CN110512521A - The docking facilities and interconnection method of big segment steel truss girder - Google Patents

The docking facilities and interconnection method of big segment steel truss girder Download PDF

Info

Publication number
CN110512521A
CN110512521A CN201910696451.6A CN201910696451A CN110512521A CN 110512521 A CN110512521 A CN 110512521A CN 201910696451 A CN201910696451 A CN 201910696451A CN 110512521 A CN110512521 A CN 110512521A
Authority
CN
China
Prior art keywords
section
place
roof beam
pair
steel truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910696451.6A
Other languages
Chinese (zh)
Other versions
CN110512521B (en
Inventor
邹冠
胡杰
张文斌
许佳平
毛玮琦
涂满明
李军堂
姚森
胡勇
崔一兵
陈涛
朱云萍
耿豪
姜江华
贾维君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN201910696451.6A priority Critical patent/CN110512521B/en
Publication of CN110512521A publication Critical patent/CN110512521A/en
Application granted granted Critical
Publication of CN110512521B publication Critical patent/CN110512521B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of docking facilities of big segment steel truss girder, and be used to have set a roof beam in place section and section to be set a roof beam in place docking;Big segment steel truss girder include wind up, lower edge, vertical bar, to extension bar and cross bearer;Docking facilities include: first pair of drawing mechanism, and one end is connect with wait the cross bearer in section of setting a roof beam in place, and the other end is connected with cross bearer corresponding in section of having set a roof beam in place;When first pair of drawing mechanism is when to drawing, a cross bearer of section to be set a roof beam in place corresponding cross bearer into section of having set a roof beam in place is close;Second pair of drawing mechanism, both ends are respectively provided at the middle part of section of having set a roof beam in place, section to be set a roof beam in place;When second pair of drawing mechanism to draw when, it is corresponding close to extension bar into section of having set a roof beam in place wait a pair of of extension bar in section of setting a roof beam in place;Top lifting mechanism comprising lift up device;Lift up device is set to wait on winding up in section of setting a roof beam in place, and top is fixed;When the upward top lifting of lift up device, section to be set a roof beam in place is pushed.The present invention effectively adjusts the section and wait the relative deformation between section of setting a roof beam in place of having set a roof beam in place, and realizes big segment steel truss girder docking.

Description

The docking facilities and interconnection method of big segment steel truss girder
Technical field
The present invention relates to steel truss girder docking technique fields, and in particular to a kind of docking facilities of big segment steel truss girder and docking Method.
Background technique
With the fast development of economy and scientific and technical innovation, the bridge span in transport development is also progressively longer.Large span Bridge is mostly cable-stayed bridge, and for cable-stayed bridge, for especially combined heavily loaded cable-stayed bridge, compared to solid web girder, adopt It can reduce self weight with steel truss girder and increase rigidity to be better adapted to the load-carrying members compared with large span.
The installation of steel truss girder is by multiple segment steel truss girders mostly to realization is fetched, in the prior art, a kind of Conventional interconnection method is that temporary staging is set up below docking region, and setting is supported to the lower edge of frame steel truss girder on temporary staging, Adjustment winding up highly and to frame steel truss girder position to frame steel truss girder is suspended in midair by crane, and crane persistently suspends in midair, to butt welding After the completion, crane is removed.But when large span stayed-cable bridge uses big segment steel truss girder integral erection, due to big segment steel truss Beam has been formed from great stable structure, and therefore, front fulcrum counter-force is huge at Standing position of a crane, leads to the big segment steel truss of frame The position of beam and the banjo fixing butt jointing to frame steel truss girder is big in vertical, axially opposing deformation, in this case, according to above-mentioned normal Interconnection method is advised, big segment steel truss girder can not be directly docked by the way of punch.
Therefore, one of goal of the invention of the invention aims to solve the problem that problem of the big segment steel truss girder in docking.
Summary of the invention
In view of the deficiencies in the prior art, the purpose of the present invention is to provide a kind of big segment steel truss girders to tipping It sets and interconnection method, effectively adjusts the section and wait the relative deformation between section of setting a roof beam in place of having set a roof beam in place, realize big segment steel truss girder docking.
To achieve the above objectives, in a first aspect, the embodiment of the present invention provides a kind of docking facilities of big segment steel truss girder, For docking two big segment steel truss girders, defining two big segment steel truss girder is set a roof beam in place section and section to be set a roof beam in place;It is described Segment steel truss girder includes: greatly
The several groups string beam element of parallel interval setting, every group of string beam element include one wind up, a lower edge, at least one with It is described wind up the vertical bar being connected with lower edge and two be set to outside all vertical bars to extension bar;
Several cross bearers, wind up described in each adjacent two between be equipped at least two cross bearers, and two are described big Crossbeam be respectively arranged on two described in the both ends winded up, set wait the cross bearer in section of setting a roof beam in place is opposite with the cross bearer in section of having set a roof beam in place It sets;
The docking facilities include:
First pair of drawing mechanism, one end are connect with wait the cross bearer in section of setting a roof beam in place, and the other end is corresponding with section of having set a roof beam in place Cross bearer connection;When first pair of drawing mechanism is when to drawing, a cross bearer of the section to be set a roof beam in place is to the section of having set a roof beam in place In corresponding cross bearer it is close;
Second pair of drawing mechanism, both ends are respectively provided at the middle part of the set a roof beam in place section, section to be set a roof beam in place;It draws when described second Dui When to drawing, a pair of of extension bar wait in section of setting a roof beam in place is corresponding close to extension bar into the section of having set a roof beam in place for mechanism;
Top lifting mechanism comprising lift up device;The lift up device is set to described wait on winding up in section of setting a roof beam in place, and the top lifting The top of device is fixedly installed;When the upward top lifting of the lift up device, the section to be set a roof beam in place is pushed.
Based on the above technical solution, the top lifting mechanism further include:
One shoulder pole girder, one end are connect with winding up in section of having set a roof beam in place, and the other end is connect with wait winding up in section of setting a roof beam in place, institute State the top that shoulder pole girder is installed in the lift up device;When the lift up device jacks up the shoulder pole girder upwards, the section to be set a roof beam in place In wind up and move downward.
Based on the above technical solution, the top lifting mechanism further include:
Two third ear mounts, be installed in respectively section of having set a roof beam in place wind up and the winding up of section to be set a roof beam in place on, the shoulder pole girder Both ends pass through pin shaft respectively and are detachably connected with two third ear mounts.
Based on the above technical solution, first pair of drawing mechanism includes:
Steel cable, both ends are connected with two opposite cross bearers respectively;
Jack is set at least one end of the steel cable, for shrinking the length of the steel cable.
Based on the above technical solution, first pair of drawing mechanism further include:
Two first ear mounts are installed in the section and wait set a roof beam in place in section of having set a roof beam in place, described in each first ear mount and one respectively Steel cable is detachably connected.
Based on the above technical solution, extension bar is connect in one end of second pair of drawing mechanism and section of having set a roof beam in place, The other end is connect with wait the vertical bar in section of setting a roof beam in place close to this to extension bar.
Second aspect, the embodiment of the present invention also provide a kind of docking facilities of big segment steel truss girder, are used for big by two Segment steel truss girder is docked, and defining two big segment steel truss girder is set a roof beam in place section and section to be set a roof beam in place;The big segment steel truss girder Include:
The several groups string beam element of parallel interval setting, every group of string beam element include one wind up, a lower edge, at least one with It is described wind up the vertical bar being connected with lower edge and two be set to outside all vertical bars to extension bar;
Several cross bearers, wind up described in each adjacent two between be equipped at least two cross bearers, wait in section of setting a roof beam in place Cross bearer is oppositely arranged with the cross bearer in section of having set a roof beam in place;
The docking facilities include:
First pair of drawing mechanism, one end for connect with the cross bearer in section of having set a roof beam in place, the other end for wait set a roof beam in place Corresponding cross bearer connection in section;
Second pair of drawing mechanism, both ends are respectively used to be located at the middle part of the set a roof beam in place section, section to be set a roof beam in place;
Top lifting mechanism comprising lift up device;The bottom of the lift up device be used to be set to it is described wait winding up in section of setting a roof beam in place, Top is for being fixedly installed;The lift up device is used in upward top lifting, pushes the section to be set a roof beam in place.
The third aspect, the embodiment of the present invention also provide a kind of interconnection method of big segment steel truss girder, and the interconnection method is logical It crosses above-mentioned docking facilities such as to realize, the step of interconnection method includes:
Step 1: will align and dock with all lower edges in section of having set a roof beam in place wait all lower edges in section of setting a roof beam in place;
Step 2: using first pair of drawing mechanism to drawing Duan Yuyi to be set a roof beam in place to set a roof beam in place the cross bearer in section, slightly aligning section to be set a roof beam in place In to extension bar with set a roof beam in place in section to extension bar;
Step 3: using second pair of drawing mechanism to drawing Duan Yuyi to be set a roof beam in place to set a roof beam in place the middle part of section, exactitude position and to reception frame In beam section to extension bar with set a roof beam in place in section to extension bar;
Step 4: using the upward top lifting of lift up device in top lifting mechanism, pushing is described wait winding up in section of setting a roof beam in place, and contraposition is simultaneously It winds up described in docking, that is, completes the docking of big segment steel truss girder.
Based on the above technical solution, the specific steps of the step 4 include:
Step 401: reuse first pair of drawing mechanism to drawing Duan Yuyi to be set a roof beam in place to set a roof beam in place the cross bearer in section, thick contraposition to Winding up and winding up in section of having set a roof beam in place in section of setting a roof beam in place;
Step 402: using the upward top lifting of lift up device in top lifting mechanism, pushing is described wait winding up in section of setting a roof beam in place, accurately It aligns and sets a roof beam in place winding up and winding up in section of having set a roof beam in place in section to reception.
Based on the above technical solution, first pair of drawing mechanism includes the first ear mount, second pair of drawing mechanism Including the second ear mount, the top lifting mechanism includes third ear mount;The step 1 further include:
Before docking lower edge, first ear mount, the second ear mount, third ear mount are preset in section of having set a roof beam in place, to frame In beam section.
Compared with the prior art, the advantages of the present invention are as follows:
(1) embodiment of the present invention provides a kind of docking facilities of big segment steel truss girder, at the docking of big segment steel truss girder Reasonable layout regulating device effectively adjusts the relative deformation set a roof beam in place between section and the banjo fixing butt jointing of section to be set a roof beam in place, and realizes big section The rapid abutting joint construction of section steel truss girder, improves joint quality.
(2) regulating device used in the embodiment of the present invention, structure is simple, and can Reusability, improve utilization rate, reduce work Cheng Chengben.
(3) embodiment of the present invention provides a kind of interconnection method of big segment steel truss girder, and this method is in particular order, right The relative deformation set a roof beam in place between section and the banjo fixing butt jointing of section to be set a roof beam in place should be adjusted, realizes that the rapid abutting joint of big segment steel truss girder is applied Work improves joint quality and sets up work efficiency.
Detailed description of the invention
Fig. 1 is the docking facilities facade arrangement schematic diagram of big segment steel truss girder in the embodiment of the present invention;
Fig. 2 is the docking facilities side arrangement schematic diagram of big segment steel truss girder in the embodiment of the present invention;
Fig. 3 is that the vertical view of the docking facilities of the big segment steel truss girder of the embodiment of the present invention arranges simplified schematic diagram;
Fig. 4 is the schematic diagram of top lifting mechanism and Fig. 1 same view angle;
Fig. 5 is the schematic diagram of first pair of drawing mechanism and Fig. 1 same view angle;
In figure: 1, string beam element;11, it winds up;12, lower edge;13, vertical bar;14, brace;140, to extension bar;2, big horizontal Beam;3, first pair of drawing mechanism;31, the first ear mount;32, wrap-up;33, steel cable;34, nut;4, second pair of drawing mechanism;5, it rises Push up mechanism;50, lift up device;51, third ear mount;52, shoulder pole girder;53, pin shaft;A, it has set a roof beam in place section;B, section to be set a roof beam in place.
Specific embodiment
The present invention is described in further detail below through specific implementation examples and in conjunction with the accompanying drawings.
Embodiment
Referring to shown in Fig. 1~3, the embodiment of the present invention provides a kind of docking facilities of big segment steel truss girder, is used for two A big segment steel truss girder is docked, and defines two big segment steel truss girder as section A and wait section B that sets a roof beam in place of having set a roof beam in place;The big segment Steel truss girder includes:
The several groups string beam element 1 of parallel interval setting, every group of string beam element 1 include one winding up 11, one lower edge 12, at least One with it is described wind up 11 and the vertical bar 13 that is connected of lower edge 12 and two be set to outside all vertical bars 13 to extension bar 140;
Several cross bearers 2 wind up described in each adjacent two and are equipped at least two cross bearers 2, and two institutes between 11 State cross bearer 2 be respectively arranged on two described in wind up 11 both ends, wait in section B that sets a roof beam in place cross bearer 2 and the big cross set a roof beam in place in section A Beam 2 is oppositely arranged;
The docking facilities include:
First pair of drawing mechanism 3, one end are connect with wait the cross bearer 2 in section B that sets a roof beam in place, in the other end and section A that set a roof beam in place Corresponding cross bearer 2 connects;When first pair of drawing mechanism 3 is when to drawing, the cross bearer 2 wait section B that sets a roof beam in place is to described Corresponding cross bearer 2 in section A of having set a roof beam in place is close;
Second pair of drawing mechanism 4, both ends are respectively provided at section A that set a roof beam in place, wait the middle part for section B that sets a roof beam in place;When described second To drawing mechanism 4 when to drawing, a pair of of extension bar 140 wait in section B that sets a roof beam in place is corresponding to extension bar into section A that set a roof beam in place 140 is close;
Top lifting mechanism 5 comprising lift up device 50;The lift up device 50 be set to it is described wait winding up on 11 in section B that sets a roof beam in place, and The top of the lift up device 50 is fixedly installed;It is described to be pushed wait section B that sets a roof beam in place when the 50 upward top lifting of lift up device.
The principle of the invention is carried out below with reference to the docking facilities of the embodiment of the present invention and the usage mode of the docking facilities It illustrates.In the actual construction process, using suspender suspend in midair wait set a roof beam in place section B so that wait in section B that sets a roof beam in place lower edge 12 with set a roof beam in place Lower edge 12 in section A is aligned and is docked;Using first pair of drawing mechanism 3 to the cross bearer 2 in section A that set a roof beam in place and wait in section B that sets a roof beam in place Cross bearer 2 carry out shortening the cross bearer 2 wait section B that sets a roof beam in place and corresponding cross bearer 2 in section A that set a roof beam in place to drawing Between space length, further also tentatively shorten wait in section B that sets a roof beam in place to extension bar 140 and corresponding docking in section A that set a roof beam in place Space length between bar 140;Section A that set a roof beam in place is drawn, wait the middle part for section B that sets a roof beam in place using second pair 4 pairs of drawing mechanism, shortens institute It states wait a pair of of extension bar 140 and the corresponding space length to extension bar 140 in section A that set a roof beam in place in section B that sets a roof beam in place, so that described Set a roof beam in place in section A to extension bar 140 and wait in section B that sets a roof beam in place to the effectively contraposition docking of extension bar 140;It will be to using top lifting mechanism 5 Set a roof beam in place section B wind up 11 press to section A that set a roof beam in place wind up 11 it is concordant after will wind up and 11 dock, due to the top of lift up device 50 It is fixed setting, therefore, when the upward top lifting of lift up device 50, then the effect by power, the bottom of the lift up device 50 is downward Movement, and then lead to 11 pushings of winding up being connected with lift up device 50, achieve the purpose that instead to push up described wait section B that sets a roof beam in place.First pair of drawing Winding up for being not aligned with 11 and is aligned and is docked to extension bar 140 by 3, second pairs of drawing mechanisms 4 of mechanism and top lifting mechanism 5, is adjusted Relative displacement between beam section connector, and then improve merging precision and joint quality.
In embodiments of the present invention, section A and be big segment steel truss girder wait section B that sets a roof beam in place of having set a roof beam in place, theoretically comes It says, by after the lower edge 12 for section B that sets a roof beam in place is docked with section A that set a roof beam in place, 11 and is and frame to extension bar 140 wait winding up for section B that sets a roof beam in place What beam section A can be aligned and be docked just, however, in actual work progress, for big segment steel truss girder, by It has been formed in it from great stable structure, therefore after the lower edge 12 for lifting section B that sets a roof beam in place to reception, wait section B that sets a roof beam in place Wind up and 11 and alignment be practically without to extension bar 140, there are vertical, axially opposing deformations, wherein wait in section A that sets a roof beam in place Wind up 11 docking at be above wind up in section B that set a roof beam in place 11 height, under these conditions, being wait section B that sets a roof beam in place can not be straight It connects and with section A that set a roof beam in place aligns and dock.Using a kind of docking facilities of big segment steel truss girder provided in an embodiment of the present invention, Can by it is vertical, axially be not aligned with wind up 11 and to extension bar 140 align and dock, by shorten adjust wait set a roof beam in place section B with The relative displacement set a roof beam in place between section A center tap, achievees the purpose that exactitude position, to directly be docked, effectively improves pair Connect precision and joint quality.
Specifically, the lift up device 50 is jack.Jack source is wide, cheap, advantageously reduces docking facilities Economic cost.
Referring to shown in Fig. 1~3, in embodiments of the present invention, set a roof beam in place section A and the section to be set a roof beam in place of the docking facilities docking It include three groups of string beam elements 1 in B, every group of string beam element 1 includes that 11, one lower edge, 12, two parallel verticals settings of winding up exist The brace 14 set on the diagonal line of 13, two vertical bars 13 of vertical bar winded up between 11 and lower edge 12 and two Outside all vertical bars 13 to extension bar 140, wherein can be with phase in section A that set a roof beam in place wait a pair of of extension bar 140 in section B that sets a roof beam in place It is corresponding to extension bar 140 be connected constitute an oblique rod identical with the brace 14.Wherein, two adjacent to wind up between 11 If there are two cross bearer 2, two cross bearers 2 be located at it is described wind up 11 both ends, for the big segment steel that connects Trusses connects.
Shown in Figure 4, as further improving and supplementing to the present embodiment, the top lifting mechanism 5 further includes one flat Spreader beam 52, one end are described flat with 11 connections of winding up in section A that set a roof beam in place, the other end and wait 11 connections of winding up in section B that sets a roof beam in place Spreader beam 52 is installed in the top of the lift up device 50;It is described to frame when the lift up device 50 jacks up the shoulder pole girder 52 upwards Winding up in beam section B 11 moves downward.52 easy processing of shoulder pole girder, source is wide, can consolidate by welding with lift up device 50 Even, entire mode is simply easily constructed.Meanwhile shoulder pole girder 52 being erected to the top of lift up device 50, and the both ends of shoulder pole girder 52 are solid It is fixed, when increasing the length of lift up device 50, due to the top of lift up device 50 is confined, lift up device 50 downwardly against with rise Apical organ 50 it is direct-connected wind up 11, therefore, can be concordant with section A that set a roof beam in place by being pressed to wait section B that sets a roof beam in place of upwarping, be conducive to wind up 11 Contraposition docking.
Further, the top lifting mechanism 5 further includes two third ear mounts 51, is installed in winding up for section A that set a roof beam in place respectively 11 and winding up on 11 wait section B that sets a roof beam in place, the both ends of the shoulder pole girder 52 pass through pin shaft 53 and two third ear mounts 51 respectively It is detachably connected.By the way that third ear mount 51 is arranged on 11 winding up, by the both ends of shoulder pole girder 52 by can by way of pin joint The mode of disassembly, which is connected in, winds up on 11, the anti-top purpose wait section B that sets a roof beam in place of lift up device 50 not only may be implemented, also, can The mode of disassembly is conducive to the Reusability of top lifting mechanism 5, when needing using top lifting mechanism 5, using pin shaft 53 by shoulder pole girder 52 are mounted in third ear mount 51, conversely, can then disassemble shoulder pole girder 52 so that next time continues to use, improve docking facilities In components frequency of use, the expenditure cost of construction installation is effectively reduced.
Shown in referring to fig. 2~3, each wind up 11 top be equipped with top lifting mechanism 5, meanwhile, the both ends of the top lifting mechanism 5 Also it is connected respectively with wait section B that sets a roof beam in place, section A that set a roof beam in place, multiple top lifting mechanisms 5 is set along the axial direction of big segment steel truss girder, Improve on big segment steel truss girder it is multiple wind up 11 docking point docking it is accurate, reduce the opposite position between entire beam section interface It moves, it is ensured that the joint quality of entire big segment steel truss girder avoids attending to one thing and lose sight of another, improves the precision of docking.
It is shown in Figure 5, as the first embodiment of first pair of drawing mechanism in the embodiment of the present invention, described first pair Drawing mechanism 3 includes steel cable 32 and a jack 33, and 32 both ends of steel cable are connected with two opposite cross bearers 2 respectively;It is described Jack 33 is set to one end of the steel cable 32, for shrinking the length of the steel cable 32.By be oppositely arranged two cross bearers It carries out shortening the space length of cross bearer 2 to drawing by jack 33, interval is shortened wait in the middle part of section B that sets a roof beam in place, section A that set a roof beam in place To the space length between extension bar 140.
Further, first pair of drawing mechanism further includes two first ear mounts 31, be installed in respectively set a roof beam in place section A and to It sets a roof beam in place on section B, each first ear mount 31 is detachably connected with a steel cable 32.Specifically, the both ends of the steel cable 32 Two the first ear mounts 31 are each passed through, one end is fastened by nut 34, and the other end is connected on jack 33, passes through jack 33 Adjust the length for shrinking the steel cable 32, with realize two cross bearers 2 to drawing, and in the present embodiment, dismountable mode Be conducive to the Reusability of first pair of drawing mechanism.
As second of embodiment of first pair of drawing mechanism in the embodiment of the present invention, first pair of drawing mechanism includes two Ear mount, two wrap-ups and a steel cable, two ear mounts are installed in section A and wait set a roof beam in place on section B of having set a roof beam in place respectively, each described Ear mount is detachably connected with a wrap-up, and the steel cable both ends are connected with two wrap-ups respectively, and can be wound around On the wrap-up.This form of implementation has existed in the prior art, therefore, is not illustrated in Figure of description. Two cross bearers that first pair of drawing mechanism will be oppositely arranged by the way of winding steel cable carry out shortening cross bearer to drawing Space length, interval shorten in the middle part of wait section B that sets a roof beam in place, section A that set a roof beam in place to the space length between extension bar, secondly, by will receive Winding apparatus is removably connected on cross bearer, not only may be implemented to the purpose drawn wait section B that sets a roof beam in place, section A that set a roof beam in place, Also, the Reusability that dismountable mode is conducive to first pair of drawing mechanism will be wound when needing using first pair of drawing mechanism Device is mounted in ear mount, conversely, can then disassemble first pair of drawing mechanism so that next time continues to use, improves docking facilities In components frequency of use, the expenditure cost of construction installation is effectively reduced.
As the third embodiment of first pair of drawing mechanism in the embodiment of the present invention, first pair of drawing mechanism 3 includes One wirerope, a fluid-pressure straining device, it is described wait section B that sets a roof beam in place equipped with a hole, one end of the wirerope be installed in it is described It sets a roof beam in place on a cross bearer 2 of section A, the other end passes through fluid-pressure straining device described in the Kong Houyu and is connected, by controlling hydraulic tensioning Device adjusts the length of wirerope, with reach shorten the cross bearer 2 wait section B that sets a roof beam in place with it is right in section A that set a roof beam in place The space length for the cross bearer 2 answered.
Shown in referring to fig. 2~3, uniformly distributed on each cross bearer 2 there are two first pair of drawing mechanism 3, first pair of rational deployment drawings The quantity of mechanism 3 can accurately be docked the biggish cross bearer of span 2 is whole, realize entire cross bearer 2 biggish Accurate docking in span, further increases joint quality.Meanwhile first pair of drawing mechanism 3 being set to the upper surface of cross bearer 2, Top lifting mechanism 5, which is located at, winds up on 11, is provided at the top of steel truss girder, improves mostly to the operating surface drawn or when top lifting operates Operability of constructing and the security performance of high altitude operation.
It is shown in Figure 1, as a kind of preferred embodiment of the embodiment of the present invention, one end of second pair of drawing mechanism 4 with It has set a roof beam in place and extension bar 140 has been connected in section A, the other end is connect with wait the vertical bar 13 to extension bar 140 close in section B that sets a roof beam in place.It will One end of second pair of drawing mechanism 4 is fixed in the vertical bar 13 wait section B that sets a roof beam in place, the other end be fixed on section A that set a roof beam in place to extension bar On 140, in conjunction with vertical, the axial relative displacement to extension bar 140, embodiments thereof are simple to operation.Specifically, second pair of drawing 4 one end of mechanism is set to the centre or more on the upper side of the vertical bar 13 wait section B that sets a roof beam in place, and the other end is set to the docking in section A that set a roof beam in place The free end of bar 140, also can effectively avoid to during drawing wait in section B that sets a roof beam in place with it is opposite to extension bar 140 in section A that set a roof beam in place The interference to extension bar 140.
In embodiments of the present invention, second pair of drawing mechanism 4 is similar to the mechanism of first pair of drawing mechanism 3, described Second pair of drawing mechanism 4 includes the second ear mount, the second rolling-up mechanism, the second steel cable, and therefore, second pair of drawing mechanism 4 is illustrating Book attached drawing is not shown, and the specific structure of second pair of drawing mechanism 4 no longer repeats one by one in sheet, and certainly, second pair of drawing mechanism 4 is also Can for it is in the prior art any one to pull-up structure.When the distance between second pair of 4 both ends of drawing mechanism be it is accessible most When short distance, when being mounted on other positions relative to second pair of drawing mechanism 4 to drawing ability, tensioning ability is stronger, therefore, in this way Setting effective tensioning effectively can be carried out to extension bar 140.
As the another way of the embodiment of the present invention, one end of second pair of drawing mechanism 4 is set to pair wait section B that sets a roof beam in place On extension bar 140, the other end is set to the set a roof beam in place section A opposite to extension bar 140 wait section B that sets a roof beam in place on extension bar 140, this The distance of steel cable in kind arrangement in second pair of drawing mechanism 4 can reach minimum, be conducive to pull, the present embodiment is not being said It is illustrated in bright book attached drawing.
A kind of docking facilities of big segment steel truss girder provided in an embodiment of the present invention, it is therein to drawing mechanism, top lifting mechanism Source be conventional facility, when these mechanisms are reasonably arranged on big segment steel truss girder and are collocated with each other, can will Two big segment steel truss girders are effectively docked, and adjust the relative displacement between beam section connector, and then improve merging precision and right Connect quality.
Docking for big segment steel truss girder in the construction of one bridge, needs repeatedly to be docked, will be in docking facilities The first ear mount 31, the second ear mount, third ear mount 51 be arranged on steel truss girder in advance, do not influence lifting operation, save the duration;Also Can docking components effectively in Reusability docking facilities, the construction cost in docking construction is saved, for big segment steel truss Erection has highly application value.
Referring to shown in Fig. 1~2, the embodiment of the present invention also provides second aspect, and the embodiment of the present invention also provides a kind of big section The docking facilities of section steel truss girder, are used to dock two big segment steel truss girders, and defining two big segment steel truss girder is Set a roof beam in place section A and wait section B that sets a roof beam in place;The big segment steel truss girder includes:
The several groups string beam element 1 of parallel interval setting, every group of string beam element 1 include one winding up 11, one lower edge 12, at least One with it is described wind up 11 and the vertical bar 13 that is connected of lower edge 12 and two be set to outside all vertical bars 13 to extension bar 140;
Several cross bearers 2 wind up described in each adjacent two and are equipped at least two cross bearers 2 between 11, wait section B that sets a roof beam in place In cross bearer 2 be oppositely arranged with the cross bearer 2 in section A that set a roof beam in place;
The docking facilities include:
First pair of drawing mechanism 3, one end for connect with the cross bearer 2 in section A that set a roof beam in place, the other end for to frame Corresponding cross bearer 2 connects in beam section B;
Second pair of drawing mechanism 4, both ends are respectively used to be located at section A that set a roof beam in place, wait the middle part for section B that sets a roof beam in place;
Top lifting mechanism 5 comprising lift up device 50;The bottom of the lift up device 50 is used to be set to described wait in section B that sets a roof beam in place It winds up on 11, top is for being fixedly installed;The lift up device 50 is used in upward top lifting, is pushed described wait section B that sets a roof beam in place.
Provided in an embodiment of the present invention is state of the docking facilities when not constructing, when in use, first pair of drawing mechanism 3, winding up of being not aligned with 11 and is aligned and is docked to extension bar 140 by second pair of drawing mechanism 4 and top lifting mechanism 5, adjusts beam section Relative displacement between connector, and then improve merging precision and joint quality.
The embodiment of the present invention also provides a kind of interconnection method of big segment steel truss girder, and the interconnection method passes through as above-mentioned Docking facilities realize, the step of interconnection method includes:
Step 1: will align and dock with all lower edges 12 in section A that set a roof beam in place wait all lower edges 12 in section B that sets a roof beam in place;
Step 2: being drawn wait the cross bearer 2 in section B and section A that set a roof beam in place that sets a roof beam in place using first pair 3 Duis of drawing mechanism, thick contraposition is to frame In beam section B to extension bar 140 with set a roof beam in place in section A to extension bar 140;
Step 3: the middle part drawn wait set a roof beam in place section B and section A that set a roof beam in place using second pair 4 Duis of drawing mechanism, exactitude position are simultaneously docked Wait in section B that sets a roof beam in place in the extension bar 140 and section A that set a roof beam in place to extension bar 140;
Step 4: using the upward top lifting of lift up device 50 in top lifting mechanism 5, push it is described wait wind up 11 in section B that sets a roof beam in place, Align and dock it is described wind up 11, that is, complete the docking of big segment steel truss girder.
In order to further increase joint quality, further, the specific steps of the step 4 include:
Step 401: it reuses 3 pairs of first pair of drawing mechanism and draws wait the cross bearer 2 in section B and section A that set a roof beam in place that sets a roof beam in place, it is thick right 11 11 are winded up in section A with having set a roof beam in place wait winding up in section B that sets a roof beam in place in position;
Step 402: using the upward top lifting of lift up device 50 in top lifting mechanism 5, pushing described wait winding up in section B that sets a roof beam in place 11, exactitude position simultaneously 11 winds up 11 with section A that set a roof beam in place to reception winding up in section B of setting a roof beam in place.
Specifically, first pair of drawing mechanism 3 includes the first ear mount 31, and second pair of drawing mechanism 4 includes the second ear mount, The top lifting mechanism 5 includes third ear mount 51;The step 1 further include:
Before docking lower edge 12, first ear mount 31, the second ear mount, third ear mount 51 are preset in section of having set a roof beam in place A, wait set a roof beam in place on section B.
In embodiments of the present invention, in particular order, i.e., first coarse adjustment accurate adjustment is to dock to extension bar 140, In for this method It 11 is docked to winding up, it is corresponding to adjust the relative deformation set a roof beam in place between section and the banjo fixing butt jointing of section to be set a roof beam in place, realize big section The rapid abutting joint construction of section steel truss girder, improves joint quality and sets up work efficiency, and components used in interconnection method are simply easy , interconnection method is simple, being capable of the big segment steel truss girder of effective rapid abutting joint;Secondly, default first ear mount 31, the second ear mount, the Docking facilities and big segment steel truss girder are detachably connected by three ear mounts 51, are conducive to docking facilities and are continued to use for docking next time, The frequency of use for improving the components in docking facilities, is effectively reduced the expenditure cost of construction installation.
The present invention is not limited to the above-described embodiments, for those skilled in the art, is not departing from Under the premise of the principle of the invention, several improvements and modifications can also be made, these improvements and modifications are also considered as protection of the invention Within the scope of.The content being not described in detail in this specification belongs to the prior art well known to professional and technical personnel in the field.

Claims (10)

1. a kind of docking facilities of big segment steel truss girder are used to dock two big segment steel truss girders, define two big Segment steel truss girder is set a roof beam in place section (A) and section to be set a roof beam in place (B);The big segment steel truss girder includes:
The several groups string beam element (1) of parallel interval setting, every group of string beam element (1) include one wind up (11), a lower edge (12), At least one winds up (11) and vertical bar (13) that lower edge (12) is connected and two are set to all vertical bars (13) with described Outside to extension bar (140);
Several cross bearers (2) wind up described in each adjacent two and are equipped at least two cross bearers (2) between (11), and two The cross bearer (2) is winded up the both ends of (11) described in being respectively arranged on two, the cross bearer (2) in section (B) to be set a roof beam in place with set a roof beam in place Cross bearer (2) in section (A) is oppositely arranged;
It is characterized in that, the docking facilities include:
First pair of drawing mechanism (3), one end are connect with the cross bearer (2) in section to be set a roof beam in place (B), the other end and section of having set a roof beam in place (A) corresponding cross bearer (2) connection in;When first pair of drawing mechanism (3) is when to drawing, the one of the section (B) to be set a roof beam in place is big Crossbeam (2) Xiang Suoshu corresponding cross bearer (2) in section (A) of having set a roof beam in place is close;
Second pair of drawing mechanism (4), both ends are respectively provided at the middle part of the set a roof beam in place section (A), section to be set a roof beam in place (B);When described When to drawing, a pair of of extension bar (140) Xiang Suoshu in the section (B) to be set a roof beam in place has set a roof beam in place corresponding in section (A) two pairs of drawing mechanisms (4) It is close to extension bar (140);
Top lifting mechanism (5) comprising lift up device (50);The lift up device (50) is set to winding up in the section (B) to be set a roof beam in place (11) on, and the top fixed setting of the lift up device (50);When the lift up device (50) upward top lifting, the section to be set a roof beam in place (B) it pushes.
2. the docking facilities of big segment steel truss girder as described in claim 1, which is characterized in that the top lifting mechanism (5) is also wrapped It includes:
One shoulder pole girder (52), one end are connect with wind up (11) in section of having set a roof beam in place (A), in the other end and section to be set a roof beam in place (B) It winds up (11) connection, the shoulder pole girder (52) is installed in the top of the lift up device (50);When the lift up device (50) pushes up upwards When playing shoulder pole girder (52), wind up (11) in the section (B) to be set a roof beam in place are moved downward.
3. the docking facilities of big segment steel truss girder as claimed in claim 2, which is characterized in that the top lifting mechanism (5) is also wrapped It includes:
Two third ear mounts (51), be installed in respectively section of having set a roof beam in place (A) wind up (11) and section to be set a roof beam in place (B) winds up (11) On, the both ends of the shoulder pole girder (52) pass through pin shaft (53) respectively and are detachably connected with two third ear mounts (51).
4. the docking facilities of big segment steel truss girder as described in claim 1, which is characterized in that first pair of drawing mechanism (3) Include:
Steel cable (32), both ends are connected with two opposite cross bearers (2) respectively;
Jack (33) is set at least one end of the steel cable (32), for shrinking the length of the steel cable (32).
5. the docking facilities of big segment steel truss girder as claimed in claim 4, which is characterized in that first pair of drawing mechanism (3) Further include:
Two first ear mounts (31), are installed in respectively in section of having set a roof beam in place (A) and section to be set a roof beam in place (B), each first ear mount (31) detachably it is connected with a steel cable (32).
6. the docking facilities of big segment steel truss girder as described in claim 1, which is characterized in that second pair of drawing mechanism (4) One end extension bar (140) is connect with section of having set a roof beam in place (A), close to this to extension bar (140) in the other end and section to be set a roof beam in place (B) Vertical bar (13) connection.
7. a kind of docking facilities of big segment steel truss girder are used to dock two big segment steel truss girders, define two big Segment steel truss girder is set a roof beam in place section (A) and section to be set a roof beam in place (B);The big segment steel truss girder includes:
The several groups string beam element (1) of parallel interval setting, every group of string beam element (1) include one wind up (11), a lower edge (12), At least one winds up (11) and vertical bar (13) that lower edge (12) is connected and two are set to all vertical bars (13) with described It is outer to extension bar (140);
Several cross bearers (2) wind up described in each adjacent two and are equipped at least two cross bearers (2) between (11), wait set a roof beam in place Cross bearer (2) in section (B) is oppositely arranged with the cross bearer (2) in section of having set a roof beam in place (A);
It is characterized in that, the docking facilities include:
First pair of drawing mechanism (3), one end for connect with the cross bearer (2) in section of having set a roof beam in place (A), the other end for to Corresponding cross bearer (2) connection in section of setting a roof beam in place (B);
Second pair of drawing mechanism (4), both ends are respectively used to be located at the middle part of the set a roof beam in place section (A), section to be set a roof beam in place (B);
Top lifting mechanism (5) comprising lift up device (50);The bottom of the lift up device (50) is used to be set to the section (B) to be set a roof beam in place In wind up on (11), top is for being fixedly installed;The lift up device (50) is used in upward top lifting, pushes described wait set a roof beam in place Section (B).
8. a kind of interconnection method of big segment steel truss girder, which is characterized in that the interconnection method passes through as described in claim 1 Docking facilities realize, the step of interconnection method includes:
Step 1: by section to be set a roof beam in place (B) all lower edges (12) in section of having set a roof beam in place (A) all lower edges (12) contraposition and it is right It connects;
Step 2: thick to align using first pair of drawing mechanism (3) to the cross bearer (2) for drawing section to be set a roof beam in place (B) with having set a roof beam in place in section (A) In section (B) to be set a roof beam in place to extension bar (140) with set a roof beam in place in section (A) to extension bar (140);
Step 3: using second pair of drawing mechanism (4) to the middle part for drawing section to be set a roof beam in place (B) with section (A) that set a roof beam in place, exactitude position is simultaneously right Reception set a roof beam in place in section (B) to extension bar (140) with set a roof beam in place in section (A) to extension bar (140);
Step 4: using lift up device (50) upward top lifting in top lifting mechanism (5), pushing winding up in the section (B) to be set a roof beam in place (11), align and dock it is described wind up (11), that is, complete the docking of big segment steel truss girder.
9. the interconnection method of big segment steel truss girder according to claim 8, which is characterized in that the specific step of the step 4 Suddenly include:
Step 401: reuse first pair of drawing mechanism (3) to the cross bearer (2) for drawing section to be set a roof beam in place (B) with having set a roof beam in place in section (A), It slightly aligns winding up in section to be set a roof beam in place (B) (11) and winds up (11) in section (A) with having set a roof beam in place;
Step 402: using lift up device (50) upward top lifting in top lifting mechanism (5), pushing winding up in the section (B) to be set a roof beam in place (11), exactitude position and (11) are winded up in section (A) with having set a roof beam in place to reception winding up in section (B) (11) of setting a roof beam in place.
10. the interconnection method of big segment steel truss girder according to claim 8, which is characterized in that first pair of drawing mechanism It (3) include the first ear mount (31) that second pair of drawing mechanism (4) includes the second ear mount, and the top lifting mechanism (5) includes third ear Seat (51);The step 1 further include:
Before docking lower edge (12), first ear mount (31), the second ear mount, third ear mount (51) are preset in and have been set a roof beam in place In section (A), section to be set a roof beam in place (B).
CN201910696451.6A 2019-07-30 2019-07-30 Butt joint device and butt joint method for large-section steel truss girder Active CN110512521B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910696451.6A CN110512521B (en) 2019-07-30 2019-07-30 Butt joint device and butt joint method for large-section steel truss girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910696451.6A CN110512521B (en) 2019-07-30 2019-07-30 Butt joint device and butt joint method for large-section steel truss girder

Publications (2)

Publication Number Publication Date
CN110512521A true CN110512521A (en) 2019-11-29
CN110512521B CN110512521B (en) 2021-06-29

Family

ID=68624662

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910696451.6A Active CN110512521B (en) 2019-07-30 2019-07-30 Butt joint device and butt joint method for large-section steel truss girder

Country Status (1)

Country Link
CN (1) CN110512521B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111188273A (en) * 2019-12-31 2020-05-22 湖北省路桥集团有限公司 Large-section steel truss girder erection system of large-span steel-concrete composite bridge and construction method
CN113123250A (en) * 2021-05-10 2021-07-16 南通帆森能源科技有限公司 Precise assembling and adjusting device for steel truss girder and assembling construction method

Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1081265A1 (en) * 1983-01-03 1984-03-23 Специальное Конструкторское Бюро Главмостостроя Joint of longitudinal girders
JP2003193430A (en) * 2001-12-28 2003-07-09 Kajima Corp Construction method of composite truss bridge
JP2003293320A (en) * 2002-04-02 2003-10-15 Oriental Construction Co Ltd Erection device of diagonal member in composite truss bridge and erection method
JP2004238796A (en) * 2003-02-03 2004-08-26 Kawada Construction Co Ltd Floor-slab separator
JP2010095898A (en) * 2008-10-16 2010-04-30 Ihi Corp Trussed setting beam
CN102352604A (en) * 2011-08-05 2012-02-15 中铁大桥局股份有限公司 Truss sheet unit of steel truss girder, steel truss girder structure and mounting method thereof
CN102828471A (en) * 2012-09-07 2012-12-19 中铁二十三局集团第三工程有限公司 Butt-jointing method for truss girder
CN102979033A (en) * 2012-11-16 2013-03-20 中铁大桥勘测设计院集团有限公司 Steel truss girder all-welded joist slice and construction method thereof
CN103147405A (en) * 2013-04-03 2013-06-12 中铁大桥局股份有限公司 Method for erecting steel girder of cable-stayed bridge with diagonal main trusses
CN103290785A (en) * 2013-06-30 2013-09-11 中铁一局集团有限公司 Closure method for height variable continuous steel truss girder
CN204849608U (en) * 2015-06-03 2015-12-09 中交第二航务工程局有限公司 Steel longeron cable -stay bridge rackwork that joins two sections of a bridge, etc fast
CN105951609A (en) * 2016-03-23 2016-09-21 中铁四局集团钢结构有限公司 Wide span variable girder high continuous steel truss bridge cantilever erection mid-span closure construction method
CN106223183A (en) * 2016-09-13 2016-12-14 长安大学 Assembled concrete-filled rectangular steel tube combination truss bridge and construction method
CN206143636U (en) * 2016-10-14 2017-05-03 中交一公局第五工程有限公司 Closure of steel longeron is turned over and is pushed up fine tuning device
CN106835989A (en) * 2017-02-10 2017-06-13 中交路桥华南工程有限公司 The method that floorings installation is carried out using truss-like assistance platform
KR20180019864A (en) * 2016-08-17 2018-02-27 한국철도기술연구원 CONSTRUCTION METHOD OF HYBRID RAILWAY BRIDGE USING PRESTRESSED CONCRETE FILLED TUBE and TRANSVERSE PRESTRESSED CONCRETE BLOCK
CN107761570A (en) * 2017-09-30 2018-03-06 中铁大桥局集团有限公司 It is a kind of to be accurately positioned suspension bracket for longspan steel truss girder
US20180127979A1 (en) * 2016-11-08 2018-05-10 University Of Notre Dame Du Lac Modular truss joint
CN109972533A (en) * 2019-04-24 2019-07-05 中铁十二局集团有限公司 A kind of thrustor for steel truss girder bridge closure

Patent Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1081265A1 (en) * 1983-01-03 1984-03-23 Специальное Конструкторское Бюро Главмостостроя Joint of longitudinal girders
JP2003193430A (en) * 2001-12-28 2003-07-09 Kajima Corp Construction method of composite truss bridge
JP2003293320A (en) * 2002-04-02 2003-10-15 Oriental Construction Co Ltd Erection device of diagonal member in composite truss bridge and erection method
JP2004238796A (en) * 2003-02-03 2004-08-26 Kawada Construction Co Ltd Floor-slab separator
JP2010095898A (en) * 2008-10-16 2010-04-30 Ihi Corp Trussed setting beam
CN102352604A (en) * 2011-08-05 2012-02-15 中铁大桥局股份有限公司 Truss sheet unit of steel truss girder, steel truss girder structure and mounting method thereof
CN102828471A (en) * 2012-09-07 2012-12-19 中铁二十三局集团第三工程有限公司 Butt-jointing method for truss girder
CN102979033A (en) * 2012-11-16 2013-03-20 中铁大桥勘测设计院集团有限公司 Steel truss girder all-welded joist slice and construction method thereof
CN103147405A (en) * 2013-04-03 2013-06-12 中铁大桥局股份有限公司 Method for erecting steel girder of cable-stayed bridge with diagonal main trusses
CN103290785A (en) * 2013-06-30 2013-09-11 中铁一局集团有限公司 Closure method for height variable continuous steel truss girder
CN204849608U (en) * 2015-06-03 2015-12-09 中交第二航务工程局有限公司 Steel longeron cable -stay bridge rackwork that joins two sections of a bridge, etc fast
CN105951609A (en) * 2016-03-23 2016-09-21 中铁四局集团钢结构有限公司 Wide span variable girder high continuous steel truss bridge cantilever erection mid-span closure construction method
KR20180019864A (en) * 2016-08-17 2018-02-27 한국철도기술연구원 CONSTRUCTION METHOD OF HYBRID RAILWAY BRIDGE USING PRESTRESSED CONCRETE FILLED TUBE and TRANSVERSE PRESTRESSED CONCRETE BLOCK
CN106223183A (en) * 2016-09-13 2016-12-14 长安大学 Assembled concrete-filled rectangular steel tube combination truss bridge and construction method
CN206143636U (en) * 2016-10-14 2017-05-03 中交一公局第五工程有限公司 Closure of steel longeron is turned over and is pushed up fine tuning device
US20180127979A1 (en) * 2016-11-08 2018-05-10 University Of Notre Dame Du Lac Modular truss joint
CN106835989A (en) * 2017-02-10 2017-06-13 中交路桥华南工程有限公司 The method that floorings installation is carried out using truss-like assistance platform
CN107761570A (en) * 2017-09-30 2018-03-06 中铁大桥局集团有限公司 It is a kind of to be accurately positioned suspension bracket for longspan steel truss girder
CN109972533A (en) * 2019-04-24 2019-07-05 中铁十二局集团有限公司 A kind of thrustor for steel truss girder bridge closure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周外男: "铜陵公铁两用长江大桥主桥施工关键技术", 《桥梁建设》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111188273A (en) * 2019-12-31 2020-05-22 湖北省路桥集团有限公司 Large-section steel truss girder erection system of large-span steel-concrete composite bridge and construction method
CN113123250A (en) * 2021-05-10 2021-07-16 南通帆森能源科技有限公司 Precise assembling and adjusting device for steel truss girder and assembling construction method

Also Published As

Publication number Publication date
CN110512521B (en) 2021-06-29

Similar Documents

Publication Publication Date Title
CN208899886U (en) Cantilever frame platform
CN211772901U (en) Space abnormal shape steel case arch rib installation device
AU2020348407A1 (en) Cable-supported large-span structure and construction method therefor
CN103243654A (en) Mounting method for steel anchor beam of cable-stayed bridge and assembly jig and cable bent tower mounting platform used in method
CN109236012B (en) Method for hoisting power transmission line T-shaped guyed tower
CN110512521A (en) The docking facilities and interconnection method of big segment steel truss girder
CN105970819A (en) Installation construction method for steel anchor beams
CN217324939U (en) Arch rib mounting system
CN101633483B (en) Integral lifting apparatus for steel structure net rack
CN105040591A (en) Positioning device for waveform steel web and positioning method thereof
CN112921785A (en) Telescopic sliding formwork device for prefabricating steel-concrete composite beam
CN211368423U (en) Stay cable tower top lifting traction operation platform
CN209958161U (en) Linear adjusting equipment of track beam
CN108360395B (en) Basket is hung in construction of bridge long and large section case roof beam, concrete case roof beam construction structure of hanging basket, steel case roof beam construction structure of hanging basket
CN204326570U (en) Truss temporary support structure
CN218375364U (en) Steel truss promotes auxiliary stay structure
CN108222526B (en) High-rise conjoined building tower lateral displacement control device and construction method
CN216007760U (en) Non-counterweight ultrahigh hanging basket suspension device
CN115478649A (en) Large-span diagonal member truss and installation method thereof
CN108797365A (en) A kind of bridge pier column template and its construction method
CN112982169A (en) Mounting method of through tied arch bridge
CN208718082U (en) A kind of adjustment device for overhanging steel structure
CN110886190A (en) Port roof pressure adjusting device and steel box girder cable-stayed bridge
CN110143517A (en) Platform can be recycled for steel truss arch bar part fast hoisting
CN111438309B (en) Batch beam steel bar inverted binding frame and beam steel bar binding method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant