CN110484309A CN201910742400.2A CN201910742400A CN110484309A CN 110484309 A CN110484309 A CN 110484309A CN 201910742400 A CN201910742400 A CN 201910742400A CN 110484309 A CN110484309 A CN 110484309A
Authority
CN
China
Prior art keywords
primary cooler
lower layer
coal gas
plate body
combined type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910742400.2A
Other languages
Chinese (zh)
Inventor
王明亮
田小丹
刘炎军
陆华
姚伟健
王杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KUNSHAN SANWEI HEAT EXCHANGER CO Ltd
Original Assignee
KUNSHAN SANWEI HEAT EXCHANGER CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KUNSHAN SANWEI HEAT EXCHANGER CO Ltd filed Critical KUNSHAN SANWEI HEAT EXCHANGER CO Ltd
Priority to CN201910742400.2A priority Critical patent/CN110484309A/en
Publication of CN110484309A publication Critical patent/CN110484309A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C10PETROLEUM, GAS OR COKE INDUSTRIES; TECHNICAL GASES CONTAINING CARBON MONOXIDE; FUELS; LUBRICANTS; PEAT
    • C10KPURIFYING OR MODIFYING THE CHEMICAL COMPOSITION OF COMBUSTIBLE GASES CONTAINING CARBON MONOXIDE
    • C10K1/00Purifying combustible gases containing carbon monoxide
    • C10K1/04Purifying combustible gases containing carbon monoxide by cooling to condense non-gaseous materials
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F28HEAT EXCHANGE IN GENERAL
    • F28DHEAT-EXCHANGE APPARATUS, NOT PROVIDED FOR IN ANOTHER SUBCLASS, IN WHICH THE HEAT-EXCHANGE MEDIA DO NOT COME INTO DIRECT CONTACT
    • F28D7/00Heat-exchange apparatus having stationary tubular conduit assemblies for both heat-exchange media, the media being in contact with different sides of a conduit wall

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • General Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Organic Chemistry (AREA)
  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The invention discloses a kind of combined type coal gas primary cooler and its system, which includes primary cooler shell, is set to the intracorporal heat exchanger tube of primary cooler shell, mixed liquor spraying mechanism, the disconnected tower tray for being set to heat exchanger tube downstream and the scummer positioned at disconnected tower tray downside;The mixed liquor spraying mechanism includes the nozzle of jet pipe and connecting spray nozzle, which is set to the upper end of heat exchanger tube;The present invention is by being mounted with heat exchanger tube, mixed liquor spraying mechanism, the disconnected tower tray for being set to heat exchanger tube downstream and scummer positioned at disconnected tower tray downside for primary cooler shell;And the disconnected tower tray has upper layer plate body and lower layer's plate body in umbrella, the stream on upper layer plate body and lower layer's plate body of the cleaning solution after being washed is dynamic, and it is washed after cleaning solution by scummer discharge primary cooler shell outside;It is substantially reduced the defect of the corrosive deposit blocking pipeline in coal gas, and extends the service life of combined type coal gas primary cooler.

Description

Combined type coal gas primary cooler and its system
Technical field
The present invention relates to the gas purifications in a kind of combined type coal gas primary cooler and its system more particularly to a kind of pair of coke oven Combined type coal gas primary cooler and its system.
Background technique
The temperature from the raw coke oven gas that coke oven comes out before entering cleaning procedure is at 80 DEG C or more in the prior art, and in coal gas Also contain a large amount of tar vapour and vapour containing ammonium hydroxide, further cooling must be made in primary cooler, and by most of tar vapour and contain ammonia Moisture condensation gets off, and primary cooler is one of important equipment of gas purification, if the temperature of coal gas in primary cooler, containing naphthalene and dust etc. Process conditions requirement is not achieved, will seriously affect the normal operation of coal gas conveying and coal gas rear portion purification system, and naphthalene in coal gas, Dust easily blocks rear portion tower, heat exchanger, and desulfurization, the efficiency washed ammonia, wash benzene are decreased obviously, so that the gas quality that dispatches from the factory can not reach Mark, or even jeopardize air blower operation and cause piping corrosion, the corrosion of crude benzol equipment, therefore primary-cooling working procedure is the base of gas purification Plinth.
The problems such as primary cooler of existing coking process mostly uses horizontal water-tube primary cooler, generally existing leakage, blocking, corrosion, And heat pipe must be exchanged within every 3 years or so and carry out whole replacements.
Therefore, it is necessary to a kind of combined type coal gas primary cooler be designed, to improve the defects of leaking, blocking, corrode problem.
Summary of the invention
The object of the present invention is to provide it is a kind of improve blocking and the combined type coal gas primary cooler that prolongs the service life and Its system.
The present invention has following technical solution: a kind of combined type coal gas primary cooler, including primary cooler to achieve the above object Shell is placed in the intracorporal heat exchanger tube of primary cooler shell, mixed liquor spraying mechanism, the disconnected tower tray for being set to heat exchanger tube downstream and is located at The scummer of disconnected tower tray downside;Primary cooler shell has positioned at the air inlet of upper end, the gas outlet of lower end and drain pipe outlet; The heat exchanger tube has the inlet tube and outlet for extending primary cooler shell;The mixed liquor spraying mechanism includes jet pipe and company The nozzle of jet pipe is connect, which is set to the upper end of heat exchanger tube;The disconnected tower tray has at least two layers of plate body, i.e. up and down direction The upper layer plate body and lower layer's plate body of arrangement, the upper layer plate body and lower layer's plate body are in umbrella-shaped structure, and in there is part in up and down direction Overlapping, and the channel of supplied gas flowing is formed between the upper layer plate body and lower layer's plate body;It is just cold that the scummer is equipped with connection The discharge pipe of the drain pipe outlet of gas shell and the helix transporting device being connected to discharge pipe.
Further improvement scheme has: lower layer's plate body one end of the disconnected tower tray and the inner wall of primary cooler shell are fixed on one It rises, drain pipe outlet is set to lower layer's plate body and primary cooler housing junction, and is located at the upside of lower layer's plate body.
Further improvement scheme has: the combined type coal gas primary cooler be further provided with lower layer's mixed liquor spraying mechanism, under Layer heat exchanger tube and positioned at downside end drain pipe export;Lower layer's mixed liquor spraying mechanism is set to the lower layer of the disconnected tower tray The lower end of plate body, and lower layer's mixed liquor spraying mechanism is equipped with lower jet pipe and connects the lower nozzle of lower jet pipe, which is located at institute State the upper end of lower layer's heat exchanger tube.
Further improvement scheme has: there is lower layer's heat exchanger tube the lower layer's inlet tube for extending primary cooler shell and lower layer to go out Mouth pipe.
Further improvement scheme has: the other end of lower layer's plate body of the disconnected tower tray has protruded upward protrusion.
To achieve the above object, following scheme can also be used in combined type coal gas primary cooler system of the present invention: a kind of combined type Coal gas primary cooler system comprising all technical characteristics of above-mentioned combined type coal gas primary cooler and with the combined type coal gas primary cooler The condensate circulation slot of connection, the discharge pipe of the scummer are connected in the condensate circulation slot.
Further improvement scheme has: the condensate circulation slot has upper section condensate circulation slot and lower end condensate circulation Slot;The combined type coal gas primary cooler system includes water sealed tank, drain pipe and connecting tube, which is connected to primary cooler shell End drain pipe is exported in water sealed tank, and water sealed tank is connected to by connecting tube with lower end condensate circulation slot.
Further improvement scheme has: the jet pipe of the mixed liquor spraying mechanism is connected to upper section condensate circulation slot.
Further improvement scheme has: the lower jet pipe of lower layer's spraying mechanism is connected to lower section condensate circulation slot.
Combined type coal gas primary cooler of the invention and its system have the following beneficial effects: the present invention by by primary cooler shell Body is mounted with heat exchanger tube, mixed liquor spraying mechanism, the disconnected tower tray for being set to heat exchanger tube downstream and the scummer for closing on disconnected tower tray;And The disconnected tower tray has upper layer plate body and lower layer's plate body in umbrella, and the cleaning solution after being washed is on upper layer plate body, lower layer's plate body Flowing, and it is washed after cleaning solution by scummer discharge primary cooler shell outside;The corrosive deposit being substantially reduced in coal gas is stifled The defect of pipeline is filled in, to extend the service life of combined type coal gas primary cooler.
Detailed description of the invention
Fig. 1 is the flow diagram of combined type coal gas primary cooler system of the present invention;
Fig. 2 is the partial structure diagram of combined type coal gas primary cooler shown in Fig. 1.
Specific embodiment
As shown in Figs.1 and 2, for the invention discloses a kind of combined type coal gas primary cooler system schematic diagram, should Combined type coal gas primary cooler includes primary cooler shell 1, is placed in the intracorporal heat exchanger tube 2 of primary cooler shell, mixed liquor spraying mechanism 3, disconnected tower tray 4, the scummer 5 positioned at disconnected tower tray downside for being set to heat exchanger tube downstream, and combined type coal gas primary cooler system Equipped with combined type coal gas primary cooler and the condensate circulation slot 6 being connect with combined type coal gas primary cooler.In the present embodiment, may be used Combined type coal gas primary cooler is defined as two-piece housing, i.e., it is boundary with disconnected tower tray 4, upside can be defined as upper casing, Downside is defined as lower piece housing.
The primary cooler shell 1 has positioned at the air inlet 10 of upper end, the gas outlet 11 of lower end and drain pipe outlet 12;It should Air inlet 10 is communicated with air inlet pipe 13, and gas outlet 11 is communicated with escape pipe 14, and the coal gas that will enter in primary cooler shell 1 passes through After the technical process such as heat exchange, slagging-off, primary cooler shell 1 is discharged from gas outlet 11 and escape pipe 14.
The heat exchanger tube 2 has the inlet tube 21 and outlet 22 for extending primary cooler shell 1.The mixed liquor spraying machine Structure 3 includes the nozzle 32 of jet pipe 31 and connecting spray nozzle, which is set to the upper end of heat exchanger tube 2.In the present embodiment, on State the lower layer's mixed liquor spraying mechanism 33 and lower layer's heat exchanger tube that combined type coal gas primary cooler is further provided in lower piece housing 23;Lower layer's mixed liquor spraying mechanism 33 is set to the downstream of the disconnected tower tray 4, which is equipped with down Jet pipe 35 and the lower nozzle 34 for connecting lower jet pipe 35, the lower nozzle 34 are located at the upper end of lower layer's heat exchanger tube 23, which changes Heat pipe 23 equally has the lower layer's inlet tube 24 and lower layer's outlet 25 for extending primary cooler shell 1.
The disconnected tower tray 4 have at least two layers of plate body, i.e., upper layer plate body 41 and lower layer's plate body 42 arranged in the up-down direction, The upper layer plate body 41 and lower layer's plate body 42 are in umbrella-shaped structure, and in overlapping in up and down direction, and the upper layer plate body 41 and The channel 43 that coal gas (gas) passes through is formed between lower layer's plate body 42, upper layer plate body 41 and lower layer's plate body 42 are conducive in umbrella The flowing of mixture liquid, coal gas and spray liquid realize by the device and shunt that coal gas enters lower housing section shell by channel 43 Body continues to cool down, and the spray liquid of upper casing is entered in upper section condensate circulation slot 61 by scummer 5 and discharge pipe 51.When upper When stating the coal gas of air inlet pipe 13 and entering primary cooler shell 1, the nozzle 32 for passing through mixed liquor spraying mechanism 3 sprays into mixed liquor liquid Afterwards, which can wash coal gas, and coal dust in coal gas or coke powder are mixed with spray liquid, and in top plate It is flowed on body 41 or lower layer's plate body 42, and purified coal gas can pass through the channel between the upper layer plate body 41 and lower layer's plate body 42 43 flow into next process.In the present embodiment, since the disconnected tower tray 4 has multilayered structure, sufficiently to be washed to coal gas Effect is washed, and the liquid after washing is discharged by scummer 5, is prevented from blocking, is detailed later.
The scummer 5 is equipped with the discharge pipe 51 for the drain pipe outlet 12 for being connected to just cold air shell 1 and is connected to discharge pipe Helix transporting device 52, and the discharge pipe 51 of the scummer 5 is connected in the condensate circulation slot 6, is convenient for next process Processing.
The condensate circulation slot 6 has upper section condensate circulation slot 61 and lower end condensate circulation slot 62;It is described compound Formula coal gas primary cooler 100 includes water sealed tank 7, drain pipe 8 and connecting tube 9, which is connected to the end of 1 lower end of primary cooler shell Hold in drain pipe outlet 16 to water sealed tank 8 (when having two sections of cooling structures, the end drain pipe outlet of the primary cooler shell 1 16 be by the external of wash liquid discharge primary cooler shell), and connecting tube 9 connects water sealed tank 7 and lower end condensate circulation slot 61 It is logical;The jet pipe 31 of the mixed liquor spraying mechanism 3 is connected to upper section condensate circulation slot 61;And the lower spray of lower layer's spraying mechanism 33 Pipe 34 is connected to lower section condensate circulation slot 62, so as to recycling for spray liquid.
42 one end of lower layer's plate body of the disconnected tower tray 4 and the inner wall of primary cooler shell 1 are fixed together, and lower layer's plate body 42 The other end protruded upward protrusion 44, the drain pipe of above-mentioned primary cooler shell 1 outlet 12 be set to lower layer's plate body 42 with it is first cold 1 junction of device shell, and be located at the upper end of lower layer's plate body 1, the liquid and residue indwelling after facilitating washing on the upper layer plate body, And be discharged by scummer 5, prevent residue from blocking primary cooler shell;The setting of the protrusion 44 can prevent liquid from flowing by channel 43 Enter lower layer space, is discharged outside primary cooler shell 1 as far as possible convenient for the residue after washing.
The present invention is by being mounted with heat exchanger tube 2 for primary cooler shell 1, mixed liquor spraying mechanism 3, being set to heat exchanger tube downstream Disconnected tower tray 4 and scummer 5 positioned at disconnected tower tray downside;And the disconnected tower tray 4 has upper layer plate body 41 and lower layer in umbrella Plate body 42, it is washed after cleaning solution flowed on upper layer plate body 41, lower layer's plate body 42, and it is washed after cleaning solution by removing Slag device 5 is discharged outside primary cooler shell 1;And wash and purified gas (being properly termed as gas by purified coal gas) pass through Channel 43 flows into lower section washing, and disposes the inlet tube 21 of the heat exchanger tube 2 for water on recirculated water, and is realized by outlet 22 Recirculated water return water, sufficiently to do cooling down processing to gas;The problem of corrosive deposit blocking pipeline being substantially reduced in coal gas, To extend the service life of combined type coal gas primary cooler.
In the present embodiment, for when above-mentioned gas further being done purified treatment, in the downstream of above-mentioned disconnected tower tray 4 into one Step is mounted with lower layer's mixed liquor spraying mechanism 33 and lower layer's heat exchanger tube 23, and the lower nozzle 34 of lower layer's mixed liquor spraying mechanism 33 is right Above-mentioned purified coal gas further does sprinkling washing, and in lower layer's inlet tube 24 of lower layer's heat exchanger tube 23 on recirculated water Water, and realize that recirculated water return water meets environmentally friendly mark to cool down the gas again convenient for discharge gas by lower layer's outlet 25 It is quasi-.
Although for illustrative purposes, the preferred embodiment of the present invention is had been disclosed, but the ordinary skill people of this field Member will realize without departing from the scope and spirit of the invention as disclosed by the appended claims, various to change Into, increase and replace be possible.

Claims (9)

1. a kind of combined type coal gas primary cooler, it is characterised in that: including primary cooler shell, be placed in the intracorporal heat exchange of primary cooler shell Pipe, mixed liquor spraying mechanism, the disconnected tower tray for being set to heat exchanger tube downstream and the scummer positioned at disconnected tower tray downside;
Primary cooler shell has positioned at the air inlet of upper end, the gas outlet of lower end and drain pipe outlet;
The heat exchanger tube has the inlet tube and outlet for extending primary cooler shell;
The mixed liquor spraying mechanism includes the nozzle of jet pipe and connecting spray nozzle, which is set to the upper end of heat exchanger tube;
The disconnected tower tray has at least two layers of plate body, i.e., upper layer plate body and lower layer's plate body arranged in the up-down direction, the top plate Body and lower layer's plate body are in umbrella-shaped structure, and in overlapping in up and down direction, and shape between the upper layer plate body and lower layer's plate body At the channel for thering is supplied gas to flow;The scummer be equipped with the drain pipe outlet for being connected to just cold air shell discharge pipe and with discharge The helix transporting device of pipe connection.
2. combined type coal gas primary cooler according to claim 1, it is characterised in that: lower layer's plate body one end of the disconnected tower tray It being fixed together with the inner wall of primary cooler shell, drain pipe outlet is set to lower layer's plate body and primary cooler housing junction, and Positioned at the upside of lower layer's plate body.
3. combined type coal gas primary cooler according to claim 1, it is characterised in that: the combined type coal gas primary cooler is into one Step is equipped with lower layer's mixed liquor spraying mechanism, lower layer's heat exchanger tube and the end drain pipe positioned at downside and exports;Lower layer's mixed liquor spray The lower end that mechanism is set to lower layer's plate body of the disconnected tower tray is spilt, and lower layer's mixed liquor spraying mechanism is equipped under lower jet pipe and connection The lower nozzle of jet pipe, the lower nozzle are located at the upper end of lower layer's heat exchanger tube.
4. combined type coal gas primary cooler according to claim 3, it is characterised in that: lower layer's heat exchanger tube, which has, to be extended just The lower layer's inlet tube and lower layer's outlet of cooler shell body.
5. combined type coal gas primary cooler according to claim 2, it is characterised in that: lower layer's plate body of the disconnected tower tray it is another One end has protruded upward protrusion.
6. a kind of combined type coal gas primary cooler system comprising at the beginning of there is combined type coal gas described in any one of claims 1 to 5 Cooler and the condensate circulation slot connecting with the combined type coal gas primary cooler, the discharge pipe of the scummer are connected to the condensate liquid In circulating slot.
7. combined type coal gas primary cooler system according to claim 6, it is characterised in that: the condensate circulation slot has Upper section condensate circulation slot and lower end condensate circulation slot;The combined type coal gas primary cooler system includes water sealed tank, drain pipe And connecting tube, the drain pipe connection primary cooler shell end drain pipe be exported in water sealed tank, and connecting tube by water sealed tank with The connection of lower end condensate circulation slot.
8. combined type coal gas primary cooler system according to claim 7, it is characterised in that: the mixed liquor spraying mechanism Jet pipe is connected to upper section condensate circulation slot.
9. combined type coal gas primary cooler system according to claim 7, it is characterised in that: the lower jet pipe of lower layer's spraying mechanism It is connected to lower section condensate circulation slot.
CN201910742400.2A 2019-08-14 2019-08-14 Combined type coal gas primary cooler and its system Pending CN110484309A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910742400.2A CN110484309A (en) 2019-08-14 2019-08-14 Combined type coal gas primary cooler and its system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910742400.2A CN110484309A (en) 2019-08-14 2019-08-14 Combined type coal gas primary cooler and its system

Publications (1)

Publication Number Publication Date
CN110484309A true CN110484309A (en) 2019-11-22

Family

ID=68550701

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910742400.2A Pending CN110484309A (en) 2019-08-14 2019-08-14 Combined type coal gas primary cooler and its system

Country Status (1)

Country Link
CN (1) CN110484309A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111282399A (en) * 2020-03-02 2020-06-16 上海济德能源环保技术有限公司 Medium-high temperature gas purification cooler
CN111560273A (en) * 2020-03-11 2020-08-21 上海兖矿能源科技研发有限公司 Chilling tower for separating Fischer-Tropsch synthesis products and process system thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101037602A (en) * 2007-04-20 2007-09-19 武汉钢铁(集团)公司 Gas transverse pipe initial cooler for coking oven
CN101619243A (en) * 2009-07-29 2010-01-06 马鞍山钢铁股份有限公司 Gas naphthalene washing process in primary-cooling working procedure of coke oven gas purification unit
CN202450060U (en) * 2012-01-09 2012-09-26 济南冶金化工设备有限公司 Novel coke oven gas washing and cooling device
CN104403703A (en) * 2014-11-28 2015-03-11 中冶焦耐工程技术有限公司 Spiral plate type coal gas primary cooler
CN104830352A (en) * 2015-04-29 2015-08-12 济南冶金化工设备有限公司 Direct-cooling primary-cooling device in coke oven raw gas chamber and cooling method
WO2016066553A1 (en) * 2014-10-27 2016-05-06 Thyssenkrupp Industrial Solutions Ag Column with absorption, scrubbing and cooling region and method for purifying a gas
CN206566661U (en) * 2017-03-02 2017-10-20 河南国环环保科技有限公司 A kind of waste gas cold treatment device
CN211141973U (en) * 2019-08-14 2020-07-31 昆山市三维换热器有限公司 Combined type coal gas primary cooler and system thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101037602A (en) * 2007-04-20 2007-09-19 武汉钢铁(集团)公司 Gas transverse pipe initial cooler for coking oven
CN101619243A (en) * 2009-07-29 2010-01-06 马鞍山钢铁股份有限公司 Gas naphthalene washing process in primary-cooling working procedure of coke oven gas purification unit
CN202450060U (en) * 2012-01-09 2012-09-26 济南冶金化工设备有限公司 Novel coke oven gas washing and cooling device
WO2016066553A1 (en) * 2014-10-27 2016-05-06 Thyssenkrupp Industrial Solutions Ag Column with absorption, scrubbing and cooling region and method for purifying a gas
CN104403703A (en) * 2014-11-28 2015-03-11 中冶焦耐工程技术有限公司 Spiral plate type coal gas primary cooler
CN104830352A (en) * 2015-04-29 2015-08-12 济南冶金化工设备有限公司 Direct-cooling primary-cooling device in coke oven raw gas chamber and cooling method
CN206566661U (en) * 2017-03-02 2017-10-20 河南国环环保科技有限公司 A kind of waste gas cold treatment device
CN211141973U (en) * 2019-08-14 2020-07-31 昆山市三维换热器有限公司 Combined type coal gas primary cooler and system thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张兆杰: "《工业锅炉操作安全技术》", vol. 1, 30 April 2008, 黄河水利出版社, pages: 138 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111282399A (en) * 2020-03-02 2020-06-16 上海济德能源环保技术有限公司 Medium-high temperature gas purification cooler
CN111560273A (en) * 2020-03-11 2020-08-21 上海兖矿能源科技研发有限公司 Chilling tower for separating Fischer-Tropsch synthesis products and process system thereof
CN111560273B (en) * 2020-03-11 2021-07-13 上海兖矿能源科技研发有限公司 Chilling tower for separating Fischer-Tropsch synthesis products and process system thereof

Similar Documents

Publication Publication Date Title
CN110484309A (en) Combined type coal gas primary cooler and its system
CN103836862B (en) A kind of cooling water temperature device and cool-down method
CN101760250A (en) Novel technique for cooling of coke-oven gas
CN108561756B (en) Raw coke oven gas pipeline condenses liquid processing device before a kind of primary cooler
CN109647058A (en) A kind of processing equipment of the baking tail gases of Hcl containing high concentration
CN208136190U (en) Naphthalene system is washed in coal gas primary cooler sprinkling
CN208049573U (en) A kind of rare metal smelting exhaust processing system
CN211141973U (en) Combined type coal gas primary cooler and system thereof
CN112795407A (en) Coal gas cooling device and using method thereof
CN106197062A (en) Axial flow air blast crossing current closed cooling tower
CN107875796A (en) It is used for the device and method for removing coke-stove gas impurity on coke oven gas pipe
CN207973711U (en) Fluidized-bed gasification furnace stable state slag-draining device
CN203144358U (en) Equipment for removing naphthalene in high-temperature coke-oven gas
CN206768049U (en) A kind of transverse pipe initial cooler cooling device
CN206356331U (en) Preventing clogging up device in raw gas cooling procedure
CN114181743B (en) Coke oven gas purification device
CN207904193U (en) A kind of pneumatic trough
CN210237534U (en) Dry quenching dust removal cooling device
CN220589297U (en) Desulfurizing tower heat sink
CN207941223U (en) A kind of fixed ammonia destilling tower
CN201254564Y (en) Water-bath type chiller of high temperature dust-containing synthesis gas
CN218989185U (en) Raw gas cooler with dust removal and tar removal functions
CN212881801U (en) Sulfur combustion dust removal cooling system
CN205199259U (en) Regeneration gas low temperature conveying system
CN217083481U (en) Spraying device of primary cooler

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination