CN110374200A - Large span rigidity unevenly mixes rack high altitude bulk method - Google Patents

Large span rigidity unevenly mixes rack high altitude bulk method Download PDF

Info

Publication number
CN110374200A
CN110374200A CN201910674747.8A CN201910674747A CN110374200A CN 110374200 A CN110374200 A CN 110374200A CN 201910674747 A CN201910674747 A CN 201910674747A CN 110374200 A CN110374200 A CN 110374200A
Authority
CN
China
Prior art keywords
rack
reinforcement unit
support
supporting frame
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910674747.8A
Other languages
Chinese (zh)
Inventor
宫长义
杨东
邰鹏鸣
陈磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongyifeng Construction Group Co Ltd
Original Assignee
Zhongyifeng Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongyifeng Construction Group Co Ltd filed Critical Zhongyifeng Construction Group Co Ltd
Priority to CN201910674747.8A priority Critical patent/CN110374200A/en
Publication of CN110374200A publication Critical patent/CN110374200A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/34Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of large span rigidity unevenly to mix rack high altitude bulk method, this method first uses special designing software to carry out three-dimensional modeling to rack and carries out sunykatuib analysis to work progress when constructing, determine that rack installs reinforcement unit, set up reinforcement unit support jig and movable supporting frame, then it slides and unloads using movable supporting frame and complete the installation of reinforcement unit rack, to reinforcement unit row, unloading is in bulk backward by several times again, and pre- arch camber is carried out to subsequent rack, subsequent rack is installed, after the installation of all racks, reinforcement unit is finally unloaded, to complete mixing rack high altitude bulk.Construction efficiency of the present invention is high, improves the safety of grid structure entirety and the precision of grid structure, and all kinds of large span bolt spheres non-uniform to rigidity and solder sphere mixing rack installation have directive significance.

