JP2010282496A - Progress confirmation system for plant construction work - Google Patents

Progress confirmation system for plant construction work Download PDF

Info

Publication number
JP2010282496A
JP2010282496A JP2009136443A JP2009136443A JP2010282496A JP 2010282496 A JP2010282496 A JP 2010282496A JP 2009136443 A JP2009136443 A JP 2009136443A JP 2009136443 A JP2009136443 A JP 2009136443A JP 2010282496 A JP2010282496 A JP 2010282496A
Authority
JP
Japan
Prior art keywords
construction
progress
inspection
data
database
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2009136443A
Other languages
Japanese (ja)
Inventor
Hiroshi Mizuhashi
橋 浩 水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP2009136443A priority Critical patent/JP2010282496A/en
Publication of JP2010282496A publication Critical patent/JP2010282496A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To visualize whether a progress state of construction quantity is advanced or delayed from a plan from a quantitative viewpoint in a large-scale construction work such as a nuclear power plant. <P>SOLUTION: A construction plan support system is connected to a CAD database to support plan preparation of section-classified processes in each construction section based on CAD design data of plant construction. A progress confirmation system includes an inspection schedule database for storing data concerned with inspection schedules of plant facilities, an inspection result database for storing data concerned with inspection results and an inspection schedule/result database for storing inspection progress data obtained by integrating the schedules and results of inspections and transmits construction progress data obtained by converting an inspection progress state into the physical quantity of construction progress to the construction plan support system. The construction plan support system and the progress confirmation system are combined with each other and the section-classified processes and construction progress data are integrated to display a process table to which a chart lightning display expressing the construction progress is attached. <P>COPYRIGHT: (C)2011,JPO&INPIT

Description

本発明は、原子力発電プラントなどのプラント建設工事の進捗確認システムに係り、特に、工事の進捗状況を可視化できるようにしたプラント建設工事の進捗確認システムに関する。   The present invention relates to a progress confirmation system for a plant construction work such as a nuclear power plant, and more particularly to a progress confirmation system for a plant construction work that can visualize the progress of the construction work.

建設工事の工程を管理するプロジェクト管理に関しては、工程毎の進捗状況をデータベースに記録して管理することが従来から行われている(例えば、特許文献1)。また、プロジェクト管理に用いるソフトウェアも、さまざまなものが提供されている。   With regard to project management for managing construction processes, it has been conventionally performed to record and manage the progress of each process in a database (for example, Patent Document 1). Various software for project management is also provided.

一般に、原子力発電プラントなどの大規模なプラント建設工事の工程を管理する場合、現地にて3週間工程表と3ヶ月工程表が作成され、これらの工程表により工事の作業予定を管理している。そして、3週間工程表と3ヶ月工程表に、先週、先月の作業実施日の工程を記載していくことで工事実績の管理を行っている。   In general, when managing large-scale plant construction work such as nuclear power plants, a 3-week schedule and a 3-month schedule are created locally, and the schedule of construction work is managed by these schedules. . Then, the construction results are managed by describing the processes of the work implementation date of last week and last month in the 3-week schedule and the 3-month schedule.

そこで、図5に、原子力発電プラント建設工事の工程管理に用いられる3ヶ月工程表の例を示す。
図5は、4月分の工事実績を記載した3ヶ月工程表を表している。この3ヶ月工程表では、管理対象の工事種目として、○○系配管工事、△△系配管工事、××系工事を挙げている。
FIG. 5 shows an example of a three-month process chart used for process management of nuclear power plant construction work.
FIG. 5 shows a three-month process chart describing the construction results for April. In this three-month schedule, XX system piping work, △△ system piping work, and xx system work are listed as the work items to be managed.

○○系配管工事は、4月以前からの継続作業であり、工程バーを塗り潰して4月1ヶ月間の配管工事実績が示されている。5月分、6月分は作業予定として白抜きの工程バーになっている。
△△系配管工事は、5月から配管工事が開始される予定になっており、6月以降も継続工事が予定されている。
××系配管工事は、4月中旬から工事開始の予定で、6月中旬に工事完了の予定であったところ、実際の4月分の工事実績は工程バーを塗り潰すことで示されている。
The ○○ system plumbing work has been ongoing since April, and the results of the plumbing work for the month of April are shown by filling the process bar. The process bar for May and June is a white process bar.
The △△ system plumbing is scheduled to start in May and is scheduled to continue from June.
XX piping work is scheduled to start in mid-April and is scheduled to be completed in mid-June. Actual work results for April are shown by painting the process bar. .

次に、図6は、それから一月経った同じ工事での5月分の工事実績を記載した3ヶ月工程表を示す。
○○系配管工事では、5月も引き続き作業を行い、その実績が記載され、7月以降も作業が続くとして予定を記載している。
△△系配管工事では、図5での予定は、5月初旬から開始予定であったところ、実績としては5月中旬からの作業開始となり、作業着手時点から5月末までを実績として工程バーに記載している。
Next, FIG. 6 shows a three-month process table in which the construction results for May in the same construction one month later are described.
In the ○○ system plumbing work, the work will continue in May, the results will be described, and the schedule is stated that the work will continue from July.
△△ In the system piping work, the schedule in Fig. 5 was scheduled to start from the beginning of May, but as a result, work will start from the middle of May, and the process will start from the beginning of work until the end of May. It is described.

××系配管工事では、5月分の工事実績を工具バーに記載し、6月中旬まで作業があるとして予定を記載している。   In the XX system piping work, the construction results for May are written on the tool bar, and the schedule is written assuming that there is work until mid-June.

特開2003−331016号公報JP 2003-331016 A

しかしながら、以上のような工程表による工事進捗の管理では、結局のところ、工事進行の時間的な経過を毎月毎月記載しているに過ぎず、工程表から確認できるのは、工事の実施期間がいつまで予定されていて、いまだ工事が進行中であり、終了予定までどれくらい期間があるかということであるにすぎない。   However, in the construction progress management based on the above schedule, after all, the time progress of the construction progress is only described every month, and it can be confirmed from the schedule that the construction period is It is only how long it is scheduled, how much work is still in progress, and how long it will take to finish.

ひるがえって、工事進捗の物量消化の観点からあらためて工程表をみてみると、例えば、図6の○○系配管工事では、工事期間がこれからも続くことはわかっても、現時点の消化すべき物量的な工事量に関しては、予定に対して遅れているのか、進んでいるのかを明確に判断することはできない。   On the other hand, looking at the process schedule again from the viewpoint of digesting the amount of work progress, for example, in the XX system piping work in Fig. 6, although it is known that the construction period will continue, With regard to the amount of work, it is not possible to clearly determine whether it is late or ahead of schedule.

同様に、図6の××系配管工事では、工事の実施期間という時間的な面からは、一見すると工事が終わりに近づいたようにみえる。しかし、実際の消化すべき物量的な面からは、計画した工事量に対して、現時点で消化した工事量が計画よりもより進んでいるのか、あるいは遅れているのかは、あきらかにはならない。   Similarly, in the xx system piping work of FIG. 6, it seems that the work is approaching the end from the viewpoint of the execution period of the work. However, in terms of the amount of material that should be digested, it is not clear whether the amount of construction currently digested is more advanced or delayed than planned.

そこで、本発明の目的は、前記従来技術の有する問題点を解消し、原子力発電プラントのような大規模な建設工事において、物量的な観点から、工事量の進捗状況を計画に対して進んでいるのか、遅れているのかを可視化し、一目で確認するができるようにするプラント建設工事の進捗確認システムを提供することにある。   Therefore, an object of the present invention is to solve the problems of the prior art, and in a large-scale construction work such as a nuclear power plant, the progress of the construction amount is advanced from the plan from the viewpoint of physical quantity. It is to provide a system for confirming the progress of plant construction work that makes it possible to check at a glance whether it is late or late.

前記の目的を達成するために、本発明は、CADデータベースと接続され、プラント建設のCAD設計データをもとに工事区画単位の区画別工程の計画作成を支援する工事計画支援システムと、プラント設備の検査予定に関するデータを蓄積する検査予定データベースと、検査実績に関するデータを蓄積する検査実績データベースと、検査の予定と実績を統合した検査進捗データを蓄積する検査予実データベースとを有し、検査の進捗状況を工事進捗の物量に換算した工事進捗データを、前記工事計画支援システムに伝送する進捗確認システムと、を備え、前記区画別工程と前記工事進捗データを統合させることで、工事進捗を表すチャート稲妻表示の付された工程表が表示されるようにしたことを特徴とするものである。   In order to achieve the above object, the present invention provides a construction plan support system, which is connected to a CAD database and supports the creation of a process for each section of each construction section based on CAD design data for plant construction, and plant equipment. Inspection schedule database for accumulating data related to the inspection schedule, inspection result database for accumulating data related to inspection results, and inspection prognosis database for accumulating inspection progress data integrating the inspection schedule and results, and the progress of the inspection A progress confirmation system for transmitting construction progress data converted into the amount of construction progress to the construction plan support system, and a chart representing construction progress by integrating the section-specific process and the construction progress data It is characterized in that a process chart with lightning display is displayed.

また、本発明は、検査の進捗状況を工事進捗の物量に換算した工事進捗データは、前記CADデータベースに伝送され、工事進捗データと、CAD設計データとに基づいて、3D−CADシステム上で工事の進捗状況が3Dグラフィック表示されることを特徴とする。   Further, according to the present invention, construction progress data obtained by converting the progress of inspection into the amount of construction progress is transmitted to the CAD database, and construction is performed on the 3D-CAD system based on the construction progress data and the CAD design data. The progress status is displayed in 3D graphics.

また、本発明は、検査の進捗状況を工事進捗の物量に換算した工事進捗データが、前記CADデータベースに伝送され、工事進捗データと、CAD設計データとに基づいて、3D−CADシステム上で工事の進捗状況が3Dグラフィック表示されることを特徴とする。   Further, according to the present invention, construction progress data obtained by converting the inspection progress into the amount of construction progress is transmitted to the CAD database, and construction work is performed on the 3D-CAD system based on the construction progress data and the CAD design data. The progress status is displayed in 3D graphics.

さらに、本発明は、前記チャート稲妻表示と連動させて、工事遅延が生じている工程項目に関して入力した完了目標日を実現するために必要な工程管理情報が表示されることを特徴とする。   Furthermore, the present invention is characterized in that the process management information necessary for realizing the completion target date input with respect to the process item having the construction delay is displayed in conjunction with the chart lightning display.

本発明によれば、原子力発電プラントのような大規模な建設工事において、物量的な観点から、工事量の進捗状況を計画に対して進んでいるのか、遅れているのかを可視化し、一目で進捗状況を確認することが可能になる。   According to the present invention, in a large-scale construction work such as a nuclear power plant, from a physical viewpoint, it is possible to visualize whether the progress of the construction amount is progressing or delayed with respect to the plan at a glance. It becomes possible to check the progress.

本発明の一実施形態によるプラント建設工事の進捗確認システムの構成を示すブロック図である。It is a block diagram which shows the structure of the progress confirmation system of the plant construction construction by one Embodiment of this invention. 同プラント建設工事の進捗確認システムにより作成される稲妻表示付き工程表を示す図である。It is a figure which shows the process table | surface with a lightning display produced by the progress confirmation system of the same plant construction. 同プラント建設工事の進捗確認システムにより作成される工事区画一覧表の例を示す図である。It is a figure which shows the example of the construction division list created by the progress confirmation system of the plant construction construction. 同プラント建設工事の進捗確認システムにより作成される工程フォロー表の例を示す図である。It is a figure which shows the example of the process follow-up table created by the progress confirmation system of the plant construction. 従来のプラント建設工事の工程表の例を示す図である。It is a figure which shows the example of the process table of the conventional plant construction construction. 図5の工程表作成時から一月後に作成される工程表の例を示す図である。It is a figure which shows the example of the process schedule created one month after the process schedule creation of FIG.

以下、本発明によるプラント建設工事の進捗確認システムの実施形態について、添付の図面を参照しながら説明する。
図1は、本実施形態によるプラント建設工事の進捗確認システムの概念図である。
この図1において、参照番号10は、発電プラント建設などの現地工事計画支援システムであり、このシステムは発電プラント建設現地工事での工程計画策定を支援するコンピュータシステムである。この現地工事計画支援システム10の主要な機能は、発電プラントの工事区画単位での区画別工程14を作成することである。参照番号12は、現地工事進捗確認システムで、このシステムは、現地工事の進捗状況を確認するためのコンピュータシステムである。
DESCRIPTION OF EMBODIMENTS Hereinafter, embodiments of a progress check system for plant construction work according to the present invention will be described with reference to the accompanying drawings.
FIG. 1 is a conceptual diagram of a progress check system for plant construction work according to this embodiment.
In FIG. 1, reference numeral 10 is a local work plan support system for power plant construction and the like, and this system is a computer system that supports process plan formulation in power plant construction local work. The main function of the local construction plan support system 10 is to create a zone-specific process 14 for each construction zone of the power plant. Reference numeral 12 is a local construction progress confirmation system, which is a computer system for confirming the progress of the local construction.

実際の現地での工事工程は、図5、図6に示したような3ヶ月毎、あるいは3週間毎の現地工程表16という形の工程表を用いて管理される。この現地工程表16は、工事区画単位の区画別工程14のデータをもとにして、工程作成支援システム18を利用して作成される。   The actual construction process at the site is managed by using a process chart in the form of a local process chart 16 every three months or every three weeks as shown in FIGS. This on-site process table 16 is created using the process creation support system 18 based on the data of the section-specific process 14 for each construction section.

発電プラントの工事区画には、例えば、図3に示すように区画を特定するための名称が付けられている。そして、各区画には、例えば、工事の種類として、配管工事であれば、○○系配管工事、△△系配管工事、××系配管工事というように数多くの工事がある。   For example, the construction section of the power plant is given a name for identifying the section as shown in FIG. In each section, for example, as a type of construction, if there is a piping construction, there are a number of constructions such as XX system piping work, ΔΔ system piping work, and XX system piping work.

現地工事計画支援システム10は、施設の設計図のCADデータや必要な資材の数量などの物量データを保有する3D−CADデータベース20と接続されており、これらのCADデータと作業員一人あたりの物量消化量などのデータをもとに、各工事区画単位に、例えば、配管工事であれば、○○系配管工事、△△系配管工事、××系配管工事のそれぞれの作業期間を計算して自動的に区画別工程14を生成する。   The local construction plan support system 10 is connected to a 3D-CAD database 20 that holds CAD data of facility design drawings and quantity data such as the quantity of necessary materials, and these CAD data and quantity per worker. Based on data such as digestion amount, for each construction section, for example, for piping work, calculate the work period of XX system piping work, △△ system piping work, and XX system piping work. A section-specific process 14 is automatically generated.

次に、現地工事進捗確認システム12について説明する。
この現地工事進捗確認システム12では、工事の主な作業は最後に必ず検査を伴う点に着目して、検査状況と関連させて工事進捗状況を把握する。
Next, the local construction progress confirmation system 12 will be described.
In this local construction progress confirmation system 12, paying attention to the point that the main work of construction always involves inspection, the construction progress is grasped in relation to the inspection situation.

例えば、配管工事については、主な作業である配管材搬入、配管の合わせ作業、溶接作業と順に進んでいくと、非破壊検査、耐圧試験というように検査を行って安全性等を確認してから工事は完了することになる。このため、各工事区画における検査状況のデータをデータベース化することで、この検査状況のデータを工事進捗状況の確認に活用できることになる。
図1に示すように、現地工事進捗確認システム12では、検査予定に関して、検査項目毎の実施予定に関するデータが検査予定データベース22に蓄積される。また、現地にて検査が完了したものについては、検査項目毎に検査の実績に関するデータとして検査実績データベース24に蓄積される。そして、検査項目毎に予定と実績が統合され、検査の進捗状況データとして検査予実データベース26に蓄積される。
For example, with regard to piping work, the main operations are pipe material loading, piping alignment work, welding work, etc. In order, non-destructive inspection, pressure test etc. are performed to check safety etc. Construction will be completed. For this reason, by making the database of the inspection status data in each construction section, this inspection status data can be used for confirming the construction progress status.
As shown in FIG. 1, in the local construction progress confirmation system 12, regarding the inspection schedule, data related to the execution schedule for each inspection item is accumulated in the inspection schedule database 22. Moreover, what has been inspected locally is stored in the inspection result database 24 as data relating to the inspection result for each inspection item. Then, the schedule and results are integrated for each inspection item, and are accumulated in the inspection probable database 26 as inspection progress data.

この検査予実データベース26では、検査の進捗状況はパーセンテージに置き換えられるとともに、物量(ton)にも換算される。例えば、特定の配管工事において非破壊検査、耐圧検査と順次検査が完了していれば、検査の進捗は100%で、物量としてもその工事区画での配管工事に必要とされる工事資材の物量を総て消化したものとして、その物量データが記録される。不合格の検査項目があった場合は、全項目の検査の流れの中でその進捗状況がパーセンテージで評価されるとともに、補修などの工事が必要になるので、それらを考慮した所定の算出方法にしたがって、現時点での工事資材の消化済み物量に換算することになる。   In the inspection forecast database 26, the progress of the inspection is replaced with a percentage and also converted into a quantity (ton). For example, if non-destructive inspection, pressure-resistant inspection, and sequential inspection are completed in a specific piping work, the progress of the inspection is 100%, and the quantity of construction materials required for piping work in that construction section The quantity data is recorded as having been digested. If there are unsuccessful inspection items, the progress status is evaluated as a percentage in the inspection flow of all items, and repairs and other work are required. Therefore, it will be converted into the amount of construction materials already digested.

このようにして、検査予実データベース26では、検査の進捗状況を物量換算してから、そのデータを現地工事計画支援システム10に伝送することになる。   In this manner, the inspection forecast database 26 transmits the data to the local construction plan support system 10 after converting the inspection progress into a quantity.

現地工事計画支援システム10は、検査進捗状況を工事資材の物量に換算したデータを、上述した区画別工程14と統合し、区画別工程14が更新された区画別工程14’を生成する。   The local construction plan support system 10 integrates the data obtained by converting the inspection progress into the quantity of construction material with the above-described section-by-section process 14, and generates the section-by-section process 14 'in which the section-by-section process 14 is updated.

この更新された区画別工程14’は、バーチャート稲妻表示部30によって、工事の進捗状況を可視化する稲妻表示を伴った工程表、例えば、図2に示すような工程表として表示される。   The updated section-specific process 14 ′ is displayed by the bar chart lightning display unit 30 as a process chart with a lightning display for visualizing the progress of the construction, for example, as a process chart as shown in FIG. 2.

このようにして、予定に対してどのくらいの物量が消化されているのかを示すバーチャート稲妻表示が付された工程表により、物量面から現地工事の進捗状況が可視化され、具体的に○○系配管工事の物量消化が遅れているというに、状況を一目で把握することができる。   In this way, the progress of the local construction is visualized from the quantity side by the process chart with bar chart lightning display indicating how much quantity is digested against the schedule, specifically XX series The situation of plumbing work is delayed, but the situation can be grasped at a glance.

また、検査進捗状況を工事資材の物量に換算したデータは、検査予実データベー26から3D−CADデータベース20に伝送される。この3D−CADデータベース20では、この検査進捗状況の物量換算データと該当する区画のCADデータとが統合される。3D−CAD進捗表示部32は、そのCADデータをもとに、工事の進行を表す3Dグラフィック表示、例えば検査済みの配管等と、検査未了の配管等を区別できるような色分け表示により3Dグラフィック表示を行う。   Further, data obtained by converting the inspection progress status into the amount of construction material is transmitted from the inspection predictive database 26 to the 3D-CAD database 20. In the 3D-CAD database 20, the physical quantity conversion data of the progress of the inspection and the CAD data of the corresponding section are integrated. Based on the CAD data, the 3D-CAD progress display unit 32 displays a 3D graphic indicating the progress of the construction, for example, a color-coded display that can distinguish a pipe that has been inspected and a pipe that has not been inspected. Display.

このような3Dグラフィック表示により、現地工事の進捗状況をよりリアルな臨場感をもって可視化することができる。   Such 3D graphic display makes it possible to visualize the progress of local construction with a more realistic sensation.

さらに、バーチャート稲妻表示部30は、稲妻表示を伴った工程表を表示するとともに、図3に示すような、工事区画一覧表を表示するようにしてもよい。この工事区画一覧表では、更新された区画別工程14’から工事遅延が生じている区画を集計し、進捗遅れが生じている区画がどれか一目でわかるように、遅延を指し示す表示を付している。この一覧表によって、全体の中で、どのエリアに工事の遅れが集中しているかを一目で把握することが可能になり、物量の面だけでなく工事区画の観点から、工事の進捗状況を管理するのに役立つ。   Furthermore, the bar chart lightning display unit 30 may display a process table with lightning display and a construction section list as shown in FIG. In this construction zone list, the zones where construction delays have occurred from the updated zone-specific process 14 'are tabulated, and a display indicating the delay is attached so that the zones where progress delays are occurring can be seen at a glance. ing. This list makes it possible to understand at a glance which areas of the work are concentrated in the whole area, and manage the progress of the work not only in terms of quantity but also in terms of the construction area. To help.

次に、本発明の他の実施形態について、図4を参照して説明する。
この図4に示すように、バーチャート稲妻表示付きの工程表が表示されたときには、工事遅延が生じている工程において完了目標日を指示することで、その完了目標を達成する上で必要な情報が自動的に算出され、その情報を表示する工程フォロー表が表示される。例えば、○○系配管で工事が予定よりも遅延していた場合、この工程フォロー表が表示されることにより、今後、工事完了まで日数、消化すべき物量はどのくらいか、投入すべき作業員は何人か、などといった情報が直ちに表示される。これにより、工程管理に必要な情報を瞬時に得ることができる。
Next, another embodiment of the present invention will be described with reference to FIG.
As shown in FIG. 4, when a process chart with a bar chart lightning display is displayed, information necessary for achieving the completion target is indicated by indicating the completion target date in the process where the construction delay occurs. Is automatically calculated, and a process follow-up table displaying the information is displayed. For example, if the work is delayed from the schedule for XX system piping, this process follow table will be displayed, so in the future, how many days will be required to complete the work, how much will be consumed, Information such as how many are displayed immediately. Thereby, information required for process management can be obtained instantaneously.

なお、以上のようなプラント建設工事の進捗確認システムでは、システムの設置された本社と現地とを回線で接続することで、現地においても、本社側においてもタイムリーな進捗確認および工程進行をキープするための資材・人員投入計画を立てられることから、精度の高い工事管理が可能となる。   In the above-mentioned system for confirming the progress of plant construction work, the headquarters where the system is installed is connected to the site via a line, so that timely progress confirmation and process progress can be maintained both locally and at the headquarters. Because it is possible to make a plan for material and personnel input to do so, high-precision construction management becomes possible.

以上、本発明について、好適な実施形態を挙げて説明したが、本発明は、原子力発電所、火力発電所等の発電プラントだけでなく、さまざまなプラント建設工事の工程管理に適用することが可能である。   The present invention has been described with reference to a preferred embodiment. However, the present invention can be applied not only to power plants such as nuclear power plants and thermal power plants, but also to process management of various plant construction works. It is.

10…現地工事計画支援システム、12…現地工事進捗確認システム、14…区画別工程、16…現地工程表、20…3D−CADデータベース、22…検査予定データベース、24…検査実績データベース、26…検査予実データベース   DESCRIPTION OF SYMBOLS 10 ... Local construction plan support system, 12 ... Local construction progress confirmation system, 14 ... Process according to division, 16 ... Local process table, 20 ... 3D-CAD database, 22 ... Inspection plan database, 24 ... Inspection performance database, 26 ... Inspection Preliminary database

Claims (4)

CADデータベースと接続され、プラント建設のCAD設計データをもとに工事区画単位の区画別工程の計画作成を支援する工事計画支援システムと、
プラント設備の検査予定に関するデータを蓄積する検査予定データベースと、検査実績に関するデータを蓄積する検査実績データベースと、検査の予定と実績を統合した検査進捗データを蓄積する検査予実データベースとを有し、検査の進捗状況を工事進捗の物量に換算した工事進捗データを、前記工事計画支援システムに伝送する進捗確認システムと、を備え、
前記区画別工程と前記工事進捗データを統合させることで、工事進捗を表すチャート稲妻表示の付された工程表が表示されるようにしたことを特徴とするプラント建設工事の進捗確認システム。
A construction planning support system that is connected to a CAD database and supports the creation of a process for each section of the construction section based on CAD design data for plant construction;
An inspection schedule database for accumulating data related to the inspection schedule of plant equipment, an inspection performance database for accumulating data regarding inspection results, and an inspection prognosis database for accumulating inspection progress data integrating the inspection schedule and results A progress confirmation system for transmitting construction progress data obtained by converting the progress status of the work to the amount of construction progress to the construction plan support system,
A system for confirming the progress of plant construction work, wherein a process chart with a chart lightning display indicating construction progress is displayed by integrating the section-specific processes and the construction progress data.
検査の進捗状況を工事進捗の物量に換算した工事進捗データは、前記CADデータベースに伝送され、工事進捗データと、CAD設計データとに基づいて、3D−CADシステム上で工事の進捗状況が3Dグラフィック表示されることを特徴とする請求項1に記載のプラント建設工事の進捗確認システム。   The construction progress data obtained by converting the inspection progress into the amount of construction progress is transmitted to the CAD database. Based on the construction progress data and the CAD design data, the construction progress data on the 3D-CAD system is displayed in a 3D graphic. The system for confirming the progress of the plant construction work according to claim 1, wherein the system is displayed. 工事の遅れが生じている工事区画を集計し、工事の遅れを示す表示をもって工事区画の一覧表示をすることを特徴とする請求項1に記載のプラント建設工事の進捗確認システム。   2. The system for confirming the progress of plant construction work according to claim 1, wherein the construction sections where construction delays have occurred are totaled and a list of construction sections is displayed with a display indicating the construction delays. 前記チャート稲妻表示と連動させて、工事遅延が生じている工程項目に関して入力した完了目標日を実現するために必要な工程管理情報が表示されることを特徴とする請求項1に記載のプラント建設工事の進捗確認システム。   2. The plant construction according to claim 1, wherein the process management information necessary for realizing the completion target date inputted with respect to the process item causing the construction delay is displayed in conjunction with the chart lightning display. Construction progress confirmation system.
JP2009136443A 2009-06-05 2009-06-05 Progress confirmation system for plant construction work Pending JP2010282496A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009136443A JP2010282496A (en) 2009-06-05 2009-06-05 Progress confirmation system for plant construction work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009136443A JP2010282496A (en) 2009-06-05 2009-06-05 Progress confirmation system for plant construction work

Publications (1)

Publication Number Publication Date
JP2010282496A true JP2010282496A (en) 2010-12-16

Family

ID=43539158

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009136443A Pending JP2010282496A (en) 2009-06-05 2009-06-05 Progress confirmation system for plant construction work

Country Status (1)

Country Link
JP (1) JP2010282496A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012242981A (en) * 2011-05-18 2012-12-10 Hitachi-Ge Nuclear Energy Ltd Plant construction process generation support system, plant construction process generation support method, and program
TWI633503B (en) * 2014-07-29 2018-08-21 日商千代田化工建設股份有限公司 Plant design support device and plant design support program
CN110705837A (en) * 2019-09-11 2020-01-17 中国三峡建设管理有限公司 Visual engineering construction management system and construction method thereof
JP7265295B1 (en) 2022-06-27 2023-04-26 株式会社コルク Process control system
CN116228172A (en) * 2023-05-08 2023-06-06 中国核工业二三建设有限公司 Method and device for measuring construction progress of nuclear engineering auxiliary equipment and electronic equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05282328A (en) * 1992-03-30 1993-10-29 Toshiba Corp Process control supporting device
JPH10131490A (en) * 1996-10-30 1998-05-19 Chiyoda Corp Piping work management system
JP2002007654A (en) * 2000-06-22 2002-01-11 Hitachi Ltd Task progress condition display method
JP2008217480A (en) * 2007-03-05 2008-09-18 Fujitsu Ltd Requirement confirmation support program, requirement confirmation support method, and requirement confirmation support device
JP2009116806A (en) * 2007-11-09 2009-05-28 Hitachi-Ge Nuclear Energy Ltd Progress management method, program and progress management apparatus

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05282328A (en) * 1992-03-30 1993-10-29 Toshiba Corp Process control supporting device
JPH10131490A (en) * 1996-10-30 1998-05-19 Chiyoda Corp Piping work management system
JP2002007654A (en) * 2000-06-22 2002-01-11 Hitachi Ltd Task progress condition display method
JP2008217480A (en) * 2007-03-05 2008-09-18 Fujitsu Ltd Requirement confirmation support program, requirement confirmation support method, and requirement confirmation support device
JP2009116806A (en) * 2007-11-09 2009-05-28 Hitachi-Ge Nuclear Energy Ltd Progress management method, program and progress management apparatus

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012242981A (en) * 2011-05-18 2012-12-10 Hitachi-Ge Nuclear Energy Ltd Plant construction process generation support system, plant construction process generation support method, and program
TWI633503B (en) * 2014-07-29 2018-08-21 日商千代田化工建設股份有限公司 Plant design support device and plant design support program
CN110705837A (en) * 2019-09-11 2020-01-17 中国三峡建设管理有限公司 Visual engineering construction management system and construction method thereof
JP7265295B1 (en) 2022-06-27 2023-04-26 株式会社コルク Process control system
JP2024003452A (en) * 2022-06-27 2024-01-15 株式会社コルク Process control system
CN116228172A (en) * 2023-05-08 2023-06-06 中国核工业二三建设有限公司 Method and device for measuring construction progress of nuclear engineering auxiliary equipment and electronic equipment

Similar Documents

Publication Publication Date Title
Ding et al. Building Information Modeling (BIM) application framework: The process of expanding from 3D to computable nD
JP2010282496A (en) Progress confirmation system for plant construction work
WO2013141213A1 (en) System for managing construction process and method for managing same
Gerbec et al. Design of procedures for rare, new or complex processes: Part 1–An iterative risk-based approach and case study
US20220277268A1 (en) Project management apparatus, project management method, and recording medium
Nissilä et al. BIM based schedule control for precast concrete supply chain
Inaudi Cost-benefits analysis in SHM projects
Le Blanc et al. Requirements for control room computer-based procedures for use in hybrid control rooms
None Light Water Reactor Sustainability Program: Integrated Program Plan
Shou et al. 4D BIM for improving plant turnaround maintenance planning and execution: A case study
O'Brien Construction inspection handbook: Total quality management
Russell et al. Documented constructability savings for petrochemical-facility expansion
JP2001256421A (en) Optimization system for plant repair plan
Tallgren et al. A BIM-supported framework for enhancing joint planning in construction
Mejlænder-Larsen Using BIM to follow up milestones in a project plan during the design phase
Tang et al. A conceptual workflow for BIM based prefabrication design visualization with augmented reality
Carbon-Steel et al. Environmental Product Declaration
Greaves et al. 3D Laser Scanning: Benefits and Paybacks for Industrial Plant Design, Construction and Operation
Hessler Managing small and medium-sized capital projects
Hasan An approach for building information modeling and simulation integrated look-ahead planning
Thomas 2015 Summary Report on Industrial and Regulatory Engagement Activities
Lucke Start-up and performance test
Wright et al. Advanced construction technologies for the nuclear construction industry
Winters AP1000 construction schedule
Baldwin et al. Planning and scheduling in a virtual prototyping environment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110809

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120914

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120921

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20130205