CN110700390A - 复杂地质条件下的旋流井施工方法 - Google Patents
复杂地质条件下的旋流井施工方法 Download PDFInfo
- Publication number
- CN110700390A CN110700390A CN201911051012.6A CN201911051012A CN110700390A CN 110700390 A CN110700390 A CN 110700390A CN 201911051012 A CN201911051012 A CN 201911051012A CN 110700390 A CN110700390 A CN 110700390A
- Authority
- CN
- China
- Prior art keywords
- well
- cyclone
- construction
- constructing
- cyclone well
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/04—Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
- E03F5/06—Gully gratings
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/60—Planning or developing urban green infrastructure
Landscapes
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Earth Drilling (AREA)
- Cyclones (AREA)
Abstract
本发明涉及一种复杂地质条件下的旋流井施工方法,包括一:根据土质情况首先对地表到岩层的土壤进行放坡开挖;并对边坡采用混凝土护坡;在坡面上铺设钢筋网片或钢板网并固定,然后喷射细石混凝土对开挖的坡面进行保护;二:旋流井主体逆作法施工,完成后,进行旋流井逆作法第一段外井壁的施工;三,对岩层进行开挖采用的方式为:凿岩、挖运,并进行下一段井壁的施工,以此类推直至开挖至旋流井主体底标高,进行旋流井的封底;四,旋流井主体封底后,采用正做法对其内部结构及上部的外井壁进行施工。本发明简化施工,降低施工难度,缩短工期,减少投入;降低施工安全的危险性。对类似施工工艺具有一定的借鉴和推广意义。
Description
技术领域
本发明涉及一种复杂地质条件下的旋流井施工方法。
背景技术
目前,在冶金轧钢行业中,旋流井的施工由于埋深较深,在复杂的地质条件下采用传统的沉井的方式或深基坑围护的方式对其进行施工,由于在施工中,围护结构其结构复杂,施工难度很高,施工周期长,资金投入多,安全风险高。不利于工程的进行,因此解决施工的难度和安全风险是该工程的一大难点。现根据不同的地质层进行多层次的方式进行旋流井的施工。
发明内容
本发明旨在克服现有技术的缺陷,提供一种复杂地质条件下的旋流井施工方法,简化施工,降低施工难度,缩短工期,减少投入。
为了解决上述技术问题,本发明是这样实现的:
一种复杂地质条件下的旋流井施工方法,其特征在于它包括如下步骤:
步骤一:根据土质情况首先对地表到岩层的土壤进行放坡开挖;并对边坡采用混凝土护坡;在坡面上铺设钢筋网片或钢板网并固定,然后喷射细石混凝土对开挖的坡面进行保护;
步骤二:旋流井主体逆作法施工,进行冠梁施工,冠梁施工完成后,进行旋流井逆作法第一段外井壁的施工,此时外井壁与冠梁连接牢固使之在往下开挖时井壁牢固悬挂在冠梁上;
步骤三,对岩层进行开挖采用的方式为:凿岩、挖运,并进行下一段井壁的施工,以此类推直至开挖至旋流井主体底标高,进行旋流井的封底;
步骤四,旋流井主体封底后,采用正做法对其内部结构及上部的外井壁进行施工。
本发明的有益效果是:充分利用地质条件的不同,采用放坡开挖及基础逆作法相结合的方式进行旋流井的施工,采用这种方式及降低了工程的施工难度,缩短了施工周期,减少了投入,减低了安全风险,这种方法适合于不同地质条件下的旋流井的施工。对于地下构筑物及地下深基坑可以借鉴及推广使用。
简化施工,降低施工难度,缩短工期,减少投入;降低施工安全的危险性。对类似施工工艺具有一定的借鉴和推广意义。
附图说明
下面结合附图和实施方式对本发明作进一步的详细说明:
图1为本发明旋流井基坑的结构示意图。
具体实施方式
如图1所示:一种复杂地质条件下的旋流井施工方法,它包括如下步骤:
步骤一:根据土质情况首先对地表到岩层的土壤进行放坡开挖;并对边坡采用混凝土护坡;在坡面上铺设钢筋网片或钢板网并固定,然后喷射细石混凝土对开挖的坡面进行保护;
步骤二:旋流井主体逆作法施工,进行冠梁施工,冠梁施工完成后,进行旋流井逆作法第一段外井壁的施工,此时外井壁与冠梁连接牢固使之在往下开挖时井壁牢固悬挂在冠梁上;
步骤三,对岩层进行开挖采用的方式为:凿岩、挖运,并进行下一段井壁的施工,以此类推直至开挖至旋流井主体底标高,进行旋流井的封底;
步骤四,旋流井主体封底后,采用正做法对其内部结构及上部的外井壁进行施工。
通过对不同地质层进行分析验算,得出将地表上利于开挖的土体进行放坡开挖,对于下部岩石层采用逆作法施工至工程主体设计标高,然后对放坡开挖的部分采用正做法的方法将工程主体施工至设计顶标高,这样能够方便、有效减少旋流井的施工难度并降低安全风险。
Claims (1)
1.一种复杂地质条件下的旋流井施工方法,其特征在于它包括如下步骤:
步骤一:根据土质情况首先对地表到岩层的土壤进行放坡开挖;并对边坡采用混凝土护坡;在坡面上铺设钢筋网片或钢板网并固定,然后喷射细石混凝土对开挖的坡面进行保护;
步骤二:旋流井主体逆作法施工,进行冠梁施工,冠梁施工完成后,进行旋流井逆作法第一段外井壁的施工,此时外井壁与冠梁连接牢固使之在往下开挖时井壁牢固悬挂在冠梁上;
步骤三,对岩层进行开挖采用的方式为:凿岩、挖运,并进行下一段井壁的施工,以此类推直至开挖至旋流井主体底标高,进行旋流井的封底;
步骤四,旋流井主体封底后,采用正做法对其内部结构及上部的外井壁进行施工。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911051012.6A CN110700390A (zh) | 2019-10-31 | 2019-10-31 | 复杂地质条件下的旋流井施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911051012.6A CN110700390A (zh) | 2019-10-31 | 2019-10-31 | 复杂地质条件下的旋流井施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110700390A true CN110700390A (zh) | 2020-01-17 |
Family
ID=69204068
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911051012.6A Pending CN110700390A (zh) | 2019-10-31 | 2019-10-31 | 复杂地质条件下的旋流井施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110700390A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112609732A (zh) * | 2020-12-02 | 2021-04-06 | 中国十九冶集团有限公司 | 一种旋流井施工方法 |
CN113026816A (zh) * | 2021-03-24 | 2021-06-25 | 山东建筑大学 | 一种注浆加固土体的托换逆作沉井支护结构及施工方法 |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108060683A (zh) * | 2017-12-18 | 2018-05-22 | 烟建集团有限公司 | 一种中风化地质逆作法施工方法 |
-
2019
- 2019-10-31 CN CN201911051012.6A patent/CN110700390A/zh active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108060683A (zh) * | 2017-12-18 | 2018-05-22 | 烟建集团有限公司 | 一种中风化地质逆作法施工方法 |
Non-Patent Citations (3)
Title |
---|
彭世萍 等: "浅谈复杂地质结构旋流池施工", 《建筑设计管理》 * |
李树明: "混凝土灌注桩排桩支护逆作法在旋流井施工中的应用", 《施工技术》 * |
邢华: "炼钢连铸旋流井混凝土排桩支护井壁逆作法施工技术的应用", 《科技情报开发与经济》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112609732A (zh) * | 2020-12-02 | 2021-04-06 | 中国十九冶集团有限公司 | 一种旋流井施工方法 |
CN113026816A (zh) * | 2021-03-24 | 2021-06-25 | 山东建筑大学 | 一种注浆加固土体的托换逆作沉井支护结构及施工方法 |
CN113026816B (zh) * | 2021-03-24 | 2023-10-24 | 山东建筑大学 | 一种注浆加固土体的托换逆作沉井支护结构及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108442382B (zh) | 横穿深基坑的压力管线原位保护及围护挡土结构及施工方法 | |
CN103089275B (zh) | 富水极破碎围岩隧道塌方段围岩控制方法 | |
CN205742213U (zh) | 基坑支护结构 | |
CN104612162A (zh) | 一种地铁车站深基坑开挖施工方法 | |
CN111101540B (zh) | 一种明挖隧道上穿既有电力隧道施工方法 | |
CN101892668A (zh) | 联合支护开挖溶蚀地质深基坑及其施工方法 | |
CN106638640A (zh) | 岩层地质条件下无封底混凝土组合式围堰的施工方法 | |
CN201801872U (zh) | 联合支护开挖溶蚀地质深基坑 | |
CN114233385B (zh) | 一种斜井井筒突泥涌水的治理方法 | |
CN106400820A (zh) | 一种锁扣钢管与混凝土组合桩围堰及施工方法 | |
CN106013053A (zh) | 一种用于建造地下车库沉井的钢板桩支护施工方法 | |
CN104264683B (zh) | 三面环绕文保建筑凹字形超深基坑分区支护方法 | |
CN111851523B (zh) | 一种基坑施工防沉降偏离方法 | |
CN110158579A (zh) | 一种钻孔灌注桩施工方法 | |
CN110700390A (zh) | 复杂地质条件下的旋流井施工方法 | |
CN104863183B (zh) | 大断面隧道近接建筑物施工隔离减震桩结构及施工方法 | |
CN209923935U (zh) | 一种上软下硬地层中同位组合桩墙支护结构 | |
CN106480891B (zh) | 一种竖井施工方法 | |
CN203213131U (zh) | 一种排水下沉与不排水下沉相结合的沉井 | |
CN205576990U (zh) | 一种过河段穿桥桩隧道注浆支护结构 | |
CN207111094U (zh) | 一种水中超深盾构始发/吊出井结构 | |
CN212642730U (zh) | 一种湿陷性黄土地区隧道穿越人防结构 | |
CN107905219A (zh) | 一种复杂地质条件下超深人工开挖桩孔的施工方法 | |
CN210216391U (zh) | 伸入基岩的封闭式地连墙围井结构 | |
CN210658410U (zh) | 倒挂壁围井结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200117 |
|
RJ01 | Rejection of invention patent application after publication |