A kind of assembled integral vacuum toilet and its installation method
Technical field
The present invention relates to decoration technology field, specifically a kind of assembled integral vacuum toilet and its installation method.
Background technique
In the engineering of assembled finishing, assembled integral vacuum toilet is wherein particularly important a part, and toilet is first
First need to have waterproof, the use function of humidity, existing integral vacuum toilet generally can standby waterproof function, but its structure
It is relative complex, there is no advantage in installation speed and price, for this purpose, to provide a kind of simple structure and reasonable design, installation fast by the present invention
Speed matches formula integral vacuum toilet and its installation method.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the existing defects, provides a kind of with formula integral vacuum toilet and its installation
Method connects whole chassis and wallboard, realizes Fast Installation by the way that interconnecting piece and protrusion fastener member are arranged on the keel of bottom edge
Meanwhile having effective water-proof function, by the way that integrally formed wallboard interconnecting piece and top panel interconnecting piece is arranged in top margin keel,
Wallboard and top panel are connected, structure is simple, and design is reasonable, install convenient quick distachable.
In order to solve the above-mentioned technical problems, the present invention provides one kind to match formula integral vacuum toilet and its installation method, described
Include: with formula integral vacuum toilet
Whole chassis, the entirety chassis includes chassis frame, and the chassis frame is set to the surrounding on the whole chassis, institute
It states and is additionally provided with chassis surface layer and chassis bottom on whole chassis, the chassis bottom, chassis frame, chassis surface layer are successively mutual
Connection forms whole chassis;
Bottom edge keel, the bottom edge keel are fixedly installed on the whole chassis, and the bottom edge keel are equipped with support portion, connection
Portion is provided with protrusion fastener member on the support portion, and the interconnecting piece is connected with the chassis frame;
Wallboard, the wallboard connect keel by metope and are fixedly installed on metope, and the bottom edge dragon is fallen within below the wallboard
The lower section of the support portion of bone, the wallboard is equipped with indent eye-splice slot, and the indent eye-splice slot matches with the protrusion fastener member,
By the way that indent eye-splice slot card insertion in protrusion fastener member, is connected the wallboard and the bottom edge keel;
Top panel, the top panel include top panel ontology, and the side of the top panel ontology is provided with top surface board connecting structure,
Adjacent two top panels ontology is connected by top surface board connecting structure;
Top margin keel, the top margin keel are provided with wall on the top margin keel for connecting the wallboard and the top panel
Plate interconnecting piece and top panel interconnecting piece, the wallboard interconnecting piece and top panel interconnecting piece are metal structure integrated molding.
Further, the chassis frame is elongated, and the surrounding that the whole chassis is arranged in forms carrier frame,
Filled layer is provided in the carrier frame, the filled layer is set between the chassis surface layer and the chassis bottom.
Further, the chassis frame is equipped with mounting portion, the interconnecting piece on the mounting portion and the bottom edge keel
Match, the bottom edge keel are set to the top of the chassis frame.
Further, the chassis frame is equipped with protrusion flanging part, and the side of the chassis bottom is set to described convex
Out in flanging part.
Further, the wallboard is mutually compounded to form by wallboard surface layer with wallboard base, and the wallboard surface layer is ceramic tile, institute
State the plate that wallboard base is waterproof, humidity.
Further, the top surface board connecting structure is equipped with bending edge, forms groove, the top surface in the bending edge
The side of plate ontology is set in the groove that the bending edge is formed, and the bending edge wraps the side of the top panel ontology
It wraps up in.
Further, the top surface board connecting structure includes the first connection structure, the second connection structure, first connection
It is provided with card insertion groove in structure, card insertion fastener, the card insertion groove and the card insertion are provided in second connection structure
Fastener matches, for connecting adjacent two top panels ontology.
Further, the installation method of the assembled integral vacuum toilet, comprising the following steps:
Step 1: installing whole chassis, first carries out ground levelling, is ready to complete the whole chassis and bottom edge of processing in factory
Whole chassis is placed in smooth ground by keel, and bottom edge keel are tipped in the mounting portion on whole chassis by interconnecting piece;
Step 2: installation wallboard first installs metope and connects keel, and installation metope connection keel are opened from metope angle first
Begin, after first connection keel is fixed to metope, by one on one side fixed to the connection keel for being installed to metope of wallboard
Side, while the indent eye-splice slot card insertion below wallboard connects the wallboard and the bottom edge keel, then exists in protrusion fastener member
Second connection keel is installed in the another side of the wallboard, successively installs wallboard;
Step 3: installation top margin keel tip the metope interconnecting piece card insertion of top margin keel in wallboard, successively round wall installation one
Circle forms top margin keel frame;
Step 4: first top panel is placed into the top panel interconnecting piece of top margin keel, second top panel by installation top panel
First top panel is connected by top surface board connecting structure;
Step 5: finally adjusting the gap of the top panel, repairs the gap of the wallboard and/or the chassis surface layer.
Using assembled integral vacuum toilet of the present invention and its installation method, by the way that interconnecting piece and convex is arranged on the keel of bottom edge
Fastener member out, connects whole chassis and wallboard has effective water-proof function, by top margin while realizing Fast Installation
Integrally formed wallboard interconnecting piece and top panel interconnecting piece is arranged in keel, connects wallboard and top panel, and structure is simple, and design is closed
Reason, install convenient quick distachable.
Detailed description of the invention
Attached drawing is used to provide further understanding of the present invention, and constitutes part of specification, with reality of the invention
It applies example to be used to explain the present invention together, not be construed as limiting the invention.In the accompanying drawings:
Fig. 1 is the structural schematic diagram of assembled integral vacuum toilet of the present invention;
Fig. 2 is the structural schematic diagram that whole chassis of the invention connects bottom edge keel, bottom edge keel connection wallboard;
Fig. 3 is the structural schematic diagram of metope connection keel connection wallboard of the present invention;
Fig. 4 is top panel attachment structure schematic diagram of the present invention;
Fig. 5 is the structural schematic diagram of the connection of top margin keel wallboard and top panel of the present invention.
Specific embodiment
Below in conjunction with attached drawing of the invention, technical solution of the present invention is clearly and completely described, it is clear that institute
Description is only a part of the embodiment of the present invention, instead of all the embodiments, based on the embodiments of the present invention, this field
Those of ordinary skill's every other embodiment obtained without making creative work, belongs to protection of the present invention
Range.
Fig. 1 be assembled integral vacuum toilet of the invention, including whole chassis 1, bottom edge keel 2, metope connection keel 4,
Wallboard 3, top margin keel 6, top panel 5, the entirety chassis 1 be fixedly installed on it is levelling after original flooring, bottom edge keel 2 are solid
Surely it is set to the surrounding on whole chassis 1, metope connection keel 4 are fixedly installed on original metope, and wallboard 3 connects keel by metope
4 are fixedly installed on the top of bottom edge keel 2, and top margin keel 6 are fixedly installed on the top of wallboard 3, and top panel 5 is fixedly installed on top
Keelson 6.
As shown in Fig. 2, whole chassis 1 includes chassis frame 11, the chassis frame 11 is set to the whole chassis 1
Surrounding, the chassis frame 11 are cavity structure, and for mitigating self weight and save the cost, the chassis frame 11 is elongated,
Its surrounding that the whole chassis 1 is arranged in forms carrier frame, is provided with filled layer 14, the filling in the carrier frame
Layer 14 is set between the chassis surface layer 12 and the chassis bottom 13, is additionally provided with chassis surface layer 12 on the entirety chassis 1
With chassis bottom 13, the chassis surface layer 12 is ceramic tile, and chassis bottom 13 is metal plate or plastic plate, under the chassis frame 11
Side is provided with protrusion flanging part 112, and the side of the chassis bottom 13 is set in the protrusion flanging part 112, makes the bottom
It tries to get to the heart of a matter the side seals of layer 13, the chassis bottom 13, chassis frame 11, filled layer 14, chassis surface layer 12 are successively connected with each other
Whole chassis 1 is formed, the chassis surface layer 12 and the chassis frame 11 are connected by glue;
The bottom edge keel 2 are fixedly installed on the whole chassis 1, and the bottom edge keel 2 are equipped with support portion 21, interconnecting piece
22, protrusion fastener member 211 is provided on the support portion 21, the interconnecting piece 22 is connected with the chassis frame 11, described
Chassis frame 11 is equipped with mounting portion 111, and the mounting portion 111 matches with the interconnecting piece 22 on the bottom edge keel 2, described
Bottom edge keel 2 are set to the top of the chassis frame 11, and the top of the chassis frame 11 is provided with chassis surface layer 12, described
Be provided with sealing strip 7 between bottom edge keel 2 and the chassis surface layer 12, prevent the bottom edge keel 2 and the whole chassis 1 it
Between there are gap, seep water, loosen;
Wallboard 3, the wallboard 3 connect keel 4 by metope and are fixedly installed on metope (such as Fig. 3), and the wallboard 3 is by wallboard surface layer
32 are mutually compounded to form with wallboard base 33, and the wallboard surface layer 32 is ceramic tile, and the wallboard base 33 is the plate of waterproof, humidity
Material, the plate including cement bases such as cement plate, ice fire plates, the lower section of the wallboard 3 falls within the support portion of the bottom edge keel 2
21, the lower section of the wallboard 3 is equipped with indent eye-splice slot 31, and the indent eye-splice slot 31 matches with the protrusion fastener member 211,
By the way that 31 card insertion of indent eye-splice slot in protrusion fastener member 211, is connected the wallboard 3 and the bottom edge keel 2.
As shown in figure 4, the top panel 5 includes top panel ontology 51, the top panel ontology 51 is waterproof humidity
Plate, including cement plate, ice fire plate, the low cost of plate bigger than metal, and there is visual attractiveness, the top panel ontology 51
Side be provided with top surface board connecting structure 52, adjacent two top panels ontology 51 is connected by top surface board connecting structure 52, institute
Top surface board connecting structure 52 is stated equipped with bending edge 521, the bending edge 521 is interior to form groove, the top panel ontology 51
Side 511 is set in the groove that the bending edge 521 is formed, and the bending edge 521 is by the side of the top panel ontology 51
Package solves the problems such as corner out-of-flatness or breakage;
Preferably, the top surface board connecting structure 52 includes the first connection structure 522, the second connection structure 523, and described first connects
It is provided with card insertion groove 5221 on binding structure 522, card insertion fastener 5231, the card are provided in second connection structure 523
It inserts groove 5221 and the card insertion fastener 5231 matches, for connecting adjacent two top panels ontology 51.
As shown in figure 5, the top margin keel 6 are for connecting the wallboard 3 and the top panel 5, on the top margin keel 6
It is provided with wallboard interconnecting piece 61 and top panel interconnecting piece 62, the wallboard interconnecting piece 61 and top panel interconnecting piece 62 are aluminum alloy junction
Structure is integrally formed.
The installation method of assembled integral vacuum toilet of the present invention, comprising the following steps:
Step 1: installing whole chassis 1, first carries out ground levelling, is ready to complete the whole chassis 1 and bottom of processing in factory
Whole chassis 1 is placed in smooth ground by keelson 2, and bottom edge keel 2 are tipped in the peace on whole chassis 1 by interconnecting piece 22
Dress portion 111;
Step 2: installation wallboard 3 first installs metope and connects keel 4, and installation metope connection keel 4 are first from an angle of metope
Start, after first connection keel 4 is fixed to metope, by wallboard 3 on one side fixed to the connection keel 4 for being installed to metope
One side, while 31 card insertion of indent eye-splice slot of the lower section of wallboard 3 connects the wallboard 3 and the bottom edge in protrusion fastener member 211
Then keel 2 install second connection keel 4 in the another side of the wallboard 3, successively install wallboard 3;
Step 3: installation top margin keel 6 tip 61 card insertion of metope interconnecting piece of top margin keel 6 in wallboard 3, successively round wall
One circle of installation, forms top margin keel frame;
Step 4: first top panel 5 is placed into the top panel interconnecting piece 62 of top margin keel 6 by installation top panel 5, and second
Top panel 5 connects first top panel 5 by top surface board connecting structure 52;
Step 5: finally adjusting the gap of the top panel 5, repairs the gap of the wallboard 3 and/or the chassis surface layer 12 i.e.
Complete the installation of present invention assembly integral vacuum toilet.
In conclusion a kind of assembled integral vacuum toilet and its installation method, by the way that interconnecting piece is arranged on the keel of bottom edge
With protrusion fastener member, connect whole chassis and wallboard, while realizing Fast Installation, have effective water-proof function, by
Integrally formed wallboard interconnecting piece and top panel interconnecting piece is arranged in top margin keel, connects wallboard and top panel, and structure is simple, design
Rationally, install convenient quick distachable.
In the present invention unless specifically defined or limited otherwise, term " installation ", " setting ", " connection ", " fixation ",
Equal terms shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;It can be machinery
Connection, is also possible to be electrically connected;It can be directly connected, two elements can also be can be indirectly connected through an intermediary
The interaction relationship of internal connection or two elements, unless otherwise restricted clearly, for the ordinary skill people of this field
For member, the specific meanings of the above terms in the present invention can be understood according to specific conditions.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding
And modification, the scope of the present invention is defined by the appended.