CN108505443B - A kind of big segment lifting self-anchored suspension bridge construction method not setting camber - Google Patents

A kind of big segment lifting self-anchored suspension bridge construction method not setting camber Download PDF

Info

Publication number
CN108505443B
CN108505443B CN201810264960.7A CN201810264960A CN108505443B CN 108505443 B CN108505443 B CN 108505443B CN 201810264960 A CN201810264960 A CN 201810264960A CN 108505443 B CN108505443 B CN 108505443B
Authority
CN
China
Prior art keywords
stiff girder
big segment
bridge
suspension bridge
anchored suspension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810264960.7A
Other languages
Chinese (zh)
Other versions
CN108505443A (en
Inventor
刘德宝
沈佳伟
张红星
黄鑫
周海根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Shuzhijiaoyuan Technology Co Ltd
Original Assignee
Zhejiang Provincial Institute of Communications Planning Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Provincial Institute of Communications Planning Design and Research Co Ltd filed Critical Zhejiang Provincial Institute of Communications Planning Design and Research Co Ltd
Priority to CN201810264960.7A priority Critical patent/CN108505443B/en
Publication of CN108505443A publication Critical patent/CN108505443A/en
Application granted granted Critical
Publication of CN108505443B publication Critical patent/CN108505443B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • E01D21/105Balanced cantilevered erection

Abstract

The invention discloses the big segment lifting self-anchored suspension bridge construction methods that one kind does not set camber, first construction bridge tower, auxiliary pier and handover pier, set up full framing and Temporary Piers;The stiff girder for not setting camber is inserted into bracket and Temporary Piers, stiff girder longitudinal direction temporary constraint is set;It is welded after state to unstress state at adjustment stiff girder pad, completes the welding procedure of all pads;Main push-towing rope is set up, longitudinal temporary constraint is removed, completes the construction of subsequent self-anchored suspension bridge.Construction method of the present invention is easy to operate, is conducive to monitoring, girder is welded based on unstress state, a variety of arrangement and method for construction can be derived, is conducive to the advantage for playing large span, the self-anchored suspension bridge for having requirement of opening the navigation or air flight under bridge, can not temporarily open the navigation or air flight caused by solving the problems, such as because of construction with brackets;Compared with traditional " cable after first beam " method, the big segment lifting self-anchored suspension bridge construction is simple that the present invention does not set camber is easy, can further promote the competitiveness of large span self-anchored suspension bridge.

Description

A kind of big segment lifting self-anchored suspension bridge construction method not setting camber
Technical field
The invention belongs to bridge engineering construction technical fields, and in particular to one kind does not set the big segment lifting of camber from anchor Formula suspension bridge construction method.
Background technique
Currently, self-anchored suspension bridge construction method mainly has " cable after first beam ", " beam-cable-beam " and three kinds of " First cable later girder ", Wherein, latter two method uses less because needing complicated, expensive construction interim measure." cable after first beam " sets up girder method It is divided into: Support Method, incremental launching method, big segment lifting method etc..
Support Method is one of " cable after first beam " erection most common method of stiff girder, but since self-anchored suspension bridge is constructed week Phase is longer, is not suitable for the bridge for having requirement of opening the navigation or air flight under bridge.When span is larger, when riverbed is deeper, rack construction expense is larger, because This Support Method is not suitable for compared with large span and has the self-anchored suspension bridge for requirement of opening the navigation or air flight under bridge.
Incremental launching method can meet the bridge for having requirement of opening the navigation or air flight under bridge, but neutralize slideway there are steel box-girder stress collection and come to nothing The problems such as, and nose girder height is higher, it is possible to navigational clearance is occupied, to reduce steel box-girder stress, more Temporary Piers need to be set up, no Suitable for higher ranked self-anchored suspension bridge of opening the navigation or air flight under bridge.
Big segment lifting method can meet temporarily navigation requirement under bridge, and segment lifting construction is relatively simple, due to main girder frame There are initial internal forces and initial linear after if, though girder can be made to meet design requirement at bridge is linear by the way that girder camber is arranged, But the influence of initial internal force can not be eliminated, it will Cheng Qiaohou main push-towing rope, sunpender etc. is caused to be unsatisfactory for reasonable finished dead state.
Therefore, it is badly in need of proposing a kind of big segment lifting self-anchored suspension bridge construction method suitable for not setting camber, To solve above-mentioned technical problem.
Summary of the invention
In view of above-mentioned, the present invention provides the big segment lifting self-anchored suspension bridge construction method that one kind does not set camber, Reasonable finished dead state can be reached after the completion of construction.
A kind of big segment lifting self-anchored suspension bridge construction method not setting camber, includes the following steps:
(1) according to mould absolute altitude construction bridge tower, auxiliary pier and transition pier, full framing is set up in end bay and anchor span region Or Temporary Piers, Temporary Piers are built in main span region;
(2) stiff girder for not setting camber is inserted on full framing and Temporary Piers, and then Man Tangzhi will be inserted into Stiff girder welding on frame is integral, and remaining stiff girder is divided into N number of big segment and is lifted using crane barge to Temporary Piers;Institute It states big segment to connect by temporary support and the Temporary Piers at both ends, to be correspondingly formed two welding at each big segment both ends Point, N are the natural number greater than 0;
(3) apply vertical bridge between stiff girder and bridge tower lower beam and between stiff girder and Temporary Piers to temporary constraint, And then obtain vertical displacement difference and corner difference between the stiff girder of pad two sides;
(4) for any big segment in stiff girder, the temporary support at the big segment both ends is jacked using jack, so that Stiff girder at the big segment both ends pad returns to unstress state and carries out welding procedure, falls after rise after completion;According to above-mentioned Complete all big segment jacking-welding-falling work progress;
(5) will be on main cable erection to bridge tower and pre- inclined, while main push-towing rope both ends being anchored on the stiff girder of anchor span, it removes vertical Bridge is to temporary constraint and completes subsequent self-anchored suspension bridge construction.
Further, the auxiliary pier is set on the outside of bridge tower, using it as the segmentation benchmark between end bay and anchor span region; The transition pier is set on the outside of auxiliary pier, and anchor span is located between auxiliary pier and transition pier.
Further, the decrement that stiff girder is only considered on the basis of the stiff girder processing Shi Cheng bridge is linear, without setting Set camber.
Further, Temporary Piers crest level+temporary support height+stiff girder deck-molding+pavement thickness=at the linear elevation of bridge, together Sample, full framing crest level+stiff girder deck-molding+pavement thickness=at the linear elevation of bridge.
Further, for freely-supported and there is longitudinal restraint state in N number of big segment of the stiff girder after erection.
Further, after the stiff girder at the pad returns to unstress state, then the adjacent big section in the pad two sides The vertical displacement difference and corner difference of section are zero, and everywhere pad is required to by jacking-welding-falling process.
From unstressed theory, the purpose of stiff girder is jacked i.e. so that pad returns to unstress state between segment, is returned The purpose of stiff girder is fallen i.e. so that stiff girder Internal Force Redistribution;Therefore after the completion of welding procedure, stiff girder internal force and linear it is One piece falls internal force in the case of frame and linear.
The present invention is not limited to a pad of once only constructing, the construction for being also applied for " multiple pad synchronous constructions " is suitable Sequence.
The present invention is suitable for " end bay, anchor span, main span are big segment lifting " or " the big segment lifting in part " structure type.
The present invention is suitable for the structure type of only tower, double tower or more.
The big segment lifting self-anchored suspension bridge that the present invention is not limited to be constructed by " jacking-welding-falling ", is also applied for it He uses the big segment lifting self-anchored suspension bridge of unstress state welding.
Construction method of the present invention is easy to operate, is conducive to monitoring, welds girder based on unstress state, can derive a variety of apply Work scheme is conducive to the advantage for playing large span, the self-anchored suspension bridge for having requirement of opening the navigation or air flight under bridge, solves because of construction with brackets The caused problem that can not temporarily open the navigation or air flight;Compared with traditional " cable after first beam " method, the present invention does not set the big segment lifting of camber certainly Anchoring type rope-suspension bridge construction is simple is easy, can further promote the competitiveness of large span self-anchored suspension bridge.
Detailed description of the invention
Fig. 1 is the structural schematic diagram for the big segment lifting self-anchored suspension bridge that the present invention does not set camber.
Fig. 2 is the structural schematic diagram after the big segment lifting self-anchored suspension bridge construction procedure one of the present invention.
Fig. 3 is the structural schematic diagram after the big segment lifting self-anchored suspension bridge construction procedure two of the present invention.
Fig. 4 is the deformation induced by gravity schematic diagram of stiff girder after big segment lifting.
Fig. 5 is the vertical displacement difference and outer corner difference schematic diagram that a certain pad is read.
Fig. 6 is the linear schematic diagram of stiff girder after the completion of the construction of all pads.
Fig. 7 is the structural schematic diagram after the big segment lifting self-anchored suspension bridge construction procedure four of the present invention.
Wherein: 1-bridge tower, 21-end bay stiff girders, 22-anchor span stiff girders, 23-main span stiff girders, 231~234- Main span is put more energy into girder segment, 31-main push-towing ropes, 32-hoist cables, 41-auxiliary piers, 42-transition piers, 51-end bay full framings, and 52- Anchor span full framing, 6-Temporary Piers, 71~75-indulge bridges to temporary constraint, 8-temporary supports, 91~95-pads.
Specific embodiment
In order to more specifically describe the present invention, with reference to the accompanying drawing and specific embodiment is to technical solution of the present invention It is described in detail.
As shown in Figure 1, it is double tower five across structure that the present invention, which does not set the big segment lifting self-anchored suspension bridge of camber, mainly Including two bridge towers 1, auxiliary pier 41, transition pier 42, end bay stiff girder 21, anchor span stiff girder 22, main span stiff girder 23, main push-towing rope 31 And hoist cable 32 etc..
Fig. 1 is that self-anchored suspension bridge is constructed later reasonable finished dead state by certain construction method, this is rationally at bridge like State defines the internal force or linear of component, the main cutting length including main push-towing rope and linear, hoist cable cutting length, girder it is interior Power and linear, king-tower internal force etc..
It is directed to the self-anchored suspension bridge of raft support method construction, unstress state is in when due to main beam supporting, as long as Main push-towing rope and hoist cable blanking degree are controlled, then full-bridge after completing of constructing is reasonable finished dead state.Big segment lifting from anchor Formula suspension bridge, stiff girder when setting up in there is stress state, carry out welding procedure without any processing to stiff girder, it is laggard Row main cable erection and hoist cable stretching construction, then redistribution occurs for beam stress after stiff girder takes off frame, and hoist cable internal force is caused to occur Variation, will differ greatly with reasonable finished dead state.The present invention mainly passes through jacking segment, so that vertical displacement difference at pad Adjust with corner displacement difference to zero, carried out so that the welding of the point is under unstress state, especially by with Lower step is constructed:
Step 1: after mould absolute altitude construction bridge tower 1, auxiliary pier 41 and transition pier 42, end bay full framing 51 is set up With anchor span full framing 52, main span Temporary Piers 6 are built, as shown in Figure 2.
Step 2: the end bay stiff girder 21 for not setting camber and anchor span stiff girder 22 are inserted on full framing, are used Four segments 231~234 of main span are inserted on Temporary Piers 6 by crane barge, are connected by temporary support 8, at this time between each segment and There are five pads 91~95 between segment and end bay stiff girder;Construct simultaneously end bay stiff girder 21 and bridge tower lower beam and The vertical bridge of main span stiff girder 23 and Temporary Piers 6 is to temporary constraint 71~75, as shown in Figure 3 and Figure 4.
There is no multiple spot resilient support for anchor span stiff girder 22, therefore the Internal Force Redistribution after de- frame are also not present, while anchor It is not subject to the axle power effect of main push-towing rope 31 across stiff girder 22, therefore only needs to consider due to self weight generation when the processing of anchor span stiff girder 22 Amount of deflection;End bay stiff girder 21 and main span stiff girder 23 are acted on by the axle power of main push-towing rope 31, while being constructed by the present invention program It after process, is not required to that any camber is arranged again, therefore end bay stiff girder 21 and main span stiff girder 23 only need to consider to add in processing The decrement of strength beam.
The main span stiff girder 23 being inserted on Temporary Piers 6 deforms under Gravitative Loads, as shown in figure 4, each section simultaneously The internal force distribution of section is simply supported beam mode, and there are vertical displacement difference and corners between the segment stiff girder at pad at this time Difference, as shown in Figure 5.
Step 3: by left side bridge tower 1 in Fig. 3, the temporary support 8 of first segment 231 is jacked with jack, so that the Stiff girder returns to unstress state at one pad 91, carries out welding procedure, falls after rise after the completion;Similarly, second section is jacked 232 temporary support 8 carries out welding procedure, returns after the completion so that stiff girder returns to unstress state at the second pad 92 It falls;The rest may be inferred, construct five pads 95 when, jack the 4th pad 94 at temporary support 8 so that the 5th pad 95 Place's stiff girder returns to unstress state, carries out welding procedure, falls after rise after the completion.
Jack jacks magnitude and is determined as two aspects: on the one hand very heavy as obtained by finite element software construction simulation process Top jacking magnitude, this calculated value is as reference value, for verifying whether vertical displacement difference and corner difference return to zero;On the other hand Pass through the vertical displacement surveyed when construction and corner monitoring data.
As shown in fig. 6, linear stiff girder is one continuous linear after main span segment jacking-welding-falling process.Thing In reality, jacking is the process adjusted at stiff girder pad to unstress state, and welding is to be linked to be the process of continuous beam, and falling is The internal force distribution of simply supported beam is reassigned into the process that one piece falls the internal force distribution of frame (i.e. continuous beam).
Step 4: by main push-towing rope 31 be inserted on bridge tower 1 and it is pre- while main push-towing rope 31 is anchored to end bay stiff girder 21 partially, tear open Except vertical bridge is to temporary constraint 7, subsequent self-anchored suspension bridge construction is completed, as shown in Figure 7.
The above-mentioned description to embodiment is for that can understand and apply the invention convenient for those skilled in the art. Person skilled in the art obviously easily can make various modifications to above-described embodiment, and described herein general Principle is applied in other embodiments without having to go through creative labor.Therefore, the present invention is not limited to the above embodiments, ability Field technique personnel announcement according to the present invention, the improvement made for the present invention and modification all should be in protection scope of the present invention Within.

Claims (6)

1. one kind does not set the big segment lifting self-anchored suspension bridge construction method of camber, include the following steps:
(1) according to mould absolute altitude construction bridge tower, auxiliary pier and transition pier, full framing is set up in end bay and anchor span region or is faced When pier, build Temporary Piers in main span region;
(2) stiff girder for not setting camber is inserted on full framing and Temporary Piers, and then will be inserted on full framing Stiff girder welding it is integral, remaining stiff girder is divided into N number of big segment and is lifted to Temporary Piers using crane barge;It is described big Segment is connected by temporary support and the Temporary Piers at both ends, to be correspondingly formed two pads at each big segment both ends, N is Natural number greater than 0;
(3) apply vertical bridge between stiff girder and bridge tower lower beam and between stiff girder and Temporary Piers to temporary constraint, in turn Obtain the vertical displacement difference and corner difference between the stiff girder of pad two sides;
(4) for any big segment in stiff girder, the temporary support at the big segment both ends is jacked using jack, so that this is big Stiff girder at the pad of segment both ends returns to unstress state and carries out welding procedure, falls after rise after completion;According to above-mentioned completion All big segment jacking-welding-falling work progress;
(5) will on main cable erection to bridge tower and it is pre- while main push-towing rope both ends being anchored on the stiff girder of anchor span partially, remove vertical bridge to Temporary constraint simultaneously completes subsequent self-anchored suspension bridge construction.
2. big segment lifting self-anchored suspension bridge construction method according to claim 1, it is characterised in that: the auxiliary pier On the outside of bridge tower, using it as the segmentation benchmark between end bay and anchor span region;The transition pier is set on the outside of auxiliary pier, and Anchor span is located between auxiliary pier and transition pier.
3. big segment lifting self-anchored suspension bridge construction method according to claim 1, it is characterised in that: the stiff girder The decrement of stiff girder is only considered on the basis of processing Shi Cheng bridge is linear, no setting is required camber.
4. big segment lifting self-anchored suspension bridge construction method according to claim 1, it is characterised in that: Temporary Piers are risen Journey+temporary support height+stiff girder deck-molding+pavement thickness=at the linear elevation of bridge, similarly, full framing crest level+stiff girder Deck-molding+pavement thickness=at the linear elevation of bridge.
5. big segment lifting self-anchored suspension bridge construction method according to claim 1, it is characterised in that: the stiff girder N number of big segment freely-supported and have longitudinal restraint state after erection.
6. big segment lifting self-anchored suspension bridge construction method according to claim 1, it is characterised in that: the pad After the stiff girder at place returns to unstress state, then the vertical displacement difference and corner difference of the adjacent big segment in the pad two sides are equal It is zero, everywhere pad is required to by jacking-welding-falling process.
CN201810264960.7A 2018-03-28 2018-03-28 A kind of big segment lifting self-anchored suspension bridge construction method not setting camber Active CN108505443B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810264960.7A CN108505443B (en) 2018-03-28 2018-03-28 A kind of big segment lifting self-anchored suspension bridge construction method not setting camber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810264960.7A CN108505443B (en) 2018-03-28 2018-03-28 A kind of big segment lifting self-anchored suspension bridge construction method not setting camber

Publications (2)

Publication Number Publication Date
CN108505443A CN108505443A (en) 2018-09-07
CN108505443B true CN108505443B (en) 2019-10-15

Family

ID=63379039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810264960.7A Active CN108505443B (en) 2018-03-28 2018-03-28 A kind of big segment lifting self-anchored suspension bridge construction method not setting camber

Country Status (1)

Country Link
CN (1) CN108505443B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111455862A (en) * 2020-04-30 2020-07-28 中铁大桥科学研究院有限公司 Construction method of continuous stiffening beam suspension bridge

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109883307B (en) * 2019-03-13 2021-04-16 中铁山桥集团有限公司 Method for detecting camber of bridge member
CN109989351A (en) * 2019-04-24 2019-07-09 中交第二公路工程局有限公司 A kind of self-anchored suspension bridge Datum Strand linear control method
CN112962455B (en) * 2021-01-31 2023-01-24 浙江交通职业技术学院 Cable-first-beam-second segment hoisting self-anchored suspension bridge construction method
CN113235435B (en) * 2021-04-20 2022-09-30 中交二航局第二工程有限公司 Cable-first beam-second self-anchored suspension bridge system conversion construction method
CN113221230B (en) * 2021-06-04 2022-08-26 中交第二航务工程局有限公司 Method for calculating opening amount of lower edge of stiffening beam of suspension bridge

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1173005A (en) * 1966-11-29 1969-12-03 Kawada Kogyo Kk A Method of Constructing a Suspension Bridge
US4129917A (en) * 1978-03-27 1978-12-19 Eugene W. Sivachenko Bridge structure
CN201056668Y (en) * 2007-04-29 2008-05-07 武汉理工大学 Hidden floating type overhanging cable bridge
CN101078198B (en) * 2007-07-04 2010-07-28 湖南省交通规划勘察设计院 Steel box beam erection method for self-anchored suspension bridge
CN101187199A (en) * 2007-12-24 2008-05-28 中铁大桥局股份有限公司 Self-anchoring type suspension bridge system conversion construction method
CN201198561Y (en) * 2008-05-14 2009-02-25 上海远东国际桥梁建设有限公司 Bridging system of self-anchoring type rope-suspension bridge
CN103266573B (en) * 2013-06-17 2015-12-09 中铁山桥集团有限公司 Steel Box Girder of Self-Anchored Suspension beam unidirectional single-point three slideway synchronous push construction method
CN104846747B (en) * 2015-05-19 2017-01-04 长安大学 A kind of self-anchored suspension bridge suspender tension technique based on self equilibrium systems

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111455862A (en) * 2020-04-30 2020-07-28 中铁大桥科学研究院有限公司 Construction method of continuous stiffening beam suspension bridge
CN111455862B (en) * 2020-04-30 2022-03-25 中铁大桥科学研究院有限公司 Construction method of continuous stiffening beam suspension bridge

Also Published As

Publication number Publication date
CN108505443A (en) 2018-09-07

Similar Documents

Publication Publication Date Title
CN108505443B (en) A kind of big segment lifting self-anchored suspension bridge construction method not setting camber
CN103243654B (en) Mounting method for steel anchor beam of cable-stayed bridge and assembly jig and cable bent tower mounting platform used in method
CN105178609B (en) Steel structure net rack high altitude bulk construction method
CN110175426A (en) Railroad bridge Elasto-plastic Metal limits shock absorption energy consuming device design method
CN111139749A (en) Large-span bearing type continuous steel truss girder cantilever erection construction method
CN103437299A (en) Construction method for one-time turning of large-span T-shaped single pier
CN109972494B (en) Design and construction method of large-segment hoisting self-anchored suspension bridge with hinges between segments
CN107587417A (en) Hybrid combining beam three stride continuous suspension bridge
CN108103949A (en) A kind of Cable stayed Bridge Main Tower composite steel anchor beam integral assembling process
CN107060105A (en) A kind of lifting construction method of multiple steel vestibules between high building
CN105926457A (en) Method for mounting steel box girders in main tower area of cable-stayed bridge and auxiliary girder erection crane base
CN100519943C (en) Non-cable single-tower stayed bridge
CN101691813B (en) Device and method for elevation synchronous compensation for super-high structure construction
CN102154990B (en) Electing method for side span overhang-middle span cable-stayed three-tower self-anchored type combination suspension bridge
CN109468941A (en) A kind of curve tower abnormity cable-stayed bridge and its construction method
CN106759909B (en) Bearing structure system and its construction method are hung up under one kind
CN114781026A (en) Construction control method for single leaning tower cable-stayed bridge
CN205775786U (en) A kind of novel railway curve Cable-stayed Bridge with Slanted Pylon
CN100545353C (en) Adopt external eccentric prestress system to carry out steel girder cantilever erection construction method
CN208072166U (en) Hybrid combining beam three stride continuous suspension bridge
CN104775363A (en) Assembling method of upper tower column reinforcing steel bar segment
CN202809494U (en) Bracket for pouring 0# block to rigid continuous girder bridge
CN210636294U (en) Cable-stayed bridge of semi-floating truss type bridge tower
CN205242238U (en) Be applied to self anchored suspension bridge's main girder structure
CN102877412A (en) Method of pre-assembly in integral erecting way of steel tower

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 310006 No. 89 West Ring Road, Hangzhou, Zhejiang, Xihu District

Patentee after: ZHEJIANG PROVINCIAL INSTITUTE OF COMMUNICATIONS PLANNING DESIGN & RESEARCH Co.,Ltd.

Address before: 310006 No. 89 West Ring Road, Hangzhou, Zhejiang, Xihu District

Patentee before: ZHEJIANG PROVINCIAL INSTITUTE OF COMMUNICATIONS PLANNING, DESIGN & RESEARCH

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No. 928, yuhangtang Road, Xihu District, Hangzhou City, Zhejiang Province 310011

Patentee after: Zhejiang shuzhijiaoyuan Technology Co.,Ltd.

Address before: 310006 No. 89 West Ring Road, Hangzhou, Zhejiang, Xihu District

Patentee before: ZHEJIANG PROVINCIAL INSTITUTE OF COMMUNICATIONS PLANNING DESIGN & RESEARCH Co.,Ltd.