Description

Large span rigidity unevenly mixes rack high altitude bulk method
Technical field
The invention belongs to industrial building technical fields, and in particular to a kind of large span rigidity unevenly mixes rack high-altitude and dissipates Dress method.
Background technique
Grid structure is the space structure that the rod pieces such as steel pipe are linked by sphere nodes, have light-weight, rigidity is big, The advantages that anti-seismic performance is good is suitable for the large public buildings and Large Column Spacing workshop etc. such as gymnasium, theater, station, public place of entertainment Industrial building.Increase welded spherical node in the large span grid span centre that single bolt ball is unable to satisfy design requirement and forms hybrid network Frame, not only increases rack overall stiffness to control the deformation of rack, and the mixing rack of this local welding ball, than Integral solder ball grid is more economical;Mixing rack eliminates influence and welding of the extensive overhead welding to the whole duration simultaneously Deform the influence generated to rack installation accuracy.But existing large span mixing rack form of construction work is applied to large span and just It is unloaded when in the uneven mixing rack of degree in the bolt sphere of movable supporting frame construction and solder sphere mixed form rack monolithic region Afterwards, the solder sphere region being relatively large in diameter can generate biggish deformation, influence integrally-built safety, the hybrid network after being installed Frame precision is low.
Summary of the invention
The present invention provides a kind of large span rigidity and unevenly mixes rack high altitude bulk method, to solve it is existing greatly across Degree rigidity unevenly mixes that rack construction precision is low, the problem of safety of structure difference.
In order to reach above-mentioned technical effect, the technical solution adopted by the present invention is that:
A kind of large span rigidity unevenly mixes rack high altitude bulk method, which is characterized in that including following operating procedure:
S1. it determines that rack installs reinforcement unit: three-dimensional modeling being carried out to rack using special designing softwares such as MST and to applying Work process carries out sunykatuib analysis, determines that rack in the work progress before no system, finds the operating condition of overstressing, and use Increase the mode of support jig to form the first across the operating condition to overcome overstressing of reinforcement unit, analyzes each installation operating condition and use Temporary support moulding bed is in the presence of after reinforcing to rack, determines the unit truss of suitable quantity temporary support as rack The arrangement and method for construction of reinforcement unit is installed;
S2. reinforcement unit support jig is set up: being analyzed identified rack according to construction simulation analysis and is installed reinforcement unit Arrangement and method for construction, arrange reinforcement unit support jig supporting point deforming biggish solder sphere region, set up reinforcement unit support Moulding bed;
S3. movable supporting frame is set up: setting up reinforcement unit support jig simultaneously, it is flat as operation to set up movable supporting frame Platform, movable supporting frame use a standard column away from for a sliding element, and the operating surface of movable supporting frame is lower than lower edge;
S4. reinforcement unit rack is installed: after having set up reinforcement unit support jig and movable supporting frame, in movable supporting frame Upper carry out unwrapping wire, makes lower edge ball node coordinate, and arrange positioning bracket, adjusts absolute altitude;In ball node lower part, interim branch is set It asks the mode being supported to slide and unload by movable supporting frame and completes single unit truss installation;When installation, rack exists In bulk to carrying out on movable supporting frame, after single span region rack is installed, movable supporting frame is skidded off, then installs second piece of region Rack, and so on until complete the installation of all racks, twisted eventually to first rack bolt ball, the welding of solder sphere region is completed Afterwards, the temporary support point on movable supporting frame top starts to start to unload to two sides from intermediate position;It is temporarily propped up in movable supporting frame Setting monitoring point carries out the monitoring of reinforcement unit installation process after support point unloading;
S5. reinforcement unit unloads by several times: simulating reinforcement unit by professional software and dismantles by several times, and analyzes it and apply to subsequent Work influences, and formulates optimal gradation unloading arrangement and method for construction, divides according to the gradation unloading arrangement and method for construction of formulation reinforcement unit Secondary unloading construction, after unloading, it is in bulk to carry out senior middle school outward based on reinforcement unit;
S6. the pre- arch camber of subsequent rack: simulating subsequent rack by professional software and install, and to the installation of subsequent rack deform into The deformation values of row analysis, the subsequent rack installation before not unloaded with reinforcement unit are analysis foundation, and deformation values are subtracted unloading value As springing quantum, calculated by sequential construction analysis in the case where interim moulding bed partial relief, subsequent rack pre- arch camber, Feasible arch camber scheme is formulated, the pre- arch camber of subregion is carried out to ball node according to the arch camber scheme of formulation;
S7. subsequent rack installation and installation process monitoring: equally pass through mobile support with reinforcement unit rack mounting means Subsequent rack installation is completed in frame sliding and unloading, and every rack is respectively provided with monitoring point after movable supporting frame unloading and is installed Process monitoring;
S8. reinforcement unit is finally unloaded and is monitored: being carried out most using gradation, staging to reinforcement unit temporary support moulding bed Unloading eventually waits half an hour after every grade of unloading, and repetition measurement monitors rack deformation, carries out in the case where ensuring safety next Grade unloading finally unloads until completing reinforcement unit.
