JP2003293320A - Erection device of diagonal member in composite truss bridge and erection method - Google Patents
Erection device of diagonal member in composite truss bridge and erection methodInfo
- Publication number
- JP2003293320A JP2003293320A JP2002099731A JP2002099731A JP2003293320A JP 2003293320 A JP2003293320 A JP 2003293320A JP 2002099731 A JP2002099731 A JP 2002099731A JP 2002099731 A JP2002099731 A JP 2002099731A JP 2003293320 A JP2003293320 A JP 2003293320A
- Authority
- JP
- Japan
- Prior art keywords
- floor slab
- diagonal member
- diagonal
- existing
- receiving beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、トラス橋あるいは
その他の複合トラス橋等の橋梁を構築する場合の斜材の
架設装置および架設方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus and method for constructing diagonal members when constructing a bridge such as a truss bridge or other composite truss bridge.
【0002】[0002]
【従来の技術】従来、柱頭部から順次橋軸方向に斜材を
設けると共に、その斜材に下床版並びに上床版を結合し
て、複合トラス橋を張り出すように築造する場合におい
て、複合トラス橋の斜材の取付方法(現場打ちコンクリ
ートの場合の斜材は除く)については、図13および
図14に示すように柱頭部上あるいは既設上床版3上に
架設されたワーゲン(移動作業用台車)10により斜材
11の上下両端部を吊下げ保持する形式をとっていた
が、この方法では、施工誤差が生じやすいという問題が
あると共に、ワーゲン10により、斜材11の両端部を
支持する形態であるので、斜材11の全荷重を支持する
ようになり、ワーゲン10が大型になるという問題があ
る。2. Description of the Related Art Conventionally, when a diagonal truss is sequentially provided from a pillar head in the axial direction of the bridge, and a lower floor slab and an upper floor slab are connected to the diagonal timber to construct a composite truss bridge, Regarding the method of installing the diagonal members of the truss bridge (excluding the diagonal members in the case of cast-in-place concrete), as shown in Figs. 13 and 14, the wagon (for moving work) installed on the pillar head or on the existing upper deck 3 Although the upper and lower ends of the diagonal member 11 are suspended and held by the trolley 10, this method has a problem that construction errors are likely to occur, and the wagon 10 supports both ends of the diagonal member 11. Since it is a form which carries out, the whole load of diagonal member 11 will be supported, and there is a problem that Wagen 10 will become large.
【0003】また、トラス橋における斜材を建て込む
場合、斜材同士をトラスで構成した梁を用いて固定して
いたが、この方法では、架設材が大きくなり、施工誤差
が生じやすいという問題がある。In addition, when building a diagonal member in a truss bridge, the diagonal members were fixed by using beams made of trusses, but with this method, the erection material becomes large and construction errors tend to occur. There is.
【0004】前記およびの従来の架設方法では、施
工誤差が生じやすく、また、ワーゲンが大型になり、さ
らに、の場合は、架設材も大掛かりとなり、いずれの
場合も施工コストが高くなっていた。In the above-mentioned conventional erection methods, a construction error is likely to occur, the wagon becomes large, and in the case of (1), the erection material becomes large-scaled, and in both cases, the construction cost is high.
【0005】本発明者は、前記従来の欠点に鑑み、これ
らの欠点を解消すべく、研究した結果、既設の上下の一
方または両方のコンクリート床版に梁をはわせ、その梁
から斜材の上下方向の少なくとも一端側を治具により固
定すれば、斜材の架設施工誤差は生じにくく、また、梁
が軽量になること、および必要に応じ、前記梁が床版の
型枠受け梁と共用することも可能となり、工費も安価に
なること。そして、コンクリート製のトラス材だけでな
く、鋼製のトラス材あるいはその他の斜材でも可能であ
ること。また、従来の施工方法では、格点部付近で施工
目地を作っていたが、下床版施工区間をさらに伸ばすこ
とによって、前記の梁をより簡単なものにすることも可
能となる等の知見を得て本発明を完成させた。In view of the above-mentioned conventional drawbacks, the present inventor has conducted research to eliminate these drawbacks. As a result, one or both of the existing concrete floor slabs with beams are fitted with beams and the beams are If at least one end in the vertical direction is fixed with a jig, the construction error of the diagonal members will not occur easily, the beam will be lighter, and if necessary, the beam will be shared with the formwork receiving beam of the floor slab. It will be possible to do it, and the construction cost will be low. And it is possible to use not only concrete truss materials but also steel truss materials and other diagonal materials. Also, in the conventional construction method, construction joints were made near the grade points, but by further extending the floor slab construction section, it is possible to make the above-mentioned beam simpler, etc. Thus, the present invention was completed.
【0006】[0006]
【発明が解決しようとする課題】本発明は、施工精度が
向上する比較的簡単な複合トラス橋における斜材の架設
装置を提供すると共に、その施工装置を使用して、斜材
を容易に精度良く安価に架設することができる複合トラ
ス橋における斜材の架設方法を提供することを目的とす
る。SUMMARY OF THE INVENTION The present invention provides a relatively simple erection device for a diagonal truss in a composite truss bridge with improved construction accuracy, and the construction device is used to easily and accurately measure the diagonal member. An object of the present invention is to provide a method of erection of diagonal members in a composite truss bridge that can be erected well at low cost.
【0007】[0007]
【課題を解決するための手段】前記課題を解決するため
に、請求項1に記載の複合トラス橋における斜材の架設
装置においては、既設下床版の上面または既設上床版の
下面の何れか一方の床版に、先端部が新設側に突出する
ように配置された受け梁の基端部を固定し、前記受け梁
に斜材を保持する治具を設け、前記治具により斜材の一
端側を保持すると共に、斜材の他端側をワーゲンにより
吊り下げ支持するようにしたことを特徴とする。In order to solve the above-mentioned problems, in the erection device for diagonal members in the composite truss bridge according to claim 1, either the upper surface of the existing lower floor slab or the lower surface of the existing upper floor slab is used. On one of the floor slabs, the base end of the receiving beam arranged so that the tip portion projects toward the new side is fixed, and a jig for holding the diagonal member is provided on the receiving beam. It is characterized in that one end is held and the other end of the diagonal member is suspended and supported by a wagon.
【0008】また、請求項2に記載の複合トラス橋にお
ける斜材の架設装置においては、既設下床版1の上面
に、先端部が新設側に突出するように配置された下部受
け梁2の基端部を固定し、既設上床版3の下面に、先端
部が新設側に突出するように配置された上部受け梁4の
基端部を固定し、前記各上下の受け梁2,4に斜材11
を保持する治具6を設けたことを特徴とする。Further, in the device for constructing the diagonal members in the composite truss bridge according to the second aspect, the lower receiving beam 2 is arranged on the upper surface of the existing lower floor slab 1 so that the tip portion thereof projects to the new side. The base end portion is fixed, and the base end portion of the upper receiving beam 4 arranged so that the tip end portion projects toward the new side is fixed to the lower surface of the existing upper floor slab 3, and the upper and lower receiving beams 2 and 4 are respectively fixed. Diagonal material 11
It is characterized in that a jig 6 for holding is provided.
【0009】さらに、請求項3に記載の発明は、請求項
1に記載の発明において、斜材11を保持する前記治具
6には、斜材11の保持位置を調整するための保持位置
調整装置7を備えていることを特徴とする。Further, in the invention described in claim 3, in the invention described in claim 1, the jig 6 for holding the diagonal member 11 is provided with a holding position adjustment for adjusting the holding position of the diagonal member 11. A device 7 is provided.
【0010】さらにまた、請求項4の発明においては、
請求項1〜3のいずれかに記載の発明において、既設の
床版が、次に構築される新設の格点部付近まで突出する
ように施工されて、前記既設の床版に基端部が固定され
る前記受け梁の張り出し距離が短くされていることを特
徴とする。Furthermore, in the invention of claim 4,
In the invention according to any one of claims 1 to 3, an existing floor slab is constructed so as to project to the vicinity of a newly constructed rating part, and a base end portion is attached to the existing floor slab. It is characterized in that the overhang distance of the fixed receiving beam is shortened.
【0011】なおまた、請求項5に記載の複合トラス橋
における斜材の架設方法においては、既設下床版の上面
または既設上床版の下面の何れか一方の床版に、先端部
が新設側に突出するように配置された受け梁の基端部を
固定し、前記受け梁に斜材を保持する治具を設け、前記
治具により斜材の一端側を保持すると共に、斜材の他端
側をワーゲンにより吊り下げ支持して、斜材を所定の位
置に保持した後、新設の下床版または新設の上床版を前
記斜材と結合するように設けることを特徴とする。Further, in the method of erection of the diagonal members in the composite truss bridge according to the fifth aspect, the tip end is newly installed on the floor plate of either the upper surface of the existing lower floor slab or the lower surface of the existing upper floor slab. The base end portion of the receiving beam arranged so as to project to is fixed to the receiving beam, and a jig for holding the diagonal member is provided on the receiving beam. It is characterized in that the end side is suspended and supported by a wagon to hold the diagonal member at a predetermined position, and then a new lower floor slab or a new upper floor slab is provided so as to be coupled with the diagonal member.
【0012】さらにまた、請求項6の複合トラス橋にお
ける斜材の架設方法においては、既設下床版1の上面の
両側に、先端部が新設側に突出するように配置された各
下部受け梁2の基端部を固定すると共に、既設上床版3
の下面の両側に、先端部が新設側に突出するように配置
された各上部受け梁4の基端部を固定し、前記各側部の
上下の受け梁2,4に、斜材11を保持する治具6をそ
れぞれ設け、各側部の上下の治具6に斜材11を保持さ
せた後、新設の下床版または新設の上床版を前記斜材1
1と結合するように設けることを特徴とする。Furthermore, in the method of erection of the diagonal members in the composite truss bridge according to claim 6, the lower receiving beams are arranged on both sides of the upper surface of the existing lower floor slab 1 so that the tips thereof project to the new side. While fixing the base end of 2, existing upper floor slab 3
The base end portions of the upper receiving beams 4 arranged so that the tip portions thereof protrude toward the new side are fixed to both sides of the lower surface of the, and the diagonal members 11 are attached to the upper and lower receiving beams 2 and 4 of the respective side portions. The jigs 6 for holding are provided respectively, and after the diagonal members 11 are held by the jigs 6 on the upper and lower sides of each side, a new lower floor slab or a new upper floor slab is attached to the diagonal member 1.
It is characterized in that it is provided so as to be coupled with 1.
【0013】[0013]
【発明の実施の形態】本発明における複合トラス橋にお
ける斜材の架設装置および架設方法の第1実施形態につ
いて、図1〜図7参照して説明する。BEST MODE FOR CARRYING OUT THE INVENTION A first embodiment of an apparatus and method for installing a diagonal member in a composite truss bridge according to the present invention will be described with reference to FIGS.
【0014】図1〜図7は、本発明の複合トラス橋にお
ける斜材の架設装置の第1実施形態を示すものであっ
て、先ず、図1の状態は、図示省略の柱頭部から順次築
造されてきた既設の張り出し複合トラス橋9からなる橋
体上を移動可能なワーゲン(作業移動台車)10によっ
て、新設の下床版1aを築造する直前の状態を示す側面
図である。この実施形態では、既設の張り出し複合トラ
ス橋9は、鉄筋コンクリート製下床版1とプレストレス
トコンクリート製上床版3とこれらに結合される斜材1
1とにより、順次張り出すように築造された部分であ
る。1 to 7 show a first embodiment of an apparatus for constructing a diagonal member in a composite truss bridge of the present invention. First, the state of FIG. 1 is sequentially constructed from a column head (not shown). It is a side view which shows the state just before constructing the new lower floor slab 1a by the wagon (working trolley) 10 which can be moved on the bridge which consists of the existing overhang compound truss bridge 9. In this embodiment, an existing overhanging composite truss bridge 9 includes a reinforced concrete lower floor slab 1, a prestressed concrete upper floor slab 3 and a diagonal member 1 connected to these.
It is a part that was built so as to project in sequence by 1.
【0015】前記図1に示す状態までに施工される概略
施工手順は、以下の(1)〜(2)通りである。
(1)図示省略の柱頭部上部に、トラスを組み、起点と
なる下床版と上床版とを築造すべく、それぞれコンクリ
ートを打設して起点となる下床版および上床版を築造
し、前記下床版を既設下床版1とし、また前記上床版を
既設上床版3とする。
(2)ワーゲンを架設する。
(3)柱頭部上部の施工が完了した段階で、既設下床版
1上に斜材11を受けるための下部受け梁2を所定の位
置にセットし、既設下床版1にPC鋼棒からなるアンカ
ーボルト12で1箇所以上固定する。また、既設上床版
3の下面に、斜材11を受けるための上部受け梁4を保
持する形式で、前記と同様にPC鋼棒からなるアンカー
ボルト14を使って既設上床版3に固定する。以下、順
次、斜材11を保持して新設の下床版1aおよび上床版
3aを築造する工程を繰り返すことになるが、図1(図
2も同様)は、この繰り返す工程において、斜材11の
下部に新設の下床版1aを築造して結合するための説明
図である。The general construction procedure up to the state shown in FIG. 1 is as follows (1) to (2). (1) A truss is assembled on the upper part of a column head (not shown), and in order to build a lower floor slab and an upper floor slab as a starting point, concrete is respectively cast to build a lower floor slab and an upper floor slab as a starting point, The lower floor slab is an existing lower floor slab 1, and the upper floor slab is an existing upper floor slab 3. (2) Build a wagon. (3) When the construction of the upper part of the stilt head is completed, set the lower receiving beam 2 for receiving the diagonal member 11 on the existing lower floor slab 1 at a predetermined position, and attach it to the existing lower floor slab 1 from the PC steel bar. Secure it with one or more anchor bolts 12 at one place. Further, the upper receiving beam 4 for receiving the diagonal member 11 is held on the lower surface of the existing upper floor slab 3 and is fixed to the existing upper floor slab 3 by using the anchor bolts 14 made of PC steel rods as described above. Hereinafter, the steps of sequentially holding the diagonal members 11 and constructing the new lower floor slab 1a and the new floor slab 3a are repeated, but FIG. 1 (also in FIG. 2) shows that the diagonal members 11 FIG. 3 is an explanatory view for constructing and joining a new lower floor slab 1 a in the lower part of FIG.
【0016】さらに詳細に説明すると、柱頭部(図示省
略した)から張り出すように築造された既設の複合トラ
ス橋Aにおける既設の鉄筋コンクリート製下床版1の上
面には、図3および図5(a)に示すように、橋軸直角
方向(前後方向)の両側に、左右方向(橋軸方向)に間
隔をおいて複数の鋼製スライド支持板8が載置されて、
必要に応じ固定され、その鋼製スライド支持板8を介し
て、各下部受け梁2の基端部が鉄筋コンクリート製下床
版1に、一つまたは左右方向に間隔をおいて複数のアン
カーボルト12により固定されている。前後方向に平行
に間隔をおいて対向する各下部受け梁2の内側の溝形鋼
17は、左右方向に間隔をおいて、前後方向に延長する
ように配置された繋ぎ梁2aの端部が溶接等により結合
されて一体化されている。また、外側の溝形鋼17は、
内側の溝形鋼17に溶接等により固定された鋼製連結板
2bにより一体化されている。More specifically, the upper surface of the existing reinforced concrete lower floor slab 1 of the existing composite truss bridge A constructed so as to project from the pillar head (not shown) is shown in FIGS. As shown in a), a plurality of steel slide support plates 8 are placed on both sides in the direction perpendicular to the bridge axis (front-rear direction) at intervals in the left-right direction (bridge axis direction),
The bottom end of each lower receiving beam 2 is fixed to the lower slab 1 made of reinforced concrete via the steel slide supporting plate 8 and is fixed to one or a plurality of anchor bolts 12 at intervals in the left-right direction. It is fixed by. The channel steels 17 inside each of the lower receiving beams 2 facing each other in parallel with the front-rear direction at intervals have the ends of the connecting beams 2a arranged so as to extend in the front-rear direction at intervals in the left-right direction. They are integrated by being joined by welding or the like. Further, the outer channel steel 17 is
It is integrated by a steel connecting plate 2b fixed to the inner channel steel 17 by welding or the like.
【0017】前記下部受け梁2の先端部は、次に構築す
る下部の格点部Kを超える寸法以上に新設側に突出する
ように(片持ち式に)配置されている。なお、前記アン
カーボルト12の下端部は、下床版1に挿通されて下床
版1の下面に係合し、前記アンカーボルト12に挿通さ
れた支圧板およびナット12aが螺合されて、下床版1
に係合している(前記アンカーボルト12の上部の係合
は後記する)。また、下部受け梁2の先端部は、ワーゲ
ン10により一端部(上部)が吊り下げ支持された吊り
下げ支持金具36によりレベル調整自在に支持されてい
る。なお、ワーゲン10の後端部は、着脱自在なアンカ
ー部材46により既設の上床版3に反力をとると共にジ
ャッキ等の突っ張り支持材(図示を省略)により所定の
位置に支持されるように構成されている。The tip end portion of the lower receiving beam 2 is arranged so as to project (cantilever) toward the new side by a size larger than the size of the lower rating portion K to be constructed next. The lower end of the anchor bolt 12 is inserted into the lower floor slab 1 and engages with the lower surface of the lower floor slab 1, and the bearing plate and the nut 12a inserted into the anchor bolt 12 are screwed together to form a lower portion. Floor slab 1
(The engagement of the upper portion of the anchor bolt 12 will be described later). Further, the tip end portion of the lower receiving beam 2 is supported by a hanging support metal fitting 36 whose one end (upper portion) is suspended and supported by the wagon 10 so that the level can be adjusted. In addition, the rear end of the wagon 10 is constructed so that a detachable anchor member 46 exerts a reaction force on the existing upper floor slab 3 and is supported at a predetermined position by a supporting member (not shown) such as a jack. Has been done.
【0018】前記下部受け梁2は、図5(a)および図
12に示すように、一対の溝形鋼17をウエブ部17a
が間隔をおいて平行に互いに背中合わせになるように配
置され、そのウエブ17a間にアンカーボルト12の中
間軸部が配置され、前記一対の溝形鋼17の上部フラン
ジ15に溝形断面の押え金具16が嵌合当接され、前記
押え金具16のボルト孔に挿通された前記アンカーボル
ト12の上部雄ねじ部12aに、ナット17bが螺合緊
締されて、押え金具16を介し下部受け梁2の基端部
は、既設下床版1に固定されている。なお、前記ウエブ
17a間の空間が、下部受け梁2をスライド移動する時
に、アンカーボルト12と干渉しないように構成されて
いる(後記の上部受け梁4とアンカーボルト14との関
係も同様である)。As shown in FIGS. 5 (a) and 12, the lower receiving beam 2 has a pair of channel steels 17 and a web portion 17a.
Are arranged so as to be back-to-back with each other in parallel with each other, and an intermediate shaft portion of the anchor bolt 12 is arranged between the webs 17a thereof, and a pressing member having a groove-shaped cross section is attached to the upper flanges 15 of the pair of groove-shaped steels 17. 16 is fitted and abutted, and a nut 17b is screwed and tightened to the upper male screw portion 12a of the anchor bolt 12 inserted into the bolt hole of the holding metal fitting 16, and the base of the lower receiving beam 2 is inserted via the holding metal fitting 16. The ends are fixed to the existing lower floor slab 1. The space between the webs 17a is configured so as not to interfere with the anchor bolt 12 when the lower receiving beam 2 slides (the same applies to the upper receiving beam 4 and the anchor bolt 14 described later). ).
【0019】また、既設の複合トラス橋Aにおける既設
のプレストレストコンクリート製上床版3の下面には、
図5(b)に示すように、橋軸直角方向(前後方向)の
両側に、左右方向に延長するように鋼製支持板13が配
置されて固定され、その鋼製支持板13を介して、各上
部受け梁4の基端部がプレストレストコンクリート製上
床版3に、一つまたは左右方向に間隔をおいて複数のア
ンカーボルト14により固定されている。前記上部受け
梁4の先端部は、次に構築する上部の格点部Kを超える
寸法以上に新設側に突出するように(片持ち式に)配置
されている。前記アンカーボルト14の上端部は、上床
版3の上面に係合し、前記アンカーボルト14に挿通さ
れた支圧板およびナット17bにより、上床版3に係止
している。また、図12(a)に示すように、前後方向
に平行に間隔をおいて対向する各上部受け梁4の内側の
溝形鋼17は、左右方向に間隔をおいて、前後方向に延
長するように配置された繋ぎ梁4aの端部が結合されて
一体化されている。また、外側の溝形鋼17は、内側の
溝形鋼17に溶接等により固定された鋼製連結板4bに
より一体化されている。On the lower surface of the existing prestressed concrete floor slab 3 of the existing composite truss bridge A,
As shown in FIG. 5 (b), steel support plates 13 are arranged and fixed on both sides in the direction perpendicular to the bridge axis (front-rear direction) so as to extend in the left-right direction. The base end portion of each upper receiving beam 4 is fixed to the prestressed concrete upper floor slab 3 by one or a plurality of anchor bolts 14 at intervals in the left-right direction. The tip end portion of the upper receiving beam 4 is arranged (cantilever type) so as to project to the new side by a size equal to or larger than the dimension of the upper graded portion K to be constructed next. The upper end portion of the anchor bolt 14 engages with the upper surface of the upper floor slab 3 and is locked to the upper floor slab 3 by a bearing plate and a nut 17b inserted in the anchor bolt 14. Further, as shown in FIG. 12A, the channel steels 17 inside the upper receiving beams 4 facing each other in parallel with each other in the front-rear direction at intervals are extended in the front-rear direction at intervals in the left-right direction. The ends of the connecting beams 4a thus arranged are joined and integrated. The outer grooved steel 17 is integrated with the inner grooved steel 17 by a steel connecting plate 4b fixed by welding or the like.
【0020】また、上部受け梁4の先端部は、ワーゲン
10により一端部が吊り下げ支持された吊り下げ支持金
具37によりレベル調整自在に支持されている。前記の
吊り下げ金具36,37の下端部は、図5(c)に示す
ように、吊り下げ金具36,37の螺杆36aおよび3
7aは前記ウエブ17a間に配置されると共に、前記各
溝形鋼17の下部に嵌合された断面溝形の押え部材16
に挿通されると共に、前記螺杆36a,37aに螺合さ
れたナット36c,37cにより、所定のレベルに支持
されている。The tip end of the upper receiving beam 4 is supported by a hanging support metal fitting 37, one end of which is suspended and supported by the wagon 10, so that its level can be adjusted. As shown in FIG. 5C, the lower end portions of the hanging metal fittings 36 and 37 are provided with screw rods 36 a and 3 of the hanging metal fittings 36 and 37.
7a is arranged between the webs 17a, and is a pressing member 16 having a groove-shaped cross section fitted to the lower portion of each groove-shaped steel 17.
And is supported at a predetermined level by nuts 36c and 37c screwed to the screw rods 36a and 37a.
【0021】また、前記と同様に、上部受け梁4は、図
12に示すように、一対の溝形鋼17をウエブ部17a
が間隔をおいて平行に互いに背中合わせになるように配
置され、そのウエブ17a間に左右方向に間隔をおいて
複数のアンカーボルト14の中間軸部が配置され、前記
一対の溝形鋼17の下部に押え金具16が当接され、前
記アンカーボルト14の下部雄ねじ部14aに螺合され
たナット14bにより緊締されて、押え金具16を介し
て、上部受け梁4の基端部は上床版3に固定されてい
る。このように、ワーゲン10により下部受け梁2およ
び上部受け梁4の全体を支持することなく、既設床版
1,3に基端部を固定した状態で、これらの先端部のみ
を支持するので、ワーゲン10の負担が少なくなり、ワ
ーゲン10の小型化が図ることができる。Further, similarly to the above, as shown in FIG. 12, the upper receiving beam 4 is provided with a pair of channel steels 17 and a web portion 17a.
Are arranged parallel to each other with a space therebetween so as to be back-to-back, and intermediate shaft portions of a plurality of anchor bolts 14 are arranged between the webs 17a with a space therebetween in the left-right direction. The pressing metal fitting 16 is brought into contact with the above and is tightened by the nut 14b screwed to the lower male screw portion 14a of the anchor bolt 14, and the base end portion of the upper receiving beam 4 is attached to the upper floor slab 3 via the pressing metal fitting 16. It is fixed. As described above, since the lower receiving beam 2 and the upper receiving beam 4 are not entirely supported by the wagon 10, the base end portions of the existing floor slabs 1 and 3 are fixed and only the front end portions thereof are supported. The load on the wagon 10 is reduced, and the size of the wagon 10 can be reduced.
【0022】前記下部受け梁2の上部および上部受け梁
4の下部には、次に築造する格点部Kに近接した位置に
おいて、斜材11を位置調整して保持するための治具6
がボルト・ナットによりフランジ15に固定され、橋軸
方向に間隔をおいて配置されている。前記各治具6の取
付け位置は、トラスの格点部Kの位置が一定間隔である
ので、治具6の取付け位置は、橋軸方向の調整は不要で
ある。On the upper portion of the lower receiving beam 2 and the lower portion of the upper receiving beam 4, a jig 6 for adjusting the position of the diagonal member 11 and holding the diagonal member 11 at a position close to the grading portion K to be built next.
Are fixed to the flange 15 by bolts and nuts and are arranged at intervals in the bridge axial direction. Since the positions of the rating portions K of the truss are at regular intervals, the jigs 6 need not be adjusted in the bridge axis direction.
【0023】前記の治具6は、この実施形態では、斜材
11を所定の姿勢に保持した状態で支持するため、橋軸
方向の格点部Kから離れてこれに近接した位置において
保持すると、斜材11を安定した状態で支持させること
ができる。なお、斜材11の端部は新設の上床版3aあ
るいは下床版1aとの一体化を図るために、この部分を
外した位置で、治具6により保持される。In the present embodiment, the jig 6 supports the diagonal member 11 in a state in which it is held in a predetermined posture. Therefore, when the jig 6 is held at a position apart from the graded portion K in the bridge axis direction and close to it. The diagonal member 11 can be supported in a stable state. The end portion of the diagonal member 11 is held by the jig 6 at a position where this portion is removed in order to integrate it with the newly installed upper floor slab 3a or lower floor slab 1a.
【0024】次に、図6および図7を参照しながら治具
6について説明すると、前記各治具6は、鉛直な縦雌ね
じ孔18aを有する鋼製台座19と、鉛直方向位置調整
ジャッキ20を介して鉛直方向に上下移動可能に支持さ
れた鋼製保持部材21と、前記保持部材21に傾斜調整
装置22および横方向位置調整装置23を介して支持さ
れた鋼管製斜材11等のウエブ固定部24からなる保持
位置調整装置7を備えている。以下、各部分の構造につ
てい説明する。Next, the jigs 6 will be described with reference to FIGS. 6 and 7. Each jig 6 includes a steel pedestal 19 having a vertical female screw hole 18a and a vertical position adjusting jack 20. Via a steel holding member 21 which is vertically movably supported by a holding member 21 and a steel pipe diagonal member 11 supported by the holding member 21 through a tilt adjusting device 22 and a lateral position adjusting device 23. The holding position adjusting device 7 including the portion 24 is provided. The structure of each part will be described below.
【0025】この実施形態では、前記保持部材21に
は、その下面に開口する鉛直な縦雌ねじ孔18bが設け
られ、前記台座19の雌ねじ孔18aと保持部材21の
雌ねじ孔18bとは、ねじ方向の異なる雌ねじ孔18
a,18bとされ、これらに、両端部にねじ方向の異な
る螺杆18c,18dが螺合されると共に、その螺杆1
8c,18dの中央部に回動用ハンドル29を固着し
て、保持部材21の鉛直方向の位置調整が可能な鉛直方
向位置調整ジャッキ20が構成されている。また、前記
台座19には、下端部が前記台座19に固定された鉛直
なガイド杆40が固定され、前記ガイド杆40に摺動可
能に嵌挿された受け金具41が、前記保持部材21に溶
接等により固定されて、前記保持部材21が上下方向に
移動可能にかつ回転不能に構成されている。In this embodiment, the holding member 21 is provided with a vertical vertical female screw hole 18b opening on its lower surface, and the female screw hole 18a of the pedestal 19 and the female screw hole 18b of the holding member 21 are screwed in the screw direction. Female screw holes of different 18
a and 18b, and screw rods 18c and 18d having different screw directions are screwed to both ends thereof, and the screw rod 1
A vertical handle 29 is fixed to the central portions of 8c and 18d to form a vertical position adjustment jack 20 capable of adjusting the position of the holding member 21 in the vertical direction. Further, a vertical guide rod 40 having a lower end fixed to the pedestal 19 is fixed to the pedestal 19, and a receiving metal fitting 41 slidably inserted in the guide rod 40 is attached to the holding member 21. The holding member 21 is fixed by welding or the like so that the holding member 21 is vertically movable and non-rotatable.
【0026】前記保持部材21の前後方向の前部側の内
部には、上下の各断面円弧状支承面26を有する溝27
が設けられ、前記溝27内には、橋軸直角方向の垂直面
内において、回動可能に雌ねじ部材28が支持され、前
記雌ねじ部材28には、前後方向に延長するように配置
された横ねじ杆25の基端部が螺合連結されている。前
記横ねじ杆25の中間部には回動用ハンドル30が固定
され、前記横ねじ杆25の先端部には、斜材固定用バン
ド金具31からなる斜材固定金具32の基端部が回動可
能に支持されている。したがって、前記回動用ハンドル
30を正回転または逆回転させることにより、前記ウエ
ブ固定金具32を前進移動または後退移動させることが
できる。Inside the front side of the holding member 21 in the front-rear direction, a groove 27 having upper and lower bearing surfaces 26 each having an arcuate cross section is formed.
The female screw member 28 is rotatably supported in the groove 27 in a vertical plane perpendicular to the bridge axis, and the female screw member 28 has a lateral screw member extending in the front-rear direction. The base end of the screw rod 25 is screwed and connected. A turning handle 30 is fixed to an intermediate portion of the horizontal screw rod 25, and a base end portion of a diagonal member fixing metal member 32 including a diagonal member fixing band metal member 31 is rotated at a tip end portion of the horizontal screw rod 25. Supported as possible. Therefore, by rotating the rotating handle 30 forward or backward, the web fixing member 32 can be moved forward or backward.
【0027】前記保持部材21の前面側と前記回動用ハ
ンドル30との間には、前記保持部材21の前面側に係
合すると共に、前記横ねじ杆25に螺合されたナットか
らなる雌ねじ部材21aが設けられ、前記雌ねじ部材2
1を回動用ハンドル30に近づく方向に回動すると、前
記雌ねじ部材21aの下部が保持部材21に当接した状
態で、横ねじ杆25はその先端部に螺合されている前記
雌ねじ部材28を反時計方向に回動(図6参照)し、そ
の回動により反時計方向の下降回動して、斜材11のレ
ベル調整をすることができる。前記横ねじ杆25,雌ね
じ部材21a,上下の各断面円弧状支承面26を有する
溝27,雌ねじ部材28等により傾斜調整装置22が構
成され、前記横ねじ杆25,雌ねじ部材28,回動用ハ
ンドル30等により横方向調整装置23が構成されてい
る。Between the front side of the holding member 21 and the rotating handle 30, a female screw member which is engaged with the front side of the holding member 21 and which is a nut screwed to the horizontal screw rod 25 is formed. 21a is provided, and the female screw member 2
When 1 is rotated in the direction of approaching the rotation handle 30, the horizontal screw rod 25 holds the female screw member 28 screwed to the tip end of the horizontal screw rod 25 with the lower portion of the female screw member 21a abutting the holding member 21. It rotates in the counterclockwise direction (see FIG. 6), and by the rotation, it rotates in the counterclockwise downward direction and the level of the diagonal member 11 can be adjusted. The horizontal screw rod 25, the female screw member 21a, the groove 27 having upper and lower arcuate cross-section bearing surfaces 26, the female screw member 28, and the like constitute an inclination adjusting device 22, and the horizontal screw rod 25, the female screw member 28, and a turning handle. The lateral adjustment device 23 is configured by 30 and the like.
【0028】なお、前記円弧状支承面26の中心点は、
横ねじ杆25の中心軸線上にあり、横ねじ杆25の若干
の回動を許容するため、保持部材21の横ねじ杆25の
出口は若干大径の透孔に構成されている。なお、前記円
弧状支承面26は球状支承面とすると、左右方向にも動
いてしまうので好ましくない。The center point of the arcuate bearing surface 26 is
The horizontal screw rod 25 is located on the central axis of the horizontal screw rod 25 and allows the horizontal screw rod 25 to slightly rotate, so that the outlet of the horizontal screw rod 25 of the holding member 21 is formed as a through hole having a slightly larger diameter. If the arcuate bearing surface 26 is a spherical bearing surface, it will move in the left-right direction, which is not preferable.
【0029】また、前記ウエブ固定金具32の基端部の
金具本体33における係止溝34には、前記横ねじ杆2
5の先端部が回動可能に嵌設され、前記金具本体33の
左右方向両側部には、それぞれ斜材把持用鋼製バンド3
5の基端部が縦軸により枢着され、前記各鋼製バンド3
5の先端部には、連結用フランジ42が設けられ、前記
連結用フランジ42相互はこれらの横透孔に渡って挿通
されたボルト43およびこれに螺合されたナットにより
緊締されて、斜材(鋼管)11の端部よりの中間部が把
持されるように構成されている。Further, in the locking groove 34 in the metal fitting body 33 at the base end portion of the web fixing metal fitting 32, the horizontal screw rod 2 is provided.
5 has a distal end portion rotatably fitted therein, and the left and right side portions of the metal fitting body 33 each have a steel band 3 for holding a diagonal member.
The base end of 5 is pivotally attached by the vertical axis, and the steel bands 3
5, a connecting flange 42 is provided at the tip end portion, and the connecting flanges 42 are tightened by bolts 43 and nuts screwed to the bolts 43 inserted through the lateral through holes to form a diagonal member. The intermediate portion from the end portion of the (steel pipe) 11 is configured to be gripped.
【0030】前記のように、斜材11の端部から離れた
位置において、治具6により保持された状態で、斜材1
1の端部が所定の格点部位置付近になるように構成され
ている。As described above, the diagonal member 1 is held at the position away from the end of the diagonal member 11 while being held by the jig 6.
The end portion of 1 is configured to be near the predetermined position of the mark portion.
【0031】このように構成された治具6が、前記下部
受け梁2と上部受け梁4における左右方向に複数(図示
の場合は、前後両側とも同様で、上部側に2つまたは3
つ、下部側に2つまたは3つ)間隔をおいて設けられ、
例えば、図1に示すように、2つの斜材11がほぼV字
状に配置される場合には、上部側の治具6は、隣合う格
点部Kに近接した位置において広い間隔をおいて配置さ
れ、また、ほぼ斜材11の下部を保持する治具6は、一
つの格点部Kの左右両側に近接した位置においてほぼ対
称位置に配置される。A plurality of jigs 6 constructed in this way are provided in the left and right directions of the lower receiving beam 2 and the upper receiving beam 4 (in the case shown, the same applies to both front and rear sides, and two or three jigs are provided on the upper side).
One, two or three on the lower side) provided with an interval,
For example, as shown in FIG. 1, when the two diagonal members 11 are arranged in a substantially V shape, the jig 6 on the upper side has a wide space at a position close to the adjacent mark portions K. The jigs 6 that are arranged so as to hold the lower portion of the diagonal member 11 are arranged substantially symmetrically at positions close to the left and right sides of one grading portion K.
【0032】前記斜材11は既設の上床版3上を搬送し
て、ワーゲン10における電動チェーンブロックにより
吊り降ろして、各治具6に取付ける。また、床版に一端
側のみを固定された斜材11の自由端側は治具6により
所定に位置に保持する。そして、図1に示すように、上
部受け梁4側の既設側に位置する治具6(6a)と、下
部受け梁2側の既設側に位置する治具6(6b)によ
り、既設側に位置する一方の斜材11(11a)が位置
調整された状態で保持されていると共に、上部受け梁4
側の新設側に位置する治具6(6c)と、下部受け梁2
側の新設側に位置する治具6(6d)により、新設側に
位置する他方の斜材11(11b)が位置調整された状
態で保持されている。The diagonal member 11 is carried on the existing upper floor slab 3 and is hung by the electric chain block of the wagon 10, and attached to each jig 6. Further, the free end side of the diagonal member 11, which is fixed to the floor slab only at one end side, is held at a predetermined position by the jig 6. Then, as shown in FIG. 1, the jig 6 (6a) located on the existing side of the upper receiving beam 4 side and the jig 6 (6b) located on the existing side of the lower receiving beam 2 side The one diagonal member 11 (11a) positioned is held in a position adjusted state, and the upper receiving beam 4
Jig 6 (6c) located on the newly installed side and the lower receiving beam 2
By the jig 6 (6d) located on the newly installed side, the other diagonal member 11 (11b) located on the newly installed side is held with its position adjusted.
【0033】前記のように各斜材11が支持された状態
で、新設の下床版1aを築造するために、ワーゲン10
から吊り下げ支持された支持金具44により下部型枠4
3を所定の位置に吊り下げ支持して、配筋した後、前記
各斜材11の下端部を結合するように、コンクリートを
打設して新設の下床版1aを築造し、脱型される。ま
た、新設の下床版1aと下部受け梁2には、図示を省略
するが、既設側に設けたアンカーボルト12と保持部材
16と同様な保持装置を橋軸方向に間隔をおいて設け
て、緊締しない状態でおく。なお、前記斜材11(5)
の端部と床版との結合のため、斜材11の両端部には、
図示を省略するが、床版1,3に埋め込み固定するため
の連結鉄筋等を設けておく。In order to build a new lower floor slab 1a with each diagonal member 11 supported as described above, the wagon 10
The lower metal mold 4 is supported by the support metal fittings 44 suspended from the
After suspending and supporting 3 at a predetermined position and arranging, concrete is poured to construct the new lower floor slab 1a so that the lower end portions of the diagonal members 11 are joined, and the mold is demolded. It Although not shown, the new lower floor slab 1a and the lower receiving beam 2 are provided with holding devices similar to the anchor bolts 12 and the holding members 16 provided on the existing side at intervals in the bridge axial direction. , Do not tighten. In addition, the diagonal member 11 (5)
Because of the connection between the end of the and the floor slab, at both ends of the diagonal member 11,
Although illustration is omitted, connecting rebars and the like for embedding and fixing in the floor slabs 1 and 3 are provided.
【0034】次いで、新設の上床版3を築造するため
に、上部受け梁4と下部受け梁2の先端部付近に、それ
ぞれ治具6を固定すると共に、前記各治具6により新た
な斜材11を所定の位置に支持し、また上部型枠45を
所定の位置に吊り下げ支持した状態で、配筋した後、コ
ンクリートを打設して新設の上床版3aを築造し、型枠
45を脱型する。また、新設の上床版3aと上部受け梁
4には、図示を省略するが、既設側に設けたアンカーボ
ルト14と保持部材16と同様な保持装置を橋軸方向に
間隔をおいて設けて、緊締しない状態で仮保持する。Next, in order to build a new upper floor slab 3, jigs 6 are fixed near the tips of the upper receiving beam 4 and the lower receiving beam 2, respectively, and a new diagonal member is added by each jig 6. 11 is supported at a predetermined position, and the upper form 45 is suspended and supported at a predetermined position. After arranging, concrete is poured to build a new upper floor slab 3a. Remove the mold. Further, although not shown, the new upper floor slab 3a and the upper receiving beam 4 are provided with holding devices similar to the anchor bolts 14 and the holding members 16 provided on the existing side at intervals in the bridge axial direction, Hold temporarily without tightening.
【0035】前記のように、新設の下床版1aと新設の
上床版3aを築造した後、上床版3a上にレールを敷設
し、前記吊り下げ支持金具36,37を開放した状態
で、ワーゲン10を新設側に前進移動し、ワーゲン10
の後部は、上床版3に着脱自在に係止されるアンカー部
材46により反力をとる。As described above, after the new lower floor slab 1a and the new upper floor slab 3a are built, rails are laid on the upper floor slab 3a, and the hanging support fittings 36, 37 are opened, and the wagon Move the 10 forward to the new side,
The rear part takes a reaction force by an anchor member 46 which is detachably locked to the upper floor slab 3.
【0036】その後、下部受け梁2と上部受け梁4を係
止しているアンカーボルト12,14に係合しているナ
ットを緩め、また下部受け梁2と上部受け梁4に取付け
られている治具6における把持用バンド35を解放した
状態で、新設の上床版3aに保持されている上部受け梁
4を新設側に前進移動すると共に、前記アンカーボルト
14に係合しているナットを緊締して、上部受け梁4を
保持部材16を介して新設の上床版3aに固定する。ま
た同様に下部受け梁2を新設側に前進移動して、前記新
設側のアンカーボルト12に係合しているナットを緊締
して、下部受け梁2を新設の下床版1aに保持部材16
を介して新設の下床版1aに固定する。(図5a,b参
照)なお、スライド支持板8とスライド支持板13は、
新設の下床版1aおよび上床版3aに適宜取付ける。After that, the nuts engaged with the anchor bolts 12 and 14 that lock the lower receiving beam 2 and the upper receiving beam 4 are loosened, and the nuts are attached to the lower receiving beam 2 and the upper receiving beam 4. With the gripping band 35 of the jig 6 released, the upper receiving beam 4 held by the new upper floor slab 3a is moved forward to the new side, and the nut engaged with the anchor bolt 14 is tightened. Then, the upper receiving beam 4 is fixed to the new upper floor slab 3a via the holding member 16. Similarly, the lower receiving beam 2 is moved forward to the new installation side, the nuts engaged with the anchor bolts 12 on the new installation side are tightened, and the lower receiving beam 2 is held on the new lower floor slab 1a.
It is fixed to the new lower floor slab 1a via. (See FIGS. 5a and 5b) The slide support plate 8 and the slide support plate 13 are
It is properly attached to the new lower floor slab 1a and upper floor slab 3a.
【0037】次いで、前記のように、新たな斜材11等
を既設の上床版3(3a)上を搬送して、ワーゲン10
における電動チェーンブロックにより吊り降ろして、各
治具6に取付ける。また、床版に一端側のみを固定され
た斜材11の自由端側は治具6により所定の位置に保持
する。Next, as described above, the new diagonal member 11 or the like is conveyed over the existing upper floor slab 3 (3a), and the wagon 10 is removed.
It is hung by the electric chain block in and attached to each jig 6. Further, the free end side of the diagonal member 11 whose one end side is fixed to the floor slab is held at a predetermined position by the jig 6.
【0038】以下、前記と同様な工程を繰り返して順次
複合トラス橋Aを築造していく。なお、新設の床版1a
または3aを築造した時点で、各床版1a,3aはその
内部または外部に配置のPCケーブルにより緊張定着さ
れる。Thereafter, the same steps as described above are repeated to successively build the composite truss bridge A. The new floor slab 1a
Alternatively, when the 3a is built, each floor slab 1a, 3a is tensioned and fixed by a PC cable arranged inside or outside the slab.
【0039】以上の工程を簡単に列記すると、一部重複
するが下記のようになる。
(1)柱頭部上部は、トラスを組み下床版上床版それぞ
れコンクリートを打設する。
(2)ワーゲンを架設する。
(3)柱頭部上部の施工が完了した段階で、既設下床版
1上に斜材11を受けるための下部受け梁2を所定の位
置にセットし、既設下床版1にPC鋼棒からなるアンカ
ーボルト12で1箇所以上固定する。また、既設上床版
3の下面に、斜材等の斜材11を受けるための上部受け
梁4を保持する形式で、前記と同様にPC鋼棒からなる
アンカーボルト14を使って既設上床版3に固定する。
(4)トラスの格点部Kの位置は橋軸方向に一定間隔で
決まっているので、その位置付近の各下部受け梁2およ
び上部受け梁4に斜材11を受けるための取付治具6を
取付けておく。格点部Kの間隔が決まっているので、治
具6の橋軸方向の調整は不要である。橋軸直角方向の水
平方向位置調整ジャッキなどの横方向位置調整装置2
3、鉛直方向位置調整用ジャッキ20および傾斜調整装
置22が治具6に取付けられている。横方向位置調整装
置22の先端部には、斜材11からなる斜材11を掴む
斜材固定用バンド金具31からなる斜材固定金具32が
取付けられている。斜材11の上下の先端部は上下のコ
ンクリート製床版1a,3aに埋め込まれるので、掴む
位置は先端から離れた位置とする。1本の斜材11に下
上2箇所で各治具6により支持する。このように斜材1
1を支持するので、横ねじ杆25の軸まわりに斜材11
は回動することなく、所定の位置に保持される。The above steps will be briefly described below, although some overlaps will occur. (1) On the upper part of the pillar, a truss is assembled and concrete is placed on each of the lower slab and the upper slab. (2) Build a wagon. (3) When the construction of the upper part of the stilt head is completed, set the lower receiving beam 2 for receiving the diagonal member 11 on the existing lower floor slab 1 at a predetermined position, and attach it to the existing lower floor slab 1 from the PC steel bar. Secure it with one or more anchor bolts 12 at one place. In addition, the upper receiving beam 4 for receiving the diagonal member 11 such as a diagonal member is held on the lower surface of the existing upper slab 3, and the existing upper slab 3 is formed by using the anchor bolts 14 made of PC steel rods as described above. Fixed to. (4) Since the positions of the rating portions K of the truss are determined at regular intervals in the bridge axis direction, the mounting jigs 6 for receiving the diagonal members 11 on the lower receiving beams 2 and the upper receiving beams 4 near that position are provided. Install. Since the interval between the graded portions K is fixed, adjustment of the jig 6 in the bridge axis direction is unnecessary. Horizontal position adjusting device such as a horizontal position adjusting jack for the direction perpendicular to the bridge axis 2
3, the vertical position adjusting jack 20 and the inclination adjusting device 22 are attached to the jig 6. A diagonal member fixing metal fitting 32 made of a diagonal metal fitting band metal fitting 31 for gripping the diagonal material 11 made of the diagonal material 11 is attached to the tip of the lateral position adjusting device 22. Since the upper and lower end portions of the diagonal member 11 are embedded in the upper and lower concrete floor slabs 1a and 3a, the gripping position should be a position away from the tip. Each jig 6 is supported on one diagonal member 11 at two places below and above. In this way diagonal 1
1 supports the diagonal member 11 around the axis of the horizontal screw rod 25.
Is held in place without turning.
【0040】(5)斜材11を既設上床版1から運搬さ
れ、ワーゲン10を使って吊り下ろされ、斜材固定用バ
ンド金具31に取付ける。
(6)前記横方向位置調整装置23、鉛直方向位置調整
用ジャッキ20および傾斜調整装置22等からなる保持
位置調整装置7を使って水平、垂直方向の調整し、斜材
11を所定の位置および姿勢に保持し、所定の保持位置
に固定する。
(7)下部型枠43を組む。(この場合、この実施形態
では、格点部K位置を過ぎた位置まで下床版1を施工す
る形態を示したが、次の実施形態で説明するように、次
の格点部K位置の手前まで下部型枠43を組みコンクリ
ートを打設する方が、次に下部受け梁2が斜材11の荷
重を受ける場合、新設側に片持ち式に突出する腕長さが
短く有利となる。これらの点は、上部型枠45,上床版
3および上部受け梁4も同様である。)(5) The diagonal member 11 is transported from the existing upper floor slab 1, suspended by the wagon 10, and attached to the diagonal member fixing band fitting 31. (6) The holding position adjusting device 7 including the lateral position adjusting device 23, the vertical position adjusting jack 20 and the inclination adjusting device 22 is used to adjust the horizontal and vertical directions to move the diagonal member 11 to a predetermined position and a predetermined position. It is held in a posture and fixed in a predetermined holding position. (7) Assemble the lower mold 43. (In this case, in this embodiment, the form in which the lower floor slab 1 is installed up to a position past the position of the grading point K is shown, but as described in the next embodiment, When the lower formwork 43 is assembled up to this side and concrete is placed, when the lower receiving beam 2 receives the load of the diagonal member 11 next time, the arm length protruding in a cantilever manner to the new side is short and advantageous. These points also apply to the upper mold 45, the upper floor slab 3, and the upper receiving beam 4.)
【0041】(8)下床版鉄筋を組み立てる。
(9)下床版のコンクリートを打設し、硬化後、脱型す
る。
(10)次に、上部格点部Kに取付く斜材11を取付
け、斜材11の姿勢および位置を調整する。
(11)以下、上部型枠45を組み、上床版鉄筋を組み
立て、コンクリートを打設し、硬化後、脱型する。
(12)上床版3上にレール等を敷設して、ワーゲン1
0を所定の位置に前進させる。
(13)橋軸方向新設側の先端の斜材11を保持してい
た治具6に代えて、前記斜材11の床版に固定されてい
ない先端部を、ワーゲン10から吊り下げ支持される適
宜の保持手段によりワーゲン10に持たせ、またその他
の治具6の斜材固定金具32(斜材固定用バンド金具3
1)を開放し、アンカーボルト12,14のナットを弛
緩させて下部受け梁2および上部受け梁4を前進させた
後、各新設の床版1a,3aに下部受け梁2および上部
受け梁4を固定する。
(14)前記(5)に戻り、順次(6)以降の工程を繰
り返す。(8) Assemble the lower floor slabs. (9) Pour the concrete of the lower floor slab, remove the mold after curing. (10) Next, the diagonal member 11 to be attached to the upper rating portion K is attached, and the posture and position of the diagonal member 11 are adjusted. (11) After that, the upper form 45 is assembled, the upper floor slabs are assembled, concrete is poured, and after hardening, the mold is removed. (12) By laying rails on the upper floor slab 3 and wagon 1
0 is advanced to a predetermined position. (13) Instead of the jig 6 that holds the diagonal member 11 at the tip on the new side in the bridge axis direction, the tip portion of the diagonal member 11 that is not fixed to the floor slab is suspended and supported from the wagon 10. The wagon 10 is held by appropriate holding means, and the diagonal member fixing metal fitting 32 (the diagonal material fixing band metal fitting 3) of the other jig 6 is held.
1) is opened, the nuts of the anchor bolts 12 and 14 are loosened to advance the lower receiving beam 2 and the upper receiving beam 4, and then the lower receiving beam 2 and the upper receiving beam 4 are attached to each new floor slab 1a, 3a. To fix. (14) Returning to (5), the steps from (6) are sequentially repeated.
【0042】次に、図8および図9によって、本発明の
第2実施形態を説明する。この実施形態は、新設の床版
1a,3aを築造する場合に、その次に築造する新設の
格点部位置の手前まで型枠を組み、コンクリートを打設
する方が、次に、受け梁2,4を前進して、受け梁2,
4により斜材11の荷重を受ける場合、受け梁2,4の
張り出し腕長さが短くなり、有利となる形態を示したも
のである。したがって、既設の床版1,3の先端部も格
点部Kの手前まで築造されている状態である。Next, a second embodiment of the present invention will be described with reference to FIGS. In this embodiment, when constructing the new floor slabs 1a and 3a, it is better to assemble the formwork up to the position of the new grade part to be built next and place the concrete next to the receiving beam. Forward 2 and 4 to receive beam 2,
When the load of the diagonal member 11 is received by 4, the overhang arm length of the receiving beams 2 and 4 is shortened, which is advantageous. Therefore, the tip portions of the existing floor slabs 1 and 3 are also built up to the point before the rating portion K.
【0043】このように、既設の床版1,3(または新
設の床版1a,3a)が、次に構築される新設の格点部
K付近まで突出するように施工されて、前記既設の床版
1に基端部が固定される前記受け梁2,4の張り出し
(はね出し)距離が短くされていると、斜材11の荷重
および受け梁2,4による曲げモーメントが小さくな
り、ワーゲン10の吊り下げ支持金具36,37を介し
た負担も小さくなり、施工精度も向上する。また、受け
梁2,4の張り出し距離が短くなるので、受け梁2,4
の負担が小さくなり、受け梁2,4を軽量化できる。そ
の他の構成は、前記実施形態と同様であるので、同様な
要素には同様な符号を付して説明を省略する。In this way, the existing floor slabs 1 and 3 (or the new floor slabs 1a and 3a) are constructed so as to project to the vicinity of the newly constructed graded portion K, and the existing floor slabs are installed. When the projecting distance of the receiving beams 2 and 4 whose base ends are fixed to the floor slab 1 is short, the load of the diagonal member 11 and the bending moment by the receiving beams 2 and 4 are small, The burden on the wagon 10 via the suspension support fittings 36, 37 is also reduced, and the construction accuracy is improved. Moreover, since the overhang distance of the receiving beams 2 and 4 becomes short,
The load on the receiving beams 2 and 4 can be reduced, and the weight of the receiving beams 2 and 4 can be reduced. Since other configurations are the same as those of the above-described embodiment, the same reference numerals are given to the same elements and the description thereof will be omitted.
【0044】なお、前記各実施形態の場合、上部受け梁
4に上部型枠45の一部を支持させるようにしてもよ
く、また下部受け梁2に下部型枠43の一部を支持させ
るようにしてもよい。In each of the above embodiments, the upper receiving beam 4 may support a part of the upper mold 45, or the lower receiving beam 2 may support a part of the lower mold 43. You may
【0045】次に、図10および図11によって、本発
明の第3実施形態を説明する。図10は、複合トラス橋
における斜材の架設装置および架設方法を説明するため
の説明図であり、既設上床版に固定されると共にワーゲ
ンにより先端部が支持された上部受け梁4ならびにこれ
らに取付けられた治具6により斜材の上部を保持すると
共に、斜材11の下部相互を連結挟持金具48および連
結タイロッド56等により連結した状態で新設の上床版
3aを築造する直前の状態を示す概略側面説明図であ
る。Next, a third embodiment of the present invention will be described with reference to FIGS. FIG. 10 is an explanatory diagram for explaining the erection device and the erection method of the diagonal member in the composite truss bridge, and the upper receiving beam 4 fixed to the existing upper floor slab and having its tip end supported by the wagon, and the upper receiving beam 4 attached thereto. The jig 6 held by the jig 6 holds the upper portion of the diagonal member, and the lower portions of the diagonal member 11 are connected to each other by the connecting clamp 48, the connecting tie rod 56, and the like, immediately before the construction of the new upper floor slab 3a. FIG.
【0046】この実施形態は、各上下の床版1,3のい
ずれか一方に受け梁(2,4)を設けて、その受け梁に
より斜材11の一端側を保持するようにしても、斜材1
1の架設精度が向上すると共に、ワーゲン10の負担が
軽くなることを説明するための実施形態であって、図1
0の場合は、上床版3側には、前記各実施形態と同様に
上部受け梁4およびこれに固定された治具6により、斜
材11の上部が所定の位置に保持されるように構成さ
れ、前記治具6により斜材11の全荷重が保持されてい
る。In this embodiment, a receiving beam (2, 4) is provided on one of the upper and lower floor slabs 1 and 3, and one end of the diagonal member 11 is held by the receiving beam. Diagonal material 1
1 is an embodiment for explaining that the erection accuracy of No. 1 is improved and the burden on the wagon 10 is lightened.
In the case of 0, on the upper floor slab 3 side, the upper portion of the diagonal member 11 is held at a predetermined position by the upper receiving beam 4 and the jig 6 fixed to the upper receiving beam 4 as in the above embodiments. The jig 6 holds the entire load of the diagonal member 11.
【0047】また、図11に拡大して示すように、各斜
材11の下部に、斜材11の外側から包むように把持す
る連結挟持金具48を固定している。この連結挟持金具
48は、先端部に横孔を有するブラケット49の基端部
を固定した一対の把持片50を斜材11の橋軸方向両側
から挟むように配置されると共に、対向する前記各把持
片50の橋軸直角方向の側部に、上下方向に間隔をおい
て設けられたボルト挿通用透孔が設けられ、各把持片5
0の前記ボルト挿通孔に渡って挿通された複数のボルト
51およびこれに螺合されるナット52を緊締すること
により、斜材11を強固に挟持できるように構成されて
いる。Further, as shown in an enlarged manner in FIG. 11, a connecting and sandwiching metal fitting 48, which is grasped so as to be wrapped from the outside of the diagonal member 11, is fixed to the lower portion of each diagonal member 11. The connecting and sandwiching metal fitting 48 is arranged so as to sandwich a pair of gripping pieces 50, to which the base end portion of a bracket 49 having a lateral hole at the tip end portion is fixed, from both sides of the diagonal member 11 in the bridge axis direction, and each of the facing opposing pieces. Through holes for bolt insertion, which are provided at intervals in the up-down direction, are provided on the side portions of the gripping pieces 50 in the direction perpendicular to the bridge axis.
The diagonal member 11 can be firmly clamped by tightening the plurality of bolts 51 inserted through the zero bolt insertion holes and the nuts 52 screwed into the bolts 51.
【0048】また、前記各ボルト51の中間部に渡っ
て、支軸53を有する鋼製支承板54の端部が溶接によ
り固定され、前記支軸53に、ワーゲン10に一端側を
ナット等により係止されて吊り下げ支持された鋼製支持
金具54の下部が連結されて、斜材11の下部を所定の
位置に支持するように構成されている。An end of a steel support plate 54 having a support shaft 53 is fixed by welding across the intermediate portion of each bolt 51, and one end side of the wagon 10 is attached to the support shaft 53 by a nut or the like. The lower parts of the steel support fittings 54 that are locked and suspended and supported are connected to support the lower part of the diagonal member 11 at a predetermined position.
【0049】また、橋軸方向に近接してまたは間隔をお
いて隣接する斜材11に固定される連結挟持金具48に
おけるブラケット49相互は、直接ボルト等からなる横
ピン55により連結されるか、橋軸方向に間隔をおいて
隣合う挟持金具48におけるブラケット49相互を短尺
または長尺の鋼製タイロッド56およびボルト等からな
る横ピン57を介して連結されて構成される間隔保持装
置58により、橋軸方向に近接または間隔をおいた新設
側の各斜材11は橋軸方向に所定の間隔が保たれる。Further, the brackets 49 of the connecting and sandwiching metal fittings 48 fixed to the diagonal members 11 which are adjacent to each other or are spaced apart in the axial direction of the bridge are directly connected to each other by the horizontal pins 55 such as bolts. With the spacing device 58 configured by connecting the brackets 49 of the sandwiching fittings 48 adjacent to each other at intervals in the bridge axis direction via the short or long steel tie rods 56 and the horizontal pins 57 such as bolts, The diagonal members 11 on the new side that are close to or spaced apart from each other in the bridge axis direction are kept at a predetermined distance in the bridge axis direction.
【0050】この実施形態の変形形態として、斜材11
の上下の支持形態を逆に、すなわち、下床版1側に下部
受け梁2を使用して、斜材11の下部を治具6により支
持し、上部側を前記連結挟持金具48および鋼製タイロ
ッド56を使用して、斜材11の上部をワーゲン10か
ら吊り下げ支持された支持金具54により支持するよう
にしてもよい。これらの形態では、新設の上床版3aま
たは下床版1aにおける格点部Kに埋め込み固定される
新設の斜材11の上下の一端部は治具6を介して受け梁
(2,4)側に位置保持され、前記新設の斜材11の他
端部は、既設の斜材11の位置を基準にしてこれに連結
される間隔保持装置58により所定の橋軸方向の位置に
保持される。間隔保持装置58により保持される斜材1
1の橋軸直角方向については、適宜の手段に保持しても
よいが、前記間隔保持装置58および支持金具56によ
り保持されていると共に、新設斜材11の一端部が治具
6により支持されているので、新設斜材11の他端部の
橋軸直角方向の位置もきまる。このように既設の下床版
1または上床版3の一方の床版に固定された受け梁
(2,4)に固定の治具6を使用して斜材11の一端部
を保持すると共に、ワーゲン10により斜材11の他端
部を吊り下げ支持するようにしても、比較的精度よく、
効率的に施工することができ、ワーゲンの負担を少なく
することができる。As a modification of this embodiment, the diagonal member 11
The upper and lower support forms are reversed, that is, the lower receiving beams 2 are used on the lower floor slab 1 side, the lower part of the diagonal member 11 is supported by the jig 6, and the upper side is connected by the connecting clamp 48 and steel. A tie rod 56 may be used to support the upper portion of the diagonal member 11 by a support fitting 54 that is suspended and supported from the wagon 10. In these configurations, the upper and lower ends of the newly installed diagonal member 11 embedded and fixed in the rating portion K of the newly installed upper floor slab 3a or lower floor slab 1a are connected via the jig 6 to the receiving beam (2, 4) side. The other end of the newly installed diagonal member 11 is held at a predetermined position in the bridge axial direction by a spacing device 58 connected to the existing diagonal member 11 with the position of the existing diagonal member 11 as a reference. Diagonal member 1 held by the spacing device 58
In the direction perpendicular to the bridge axis of No. 1, it may be held by an appropriate means, but it is held by the spacing device 58 and the support fitting 56, and one end of the new diagonal member 11 is supported by the jig 6. Therefore, the position of the other end of the newly installed diagonal member 11 in the direction perpendicular to the bridge axis is also determined. In this way, while holding one end of the diagonal member 11 using the jig 6 fixed to the receiving beam (2, 4) fixed to one of the existing lower floor slab 1 or upper floor slab 3, Even if the other end of the diagonal member 11 is suspended and supported by the wagon 10, it is relatively accurate.
It can be constructed efficiently and the burden on the wagon can be reduced.
【0051】前記各実施形態では、斜材として鋼管から
なる斜材トラスの場合を示したが、本発明を実施する場
合、斜材としては、プレストレストコンクリート製斜材
トラスでもよく、波形鋼板あるいはFRP製の板体でも
よい。板状の斜材を保持する場合には、前記の板状斜材
11に、複数のボルト螺合用雌ねじ孔等の支持部を設け
ておき、把持用バンド35に代えて、適宜のボルト挿通
孔を有する斜材固定金具32により対応すればよい。In each of the above-mentioned embodiments, the case of the diagonal truss made of steel pipe as the diagonal is shown. However, when the present invention is carried out, the diagonal may be a prestressed concrete diagonal truss, a corrugated steel plate or a FRP. It may be made of a plate. In the case of holding a plate-shaped diagonal member, the plate-shaped diagonal member 11 is provided with a supporting portion such as a plurality of female screw holes for bolt screwing, and instead of the grip band 35, an appropriate bolt insertion hole is provided. It may be dealt with by the diagonal member fixing bracket 32 having.
【0052】前記実施形態では、ねじ式ジャッキ等の保
持位置調整装置7を使用した形態を示したが、本発明を
実施する場合、前記保持位置調整装置7としては、油圧
式ジャッキあるいはその他の適宜の保持位置調整装置と
してもよい。In the above embodiment, the holding position adjusting device 7 such as a screw type jack is used. However, when the present invention is embodied, the holding position adjusting device 7 may be a hydraulic jack or any other suitable device. May be used as the holding position adjusting device.
【0053】[0053]
【発明の効果】請求項1の発明によると、 既設下床版
の上面または既設上床版の下面の何れか一方の床版に、
先端部が新設側に突出するように配置された受け梁の基
端部を固定し、前記受け梁に斜材を保持する治具を設
け、前記治具により斜材の一端側を保持すると共に、斜
材の他端側をワーゲンにより吊り下げ支持するようにし
たので、比較的簡単な複合トラス橋における斜材の架設
装置を使用して、斜材を確実に保持して、施工誤差が生
じないように施工精度良く床版に固定することができ、
また、受け梁の一端側を床版に固定する形態であるの
で、受け梁を軽量にすることができ、ワーゲンの荷重負
担も比較的小さくすることができ、ワーゲンを小型にす
ることもでき、施工コストを低減することができる。According to the invention of claim 1, on either one of the upper surface of the existing lower floor slab or the lower surface of the existing upper floor slab,
The base end of the receiving beam arranged so that the tip portion projects toward the new side is fixed, a jig for holding the diagonal member is provided on the receiving beam, and one end side of the diagonal member is held by the jig. Since the other end of the diagonal member is suspended and supported by the wagon, the diagonal member erection device in a relatively simple composite truss bridge is used to securely hold the diagonal member, resulting in construction errors. It can be fixed to the floor slab with good construction accuracy so that there is no
Further, since the one end side of the receiving beam is fixed to the floor slab, the receiving beam can be made lightweight, the load burden on the wagon can be made relatively small, and the wagon can be made small. The construction cost can be reduced.
【0054】請求項2の発明によると、既設下床版の上
面に、先端部が新設側に突出するように配置された下部
受け梁の基端部を固定し、既設上床版の下面に、先端部
が新設側に突出するように配置された上部受け梁の基端
部を固定し、前記各上下の受け梁に斜材を保持する治具
を設けたので、比較的簡単な複合トラス橋における斜材
の架設装置を使用して、斜材を確実に保持して、施工誤
差が生じないように施工精度良く床版に固定することが
でき、また、受け梁の一端側を床版に固定する形態であ
るので、受け梁を軽量にすることができ、ワーゲンの負
担を小さくすることができ、ワーゲンを小型にすること
もでき、施工コストを低減することができる。According to the second aspect of the present invention, the base end portion of the lower receiving beam arranged so that the tip portion thereof projects toward the new side is fixed to the upper surface of the existing lower floor slab, and the lower end of the existing upper floor slab is Since the base end of the upper receiving beam, which is arranged so that its tip projects toward the new side, is fixed, and a jig for holding diagonal members is provided on each of the upper and lower receiving beams, a relatively simple composite truss bridge The sloping material erection device can be used to securely hold the sloping material and fix it to the floor slab with good construction accuracy to prevent construction errors. Since the fixing beam is fixed, the receiving beam can be made light in weight, the load on the wagon can be reduced, the wage can be made small, and the construction cost can be reduced.
【0055】また、コンクリート製のトラス材だけでな
く、鋼製のトラス材その他の斜材でも治具の先端部の斜
材固定金具を代えるだけで対応することが可能である。Further, not only concrete truss members but also steel truss members and other diagonal members can be dealt with by simply replacing the diagonal member fixing fittings at the tip of the jig.
【0056】請求項3のように、斜材を保持する前記治
具には、斜材の保持位置を調整するための保持位置調整
装置を備えていると、斜材の姿勢および位置調整の微調
整をして保持することができ、斜材を精度良く保持する
ことができる。When the jig for holding the diagonal member is provided with a holding position adjusting device for adjusting the holding position of the diagonal member, the posture and position of the diagonal member can be finely adjusted. It can be adjusted and held, and the diagonal member can be held accurately.
【0057】請求項4の発明のように、既設の床版が、
次に構築される新設の格点部付近まで突出するように施
工されて、前記既設の床版に基端部が固定される前記受
け梁の張り出し距離が短くされていると、各受け梁をさ
らに軽量にすることができ、ワーゲンの負担を小さくし
て、ワーゲンを小型にすることができる。According to the invention of claim 4, the existing floor slab is
When the projecting beam of the receiving beam, which is constructed so as to project to the vicinity of the newly constructed rating part, and whose base end is fixed to the existing floor slab, is short, Further, the weight can be reduced, the burden on the wagon can be reduced, and the wagon can be downsized.
【0058】請求項5の発明によると、既設下床版の上
面または既設上床版の下面の何れか一方の床版に、先端
部が新設側に突出するように配置された受け梁の基端部
を固定し、前記受け梁に斜材を保持する治具を設け、前
記治具により斜材の一端側を保持すると共に、斜材の他
端側をワーゲンにより吊り下げ支持して、斜材を所定の
位置に保持した後、新設の下床版または新設の上床版を
前記斜材と結合するように設けるので、治具を備えた受
け梁を使用した比較的簡単な架設装置を使用して、簡単
に斜材を所定の姿勢および位置に保持して、上床版また
は下床版に結合することができる。また、複合トラス橋
における斜材の架設方法として簡単な施工方法を提供で
き、しかも、施工コストも低減できる。According to the fifth aspect of the present invention, the base end of the receiving beam is arranged on one of the upper surface of the existing lower floor slab and the lower surface of the existing upper floor slab so that the tip portion thereof projects toward the new side. A jig for holding the diagonal member is provided on the receiving beam, and one end side of the diagonal member is held by the jig, and the other end side of the diagonal member is suspended and supported by the wagon to support the diagonal member. After holding it in place, a new lower floor slab or new upper floor slab is installed so as to be connected to the diagonal member.Therefore, use a relatively simple erection device that uses a receiving beam equipped with a jig. Thus, the diagonal member can be easily held in a predetermined posture and position and connected to the upper floor plate or the lower floor plate. In addition, a simple construction method can be provided as a method of erection of diagonal members in a composite truss bridge, and the construction cost can be reduced.
【0059】請求項6の発明によると、既設下床版の上
面の両側に、先端部が新設側に突出するように配置され
た各下部受け梁の基端部を固定すると共に、既設上床版
の下面の両側に、先端部が新設側に突出するように配置
された各上部受け梁の基端部を固定し、前記各側部の上
下の受け梁に、斜材を保持する治具をそれぞれ設け、各
側部の上下の治具に斜材を保持させた後、新設の下床版
または上床版を前記斜材と結合するように設けるので、
治具を備えた受け梁を使用した比較的簡単な架設装置を
使用して、簡単に斜材を所定の姿勢および位置に保持し
て、上床版または下床版に結合することができる。ま
た、複合トラス橋における斜材の架設方法として簡単な
施工方法を提供でき、しかも、施工コストも低減でき
る。According to the sixth aspect of the present invention, the base end portions of the respective lower receiving beams arranged so that the tips thereof project to the new side are fixed to both sides of the upper surface of the existing lower floor slab, and the existing upper floor slab is also fixed. Fix the base end of each upper receiving beam arranged so that the tip projects to the new side on both sides of the lower surface of the, and hold jigs on the upper and lower receiving beams of each side. Provided respectively, after holding the diagonal members on the upper and lower jigs on each side, the new lower floor slab or upper floor slab is provided so as to be coupled with the diagonal members,
By using a relatively simple erection device using a receiving beam provided with a jig, the diagonal member can be easily held in a predetermined posture and position and can be coupled to the upper floor plate or the lower floor plate. In addition, a simple construction method can be provided as a method of erection of diagonal members in a composite truss bridge, and the construction cost can be reduced.
【図1】本発明の複合トラス橋における斜材の架設装置
および架設方法を説明するための説明図であり、既設床
版に固定されると共にワーゲンにより先端部が支持され
た下部受け梁および上部受け梁ならびにこれらに取付け
られた治具により斜材を保持した状態で新設の下床版を
築造する直前の状態を示す概略側面説明図である。FIG. 1 is an explanatory diagram for explaining an apparatus and method for erection of diagonal members in a composite truss bridge of the present invention, which is a lower receiving beam and an upper portion which are fixed to an existing floor slab and whose front end is supported by a wagon. FIG. 3 is a schematic side view showing a state immediately before a new lower floor slab is built in a state in which a diagonal member is held by a receiving beam and a jig attached thereto.
【図2】図1と同様な説明図あり、新設の上床版を築造
する直前の状態を示す概略側面説明図である。FIG. 2 is an explanatory view similar to FIG. 1, and is a schematic side view illustrating a state immediately before a new upper floor slab is built.
【図3】各受け梁と治具および斜材からなる斜材並びに
各床版との関係を示す一部縦断正面図である。FIG. 3 is a partially longitudinal front view showing a relationship between each receiving beam, a diagonal member made of a jig and a diagonal member, and each floor slab.
【図4】図3の一部を拡大して示す図である。FIG. 4 is a diagram showing a part of FIG. 3 in an enlarged manner.
【図5】受け梁と床版との関係を示す図であって、
(a)は下部受け梁と下床版との取付け構造を示す正面
図、(b)は上部受け梁と上床版との取付け構造を示す
正面図、(c)は各受け梁の先端部がワーゲンから吊り
下げ支持されている吊り下げ支持金具により支持されて
いる状態を示す正面図である。FIG. 5 is a diagram showing the relationship between the receiving beam and the floor slab,
(A) is a front view showing a mounting structure of a lower receiving beam and a lower floor slab, (b) is a front view showing a mounting structure of an upper receiving beam and an upper floor slab, (c) is a front end of each receiving beam It is a front view which shows the state supported by the hanging support metal fitting suspended and supported from the wagon.
【図6】斜材の保持治具を示す一部縦断正面図である。FIG. 6 is a partial vertical sectional front view showing a jig for holding a diagonal member.
【図7】図6の一部横断平面図である。7 is a partial cross-sectional plan view of FIG.
【図8】本発明の他の実施形態の複合トラス橋における
斜材の架設装置および架設方法を説明するための説明図
であり、既設床版に固定されると共にワーゲンにより先
端部が支持された下部受け梁および上部受け梁ならびに
これらに取付けられた治具により斜材を保持した状態で
新設の下床版を築造する直前の状態を示す概略側面説明
図である。FIG. 8 is an explanatory view for explaining an apparatus and method for erection of a diagonal member in a composite truss bridge according to another embodiment of the present invention, in which the tip portion is supported by a wagon while being fixed to an existing floor slab. FIG. 3 is a schematic side view illustrating a state immediately before a new lower deck slab is built with a lower support beam, an upper support beam, and jigs attached to the support members holding the diagonal members.
【図9】図8と同様な説明図あり、新設の上床版を築造
する直前の状態を示す概略側面説明図である。FIG. 9 is an explanatory view similar to FIG. 8, and is a schematic side view illustrating a state immediately before a new upper floor slab is built.
【図10】本発明の複合トラス橋における斜材の架設装
置および架設方法を説明するための説明図であり、既設
上床版に固定されると共にワーゲンにより先端部が支持
された上部受け梁ならびにこれらに取付けられた治具に
より斜材の上部を保持しすると共に、斜材下部相互を連
結挟持金具および連結タイロッド等により連結した状態
で新設の上床版を築造する直前の状態を示す概略側面説
明図である。FIG. 10 is an explanatory diagram for explaining a device and method for erection of a diagonal member in the composite truss bridge of the present invention, including an upper receiving beam fixed to an existing upper floor slab and having its tip end supported by a wagon, and these. While holding the upper part of the diagonal member by the jig attached to the lower part of the diagonal member, a schematic side view showing the state just before building a new upper floor slab with the lower parts of the diagonal member connected to each other by the connecting clamps and the connecting tie rods. Is.
【図11】図10の一部を拡大して示す側面図である。FIG. 11 is a side view showing a part of FIG. 10 in an enlarged manner.
【図12】(a)は上部受け梁と既設側のアンカーボル
トおよび吊り下げ支持金具との関係を示す平面図、
(b)は下部受け梁と既設側のアンカーボルトボルトお
よび吊り下げ支持金具との関係を示す平面図である。FIG. 12 (a) is a plan view showing the relationship between the upper receiving beam and the existing anchor bolts and hanging support fittings;
FIG. 7B is a plan view showing the relationship between the lower receiving beam, the anchor bolts on the existing side, and the hanging support fitting.
【図13】(a)は従来例の説明図、(b)は複合トラ
ス橋の正面図である。13A is an explanatory view of a conventional example, and FIG. 13B is a front view of a composite truss bridge.
【図14】従来例の説明図である。FIG. 14 is an explanatory diagram of a conventional example.
A 既設の複合トラス橋 1 既設下床版 2 下部受け梁 3 上床版 4 上部受け梁 6 治具 7 保持位置調整装置 8 スライド支持板 9 既設の張り出し複合トラス橋 10 ワーゲン 11 斜材 12 アンカーボルト 12a 上部雄ねじ部 13 支持板 14 アンカーボルト 15 上部フランジ 16 押え金具 17 溝形鋼 17b ナット 18a 雌ねじ孔 18b 雌ねじ孔 19 鋼製台座 20 鉛直方向位置調整ジャッキ 21 保持部材 22 傾斜調整装置 23 横方向位置調整装置 24 ウエブ固定部 25 横ねじ杆 26 円弧状支承面 27 溝 28 雌ねじ部材 29 回動用ハンドル 30 回動用ハンドル 31 斜材固定用バンド金具 32 ウエブ固定金具 33 金具本体 34 係止溝 35 把持用バンド 36 吊り下げ支持金具 37 吊り下げ支持金具 40 ガイド杆 41 受け金具 42 連結用フランジ 43 下部型枠 44 支持金具 45 上部型枠 46 アンカー部材 48 連結挟持材 49 ブラケット 50 把持片 51 ボルト 52 ナット 53 支軸 54 支持金具 55 横ピン 56 鋼製タイロッド 57 横ピン 58 斜材間隔保持装置 A existing compound truss bridge 1 Existing lower floor slab 2 Lower beam 3 Upper deck 4 Upper beam 6 jigs 7 Holding position adjustment device 8 Slide support plate 9 Existing overhang compound truss bridge 10 Wagen 11 diagonal materials 12 Anchor bolt 12a Upper male screw part 13 Support plate 14 Anchor bolt 15 Upper flange 16 Press fitting 17 Channel steel 17b nut 18a female screw hole 18b Female screw hole 19 Steel pedestal 20 Vertical position adjustment jack 21 Holding member 22 Tilt adjusting device 23 Lateral position adjustment device 24 Web fixing part 25 horizontal screw rod 26 Circular bearing surface 27 grooves 28 Female thread member 29 Rotating handle 30 Rotating handle 31 Band member for fixing diagonal members 32 Web fixing bracket 33 metal fittings body 34 Locking groove 35 gripping band 36 Hanging support bracket 37 Hanging support bracket 40 Guide rod 41 bracket 42 Connection flange 43 Lower formwork 44 Support bracket 45 Upper formwork 46 Anchor member 48 interlocking clamp 49 bracket 50 gripping pieces 51 bolts 52 Nut 53 spindle 54 Support bracket 55 horizontal pin 56 steel tie rod 57 Horizontal pin 58 Oblique material spacing device
Claims (6)
面の何れか一方の床版に、先端部が新設側に突出するよ
うに配置された受け梁の基端部を固定し、前記受け梁に
斜材を保持する治具を設け、前記治具により斜材の一端
側を保持すると共に、斜材の他端側をワーゲンにより吊
り下げ支持するようにしたことを特徴とする複合トラス
橋における斜材の架設装置。1. A base end portion of a receiving beam arranged so that a tip portion thereof projects toward a new side is fixed to either one of an upper surface of an existing lower floor slab or a lower surface of an existing upper floor slab, and A composite truss characterized in that a jig for holding the diagonal member is provided on the receiving beam, one end side of the diagonal member is held by the jig, and the other end side of the diagonal member is suspended and supported by a wagon. Construction equipment for diagonal members in bridges.
突出するように配置された下部受け梁の基端部を固定
し、既設上床版の下面に、先端部が新設側に突出するよ
うに配置された上部受け梁の基端部を固定し、前記各上
下の受け梁に斜材を保持する治具を設けたことを特徴と
する複合トラス橋における斜材の架設装置。2. A base end portion of a lower receiving beam, which is arranged so that a tip portion thereof projects toward a new side, is fixed to an upper surface of an existing lower floor slab, and a tip portion is attached to a new side of a lower surface of the existing upper floor slab. An apparatus for constructing diagonal members in a composite truss bridge, characterized in that a base end portion of an upper receiving beam arranged so as to project is fixed, and a jig for holding the diagonal member is provided on each of the upper and lower receiving beams.
持位置を調整するための保持位置調整装置を備えている
ことを特徴とする請求項1または2に記載の複合トラス
橋における斜材の架設装置。3. The composite truss bridge according to claim 1, wherein the jig for holding the diagonal member is provided with a holding position adjusting device for adjusting the holding position of the diagonal member. Erection equipment for diagonal members in Japan.
点部付近まで突出するように施工されて、前記既設の床
版に基端部が固定される前記受け梁の張り出し距離が短
くされていることを特徴とする請求項1〜3のいずれか
に記載の複合トラス橋における複合トラス橋における斜
材の架設装置。4. An overhang distance of the receiving beam, in which an existing floor slab is constructed so as to project to the vicinity of a newly constructed rating plate to be constructed next, and a base end portion of which is fixed to the existing floor slab. 4. The erection device for diagonal members in a composite truss bridge according to claim 1, wherein the bridge truss is shortened.
面の何れか一方の床版に、先端部が新設側に突出するよ
うに配置された受け梁の基端部を固定し、前記受け梁に
斜材を保持する治具を設け、前記治具により斜材の一端
側を保持すると共に、斜材の他端側をワーゲンにより吊
り下げ支持して、斜材を所定の位置に保持した後、新設
の下床版または新設の上床版を前記斜材と結合するよう
に設けることを特徴とする複合トラス橋における斜材の
架設方法。5. A base end portion of a receiving beam arranged such that a tip portion thereof projects toward a new side is fixed to one of the upper surface of the existing lower floor slab and the lower surface of the existing upper floor slab, and A jig for holding the diagonal member is provided on the receiving beam, one end side of the diagonal member is held by the jig, and the other end side of the diagonal member is suspended and supported by a wagon to hold the diagonal member at a predetermined position. After that, a new lower floor slab or a new upper floor slab is installed so as to be connected to the diagonal members, and the method for constructing diagonal members in a composite truss bridge.
設側に突出するように配置された各下部受け梁の基端部
を固定すると共に、既設上床版の下面の両側に、先端部
が新設側に突出するように配置された各上部受け梁の基
端部を固定し、前記各側部の上下の受け梁に、斜材を保
持する治具をそれぞれ設け、各側部の上下の治具に斜材
を保持させた後、新設の下床版または新設の上床版を前
記斜材と結合するように設けることを特徴とする複合ト
ラス橋における斜材の架設方法。6. The upper end of the existing lower floor slab is fixed on both sides of the lower surface of the existing upper floor slab, while fixing the base end of each lower receiving beam arranged so that the tip end projects to the new side. Fixing the base end of each upper receiving beam arranged so that the tip projects toward the new side, and providing jigs for holding diagonal members to the upper and lower receiving beams of each side, respectively. A method for constructing a diagonal member in a composite truss bridge, characterized in that after the diagonal members are held by upper and lower jigs, a new lower floor slab or a new upper floor slab is provided so as to be connected to the diagonal member.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002099731A JP3596613B2 (en) | 2002-04-02 | 2002-04-02 | Diagonal erection device and method for composite truss bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002099731A JP3596613B2 (en) | 2002-04-02 | 2002-04-02 | Diagonal erection device and method for composite truss bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003293320A true JP2003293320A (en) | 2003-10-15 |
JP3596613B2 JP3596613B2 (en) | 2004-12-02 |
Family
ID=29241027
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002099731A Expired - Fee Related JP3596613B2 (en) | 2002-04-02 | 2002-04-02 | Diagonal erection device and method for composite truss bridge |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3596613B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2008114655A1 (en) * | 2007-03-20 | 2008-09-25 | Ricoh Company, Ltd. | A toner manufacturing method, a toner manufacturing apparatus, and a toner |
CN106428983A (en) * | 2016-09-06 | 2017-02-22 | 山东电力设备有限公司 | Fixture for transporting power transformer core |
CN110512521A (en) * | 2019-07-30 | 2019-11-29 | 中铁大桥局集团有限公司 | The docking facilities and interconnection method of big segment steel truss girder |
CN114000440A (en) * | 2021-12-13 | 2022-02-01 | 中铁一局集团有限公司 | Truss base installation cantilever structure device and method |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109972522B (en) * | 2019-03-07 | 2020-10-23 | 中交二航局第四工程有限公司 | Self-falling type adjustable box girder installation method |
-
2002
- 2002-04-02 JP JP2002099731A patent/JP3596613B2/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2008114655A1 (en) * | 2007-03-20 | 2008-09-25 | Ricoh Company, Ltd. | A toner manufacturing method, a toner manufacturing apparatus, and a toner |
CN106428983A (en) * | 2016-09-06 | 2017-02-22 | 山东电力设备有限公司 | Fixture for transporting power transformer core |
CN110512521A (en) * | 2019-07-30 | 2019-11-29 | 中铁大桥局集团有限公司 | The docking facilities and interconnection method of big segment steel truss girder |
CN110512521B (en) * | 2019-07-30 | 2021-06-29 | 中铁大桥局集团有限公司 | Butt joint device and butt joint method for large-section steel truss girder |
CN114000440A (en) * | 2021-12-13 | 2022-02-01 | 中铁一局集团有限公司 | Truss base installation cantilever structure device and method |
Also Published As
Publication number | Publication date |
---|---|
JP3596613B2 (en) | 2004-12-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4020406B2 (en) | Formwork support mechanism and placement method | |
JP2004360378A (en) | Mould support structure and concrete placing method | |
JP2003293320A (en) | Erection device of diagonal member in composite truss bridge and erection method | |
JP2004190450A (en) | Wagen form device for box girder with strut, strut support device and construction method of box girder with strut | |
JP2000045231A (en) | Erection method for arch bridge | |
JP3466136B2 (en) | Method and apparatus for overhanging PC bridge | |
JP4414806B2 (en) | Bridge member suspension jig, bridge member transportation and installation device, and bridge member transportation and installation method | |
JP3386785B2 (en) | Scaffolding support device and scaffold device in bridge structure | |
JP4111214B2 (en) | How to mount the gate block reinforcing bar to the formwork for manufacturing the coupler assembling jig and the reinforcing bar with the coupler | |
JP2905613B2 (en) | Foundation bolt fixing device | |
JP3666870B1 (en) | Material handling method and material handling device | |
JP2000320142A (en) | Device and method for reinforcement assembly in construction work | |
JP3810007B2 (en) | Steel structure of construction and construction method | |
JP4828465B2 (en) | Floor slab construction method using cargo handling device and composite floor slab | |
KR200378426Y1 (en) | A concrete trust support | |
JP4870607B2 (en) | Floor slab construction method using cargo handling device and composite floor slab | |
JPH0771112A (en) | Piping unit | |
JP3420187B2 (en) | Scaffolding unit and scaffolding device in bridge structure | |
JP2691554B2 (en) | Pillar unit formwork device | |
JP4828466B2 (en) | Floor slab construction method using cargo handling device and composite floor slab | |
JP2004225437A (en) | Main reinforcement holder for arrangement of bar in src construction column, and method for bar arrangement | |
US9254587B1 (en) | Modular endplate for prestressed precast concrete products | |
CN114214960A (en) | Prefabricated positioning system for steel beam sections | |
JPH1030333A (en) | Construction method of temporary scaffold in steel encased reinforced concrete structure and beam scaffold device | |
JP2002303041A (en) | Temporary form support device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040819 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20040831 |
|
A61 | First payment of annual fees (during grant procedure) |
Effective date: 20040831 Free format text: JAPANESE INTERMEDIATE CODE: A61 |
|
R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080917 Year of fee payment: 4 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080917 Year of fee payment: 4 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 5 Free format text: PAYMENT UNTIL: 20090917 |
|
LAPS | Cancellation because of no payment of annual fees |