management of various engineering construction key links such as engineering progress, design technical support, capital payment and the like is realized by adding a construction design support database, a monitoring database, a material supply database and an engineering approximate calculation database and decomposing the data into field engineering project construction according to a progress plan so as to enable the data to correspond to the actual finished engineering quantity, concretization, quantization and visual management of the design technical support is realized, scientific data support is provided for the management work of key links such as main control indexes such as timely correcting engineering construction management progress deviation, adjusting engineering investment capital financing plan and material supply plan, ensuring engineering project quality safety and the like, and the final aim of fine control management of engineering construction is realized.
Drawings
FIG. 1 is a schematic diagram of the system of the present invention.
Detailed Description
As shown in fig. 1, the visual engineering construction management system includes:
and the project engineering quantity database 2 is input and generated according to project setting approved engineering design parameter conditions and is used for constructing the project 3D model 1.
The completion project amount database 3 is formed by inputting project construction units according to actual construction completion conditions and is one of important bases for judging whether to pay the project cost by the financial payment database 5.
And the engineering quantity auditing database 4 is generated after the third-party engineering supervision unit and the project investor complete the engineering quantity database 3 in sequence, and the engineering quantity auditing database 4 is one of important bases for judging whether to pay engineering expenses by the financial payment database 5.
And the project progress database 6 is generated by inputting after the project investor decomposes according to the project construction plan and the annual construction plan, and is used for controlling the project investment cost and checking the project construction unit and the design unit. The method is an important part for controlling the project investment cost and checking the work of project construction units and design units by a project supplier in a visual project construction management system.
A construction design support database 7 which is generated by inputting design data provided according to the stage of a design unit in a dynamic design project of the engineering; the project construction system is a precondition for project construction units to complete project construction according to annual plans, and is a key part of project investor assessment design technology service conditions in the project construction visual management system.
The monitoring database 8 is generated by recording various monitoring data of engineering quality, safety and the like after field acquisition, and is a key component for controlling the problems of engineering quality, safety and the like in the visual management method of engineering construction. The data submission database 9 is generated by recording important field records such as inspection and acceptance of each item in the process of completing the project construction by a project construction unit, and is one of important bases for judging whether to pay the project cost by the financial payment database 5.
The data submitting database 9 is generated by recording important field record data of various inspection and acceptance in the project construction process completed by a project construction unit and an engineering construction management control chart 12.
The material supply database 10 comprises material materials which are acquired and purchased by project investors according to a progress plan and are delivered to project construction units for use in project construction, is one of important embodiment modes of fund payment in the project construction process, is input and generated by the project investors according to the utilization conditions of the project construction units, and is one of important links for controlling investment in the project.
The financial payment database 5 is used for financial staff to determine whether to pay construction cost of project construction units according to the data of the finished engineering quantity database 3, the engineering quantity auditing database 4, the data submitting database 9 and the engineering progress database 6 according to construction contract agreement and cost composition. The financial payment database 5 is a database for the financial staff to pay the construction cost of the project construction unit according to the finished project amount database 3, the project amount auditing database 4, the data submitting database 9 and the project progress database 6 according to the construction contract agreement and the cost in the visual project construction management system.
The project approximate calculation database 11 comprises the total investment calculated by the project investor after comprehensively considering the project scale, the construction period and the market price expansion factor; is a core element for controlling the construction of engineering projects, and the total investment of the engineering is controlled according to the approximate amount.
The engineering construction management control chart 12 is generated after the data to be filed in the operation process of each component part forms a uniform format according to the requirements of project investors, and is convenient to print into a book face file after follow-up.
And the display device 13 is used for visually displaying each database data in the engineering 3D model 1 in a chart, a line or different colors after the database data is processed by the computer 15 to form a visual management interface.
The system also includes an input device and an output device 14 for printing or exporting the engineering construction management control chart 12 generated from the respective database entry data. The computer 15 is the basis for generating the engineering 3D model and each database and realizing visualization on the display equipment 13 according to requirements; the display device 13 is a main device for visually displaying the processing result of the computer 15 for viewing; all the components are mutually matched and act together to realize the visual management of engineering construction.
The engineering 3D model 1, the project engineering quantity database 2, the finished engineering quantity database 3, the engineering quantity auditing database 4, the financial payment database 5, the engineering progress database 6, the construction design support database 7, the monitoring database 8, the data submission database 9, the material supply database 10, the engineering approximate calculation database 11 and the engineering construction management control chart 12 can be independently based on the matching of display equipment, input equipment, output equipment and a computer to realize visual engineering construction management; or compiling all the components into a system and realizing visual engineering construction management based on the cooperation of display equipment, input equipment, output equipment and a computer.
In the preferred scheme, each component can be added or supplemented with a database according to the characteristics of the engineering project and the investor, so that the construction management of the engineering project is facilitated.
In a preferred scheme, the construction design support database 7, the data submission database 9, the material supply database 10 and the project approximate calculation database 11 are decomposed according to a progress plan in the project progress database 6, and then a relationship is established corresponding to the project quantity completed in the project quantity completion database 3, so that project engineering construction management is promoted and completed according to the plan.
In an optimal scheme, a construction design support database is added aiming at the construction of a large-scale dynamically designed engineering project, the construction design field support service work is specified, quantized and visualized through the mutual correlation of the construction design support database, an engineering progress database 6, an engineering quantity auditing database 4 and a financial payment database 5, the construction design field support service work and the field engineering project construction completion condition are closely correlated in the construction management of the engineering project, the design technical service work check is facilitated, and the design service fee is prevented from exceeding the budget.
In a preferred scheme, a project budget database is added to facilitate project investment expenditure control, and the visualization of the total fund use condition of the project is beneficial to fund control and overall planning management of investment fund payment and financing.
The construction method of the visual engineering construction management system comprises the following steps:
s1, construction of the engineering 3D model 1: establishing an engineering 3D model 1 consistent with an engineering construction project on a computer 15 through a display device 13, an input device and an output device 14 by using a project engineering quantity database 2;
s2, database construction: according to the requirements of engineering construction management, a finished engineering quantity database 3, an engineering quantity auditing database 4, a financial payment database 5, an engineering progress database 6, a construction design support database 7, a monitoring database 8, a data submission database 9, a material supply database 10, an engineering approximate calculation database 11 and an engineering construction management control chart 12 are established on a computer 15 through a display device 13, an input device and an output device 14;
s3, establishing a relation between the database and the engineering 3D model 1: after the construction of the engineering quantity database 3, the engineering quantity auditing database 4, the financial payment database 5, the engineering progress database 6, the construction design support database 7, the monitoring database 8, the data submission database 9, the material supply database 10, the engineering approximate calculation database 11 and the engineering construction management control chart 12 is completed, the data are correlated with the engineering 3D model 1, so that the data of each database can be smoothly reflected and expressed on the engineering 3D model 1 by different colors or lines;
s4, visualization management: and after the data of each database is reflected and expressed on the engineering 3D model 1 in different colors or lines, displaying the engineering 3D model 1 on the display equipment 13 to realize data visualization, and timely adjusting or correcting engineering construction management aiming at the data displayed on the display equipment 13.

Claims (7)

1. Visual engineering construction management system, its characterized in that includes:
the project engineering quantity database (2) is input and generated according to project setting approved engineering design parameter conditions and is used for constructing a project 3D model (1);
a completion engineering quantity database (3) is formed by recording project construction units according to the actual completion condition of construction;
the project amount auditing database (4) is generated after the project amount database (3) is audited and finished by a third-party project supervision unit and a project sponsor;
the project progress database (6) is generated by the project supplier after being decomposed according to the project construction plan and the annual construction plan and is used for controlling the project investment cost and checking the project construction unit and the design unit;
a construction design support database (7) which is generated by inputting design data provided according to a design unit stage in a dynamic engineering design project;
the monitoring database (8) is generated by recording engineering quality and safety monitoring data after field acquisition;
the data submitting database (9) is used for recording and generating various inspection acceptance important field record data and engineering construction management control charts (12) in the project construction process completed by a project construction unit;
the material supply database (10) comprises material materials which are acquired and purchased by a project supplier according to a progress plan and are delivered to project construction units for project construction, and the material materials are input and generated by project investors according to the receiving conditions of the project construction units;
the financial payment database (5) is used for financial staff to determine whether to pay construction cost of project construction units according to the data of the finished engineering quantity database (3), the engineering quantity auditing database (4), the data submitting database (9) and the engineering progress database (6) according to construction contract agreement and cost composition;
the project approximate calculation database (11) comprises total investment calculated by a project investor after comprehensive consideration according to the project scale, the construction period and the market price expansion factor;
the engineering construction management control chart (12) is generated after the data needing to be filed in the operation process of each component part form a uniform format according to the requirements of project investors;
and the display device (13) is used for intuitively displaying each database data in the engineering 3D model (1) in a chart, a line or different colors after the database data are processed by the computer (15) to form a visual management interface.
2. The visual engineering construction management system according to claim 1, characterized in that:
the system also includes input and output devices (14) for printing or exporting the engineering construction management control chart (12) generated from the respective database entry data.
3. The visual engineering construction management system according to claim 1, characterized in that: the engineering 3D model (1), the project engineering quantity database (2), the finished engineering quantity database (3), the engineering quantity auditing database (4), the financial payment database (5), the engineering progress database (6), the construction design support database (7), the monitoring database (8), the data submitting database (9), the material supply database (10), the engineering approximate calculation database (11) and the engineering construction management control chart (12) can be independently based on the cooperation of display equipment, input equipment, output equipment and a computer to realize visual engineering construction management; or compiling all the components into a system and realizing visual engineering construction management based on the cooperation of display equipment, input equipment, output equipment and a computer.
4. The visual engineering construction management system according to claim 1, characterized in that: the construction design support database (7), the data submission database (9), the material supply database (10) and the project approximate calculation database (11) are decomposed according to a progress plan in the project progress database (6), and then a relation is established corresponding to the project amount completed in the project amount database (3), so that project construction management is promoted and completed according to the plan.
5. The visual engineering construction management system according to claim 1, characterized in that: the system also comprises a construction design support database, and the construction design field support service work is concretized, quantized and visualized through the mutual correlation of the construction design support database, the project progress database (6), the project amount auditing database (4) and the financial payment database (5), so that the construction design field support service work and the field project construction completion condition are closely correlated in the construction management of the project.
6. The visual engineering construction management system according to claim 1, characterized in that: the system also comprises a project budget database, so that the visualization of the total fund use condition of the engineering project is beneficial to the overall management of fund control and investment fund payment and financing.
7. The construction method of the visual engineering construction management system by using the system according to any one of claims 1 to 6, characterized by comprising the following steps:
s1, construction of the engineering 3D model (1): establishing an engineering 3D model (1) consistent with an engineering construction project on a computer (15) through a display device (13), an input device and an output device (14) by using a project engineering quantity database (2);
s2, database construction: according to the requirements of engineering construction management, a finished engineering quantity database (3), an engineering quantity auditing database (4), a financial payment database (5), an engineering progress database (6), a construction design support database (7), a monitoring database (8), a data submission database (9), a material supply database (10), an engineering approximate calculation database (11) and an engineering construction management control chart (12) are established on a computer (15) through a display device (13), an input device and an output device (14);
s3, establishing a relation between the database and the engineering 3D model (1): after the construction of the engineering quantity database (3), the engineering quantity auditing database (4), the financial payment database (5), the engineering progress database (6), the construction design support database (7), the monitoring database (8), the data submission database (9), the material supply database (10), the engineering approximate calculation database (11) and the engineering construction management control chart (12) is completed, the construction is associated with the engineering 3D model (1) so that the data of each database can be smoothly reflected and expressed on the engineering 3D model (1) in different colors or lines;
s4, visualization management: and after the data of each database is reflected and expressed on the engineering 3D model (1) in different colors or lines, displaying the engineering 3D model (1) on the display equipment (13), realizing data visualization, and timely adjusting or correcting engineering construction management aiming at the data displayed on the display equipment (13).
CN201910859257.5A 2019-09-11 2019-09-11 Visual engineering construction management system and construction method thereof Pending CN110705837A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910859257.5A CN110705837A (en) 2019-09-11 2019-09-11 Visual engineering construction management system and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910859257.5A CN110705837A (en) 2019-09-11 2019-09-11 Visual engineering construction management system and construction method thereof

Publications (1)

Publication Number Publication Date
CN110705837A true CN110705837A (en) 2020-01-17

Family

ID=69194482

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910859257.5A Pending CN110705837A (en) 2019-09-11 2019-09-11 Visual engineering construction management system and construction method thereof

Country Status (1)

Country Link
CN (1) CN110705837A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112862440A (en) * 2021-02-09 2021-05-28 广西路桥工程集团有限公司 Construction method and system of visual management platform of engineering project
CN117709695A (en) * 2024-02-06 2024-03-15 建发合诚工程咨询股份有限公司 Engineering supervision three-stage technology management and control platform system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010282496A (en) * 2009-06-05 2010-12-16 Toshiba Corp Progress confirmation system for plant construction work
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
CN106022979A (en) * 2016-05-13 2016-10-12 郑州双杰科技股份有限公司 BIM-based water conservancy and hydropower project management cloud platform and application method thereof
CN109784681A (en) * 2018-12-26 2019-05-21 中国大唐集团科学技术研究院有限公司 Power engineering project investment management system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010282496A (en) * 2009-06-05 2010-12-16 Toshiba Corp Progress confirmation system for plant construction work
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
CN106022979A (en) * 2016-05-13 2016-10-12 郑州双杰科技股份有限公司 BIM-based water conservancy and hydropower project management cloud platform and application method thereof
CN109784681A (en) * 2018-12-26 2019-05-21 中国大唐集团科学技术研究院有限公司 Power engineering project investment management system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
林全兵: "核电建造项目管理可视化信息系统设计与实施", 《中国优秀硕士学位论文全文数据库信息科技辑》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112862440A (en) * 2021-02-09 2021-05-28 广西路桥工程集团有限公司 Construction method and system of visual management platform of engineering project
CN117709695A (en) * 2024-02-06 2024-03-15 建发合诚工程咨询股份有限公司 Engineering supervision three-stage technology management and control platform system
CN117709695B (en) * 2024-02-06 2024-05-28 建发合诚工程咨询股份有限公司 Engineering supervision three-stage technology management and control platform system

Similar Documents

Publication Publication Date Title
CN104850940B (en) Budget needed for the completion of projects preparation method and system based on engineering Whole Course Management
CN110705837A (en) Visual engineering construction management system and construction method thereof
CN109949910A (en) Medical Devices Life cycle Network Management System
CN113112233A (en) BIM-based intelligent management method and platform for full life cycle of wind power project
CN112446608A (en) OEE and Andon safety lamp management system and working method thereof
Chakravorty Prioritizing improvement projects: Benefit & effort (B&E) analysis
CN111353787A (en) Equipment comprehensive guarantee system based on cloud platform
CN113610486A (en) Project cost accounting method
JP2002288278A (en) Analysis system for product cost variation
Owais et al. Readiness and challenges for applying IFRS 17 (insurance contracts): The case of Jordanian insurance companies
CN114677044A (en) Management system and method for intelligent building supervision engineering project
CN110957023A (en) Hospital logistics supply ecological chain management system based on zero-inventory concept
CN109325646A (en) A kind of turnaround of unit scene high-risk operations dynamic control method
JP4152611B2 (en) Measures planning support method for management reform and system therefor
CN104424513A (en) Supplier information management processing system for decoration market industry
CN113361961A (en) PDCA closed-loop management-based national collection full-process monitoring system and intelligent system implementation
RU122793U1 (en) DEVICE OF AUTOMATED FORMATION, CALCULATION AND ANALYSIS OF WORKERS SALES AT THE PRODUCTION ENTERPRISE
CN108090825A (en) A kind of financial budget system and method
Vera et al. Competency development of quality control in automotive companies to improve service quality
TW200304603A (en) Asset managing apparatus, asset managing method, trust/leasing method for asset management
CN114493155A (en) Carbon emission reduction management method and device
CN112529441A (en) Engineering project management system
Lee et al. A method for analyzing the effect of implementing an enterprise system based on the complexity of activities
Larbi‐Apau et al. Performance‐based measurement: Action for organizations and HPT accountability
Fine et al. Managing quality improvement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200117

RJ01 Rejection of invention patent application after publication