Further, in the reinforcement unit that the step S1 determines rack installation, suitable quantity temporary support is determined The method of unit truss are as follows: in construction simulation analysis analysis, to increase after support it is ensured that the operating condition rod piece do not occur super The mode of the case where stress analyzes situation of each installation operating condition after reinforcing using temporary support to rack, until due to facing When support it is too many, interior welds deformation of ball is insufficient, and support is caused to be shifted out code requirement, and temporary support moulding bed quantity is excessive Caused by support be shifted out the reinforcement unit that the unit truss before code requirement is installed as rack.
Further, during the step S2 reinforcement unit support jig is set up, the temporary support moulding bed uses single-point branch Support, gate type support frame, the support of combination Bailey bracket or self-control lattice support frame.
Further, during the step S2 reinforcement unit support jig is set up, the supporting frame lower part of support jig is set up Ground need to have enough bearing capacities.
Further, during the step S3 movable supporting frame is set up, the support frame width for the movable supporting frame set up is greater than Column is away from the operating surface of movable supporting frame is lower than lower edge 300mm.
Further, during the step S3 movable supporting frame is set up, the movable supporting frame is in fixed scaffold lower end The fixation scaffold repacking structure of certain amount and the scaffold special pulley part with certain bearing capacity is added, pulley part passes through Upright bar is fixedly connected with fixed scaffold, and pulley part is evenly distributed in fixed scaffold lower part, and setting is flat below movable supporting frame Steady sliding rail, pulley part pulley are set in sliding rail.
Further, in the step S4 reinforcement unit rack installation, unit truss installation is using every point-supported mode Installation, frame ball and rod member for grid are installed simultaneously.
Further, during the subsequent rack installation of the step S7 and installation process monitor, subsequent rack supporting point setting exists Deform maximum region.
Further, during the step S8 reinforcement unit is finally unloaded and monitored, rack unloading is using adjusting branch support Jack is completed, and when unloading draws scale value on jack, and has special messenger to command the synchronism for guaranteeing unloading.
Further, it further includes rack after the completion of load shedding that the step S8 reinforcement unit, which is finally unloaded and monitored, Grid structure is checked again when not being detached from jack, is reinforced when necessary.
Compared with prior art, the beneficial effects of the present invention are:
The present invention carries out three-dimensional modeling by using special designing software and analyzes construction simulation analysis, determines that rack is pacified Reinforcement unit is filled, interim moulding bed is set up to initial part rack and forms reinforcement unit, using reinforcement unit as subsequent outside progress The basis of high altitude bulk, thus the deformation during reducing high altitude bulk, it is ensured that the safety of structure.By gradation to " reinforcement is single Member " support jig is unloaded, and is avoided disturbing deficiency under welding ball portion, is pushed up inclined net rack support;By to the subsequent net of reinforcement unit Frame installation carries out sequential construction analysis, and carries out pre- arch camber to rack according to each operating condition deformation values being calculated, after ensure that The precision of continuous rack installation, improves the safety of grid structure.
The above description is only an overview of the technical scheme of the present invention, in order to better understand the technical means of the present invention, And it can be implemented in accordance with the contents of the specification, and in order to allow above and other objects, features and advantages of the invention can It is clearer and more comprehensible, the present invention is described in further details with reference to the accompanying drawings and examples, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.
Detailed description of the invention
Fig. 1 is present invention mixing rack high altitude bulk construction process figure.
Fig. 2 is lifting jack unloading schematic diagram when reinforcement unit of the present invention finally unloads.
Specific embodiment
As shown in Figure 1, a kind of large span rigidity unevenly mixes rack high altitude bulk method, this method includes following step It is rapid:
S1. it determines that rack installs reinforcement unit: three-dimensional modeling is carried out to rack using MST or other special designing softwares, And carry out construction simulation analysis analysis, by sunykatuib analysis, determine rack in the work progress before no system each operating condition from Body stress condition finds the operating condition of overstressing, by the operating condition of overstressing come shape by the way of increasing support jig in time At the first across dividing by this method it is ensured that the case where rod piece overstressing does not occur in the operating condition after increasing support of reinforcement unit Situation of each installation operating condition after reinforcing using temporary support to rack is analysed, until since temporary support is too many, inside weldering It receives and deforms deficiency, support is caused to be shifted out code requirement, excessively cause support to be shifted out specification interim moulding bed quantity The reinforcement unit that unit truss before it is required that is installed as rack.
S2. reinforcement unit support jig is set up: setting up reinforcement unit support jig, the supporting point of reinforcement unit support jig It is arranged in the biggish solder sphere region of deformation, after all racks all installation, temporary support moulding bed can unload dismounting;Temporarily Support jig can be using shapes such as simple single-point support, gate type support frame, the support of combination Bailey bracket and self-control lattice support frames Formula should specifically be determined according to the specific stress condition of support frame and height.Specially bearing capacity is smaller, the lower feelings of support height Preferred single-point and gate type support under condition;Bearing capacity is larger, Bailey bracket support is preferably combined in the higher situation of support height and Make lattice support frame by oneself;When setting up, support jig is subjected to certain rack load, and the ground of supporting frame lower part is necessary There are enough bearing capacities, rail case need to be set when site condition is poor, lower part needs that concrete foundation is arranged when necessary.
S3. movable supporting frame is set up: using movable supporting frame as operating platform;Movable supporting frame uses a standard column Away from for a sliding element, support frame width is preferably slightly larger than column away from so as to installation unit edge rack and installation peace when setting up Full fence;To guarantee the installation of rack and facilitating support rack ball node, the operating surface of movable supporting frame is slightly below lower edge, preferably For lower than lower edge 300mm.It is transformed as far as possible using having fixed scaffold when movable supporting frame is set up, bottom is using carrying Power is 2 tons of scaffold special pulley parts, while according to scaffold self weight and the bearing capacity of top construction loads and pulley, being calculated The upright bar quantity of pulley need to be set, and accomplish that the pulley of setting is evenly distributed in movable supporting frame lower part.To guarantee that pulley is normal It rolls, stable sliding rail is set below pulley, is i.e. the ground of rail inferior portion needs to do compacting leveling processing.
S4. reinforcement unit rack is installed: unwrapping wire is first carried out on movable supporting frame, tentatively makes lower edge ball node coordinate, And arrange positioning bracket, absolute altitude is adjusted using screw rod;It is arranged by the way of interim rest is supported using in ball node lower part again Carry out rack installation;Settable interim chock increases the stability of interim rest between supporting point and movable supporting frame.To subtract Pressure of the light rack to support frame interim rest point, it is preferred to use every point-supported mode.Rack, which is mounted on, places lower edge ball extremely Using the jack on bracket or the adjustment that the adjustment device such as screw rod carries out absolute altitude and coordinate is reconciled when on bracket.Frame ball and net Hack lever part is installed simultaneously, installs lower edge ball and installation band winds up the cone rack of ball while lower edge rod piece, installation upper cord member, The transverse bar member winded up between ball node.And it is done in the same fashion installation, until completing single unit truss.Due to welding Ball takes control welded gaps, control unit lattice size in solder sphere installation the problem of assembly is easy to produce cumulative errors, And then the method for controlling control overall dimensions, making to be welded on can be completed after the completion of assembly, shorten the solder sphere region construction time. Control will make the cornerwise error of every cell first when solder sphere is constructed, and control the deviation of overall dimensions simultaneously, preferably control Making the cornerwise error of every cell is ± 3mm, and the offset of lower edge ball node is 2mm, and controls the deviation of overall dimensions simultaneously Value is not greater than ± 2mm.When the both ends of a piece rod piece and solder sphere are welded, forbid two ends while welding, solder sphere and The group of rod piece, which is filled with three spot welding, to be advisable, and confirms that bushing pipe is installed in place before spot welding, sews up quality by regulation detection after welding procedure is complete, Guarantee that welding quality must reach design requirement.
Movable supporting frame sliding and unloading in reinforcement unit rack installation process: rack carries out scattered on movable supporting frame Fill rack, after single span region rack is installed, scaffold is skidded off, second piece of region rack is installed, and so on until complete All rack installations.Twisted eventually after first rack bolt ball, after the completion of the welding of solder sphere region, movable supporting frame top it is interim Supporting point starts to start to unload to two sides from intermediate position.Since the support jig of reinforcement unit is not removed, unloading point net The amount of deflection of frame will not generate too big variation;After rack has unloaded, rack own wt is all born on pillar, shelf Activity fixed column stretches height, removes bottom and is fixed temporarily with timber wedge, shelf is shifted onto second rack installation site using hoist engine. Butter is arranged in slipping, avoid it is stuck, while after sliding in place on channel steel welding steel or reinforcing bar as limit;It is slid onto Rail pulley both sides are blocked with timber wedge after installation site, fix shelf, stablize power when bearing rack installation.Then second is installed Pin rack, same method operating, is attached to always the other end of rack.
S5. reinforcement unit unloads by several times: setting since the interim moulding bed of reinforcement unit can be such that solder sphere region deformation does not reach Evaluation influences bolt sphere and standoff region, it is therefore desirable to carry out gradation unloading to reinforcement unit unit.Pass through professional software mould Quasi- reinforcement unit is dismantled by several times, and analyzes it to subsequent construction influence, optimal gradation unloading arrangement and method for construction is formulated, according to formulation Gradation unloading arrangement and method for construction to reinforcement unit carry out by several times unloading construct, by several times unload after, rack is laggard to reinforcement unit Row is in bulk, to ensure that stress is controlled, will not transfinite.
S6. the pre- arch camber of subsequent rack: simulating subsequent rack by professional software and install, and to the installation of subsequent rack deform into Row analysis is not unloaded front and back with reinforcement unit and continues the deformation values of rack installation for analysis foundation, deformation values are being subtracted unloading value As springing quantum, calculated by sequential construction analysis in the case where interim moulding bed partial relief, subsequent rack pre- arch camber, Arch camber arrangement and method for construction is formulated, pre- arch camber is carried out to ball node according to the arch camber arrangement and method for construction of formulation.
S7. subsequent rack installation and installation process monitoring: subsequent rack installation is installed with reinforcement unit rack, due to movement After support frame is unloaded and slid away, subsequent scaffold does not have support jig support, it is therefore necessary to carry out the prison of each operating condition in this part It surveys, every rack is required to setting monitoring point after movable supporting frame unloading, it is ensured that safety.Subsequent rack installation is using interim branch When holding in the palm dot interlace support, supporting point setting is deforming maximum region, such as span centre position.
S8. reinforcement unit is finally unloaded and is monitored: rack be all installed after to reinforcement unit temporary support moulding bed into The final unloading of row.Unloading is carried out using gradation, staging, and fractional load, remaining load have been shed after the completion of reinforcement unit Divide 2-3 progress according to rack theoretical calculation deformation values, half an hour, and repetition measurement monitoring rack deformation waited after every grade of unloading, Ensure to carry out next stage unloading in the case where safety.Unloading (such as Fig. 2 of rack is completed using branch support jack 1 is adjusted It is shown), it needs when unloading to draw scale value on jack, and there is special messenger to command the synchronism for guaranteeing unloading.Load shedding is complete Cheng Hou, rack illustrate that practical distortion is deformed greater than theoretical calculation still without jin top is detached from, existing defects after rack installation, at this time It needs to be reinforced when necessary from new review grid structure.
Present invention process principle: the rack of bolt sphere and solder sphere mixed form is in construction, above movable supporting frame After the unloading of monolithic rack, due to the not formed entirety of uneven and rack of the rigidity of rack, the solder sphere region meeting being relatively large in diameter Biggish deformation is generated, to influence whether the safety of structure.Therefore not formed whole rack lower part is unloaded in support frame monolithic It must be provided with interim moulding bed before load, be supported in the biggish position of rigidity, form local strengthening.Simultaneously during the installation process, rigidity Biggish solder sphere position is as excessive such as setting support, can be produced without the case where reaching expected deformation values, can make in this way rigidity compared with Low bolt sphere position generates offset.In the case that especially bolt sphere is heavily located at support periphery, internal solder sphere does not have It is disturbed under enough, it is excessive and the case where support node is lifted off embedded part to will lead to neighboring area stress.Therefore temporary support moulding bed It only is preferably used to reinforce unit, and determines reinforced region and reinforced region in such a way that construction simulation analysis is analyzed Influence with construction progress to peripheral structure.Pass through analysis, it is ensured that it is inadequate in reinforcement unit moulding bed jack-up position distortions, to periphery Before structure has an impact, partial relief is carried out in advance, it is ensured that reinforcement unit will not force rack to generate deviation and internal force because of crossing It transfinites.Based on the reinforcement unit for having formd certain globality, high altitude bulk is carried out outward.Support frame moves unloading and opens The deformation values of rack are at controllable state afterwards, will not be deformed it is excessive cause structure safe, then by sequential construction analysis, It predicts subsequent deformation values in bulk, by each operating condition deformation values, carries out the pre- arch camber in subregion, to guarantee the mobile support of rack installation Frame remove after rack deformation in the allowed band for designing and standardizing.By determining that rack is reinforced with sequential construction analysis Unit carries out high altitude bulk by reinforcement unit, is unloaded the major diameter solder sphere region deformation of reinforcement unit not by gradation Enough influences generated to peripheral structure are eliminated.Become simultaneously with each unit operating condition in bulk on the outside of the reinforcement unit that is calculated Based on shape value, the pre- arch camber of subregion is carried out, it is ensured that the installation accuracy of rack.
The present invention carries out three-dimensional modeling by using special designing software and analyzes construction simulation analysis, determines that rack is pacified Reinforcement unit is filled, interim moulding bed is set up to initial part rack and forms reinforcement unit, using reinforcement unit as subsequent outside progress The basis of high altitude bulk, thus the deformation during reducing high altitude bulk, it is ensured that the safety of structure.By gradation to " reinforcement is single Member " support jig is unloaded, and is avoided disturbing deficiency under welding ball portion, is pushed up inclined net rack support;By to the subsequent net of reinforcement unit Frame installation carries out sequential construction analysis, and carries out pre- arch camber to rack according to each operating condition deformation values being calculated, after ensure that The precision of continuous rack installation, improves the safety of grid structure.The present invention is suitable for that full hall support frame is not used to carry out whole All kinds of large span bolt spheres and solder sphere of body bearing mix rack, and it is full that sliding support frame has used part support frame just to accomplish The effect of hall mounting platform, saves place, supporting frame construction time and funds, and rack increases part during the installation process and faces When support, greatly improve installation effectiveness, make rack installation be more easier.The setting of rack springing quantum, completely solves rack The numerical problem of arch camber has directive significance to the construction of rack, be suitable for the non-uniform all kinds of large span bolt spheres of rigidity and Solder sphere mixes rack.
The present invention is not limited to above-mentioned specific embodiment, for those of ordinary skill in the art from above-mentioned structure Think of sets out, and without creative labor, made various transformation are within the scope of the present invention.

Claims (10)

1. a kind of large span rigidity unevenly mixes rack high altitude bulk method, which is characterized in that including following operating procedure:
S1. determine rack install reinforcement unit: using special designing software to rack carry out three-dimensional modeling and to work progress into Row sunykatuib analysis determines rack in the work progress before no system, finds the operating condition of overstressing, and support using increasing Head of the mode of moulding bed to form reinforcement unit analyzes each installation operating condition and uses temporary support across the operating condition to overcome overstressing Moulding bed is in the presence of after reinforcing to rack, determines that the unit truss of suitable quantity temporary support is installed as rack and reinforces The arrangement and method for construction of unit;
S2. reinforcement unit support jig is set up: analyzing applying for identified rack installation reinforcement unit according to construction simulation analysis Work scheme arranges reinforcement unit support jig supporting point deforming biggish solder sphere region, sets up reinforcement unit support jig;
S3. movable supporting frame is set up: it is setting up reinforcement unit support jig simultaneously, is setting up movable supporting frame as operating platform, When setting up, movable supporting frame uses a standard column away from for a sliding element, and the operating surface of movable supporting frame is lower than lower edge;
S4. reinforcement unit rack is installed: enterprising in movable supporting frame after having set up reinforcement unit support jig and movable supporting frame Row unwrapping wire makes lower edge ball node coordinate, and arranges positioning bracket, adjusts absolute altitude;Ball node lower part be arranged interim rest into The mode of row support slides and unloads the single unit truss of completion by movable supporting frame and installs;When installation, rack is in movement In bulk to carrying out on support frame, after single span region rack is installed, movable supporting frame is skidded off, then installs second piece of regional network Frame, and so on until complete the installation of all racks, twisted eventually after first rack bolt ball, after the completion of the welding of solder sphere region, The temporary support point on movable supporting frame top starts to start to unload to two sides from intermediate position;In movable supporting frame temporary support point Monitoring point is set after unloading and carries out the monitoring of reinforcement unit installation process;
S5. reinforcement unit unloads by several times: simulating reinforcement unit by professional software and dismantles by several times, and analyzes it to subsequent construction shadow It rings, formulates optimal gradation unloading arrangement and method for construction, reinforcement unit unload by several times according to the gradation unloading arrangement and method for construction of formulation Construction is carried, after unloading, it is in bulk to carry out senior middle school outward based on reinforcement unit;
S6. the pre- arch camber of subsequent rack: simulating subsequent rack by professional software and install, and divides the installation deformation of subsequent rack Analysis, before not unloaded with reinforcement unit subsequent rack installation deformation values be analysis foundation, using deformation values subtract unloading value as Springing quantum is calculated in the case where interim moulding bed partial relief, subsequent rack pre- arch camber by sequential construction analysis, is formulated Arch camber arrangement and method for construction carries out pre- arch camber to ball node according to the arch camber arrangement and method for construction of formulation;
S7. subsequent rack installation and installation process monitoring: equally sliding by movable supporting frame with reinforcement unit rack mounting means It moves and subsequent rack installation is completed in unloading, and every rack is respectively provided with monitoring point after movable supporting frame unloading and carries out installation process Monitoring;
S8. reinforcement unit is finally unloaded and is monitored: finally being unloaded using gradation, staging to reinforcement unit temporary support moulding bed It carries, half an hour is waited after every grade of unloading, and repetition measurement monitors rack deformation, next stage is carried out in the case where ensuring safety and is unloaded It carries, is finally unloaded until completing reinforcement unit.
2. large span rigidity according to claim 1 unevenly mixes rack high altitude bulk method, which is characterized in that in institute It states step S1 to determine in the reinforcement unit of rack installation, the method for determining the unit truss of suitable quantity temporary support are as follows: applying When work process simulation is analyzed, after to increase support it is ensured that there is not the case where rod piece overstressing in the operating condition in a manner of analyze it is each Situation of the installation operating condition after being reinforced using temporary support to rack, until since temporary support is too many, interior welds ball Deformation is insufficient, and support is caused to be shifted out code requirement, by temporary support moulding bed quantity it is excessive caused by support be shifted out rule The reinforcement unit that unit truss before model requirement is installed as rack.
3. large span rigidity according to claim 1 unevenly mixes rack high altitude bulk method, which is characterized in that described During step S2 reinforcement unit support jig is set up, the temporary support moulding bed is using single-point support, gate type support frame, combination shellfish thunder Frame support or self-control lattice support frame.
4. large span rigidity according to claim 1 unevenly mixes rack high altitude bulk method, which is characterized in that described During step S2 reinforcement unit support jig is set up, the supporting frame lower part ground for setting up support jig need to have enough carryings Power.
5. large span rigidity according to claim 1 unevenly mixes rack high altitude bulk method, which is characterized in that described During step S3 movable supporting frame is set up, the support frame width for the movable supporting frame set up is greater than column away from the operation of movable supporting frame Face is lower than lower edge 300mm.
6. large span rigidity according to claim 1 unevenly mixes rack high altitude bulk method, which is characterized in that described During step S3 movable supporting frame is set up, the movable supporting frame is to add certain amount in fixed scaffold lower end and have certain The fixation scaffold of the scaffold special pulley part of bearing capacity reequips structure, and pulley part is fixed and connected by upright bar and fixed scaffold It connects, pulley part is evenly distributed in fixed scaffold lower part, and stable sliding rail, pulley part pulley is arranged below movable supporting frame It is set in sliding rail.
7. large span rigidity according to claim 1 unevenly mixes rack high altitude bulk method, which is characterized in that described In the installation of step S4 reinforcement unit rack, unit truss installation is used installs every point-supported mode, frame ball and rod member for grid It installs simultaneously.
8. large span rigidity according to claim 1 unevenly mixes rack high altitude bulk method, which is characterized in that described In the subsequent rack installation of step S7 and installation process monitoring, subsequent rack supporting point setting is deforming maximum region.
9. large span rigidity according to claim 1 unevenly mixes rack high altitude bulk method, which is characterized in that described During step S8 reinforcement unit is finally unloaded and monitored, rack unloading is completed using adjusting branch support jack, when unloading Scale value is drawn on jack, and has special messenger to command the synchronism for guaranteeing unloading.
10. large span rigidity according to claim 9 unevenly mixes rack high altitude bulk method, which is characterized in that institute Stating step S8 reinforcement unit and finally unloading and monitor further includes after the completion of load shedding, to net when rack is not detached from jack Frame structure is checked again, is reinforced when necessary.
CN201910674747.8A 2019-07-25 2019-07-25 Large span rigidity unevenly mixes rack high altitude bulk method Pending CN110374200A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910674747.8A CN110374200A (en) 2019-07-25 2019-07-25 Large span rigidity unevenly mixes rack high altitude bulk method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910674747.8A CN110374200A (en) 2019-07-25 2019-07-25 Large span rigidity unevenly mixes rack high altitude bulk method

Publications (1)

Publication Number Publication Date
CN110374200A true CN110374200A (en) 2019-10-25

Family

ID=68255844

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910674747.8A Pending CN110374200A (en) 2019-07-25 2019-07-25 Large span rigidity unevenly mixes rack high altitude bulk method

Country Status (1)

Country Link
CN (1) CN110374200A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111321806A (en) * 2020-03-25 2020-06-23 中建科工集团有限公司 Net rack completion structure, net rack and net rack lifting completion method
CN112411759A (en) * 2020-10-28 2021-02-26 上海二十冶建设有限公司 Non-full-cloth support large-span steel structure high-altitude bulk accurate assembly method
CN114319885A (en) * 2022-01-14 2022-04-12 中建钢构天津有限公司 Truss installation method
CN114412228A (en) * 2022-03-30 2022-04-29 中国铁路设计集团有限公司 Underpinning system for stress conversion of existing structure and control method thereof
CN114687558A (en) * 2022-04-11 2022-07-01 长江精工钢结构(集团)股份有限公司 Method for synchronously unloading structure by utilizing sandbox
CN114809584A (en) * 2022-05-11 2022-07-29 中国建筑第二工程局有限公司 High-efficiency and high-precision jig frame and net rack assembling method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102364012A (en) * 2011-05-26 2012-02-29 浙江精工钢结构有限公司 Method for expanding existing large-span truss
CN104947942A (en) * 2015-05-06 2015-09-30 浙江东南网架股份有限公司 Computer-controlled expansion accumulative lifting method for erecting super-high arch grid structure
CN105089152A (en) * 2015-07-10 2015-11-25 中铁十八局集团建筑安装工程有限公司 Reverse installation and construction method for large bifurcated column and complex curved net rack
CN105569358A (en) * 2015-12-15 2016-05-11 中国建筑第八工程局有限公司 Construction method of special-shaped curved surface roof with large span and multiple curvatures
CN106638960A (en) * 2016-12-16 2017-05-10 徐州中煤百甲重钢科技股份有限公司 Super-span cylindrical latticed shell construction method
CN107130687A (en) * 2017-04-27 2017-09-05 上海二十冶建设有限公司 The quick mixed construction method of large area space grid structure
JP2017203328A (en) * 2016-05-13 2017-11-16 株式会社竹中工務店 Building having a portal frame
US20180155928A1 (en) * 2016-12-02 2018-06-07 Columbia Insurance Company Long span masonry lintel support system
CN108532767A (en) * 2018-05-09 2018-09-14 中建七局安装工程有限公司 Lifting construction method after space Reticulated dome is first pushed up by ring expansion
JP2019070291A (en) * 2017-10-11 2019-05-09 株式会社竹中工務店 Two-layer structure roof and repair method of existing structure
CN109881897A (en) * 2019-03-13 2019-06-14 徐州中煤百甲重钢科技股份有限公司 A kind of starting unit construction method of unilateral arch camber
CN109879179A (en) * 2019-01-25 2019-06-14 中亿丰建设集团股份有限公司 A kind of assembling type steel structure tower crane platform

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102364012A (en) * 2011-05-26 2012-02-29 浙江精工钢结构有限公司 Method for expanding existing large-span truss
CN104947942A (en) * 2015-05-06 2015-09-30 浙江东南网架股份有限公司 Computer-controlled expansion accumulative lifting method for erecting super-high arch grid structure
CN105089152A (en) * 2015-07-10 2015-11-25 中铁十八局集团建筑安装工程有限公司 Reverse installation and construction method for large bifurcated column and complex curved net rack
CN105569358A (en) * 2015-12-15 2016-05-11 中国建筑第八工程局有限公司 Construction method of special-shaped curved surface roof with large span and multiple curvatures
JP2017203328A (en) * 2016-05-13 2017-11-16 株式会社竹中工務店 Building having a portal frame
US20180155928A1 (en) * 2016-12-02 2018-06-07 Columbia Insurance Company Long span masonry lintel support system
CN106638960A (en) * 2016-12-16 2017-05-10 徐州中煤百甲重钢科技股份有限公司 Super-span cylindrical latticed shell construction method
CN107130687A (en) * 2017-04-27 2017-09-05 上海二十冶建设有限公司 The quick mixed construction method of large area space grid structure
JP2019070291A (en) * 2017-10-11 2019-05-09 株式会社竹中工務店 Two-layer structure roof and repair method of existing structure
CN108532767A (en) * 2018-05-09 2018-09-14 中建七局安装工程有限公司 Lifting construction method after space Reticulated dome is first pushed up by ring expansion
CN109879179A (en) * 2019-01-25 2019-06-14 中亿丰建设集团股份有限公司 A kind of assembling type steel structure tower crane platform
CN109881897A (en) * 2019-03-13 2019-06-14 徐州中煤百甲重钢科技股份有限公司 A kind of starting unit construction method of unilateral arch camber

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李世昂: "大跨柱面网壳结构滑移法施工方案及过程模拟研究", 《工程科技Ⅱ辑》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111321806A (en) * 2020-03-25 2020-06-23 中建科工集团有限公司 Net rack completion structure, net rack and net rack lifting completion method
CN112411759A (en) * 2020-10-28 2021-02-26 上海二十冶建设有限公司 Non-full-cloth support large-span steel structure high-altitude bulk accurate assembly method
CN114319885A (en) * 2022-01-14 2022-04-12 中建钢构天津有限公司 Truss installation method
CN114319885B (en) * 2022-01-14 2023-11-07 中建钢构天津有限公司 Truss installation method
CN114412228A (en) * 2022-03-30 2022-04-29 中国铁路设计集团有限公司 Underpinning system for stress conversion of existing structure and control method thereof
CN114687558A (en) * 2022-04-11 2022-07-01 长江精工钢结构(集团)股份有限公司 Method for synchronously unloading structure by utilizing sandbox
CN114809584A (en) * 2022-05-11 2022-07-29 中国建筑第二工程局有限公司 High-efficiency and high-precision jig frame and net rack assembling method

Similar Documents

Publication Publication Date Title
CN110374200A (en) Large span rigidity unevenly mixes rack high altitude bulk method
CN106284663B (en) A kind of construction method of ellipse suspended-dome structure
CN103866986B (en) Long span variable cross-section bolted spherical node net shell mounting method
CN106836498A (en) A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN106906955A (en) A kind of integral prefabricated reinforcing bar web frame of shear wall and its construction method
CN107476581B (en) Hoisting and mounting method for steel structure double-layer overhanging structure
CN106337501A (en) Inverted lifting installation method of arched reticulated shell
CN103938875A (en) Ground single body tensioning lifting construction method of single layer suspendome
CN105067211A (en) Detachable and reusable shear wall earthquake-proof performance test loading rack and test method
CN108505443B (en) A kind of big segment lifting self-anchored suspension bridge construction method not setting camber
CN104712083A (en) Dragline tensioning method for long-span dragline glass curtain wall
CN102108748B (en) Quadrilateral endless rope chord supporting structure and construction process
CN105386604B (en) A kind of high-altitude wire frame installation method
CN111218987A (en) Bearing type net rack construction method
CN104458455B (en) Narrow base power transmission steel pipe tower space tower leg structured testing method
CN109208915A (en) A kind of cooling tower systems and steel vestibule construction method for lifting whole
CN108842954A (en) Installation and construction method of huge different-section honeycomb beam structure system of wing-shaped roof
CN111382538A (en) Spherical net rack suspension assembly integral lifting construction method
CN101250945B (en) Method for reinforcing floor belt-loading, load-off reinforcing or loading test in building field
CN106481083A (en) A kind of installation method of globe building steel construction
CN104060836B (en) The lifting installation method of high curved surface rack
CN210597630U (en) Net rack integral lifting structure
CN111535446A (en) Construction method of large-span stadium
CN109305619A (en) A kind of building hoist guide rail bracket
CN208088520U (en) A kind of rack integral installation device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191025