CN206356331U - Preventing clogging up device in raw gas cooling procedure - Google Patents

Preventing clogging up device in raw gas cooling procedure Download PDF

Info

Publication number
CN206356331U
CN206356331U CN201621179699.3U CN201621179699U CN206356331U CN 206356331 U CN206356331 U CN 206356331U CN 201621179699 U CN201621179699 U CN 201621179699U CN 206356331 U CN206356331 U CN 206356331U
Authority
CN
China
Prior art keywords
wash tub
raw gas
tub pipe
triple valve
valve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621179699.3U
Other languages
Chinese (zh)
Inventor
刘常进
徐海昌
田政
田一政
刘凯
宋育勇
陈博
郭慧冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XINJIANG GUANGHUI NEW ENERGY Co Ltd
Original Assignee
XINJIANG GUANGHUI NEW ENERGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XINJIANG GUANGHUI NEW ENERGY Co Ltd filed Critical XINJIANG GUANGHUI NEW ENERGY Co Ltd
Priority to CN201621179699.3U priority Critical patent/CN206356331U/en
Application granted granted Critical
Publication of CN206356331U publication Critical patent/CN206356331U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Industrial Gases (AREA)

Abstract

The utility model belongs to coal water slurry gasification technical field, preventing clogging up device in specifically related to a kind of raw gas cooling procedure, including medium-pressure boiler supply mains, final cooler and final separator, raw gas outlet is provided with described final cooler, wash tub pipe interface, raw gas outlet is connected by raw gas house steward with final separator, triple valve C is provided with raw gas house steward, triple valve A and triple valve B are provided with medium-pressure boiler supply mains, triple valve A is connected with wash tub pipe A, wash tub pipe A is connected with wash tub pipe interface, showering guilding valve A is provided with wash tub pipe A, 8 word blind plate A and gate valve, wash tub pipe A end is provided with shower nozzle, triple valve B is connected with wash tub pipe B, wash tub pipe B one end is connected with triple valve C, the present apparatus may be implemented in after coal gas cooling device operation and system shutdown to final cooler tube side, the total inside pipe wall crystal on-line rinsing of raw gas disappears stifled, plant running load is not influenceed.

Description

Preventing clogging up device in raw gas cooling procedure
Technical field
The utility model belongs to coal water slurry gasification technical field, and in particular to the anti-clogging in a kind of raw gas cooling procedure Device.
Background technology
After raw gas is by washing, dedusting, cooling, raw gas is set to be changed into temperature:37 DEG C, pressure:2.84Mpa clean coal Gas, then it is sent to purifier.By the material such as institute's band tar, oil, phenol, ammonia, dirt is more in raw gas, raw gas is cooled down in coal gas Device is after cleaning dust cools, when entering final cooler, because temperature is relatively low(37-85℃), the ammonia in raw gas Reacted with CO2 and generate ammonium hydrogen carbonate crystal, long-play can make depositing crystalline in final cooler tube side, form resistance Power, on the one hand influence final cooler heat transfer effect, on the other hand make it that raw gas manifold pressure is higher, gasification furnace is difficult to high negative Lotus runs.Purified gas after cleaning dust simultaneously, due to ammonia salt therein rapid crystallization at low ambient temperatures, causes clean coal Gas outlet line inwall is crystallized, and pipeline caliber is diminished, system is built the pressure.Due to the limitation of equipment Design cooling load so that thick Coal gas washs incomplete before final cooler is entered, and causes heat exchanger to block, and influence operating load and cycle, runs about 2 months Left and right must be dredged to final cooler and gas exit pipeline, be cleared up, service work, and parking maintenance takes time and effort, and And frequently parking influences whole year production task for a long time, influences the performance of enterprises.
The content of the invention
The purpose of this utility model is to overcome the deficiencies in the prior art normally to transport in coal gas cooling device there is provided one kind When row or system shutdown, the anti-clogging in the raw gas cooling procedure for the crystal for removing final cooler and gas exit pipeline Device.
What the utility model was realized in:A kind of preventing clogging up device in raw gas cooling procedure, including medium-pressure boiler Supply mains, final cooler and final separator, it is characterised in that:Be provided with described final cooler raw gas import, It is provided with raw gas house steward, final separator and sets in raw gas outlet, wash tub pipe interface and discharge outlet A, raw gas outlet Import, outlet and discharge outlet B are equipped with, raw gas house steward's other end is connected with import, and triple valve C is provided with raw gas house steward, Triple valve A and triple valve B are provided with medium-pressure boiler supply mains, triple valve A is connected with wash tub pipe A, and wash tub pipe A is with rinsing Waterpipe jointing is connected, and gate valve is connected after being provided with showering guilding valve A, showering guilding valve A connections 8 word blind plate A, 8 word blind plate A on wash tub pipe A, Wash tub pipe A end, which is provided with shower nozzle joint, shower nozzle joint, is provided with shower nozzle, and wash tub pipe B is provided with triple valve B, Wash tub pipe B one end is connected with triple valve C, is provided with wash tub pipe B after showering guilding valve B, showering guilding valve B and is connected with 8 word blind plates B, discharge outlet A are connected with coal gas separator, and discharge outlet B is connected with coal gas separator.
Described triple valve A and triple valve B is reducing flow divider, and triple valve C is reducing converging valve.
Described shower nozzle is Conic nozzle.
Compared with prior art, the beneficial effects of the utility model are:Preventing clogging up device in raw gas cooling procedure is thrown With rear, it may be implemented in and rough coal gas pipeline water is boiled after coal gas cooling device operation and system shutdown, rinsed, it is to avoid because raw gas is total Pipe pressure height causes gasification furnace to be difficult to heavy-duty service, while reducing water boils frequency, adds the on-line operation rate of the present apparatus; By periodically boiling, rinsing to rough coal gas pipeline water, pressure difference between raw gas house steward and gasification furnace can be effectively reduced, it is to avoid gasification furnace Because raw gas manifold pressure Gao Erjia does not play load;By periodically boiling, rinsing to final cooler water, changing for heat exchanger is added Thermal effect, ensures that process producing index in normal control range, reduces the scavenging period and cost of heat exchanger in device, saves After preventing clogging up device in energy consumption reduction, raising company productivity effect, raw gas cooling procedure comes into operation, realize to final cooler pipe The total inside pipe wall crystal on-line rinsing of journey, raw gas disappears stifled, and plant running load is not influenceed.
Brief description of the drawings
The structural representation of preventing clogging up device in Fig. 1 raw gas cooling procedures
In figure:1- discharge outlet A, 2- final cooler, 3- shower nozzles, 4- shower nozzle joints, 5- raw gas imports, 6- wash tub pipes Interface, 7- medium-pressure boiler supply mains, 8- wash tub pipes A, 9- triple valve A, 10- triple valve B, 11- showering guilding valve A, 12-8 word blind plate A, 13- showering guilding valve B, 14-8 word blind plate B, 15- gate valve, 16- outlets, 17- final separators, 18- imports, 19- discharge outlet B, 20- Raw gas house steward, the outlet of 21- wash tub pipes B, 22- triple valve C, 23- raw gas, 24- coal gas separators.
Embodiment
Embodiment 1, as shown in Fig. 1 structures, the preventing clogging up device in a kind of raw gas cooling procedure, including medium-pressure boiler water House steward 7, final cooler 2 and final separator 17, it is characterised in that:Raw gas is provided with described final cooler 2 to enter Raw gas house steward 20 is provided with mouth 5, raw gas outlet 23, wash tub pipe interface 6 and discharge outlet A1, raw gas outlet 23, most Import 18,16 and discharge outlet B19 of outlet are provided with whole separator 17, the other end of raw gas house steward 20 is connected with import 18, slightly Triple valve C22 is provided with gas main 20, triple valve C22 is to be provided with threeway on reducing converging valve, medium-pressure boiler supply mains 7 Valve A9 and triple valve B10, triple valve A9 and triple valve B10 are reducing flow divider, and triple valve A9 is connected with wash tub pipe A8, are rinsed Water pipe A8 is connected with wash tub pipe interface 6, and showering guilding valve A11, the word blind plate of showering guilding valve A11 connections 8 are provided with wash tub pipe A8 Gate valve 15 is connected after A12,8 word blind plate A12, wash tub pipe A8 end, which is provided with shower nozzle joint 4, shower nozzle joint 4, to be provided with Shower nozzle 3, shower nozzle 3 is to be provided with wash tub pipe B21, wash tub pipe B21 one end and triple valve on Conic nozzle triple valve B10 It is provided with C22 connections, wash tub pipe B21 after showering guilding valve B13, showering guilding valve B13 and is connected with 8 word blind plate B14, discharge outlet A1 connections There is coal gas separator 24, discharge outlet B19 is connected with coal gas separator 24.
The utility model when in use, to final cooler and raw gas when may be implemented in system operation and after system shutdown Pipeline water is boiled, rinsed, when in use, and 8 word blind plate iron rings are terminated into tube side, connect wash tub pipe A and wash tub pipe B, open three Port valve A makes triple valve A two outlets have medium-pressure boiler water to pass through, and therefrom presses a boiler supply mains shunting part to arrive flushing water Pipe A, then shower nozzle is flow to by wash tub pipe A, sprayed to by shower nozzle on the inwall and internal pipeline of final cooler, to final cooling Crystallization in device is rinsed, while opening triple valve B and triple valve C, makes two outlets of triple valve B have medium-pressure boiler water to lead to Cross, raw gas and medium-pressure boiler hydration stream in triple valve C is flow to final separator, the crystallization to the total inside pipe wall of raw gas is carried out Water is boiled, rinsed, and the medium-pressure boiler flushing water in final cooler is discharged into coal gas water separation device, rough coal from final cooler bottom Medium-pressure boiler flushing water in gas house steward flows into final separator through house steward, and gas liquor separation dress is discharged into through final separator bottom Put;When not in use, the outlet of the corresponding flushing water pipe ends of triple valve A and triple valve B is closed, closing gate valve closes triple valve C's Wash tub pipe entrance, opens the medium-pressure boiler water in showering guilding valve A and showering guilding valve B emptying wash tub pipes, and 8 word blind plates connect blind plate end, Separate medium-pressure boiler water;Medium-pressure boiler water is used by exchange-column shift, changes coal gas cooling final cooler, raw gas house steward's thing Matter crystallization, blocking condition, slow down or eliminate being attached to heat exchanger inwall, the crystal of pipeline inwall, dust-laden coal tar, Jin Eryou Change technic index, extension fixture run time, the medium-pressure boiler water about 20m that comes into operation is drawn through test data3During/h, washing time During for 2h, Crystallization Plugging phenomenon is on the one hand eliminated, on the other hand will not waste, influence caused by using more medium-pressure boiler water The processing of gas liquor, full factory is less using medium-pressure boiler water installations, and the amount of coming into operation is smaller during flushing, and boiler supply mains is pressed in basic centering Pressure does not result in considerable influence, and developing result is good, during being rinsed to it, to increase preferable developing result, Appropriate increase heat exchanger import and export temperature, and technic index is within control range, does not result in index off-set phenomenon.
Preferred embodiment of the present utility model is the foregoing is only, not to limit the utility model, for this area Technical staff for, the utility model can have a various modifications and variations, all within spirit of the present utility model and principle, Any modification, equivalent substitution and improvements made etc., should be included within protection domain of the present utility model.

Claims (3)

1. the preventing clogging up device in a kind of raw gas cooling procedure, including medium-pressure boiler supply mains, final cooler and final point From device, it is characterised in that:Be provided with described final cooler raw gas import, raw gas outlet, wash tub pipe interface and It is provided with discharge outlet A, raw gas outlet on raw gas house steward, final separator and is provided with import, outlet and discharge outlet B, slightly The gas main other end is connected with import, is provided with raw gas house steward on triple valve C, medium-pressure boiler supply mains and is provided with threeway Valve A and triple valve B, triple valve A are connected with wash tub pipe A, and wash tub pipe A is connected with wash tub pipe interface, is set on wash tub pipe A Gate valve is connected after being equipped with showering guilding valve A, showering guilding valve A connections 8 word blind plate A, 8 word blind plate A, wash tub pipe A end is provided with shower nozzle It is provided with joint, shower nozzle joint on shower nozzle, triple valve B and is provided with wash tub pipe B, wash tub pipe B one end and triple valve C connects Connect, be provided with wash tub pipe B after showering guilding valve B, showering guilding valve B and be connected with 8 word blind plate B, discharge outlet A is connected with gas liquor separation Device, discharge outlet B is connected with coal gas separator.
2. the preventing clogging up device in raw gas cooling procedure according to claim 1, it is characterised in that:Described triple valve A and triple valve B is reducing flow divider, and triple valve C is reducing converging valve.
3. the preventing clogging up device in raw gas cooling procedure according to claim 1, it is characterised in that:Described shower nozzle is Conic nozzle.
CN201621179699.3U 2016-11-03 2016-11-03 Preventing clogging up device in raw gas cooling procedure Active CN206356331U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621179699.3U CN206356331U (en) 2016-11-03 2016-11-03 Preventing clogging up device in raw gas cooling procedure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621179699.3U CN206356331U (en) 2016-11-03 2016-11-03 Preventing clogging up device in raw gas cooling procedure

Publications (1)

Publication Number Publication Date
CN206356331U true CN206356331U (en) 2017-07-28

Family

ID=59368989

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621179699.3U Active CN206356331U (en) 2016-11-03 2016-11-03 Preventing clogging up device in raw gas cooling procedure

Country Status (1)

Country Link
CN (1) CN206356331U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108654376A (en) * 2018-04-18 2018-10-16 陕西未来能源化工有限公司 The recovery system and its method of ammonia in a kind of novel desulphurization solution
CN110152577A (en) * 2019-06-26 2019-08-23 天津大沽化工股份有限公司 A kind of device and method removing propylene tar-like substance

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108654376A (en) * 2018-04-18 2018-10-16 陕西未来能源化工有限公司 The recovery system and its method of ammonia in a kind of novel desulphurization solution
CN110152577A (en) * 2019-06-26 2019-08-23 天津大沽化工股份有限公司 A kind of device and method removing propylene tar-like substance
CN110152577B (en) * 2019-06-26 2023-08-29 天津大沽化工股份有限公司 Device and method for removing propylene tar matters

Similar Documents

Publication Publication Date Title
CN206356331U (en) Preventing clogging up device in raw gas cooling procedure
WO2022213578A1 (en) Blast furnace top pressure-equalizing gas purification and recovery device and process
CN106554018A (en) A kind of cold hydrogenation dust pelletizing system and technique
CN105885959B (en) Vertical coal gas washing dehydration integral system
CN204455022U (en) Slag circulation of vital energy in the wrong direction flowing water Quench vapourizing furnace
CN207076270U (en) Venturi scrubber, the washing system containing it
CN201321465Y (en) Dust removing device for blast furnace gas pipe
CN201909559U (en) Pipeline structure of water cooler for production in chemical industry
CN202860338U (en) Washing device for acetylene gas
CN104922986A (en) Yellow phosphorus furnace gas dry dusting filtration system
CN211079029U (en) Coke oven air suction pipe cleaning device
CN204958841U (en) Efficient combination formula dust -laden synthetic gas washing dust collector
CN104896970B (en) On-line back flushing residue water afterheat heat exchange device
CN207734777U (en) Device on coke oven gas pipe for removing coke-stove gas impurity
CN205974437U (en) High temperature sensible heat recovery device
CN207126294U (en) Dust collector of water curtain in a kind of manufacture of cement
CN208704528U (en) A kind of wind disturbance scaler system of heat exchanger
CN203564913U (en) Flue gas cleaning device
CN206814715U (en) A kind of device for improving semiwater gas dedusting quality
CN204434562U (en) Band waste heat recovery dry-powder solid fuel gasification system
CN105885961B (en) The horizontal dewatering integrated system of gas washing
CN204154175U (en) The anti-blocking air cooler of a kind of following current
CN108534591A (en) A kind of the wind disturbance scaler system and descaling method of heat exchanger
CN204509190U (en) Equipment derived by a kind of new Type Coke Oven raw gas
CN104060026A (en) Flue gas cooling device used for dedusting in converter

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant