CN110528767A - A kind of complex model furred ceiling closing in cell cube fabrication and installation method - Google Patents

A kind of complex model furred ceiling closing in cell cube fabrication and installation method Download PDF

Info

Publication number
CN110528767A
CN110528767A CN201910770892.6A CN201910770892A CN110528767A CN 110528767 A CN110528767 A CN 110528767A CN 201910770892 A CN201910770892 A CN 201910770892A CN 110528767 A CN110528767 A CN 110528767A
Authority
CN
China
Prior art keywords
cell cube
installation
cell
furred ceiling
installation method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910770892.6A
Other languages
Chinese (zh)
Inventor
郭振江
薛秋红
陈宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taiyuan Engineering Group Co Ltd
Original Assignee
Taiyuan Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taiyuan Engineering Group Co Ltd filed Critical Taiyuan Engineering Group Co Ltd
Priority to CN201910770892.6A priority Critical patent/CN110528767A/en
Publication of CN110528767A publication Critical patent/CN110528767A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation

Abstract

The present invention relates to a kind of complex model furred ceiling closing in cell cube fabrication and installation methods, the installation method includes the following steps, complicated suspended ceiling modeling is decomposed into multiple cell cubes interconnected according to drawing, back court is according to drawing making aluminium mold, production unit body template by number adjusts the mould, determines version;Back court carries out preassembling using version mold batch making cell cube green body is determined, to the cell cube made, toning is painted;Transport qualified cell cube to construction site;Cell cube installation site line is popped up at the scene according to drawing, and cell cube is lifted by number, cell cube mounting finished product is debugged after the completion of lifting, the position of lock cell body is connect with other decorative covers;Complete the installation of cell cube;Total, the present invention has rational design, has the advantages that speed of application is fast, the easy control of quality, batch production degree are high.

Description

A kind of complex model furred ceiling closing in cell cube fabrication and installation method
Technical field
The invention belongs to engineering design technology fields, and in particular to a kind of complex model furred ceiling closing in cell cube fabrication and installation Method.
Background technique
The way of the installation of ceiling of industry universal moulding at present is essentially light steel keel gypsum board furred ceiling, adds gypsum line, GRC Decoration of cement line, wood moulding, metal wire lamp additional materials directly molding are done in the outer layer groove milling polishing of the double-deck plasterboard Method;The disadvantage is that construction quality is not easy to guarantee, construction investment is big, is also after the completion base's decoration, also needs later period emulsion paint, gold Belong to the techniques facing decorations such as paint;Existing complexity furred ceiling, which closes up, makes mainly hand-made by worker at the scene, working efficiency Low, construction quality is not easy to guarantee, the generally gypsum, wooden, cement products base to complete at the construction field (site), it is also necessary to The techniques such as repairing, polishing, the spray painting in later period are decorated.These work are limited by moulding sometimes, constructional difficulties;Therefore, it is necessary to Find the fabrication and installation of the high complex model furred ceiling closing in cell cube of a kind of fast speed of application, the easy control of quality, batch production degree Method.
Summary of the invention
The present invention is mostly base layer construction for current complex model furred ceiling (such as complicated light trough) position plasterboard construction, after The defects of phase is difficult to the Puttying of base, grinding process, and construction quality is not easy to guarantee, speed of application is at high cost slowly, provides one Plant the fabrication and installation method of the high complex model furred ceiling closing in cell cube of fast speed of application, the easy control of quality, batch production degree.
The object of the present invention is achieved like this: a kind of complex model furred ceiling closing in cell cube fabrication and installation method, described Installation method the following steps are included:
1) design drawing of furred ceiling is analyzed, complicated suspended ceiling modeling is decomposed by multiple units interconnected according to drawing Body determines each unit frame body sectional material and size, and each unit body is numbered;
2) back court is according to drawing making aluminium mold, and production unit body template, the size on template and drawing is carried out by number It checks, adjusts the mould, determines version;
3) back court carries out preassembling to the cell cube made, toning is painted using version mold batch making cell cube green body is determined; It tries to spell and detected in back court using finished unit body;
4) qualified cell cube is numbered, is packed and stored, transport construction site on demand;
5) pop up cell cube installation site line at the scene according to drawing, by installation site line to installation horizontal, elevation location into Row is checked;
6) cell cube is lifted by number, cell cube mounting finished product is debugged after the completion of lifting, lock cell body Position is connect with other decorative covers;
7) installation of cell cube is completed.
Pass through plug connection between the cell cube.
Beneficial effects of the present invention: the present invention optimizes furred ceiling node drawing according to construction drawing design, complexity The section of furred ceiling is converted into aluminum profile, is opened and is formed with metal, surface layer directly completes in factory, with plane furred ceiling interface The process seam that can satisfy installation by Deepen Design setting can shift to an earlier date the most difficult part of the construction in complicated furred ceiling in work Factory completes, and determines that colour table carries out spray painting and is fabricated to finished product and packs by user further according to the color of furred ceiling in drawing, Scene only carries out simple component connection lifting construction, reduces the workload of site operation, guarantees the progress of site operation, from And accelerate speed of application, guarantee complicated furred ceiling construction quality, cost of labor is greatly reduced, technology of the invention can cover building Most complexity furred ceiling closing in position in decoration;Total, the present invention has rational design, fast, the quality easily handle with speed of application The high advantage of control, batch production degree.
Specific embodiment
The present invention is described further below.
Embodiment 1
A kind of complex model furred ceiling closing in cell cube fabrication and installation method, the installation method the following steps are included:
1) design drawing of furred ceiling is analyzed, complicated suspended ceiling modeling is decomposed by multiple units interconnected according to drawing Body determines each unit frame body sectional material and size, and each unit body is numbered;
2) back court is according to drawing making aluminium mold, and production unit body template, the size on template and drawing is carried out by number It checks, adjusts the mould, determines version;
3) back court carries out preassembling to the cell cube made, toning is painted using version mold batch making cell cube green body is determined; It tries to spell and detected in back court using finished unit body;
4) qualified cell cube is numbered, is packed and stored, transport construction site on demand;
5) pop up cell cube installation site line at the scene according to drawing, by installation site line to installation horizontal, elevation location into Row is checked;
6) cell cube is lifted by number, cell cube mounting finished product is debugged after the completion of lifting, lock cell body Position is connect with other decorative covers;
7) installation of cell cube is completed.
Pass through plug connection between the cell cube.
It is formed when it is implemented, the present invention is opened with metal, surface layer directly completes in factory, applying in complicated furred ceiling The most difficult part of work can be prefabricated in the factory in advance and complete after drawing and phenomenon size come out, without waiting for field condition, When equal scenes can be fitted up, the component made directly is attached lifting construction at the scene, saves live interim system The time of work is made in back court using large scale equipment, and the quality for guaranteeing engineering is more advantageous to, compared to traditional mode, though material Input cost has increased slightly, but construction quality is far superior to traditional mode, also saves a large amount of cost of labor, ensure that construction Progress.

Claims (2)

1. a kind of complex model furred ceiling closing in cell cube fabrication and installation method, it is characterised in that: the installation method include with Lower step:
(1) design drawing of furred ceiling is analyzed, complicated suspended ceiling modeling is decomposed by multiple lists interconnected according to drawing First body determines each unit frame body sectional material and size, and each unit body is numbered;
(2) back court is according to drawing making aluminium mold, and production unit body template, the size on template and drawing is carried out by number It checks, adjusts the mould, determines version;
(3) back court carries out preassembling to the cell cube made, toning is sprayed using version mold batch making cell cube green body is determined Paint;It tries to spell and detected in back court using finished unit body;
(4) qualified cell cube is numbered, is packed and stored, transport construction site on demand;
(5) pop up cell cube installation site line at the scene according to drawing, by installation site line to installation horizontal, elevation location into Row is checked;
(6) cell cube is lifted by number, cell cube mounting finished product is debugged after the completion of lifting, lock cell body Position is connect with other decorative covers;
(7) installation of cell cube is completed.
2. a kind of complex model furred ceiling closing in cell cube fabrication and installation method as described in claim 1, it is characterised in that: institute Pass through plug connection between the cell cube stated.
CN201910770892.6A 2019-08-20 2019-08-20 A kind of complex model furred ceiling closing in cell cube fabrication and installation method Pending CN110528767A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910770892.6A CN110528767A (en) 2019-08-20 2019-08-20 A kind of complex model furred ceiling closing in cell cube fabrication and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910770892.6A CN110528767A (en) 2019-08-20 2019-08-20 A kind of complex model furred ceiling closing in cell cube fabrication and installation method

Publications (1)

Publication Number Publication Date
CN110528767A true CN110528767A (en) 2019-12-03

Family

ID=68663944

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910770892.6A Pending CN110528767A (en) 2019-08-20 2019-08-20 A kind of complex model furred ceiling closing in cell cube fabrication and installation method

Country Status (1)

Country Link
CN (1) CN110528767A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113360993A (en) * 2021-06-30 2021-09-07 浙江乔兴建设集团有限公司 BIM technology-based construction method for large-area complex-modeling suspended ceiling

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005035174A1 (en) * 2005-07-27 2007-02-01 Greiner, Switbert, Dr.-Ing. Covering a, in particular flat, surface with a flexible covering material, in particular textile material, and method for cladding
CN204098319U (en) * 2014-07-07 2015-01-14 深圳市晶宫设计装饰工程有限公司 A kind of ceiling structure
JP2016223074A (en) * 2015-05-27 2016-12-28 株式会社能重製作所 Joist support hanger
CN106381948A (en) * 2016-10-21 2017-02-08 孙国兵 Mounting technique for GRC curtain wallboard
CN107190900A (en) * 2017-07-19 2017-09-22 江苏东保装饰集团有限公司 A kind of passageway perforated plate aluminium sheet ceiling construction process
CN108301551A (en) * 2017-12-30 2018-07-20 浙江亚厦装饰股份有限公司 Building ceiling industrializes decorative system and installation method
CN109583145A (en) * 2019-01-17 2019-04-05 唐山铭嘉建筑设计咨询有限公司 A kind of assembled architecture design method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005035174A1 (en) * 2005-07-27 2007-02-01 Greiner, Switbert, Dr.-Ing. Covering a, in particular flat, surface with a flexible covering material, in particular textile material, and method for cladding
CN204098319U (en) * 2014-07-07 2015-01-14 深圳市晶宫设计装饰工程有限公司 A kind of ceiling structure
JP2016223074A (en) * 2015-05-27 2016-12-28 株式会社能重製作所 Joist support hanger
CN106381948A (en) * 2016-10-21 2017-02-08 孙国兵 Mounting technique for GRC curtain wallboard
CN107190900A (en) * 2017-07-19 2017-09-22 江苏东保装饰集团有限公司 A kind of passageway perforated plate aluminium sheet ceiling construction process
CN108301551A (en) * 2017-12-30 2018-07-20 浙江亚厦装饰股份有限公司 Building ceiling industrializes decorative system and installation method
CN109583145A (en) * 2019-01-17 2019-04-05 唐山铭嘉建筑设计咨询有限公司 A kind of assembled architecture design method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113360993A (en) * 2021-06-30 2021-09-07 浙江乔兴建设集团有限公司 BIM technology-based construction method for large-area complex-modeling suspended ceiling
CN113360993B (en) * 2021-06-30 2022-04-29 浙江乔兴建设集团有限公司 BIM technology-based construction method for large-area complex-modeling suspended ceiling

Similar Documents

Publication Publication Date Title
CN108972975B (en) Method for manufacturing cavity mold of landscape sculpture
CN111805696A (en) Manufacturing process of building decoration component
CN107009804A (en) A kind of manufacture craft of sculpture
CN110254112A (en) A kind of artificial hillock modeling stone packaging construction method
CN104230250A (en) Processing technique for artificial marble decorative surface by using GRC (Glass Fiber Rinforced Cement) material
CN110528767A (en) A kind of complex model furred ceiling closing in cell cube fabrication and installation method
Ivashko et al. Ways of performance and preservation of monumental art works on the facades of architectural monuments of the 19th-early 20th century
CN101769051A (en) Method for manufacturing simulated stone covering layer by machine on building wall
CN104441199A (en) Large cement flowerpot manufacturing process
CN106864144A (en) A kind of iron picture draws the manufacture method and the iron picture vase including it of core
CN104418580A (en) Method for preparing glass fiber composite decorative material
CN1141856A (en) Photoelectric sculpturing method
CN105957443A (en) Building model rapid forming method
CN108191297A (en) A kind of simulated natural marbling quartzite slate and its manufacture craft
CN113863620A (en) Water transfer printing method based on EPS lines and component finished products
CN102218764B (en) Construction process of wood furniture provided with polyurethane (PU) hard material layer on surface
CN105216531A (en) Moulded concrete decoration plate with relief sculpture is produced and installation method
CN105904908B (en) A kind of processing method of dicoration bamboo clappers charcoal drawing
CN106799918A (en) A kind of manufacture craft of pulp handicraft
CN102380928A (en) Injection molded ceiling slab and manufacturing method thereof
CN109610832A (en) A kind of pseudo-classic loam wall construction technology
CN105863252A (en) Production technical process of combined construction mold with decoration function
CN106049867A (en) Building method for special-shaped building model
CN103434320B (en) A kind of technological process with water container glass
CN103144489B (en) Manufacturing method for large azure stone wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191203