CN104712083A - Dragline tensioning method for long-span dragline glass curtain wall - Google Patents

Dragline tensioning method for long-span dragline glass curtain wall Download PDF

Info

Publication number
CN104712083A
CN104712083A CN201510130209.4A CN201510130209A CN104712083A CN 104712083 A CN104712083 A CN 104712083A CN 201510130209 A CN201510130209 A CN 201510130209A CN 104712083 A CN104712083 A CN 104712083A
Authority
CN
China
Prior art keywords
curtain wall
drag
line
stretch
draw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510130209.4A
Other languages
Chinese (zh)
Other versions
CN104712083B (en
Inventor
唐际宇
黄业信
戈祥林
郭胜文
梁秋莹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201510130209.4A priority Critical patent/CN104712083B/en
Publication of CN104712083A publication Critical patent/CN104712083A/en
Application granted granted Critical
Publication of CN104712083B publication Critical patent/CN104712083B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a dragline tensioning method for a long-span dragline glass curtain wall. The dragline method for the long-span dragline glass curtain wall comprises the following steps: a mechanical analysis model of the curtain wall is established, to-be-tensioned draglines are symmetrically arranged on the two sides of the curtain wall in the length direction of the curtain wall, a testing load is exerted on the model, and stress analyzing results of the draglines are obtained under the effect of the testing load; site measuring is carried out, positioning points of top supporting seats and bottom supporting seats used for installing of the draglines are confirmed, and the top supporting seats and the bottom supporting seats are designed in a one-to-one mode; according to the positioning points, the top supporting seats are symmetrically arranged on a top beam of the curtain wall in the length direction of the curtain wall, and based on symmetric arranging on the two sides of the curtain wall, the bottom supporting seats are arranged on the curtain wall; the draglines are arranged between the corresponding top supporting seats and the bottom supporting seats; based on the stress analyzing results, tensioning is carried out on the draglines. According to module stress analyzing, a basis is provided for controlling of the construction process, so that the basic design principle for engineering is met, and the structural safety during the tensioning process is guaranteed.

Description

The cable tension method of large span drag-line curtain wall
Technical field
The present invention relates to technical field of building construction, refer in particular to a kind of cable tension method of large span drag-line curtain wall.
Background technology
At present, newly-built large-scale public and civilian construction, particularly large space, the building of large span, all will carry out the cable tension construction of large span drag-line curtain wall.But because curtain wall span is large, drag-line quantity is many, conventional curtain wall inhaul cable stretching mode is not suitable for the cable tension construction of large span drag-line curtain wall.Therefore, be necessary to develop a kind of cable tension construction being applicable to large span drag-line curtain wall newly.
Summary of the invention
Because the problems referred to above, the invention provides a kind of cable tension method of large span drag-line curtain wall, comprising:
Set up the mechanics analysis model of curtain wall, be the both sides being symmetrically arranged in curtain wall along the length direction of curtain wall by Cable to be tensioned, test load applied to described model, obtains the force analysis result of each drag-line under described test load effect;
Job site surveying setting-out, determines installing the top support of described drag-line and the anchor point of bottom support bracket, by described top support and described bottom support bracket with patten's design one to one;
According to described anchor point, the length direction symmetry along curtain wall on curtain wall back timber is installed described top support and install described subplate bearer on the curtain wall basis being symmetricly set in curtain wall both sides;
Between corresponding described top support and described bottom support bracket, described drag-line is installed;
According to described force analysis result, stretch-draw is carried out to described drag-line.
The cable tension method of large span drag-line curtain wall of the present invention, by model force analysis, for construction process control provides foundation, to meet safe, economic, applicable, the rational basic design principle of engineering, ensure the safety of structure in stretching process, reach the stress of expection.
The cable tension further improvements in methods of large span drag-line curtain wall of the present invention are, described top support comprises top board and the top otic placode being located at described top board, and described bottom support bracket comprises base plate and the bottom otic placode being located at described base plate.
The cable tension further improvements in methods of large span drag-line curtain wall of the present invention are, described bottom support bracket is installed on curtain wall basis, comprising:
On described curtain wall basis, pre-embedded steel slab is transferred according to described anchor point;
The reinforcing bar on described curtain wall basis arranges dowel;
Concreting on described curtain wall basis, is embedded in described dowel in concrete, and is exposed to outside concrete by the upper surface of described pre-embedded steel slab;
Described base plate in described bottom support bracket is welded on described pre-embedded steel slab.
The cable tension further improvements in methods of large span drag-line curtain wall of the present invention are, transfer pre-embedded steel slab, comprising according to described anchor point on described curtain wall basis:
Make the center line of described pre-embedded steel slab;
Described center line is measured, the front-rear center point of the front-rear center of described bottom support bracket point and described top support is on same vertical line.
The cable tension further improvements in methods of large span drag-line curtain wall of the present invention are, curtain wall back timber installs described top support, comprising: according to described anchor point, are welded on described curtain wall back timber by the described top board in described top support.
The cable tension further improvements in methods of large span drag-line curtain wall of the present invention are, install described drag-line, comprising between described top support and described bottom support bracket:
At the construction field (site) cable tray is installed;
By drag-line coiling disc forming in advance, be lifted on described cable tray;
By crane, drag-line is arranged on described top support;
Adopt electric block, described drag-line is drawn to described bottom support bracket and installs.
The cable tension further improvements in methods of large span drag-line curtain wall of the present invention are, described drag-line is divided into a plurality of stretch-draw group, stretch-draw group described in each comprises two the drag-line groups being symmetricly set in curtain wall both sides, drag-line group described in each comprises two described drag-lines, is interconnected by two described drag-lines in described drag-line group by two cord clip tool.
The cable tension further improvements in methods of large span drag-line curtain wall of the present invention are, when stretch-draw is carried out to described drag-line, and four described drag-lines in stretch-draw group described in each synchronous tension, and the stretch-draw of four described drag-lines is highly identical.
The cable tension further improvements in methods of large span drag-line curtain wall of the present invention are, when stretch-draw is carried out to described drag-line, first described cable tension is extremely designed 60% of stretching force with first order stretch-draw, more described cable tension is extremely designed 105% of stretching force with second level stretch-draw.
The cable tension further improvements in methods of large span drag-line curtain wall of the present invention are, described first order stretch-draw is divided into 10%, 20%, 30%, 40% and 60% Pyatyi of design stretching force, the stretch-draw of the described second level is divided into 70%, 80%, 90%, 100% and 105% 5 rank.
Accompanying drawing explanation
Fig. 1 is the flow chart of the cable tension method of large span drag-line curtain wall of the present invention.
Fig. 2 is the schematic diagram of the curtain wall stretching-drawing structure of the cable tension method of large span drag-line curtain wall of the present invention.
Fig. 3 is the scheme of installation of the drag-line of the cable tension method of large span drag-line curtain wall of the present invention.
Detailed description of the invention
In order to make object of the present invention, technical scheme and advantage clearly understand, below in conjunction with drawings and Examples, the present invention is further elaborated.Should be appreciated that specific embodiment described herein only in order to explain the present invention, be not intended to limit the present invention.
Refer to Fig. 1, Fig. 1 is the flow chart of the cable tension method of large span drag-line curtain wall of the present invention.Coordinate referring to shown in Fig. 1, the cable tension method of large span drag-line curtain wall of the present invention, comprising:
s101finite element software is utilized to set up the mechanics analysis model of curtain wall, be the both sides being symmetrically arranged in curtain wall along the length direction of curtain wall by Cable to be tensioned, test load is applied to described model, obtains the force analysis result of each drag-line under described test load effect;
Refer to Fig. 2, Fig. 2 is the schematic diagram of the curtain wall stretching-drawing structure of the cable tension method of large span drag-line curtain wall of the present invention.Coordinate shown in Fig. 2, the below of the curtain wall back timber 10 of large span drag-line curtain wall is provided with support column 20 and stretch-draw has drag-line 30.The relevant design file set up threedimensional model provided according to designing institute, the mechanics analysis model of curtain wall is set up with large-scale general finite element software SAP2000, respectively to test loads such as model Shi Hanzhang, deadweight, wind, earthquake, temperature, and the stressed of whole drag-lines on curtain wall under each test load effect is analyzed, by model force analysis, draw the force analysis result of the amount of deflection of each drag-line, axle power, end reaction.
s102according to the complexity of job site and the technical difficulty of precision controlling, the general thought of Partial controll after determining to adopt first entirety to control, coordinate system is relied on to carry out the measurement technique of job site surveying setting-out and positioning control, determine the top support of drag-line 30 and the anchor point of bottom support bracket are installed, by described top support and described bottom support bracket with patten's design one to one;
s103refer to Fig. 3, Fig. 3 is the scheme of installation of the drag-line of the cable tension method of large span drag-line curtain wall of the present invention.Coordinate referring to shown in Fig. 3, according to described anchor point, on curtain wall back timber 10 along curtain wall length direction symmetry install top support and on the curtain wall basis being symmetricly set in curtain wall both sides mounting base bearing, wherein, top support comprises top board 40 and the top otic placode 60 being welded in top board 40, and bottom support bracket comprises base plate 50 and the bottom otic placode 70 being welded in base plate 50;
During 3.1 construction bottom support bracket:
On described curtain wall basis, accurately pre-embedded steel slab is transferred according to the anchor point of releasing; The reinforcing bar on described curtain wall basis arranges dowel, dowel and concrete beam reinforcing firm welding; Concreting on described curtain wall basis, in concreting process, send special messenger's supervision and check, embedded part of guaranteeing to vibrate is not shifted, require built-in fitting absolute altitude deviation ± 5mm, the position of embedded part and design attitude deviation ≯ 10mm, be embedded in concrete by described dowel, and the upper surface of described pre-embedded steel slab is exposed to outside concrete, then the base plate 50 of described bottom support bracket is welded on described pre-embedded steel slab.Further, when transferring pre-embedded steel slab, according to curtain wall feature, control point, four limits is found out according to drawing, make the center line of pre-embedded steel slab, described center line is measured one by one, reduce random error of measurement, make the front-rear center point of the front-rear center of bottom support bracket to be installed point and top support on same vertical line, can not run-off the straight during to ensure to install pre-stretching wire rope.
During 3.2 installation top support:
1) driven hanging basket is adopted to carry out the welding procedure of top support.Before using, hanging basket is comprehensively checked, and energising is debugged.In hanging basket use procedure, hanging basket attendant timing should tip row inspection in Steel wire rope lock.2) center of accurately locator head bearing, bottom support bracket, ejects cross wire, and error is at ± 3mm.3) weld seam requires that, for first-order weld, all welders must carry out welding examination, can carry out welding operation after qualified.4) after top support and bottom support bracket have welded, butt welded seam carries out magnetic powder inspection detection, guarantees that all weldqualities reach the requirement of first-order weld, can carry out next step operation.
s104coordinate shown in Fig. 3, between the top otic placode 60 and the bottom otic placode 70 of bottom support bracket of corresponding top support, drag-line 30 is installed;
4.1 riggings are selected
When installing drag-line, by normal cable curtain wall construction technology, the cutting length of rigging is measured and could must be started after agent structure stabilization, otherwise can have influence on guy cable length, and then affects the safety of tensioning process and structure.The rigging maximal regulated amount of standard is+170mm ~-50mm.The malformation value that the present invention causes according to the theory deformation value under the measurement error value at scene, rigging mismachining tolerance, agent structure load, stretch-draw, selects non-standard processes rigging, regulates length to reach+150mm ~-270mm.
4.2 drag-lines are installed and pretension
1) at the construction field (site) cable tray is installed, in order to site operation is convenient, by cable body coiling disc forming in processing factory, is lifted on pre-processed cable tray behind scene.
2) drag-line is according to the order first loading onto anchor point (i.e. top support position) and refill anchorage (i.e. bottom support bracket position), and install successively, upper anchor point adopts two 25t mobile cranes, wherein a responsible lifting, is responsible for auxiliary for other one.After upper anchor point installs, electric block fixed by crane, install with rope traction anchorage.Crane is utilized to carry out the construction of reeving of large span in conjunction with the mode of electric block and wire rope, simple and convenient, high construction efficiency.
During installation, described drag-line is divided into a plurality of stretch-draw group, stretch-draw group described in each comprises two the drag-line groups being symmetricly set in curtain wall both sides, and drag-line group described in each comprises two described drag-lines, is interconnected by two described drag-lines in described drag-line group by two cord clip tool.
3) in the process that drag-line upwards draws high, keep a close eye on tapered end through agent structure fixed point position, speed wants slow, prevents locking head block in adapter.
4) drag-line is pulled to top, and come loose tapered end place tied rope, by tapered end and top support bolt, then unclamps firm, completes drag-line lifting.
5) drag-line carries out pretension after installing, and namely to giving drag-line certain stretching force, the amount of deflection produced with the weight overcoming drag-line self, makes drag-line be in the pulling preparation stage.
s105according to described force analysis result, stretch-draw is carried out to described drag-line.
5.1 pulling preparation
1) drag-line is free state before installing, length 1mm ~ 3mm larger than design load.Every root drag-line is numbered, carries out target Suo Libiao in advance.
2) before stretch-draw, repetition measurement is carried out to the pitch-row of top otic placode and spacing.Contrast according to kinematic error when measurement error and blanking, if meet kinematic error requirement, need not adjust, if do not met, then readjust the position of top otic placode.The spacing of top otic placode then needs the allowable error considering that glass is installed, and is generally 6mm.
3) before stretch-draw, carry out stretching force table and target Suo Libiao, stretching force utilizes the method for tearing open to calculate according to final Suo Li.Stretch-draw completes the design Suo Li in moment, i.e. target Suo Li, is also the examination Suo Li that stretch-draw is checked and accepted simultaneously.
5.2 tension sequence
Tension sequence causes agent structure deformation values minimum for principle with stretch-draw, and during construction, the tension sequence following computer simulation emulation carries out.Particularly, four described drag-lines in stretch-draw group described in each synchronous tension, and the stretch-draw of four described drag-lines is highly identical.Adopt symmetrical stretching mode, can prevent curtain wall in the process of stretch-draw from deforming due to unbalance stress.
5.3 stretching force classifications:
1) stretch-draw is divided into two-stage, and the first order is stretched to 60% of design stretching force, and the second level is stretched to 105% of design tension force.According to Suo Li measured result, the Suo Li that do not meet the demands is finely tuned.
2) little level is segmented in every grade of stretch-draw again, and first order stretch-draw is subdivided into 5 little levels, is respectively 10%, 20%, 30%, 40%, 60% of design stretching force; Second level stretch-draw is subdivided into 5 little levels, be respectively 70%, 80%, 90%, 100%, 105% of design stretching force, of short duration pause (30 seconds) is done in the middle of every two-stage, measure the stretch value of drag-line, monitor curtain wall to deform, timely adjustment stretch-draw degree, prevents because disposable stretch-draw degree is excessive and cause curtain wall to deform.
5.4 tension operation main points
1) tensioning equipment is installed, and because tensioning equipment assembly is more, therefore must handle with care when installing, the tensioning equipment centre of form is overlapped with the drag-line centre of form, to ensure that prestressed cable does not produce bias when carrying out stretch-draw.
2) prestress steel cable stretching: utilize the method for point little level to reach progressively synchronous, each little level terminates unified adjustment, and stretch-draw slows down than faster, the pick up speed that stretch-draw is slow, finally reaches synchronous tension.
3) temperature adjustmemt: stretch-draw completes rope force value and stretch-draw force value all needs identical with design basis temperature, when when stretch-draw, temperature difference is larger, should accounting temperature correction value.According to average degree/day at that time, stretching force calculated value superposes with correction value and is actual stretching force numerical value.
4) stretching process safety controls
1. tensioning tooling installation qualification could pressurize, and stretching process strictly controls pressing speed, controls actual applying pulling force and is no more than 10% of calculating stretching force.
2. select rational tension sequence, make symmetrical configuration stressed as far as possible, the outer moment of torsion of plane of control plane truss.Adopt the method for dual control to carry out stretch-draw, stretching force is as dominant item, and stretch value is as check.
3. add the monitoring of the power of wringing and distortion in stretching process, make every effort to the accuracy measured, when monitor data error is larger, should stretch-draw be suspended, analytical error reason.
5) stretch-draw surveying record: first record drag-line original length, every stretch-draw one-level, then record pressure sensor and record pressure and total powerstation records agent structure deformation values, after stretch-draw completes, surveying record drag-line drift again, record overall stretch value, to carry out overall process monitoring to stayed structure and agent structure.
6) pulling force monitoring, check: because metal material self-characteristic can produce a certain amount of creeping in length after cable tension, value of thrust also can decline thereupon, therefore drag-line pulling force need carry out detection check after 5 days, if survey numerical value exceed scope of design should give in time stretch-draw adjustment, what value of thrust was less than design load carries out tensioning, the carrying out exceeding design load unloads power, such that the value of thrust with a pair drag-line is impartial and difference is no more than 5kN.
5.5 points for attention
1) structure stress situation and the Suo Li situation of change of each stretch-draw step should be calculated in detail, ensure that structural element and Cable forces are no more than limit condition design value, have enough safety stocks.
2) for ensureing the safety of structure and tensioning tooling, tension operation strictly should control stretching force, and stretching force must not exceed theoretical value 10%, and drag-line stretch value is listed in target Suo Libiao.
3) cable tension completes, and carries out Suo Li actual measurement, and adjustment mechanical model, checks the safety of stayed structure under various load case, guarantee safety of structure.
Finally, stretching construction monitored and check and accept
1) deformation monitoring
In the process of prestress steel cable stretching, in conjunction with simulative calculation of construction result, carry out the safety of structure and the quality of prestress application during monitoring can ensure pre-stress construction to the distortion of structure, deformation monitoring adopts total powerstation.
In stretching process, the distortion of measurement and the theory deformation of calculating are compared, if stop stretch-draw time difference comparatively large (more than 20%), find reason and continue stretch-draw again after determining solution.
2) cable force monitoring
The monitoring of Suo Li can be monitored by oil pressure sensor and dynamic tester, and Suo Li dynamic tester adopts the instrument of monitoring vibration frequency measurement Suo Li.
Oil pressure sensor is installed on hydraulic jack oil pump, can be monitored the pulling force of prestressed cable in tensioning cable process by sensor special readout instrument at any time.
3) check and accept
Cable force monitoring is after 7 days, and deformation values, in design allowed band, is organized management to check and accept, and carried out next process construction.
The cable tension method of large span drag-line curtain wall of the present invention, by model force analysis, for construction process control provides foundation, to meet safe, economic, applicable, the rational basic design principle of engineering, ensure the safety of structure in stretching process, reach the stress of expection.According to feature and the on-the-spot actual conditions of engineering, be distributed as desired value with the Suo Li of designing requirement, select rational tension sequence and stage division, pass through simulation calculation, draw the stretching force often walking every root rope, ensure the safety of structure in stretching process, reach the stress of expection.With guidance program design, select optimization design scheme, for construction process control provides foundation, to meet safe, economic, applicable, the rational basic design principle of engineering, reach simple and convenient, the beneficial effect of high construction efficiency.
The above is only preferred embodiment of the present invention, not any pro forma restriction is done to the present invention, although the present invention discloses as above with preferred embodiment, but and be not used to limit the present invention, any those skilled in the art, not departing from the scope of technical solution of the present invention, make a little change when the technology contents of above-mentioned announcement can be utilized or be modified to the Equivalent embodiments of equivalent variations, in every case be the content not departing from technical solution of the present invention, according to any simple modification that technical spirit of the present invention is done above embodiment, equivalent variations and modification, all still belong in the scope of technical solution of the present invention.

Claims (10)

1. a cable tension method for large span drag-line curtain wall, is characterized in that, comprising:
Set up the mechanics analysis model of curtain wall, be the both sides being symmetrically arranged in curtain wall along the length direction of curtain wall by Cable to be tensioned, test load applied to described model, obtains the force analysis result of each drag-line under described test load effect;
Job site surveying setting-out, determines installing the top support of described drag-line and the anchor point of bottom support bracket, by described top support and described bottom support bracket with patten's design one to one;
According to described anchor point, the length direction symmetry along curtain wall on curtain wall back timber is installed described top support and install described subplate bearer on the curtain wall basis being symmetricly set in curtain wall both sides;
Between corresponding described top support and described bottom support bracket, described drag-line is installed;
According to described force analysis result, stretch-draw is carried out to described drag-line.
2. the cable tension method of large span drag-line curtain wall as claimed in claim 1, is characterized in that, described top support comprises top board and the top otic placode being located at described top board, and described bottom support bracket comprises base plate and the bottom otic placode being located at described base plate.
3. the cable tension method of large span drag-line curtain wall as claimed in claim 2, is characterized in that, described bottom support bracket is installed on curtain wall basis, comprising:
On described curtain wall basis, pre-embedded steel slab is transferred according to described anchor point;
The reinforcing bar on described curtain wall basis arranges dowel;
Concreting on described curtain wall basis, is embedded in described dowel in concrete, and is exposed to outside concrete by the upper surface of described pre-embedded steel slab;
Described base plate in described bottom support bracket is welded on described pre-embedded steel slab.
4. the cable tension method of large span drag-line curtain wall as claimed in claim 3, is characterized in that, transfer pre-embedded steel slab, comprising according to described anchor point on described curtain wall basis:
Make the center line of described pre-embedded steel slab;
Described center line is measured, the front-rear center point of the front-rear center of described bottom support bracket point and described top support is on same vertical line.
5. the cable tension method of large span drag-line curtain wall as claimed in claim 2, it is characterized in that, curtain wall back timber installs described top support, comprising: according to described anchor point, the described top board in described top support is welded on described curtain wall back timber.
6. the cable tension method of large span drag-line curtain wall as claimed in claim 1, is characterized in that, install described drag-line, comprising between described top support and described bottom support bracket:
At the construction field (site) cable tray is installed;
By drag-line coiling disc forming in advance, be lifted on described cable tray;
By crane, drag-line is arranged on described top support;
Adopt electric block, described drag-line is drawn to described bottom support bracket and installs.
7. the cable tension method of large span drag-line curtain wall as claimed in claim 1, it is characterized in that, described drag-line is divided into a plurality of stretch-draw group, stretch-draw group described in each comprises two the drag-line groups being symmetricly set in curtain wall both sides, drag-line group described in each comprises two described drag-lines, is interconnected by two described drag-lines in described drag-line group by two cord clip tool.
8. the cable tension method of large span drag-line curtain wall as claimed in claim 7, is characterized in that, when stretch-draw is carried out to described drag-line, and four described drag-lines in stretch-draw group described in each synchronous tension, and the stretch-draw of four described drag-lines is highly identical.
9. the cable tension method of large span drag-line curtain wall as claimed in claim 1, it is characterized in that, when stretch-draw is carried out to described drag-line, first described cable tension is extremely designed 60% of stretching force with first order stretch-draw, more described cable tension is extremely designed 105% of stretching force with second level stretch-draw.
10. the cable tension method of large span drag-line curtain wall as claimed in claim 9, it is characterized in that, described first order stretch-draw is divided into 10%, 20%, 30%, 40% and 60% Pyatyi of design stretching force, the stretch-draw of the described second level is divided into 70%, 80%, 90%, 100% and 105% 5 rank.
CN201510130209.4A 2015-03-24 2015-03-24 The cable tension method of large span drag-line glass curtain wall Active CN104712083B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510130209.4A CN104712083B (en) 2015-03-24 2015-03-24 The cable tension method of large span drag-line glass curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510130209.4A CN104712083B (en) 2015-03-24 2015-03-24 The cable tension method of large span drag-line glass curtain wall

Publications (2)

Publication Number Publication Date
CN104712083A true CN104712083A (en) 2015-06-17
CN104712083B CN104712083B (en) 2017-06-09

Family

ID=53411771

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510130209.4A Active CN104712083B (en) 2015-03-24 2015-03-24 The cable tension method of large span drag-line glass curtain wall

Country Status (1)

Country Link
CN (1) CN104712083B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108151957A (en) * 2017-12-04 2018-06-12 交通运输部公路科学研究所 A kind of Suo Li dynamic testers calibrating installation and method
CN112347677A (en) * 2020-11-10 2021-02-09 中铁十四局集团建筑工程有限公司 Assembly type curtain wall integral lifting installation construction method based on BIM model construction technology support
CN112726444A (en) * 2020-12-30 2021-04-30 中铁六局集团北京铁路建设有限公司 Closed sound barrier foundation optimization structure and treatment process thereof
CN113322810A (en) * 2021-04-22 2021-08-31 西北工业大学 Debugging and installing system and method for stay cable of anti-seismic support
CN114482349A (en) * 2022-01-12 2022-05-13 浙江精工钢结构集团有限公司 Construction method of straight-through double-pull-rod steel frame supported long-span glass curtain wall system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6598359B1 (en) * 1998-06-08 2003-07-29 Heinrich Wulfert Earthquake-immune curtain wall system
CN2825786Y (en) * 2005-07-29 2006-10-11 珠海市晶艺玻璃工程有限公司 Glass curtain wall
CN201217868Y (en) * 2008-04-25 2009-04-08 东莞市坚朗五金制品有限公司 Curtain wall inhaul cable bracing rod
CN103216105A (en) * 2013-04-18 2013-07-24 成军 Construction method of overhanging inhaul cable type hyperbolic glass curtain wall

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6598359B1 (en) * 1998-06-08 2003-07-29 Heinrich Wulfert Earthquake-immune curtain wall system
CN2825786Y (en) * 2005-07-29 2006-10-11 珠海市晶艺玻璃工程有限公司 Glass curtain wall
CN201217868Y (en) * 2008-04-25 2009-04-08 东莞市坚朗五金制品有限公司 Curtain wall inhaul cable bracing rod
CN103216105A (en) * 2013-04-18 2013-07-24 成军 Construction method of overhanging inhaul cable type hyperbolic glass curtain wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
唐际宇等: "昆明新机场航站楼基于钢彩带的拉索玻璃幕墙施工技术", 《施工技术》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108151957A (en) * 2017-12-04 2018-06-12 交通运输部公路科学研究所 A kind of Suo Li dynamic testers calibrating installation and method
CN108151957B (en) * 2017-12-04 2024-03-08 交通运输部公路科学研究所 Cable force dynamic tester calibration device and method
CN112347677A (en) * 2020-11-10 2021-02-09 中铁十四局集团建筑工程有限公司 Assembly type curtain wall integral lifting installation construction method based on BIM model construction technology support
CN112726444A (en) * 2020-12-30 2021-04-30 中铁六局集团北京铁路建设有限公司 Closed sound barrier foundation optimization structure and treatment process thereof
CN113322810A (en) * 2021-04-22 2021-08-31 西北工业大学 Debugging and installing system and method for stay cable of anti-seismic support
CN114482349A (en) * 2022-01-12 2022-05-13 浙江精工钢结构集团有限公司 Construction method of straight-through double-pull-rod steel frame supported long-span glass curtain wall system
CN114482349B (en) * 2022-01-12 2023-06-27 浙江精工钢结构集团有限公司 Construction method for supporting large-span glass curtain wall system by using through double-pull-rod steel frame

Also Published As

Publication number Publication date
CN104712083B (en) 2017-06-09

Similar Documents

Publication Publication Date Title
CN107012949B (en) A kind of method for improving of large-span steel vestibule
CN104712083A (en) Dragline tensioning method for long-span dragline glass curtain wall
CN102296750B (en) Construction method of wide span prestressed beam string structure
CN101200916B (en) Construction method of prestressed suspension type building structure
CN109441127A (en) A kind of virtual emulation in-site installation construction method across overhanging steel structure greatly
CN102094489B (en) Double-layer bidirectional prestressed cable truss and construction method thereof
CN103883129B (en) A kind of steel structural roof beam installation method
CN107476581B (en) Hoisting and mounting method for steel structure double-layer overhanging structure
CN113982280A (en) Construction method of complex space truss integral hoisting system
CN111561175B (en) Prestress underpinning static force cutting and column pulling construction process
CN205558306U (en) Big profiled steel structure vestibule hoist and mount hoisting frame
CN110374200A (en) Large span rigidity unevenly mixes rack high altitude bulk method
CN104831844B (en) The unidirectional double rope inverted cone-shaped cable curtain wall construction methods of arc
CN212432397U (en) Steel structure bridge steel arch rib vertical cable stress adjustment testing device
CN108842954A (en) A kind of huge different section Honeycomb Beam structural system construction method of installation of aerofoil profile roofing
CN102094393A (en) Steel-concrete joint for steel and concrete mixed continuous steel structure bridge
CN113789712A (en) Longitudinal beam and arch rib forming control method of steel arch bridge
CN104729767B (en) Device and method for testing distribution of shearing stress on box girder section
CN102877657B (en) Large-span H-shaped plane composite structure beam string upper-air cable replacement construction method
CN105735228B (en) High-lift tooth climbs formula ship lift rack system construction method and installation accuracy control method
CN115233831B (en) Integral continuous lifting method for multi-point large-span space steel structure with freely controlled deflection
KR100305107B1 (en) an process of loading teste for loading structure use of transferable loading-apparatus
CN109142069B (en) Light steel grouting wall detection device and application method thereof
CN104863259A (en) Upside-down construction method for large-span ultra-high signal-layer cylindrical architectural steel structure
CN111620223B (en) Construction method for lifting net rack through secondary stress conversion of support

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant