CN110342374A - One kind installing elevator and existing building buffer device for collision additional without foundation pit for outdoor - Google Patents
One kind installing elevator and existing building buffer device for collision additional without foundation pit for outdoor Download PDFInfo
- Publication number
- CN110342374A CN110342374A CN201910739126.3A CN201910739126A CN110342374A CN 110342374 A CN110342374 A CN 110342374A CN 201910739126 A CN201910739126 A CN 201910739126A CN 110342374 A CN110342374 A CN 110342374A
- Authority
- CN
- China
- Prior art keywords
- collision
- existing building
- outdoor
- foundation pit
- buffer device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000002265 prevention Effects 0.000 claims abstract description 22
- 229920001971 elastomer Polymers 0.000 claims description 19
- 239000005060 rubber Substances 0.000 claims description 19
- 239000003755 preservative agent Substances 0.000 claims description 4
- 230000002335 preservative effect Effects 0.000 claims description 4
- 239000007787 solid Substances 0.000 claims description 4
- 238000000034 method Methods 0.000 abstract description 12
- 238000010276 construction Methods 0.000 abstract description 10
- 238000009434 installation Methods 0.000 abstract description 8
- 230000008569 process Effects 0.000 abstract description 6
- 230000006378 damage Effects 0.000 abstract description 5
- 239000000463 material Substances 0.000 abstract description 3
- 238000009418 renovation Methods 0.000 abstract description 2
- 230000003139 buffering effect Effects 0.000 description 7
- 230000000694 effects Effects 0.000 description 7
- 230000032683 aging Effects 0.000 description 3
- 230000018109 developmental process Effects 0.000 description 3
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000035939 shock Effects 0.000 description 2
- 238000010521 absorption reaction Methods 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 238000011010 flushing procedure Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B5/00—Applications of checking, fault-correcting, or safety devices in elevators
- B66B5/28—Buffer-stops for cars, cages, or skips
- B66B5/282—Structure thereof
Landscapes
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
The present invention relates to building renovation safeguard procedures technical fields, and it discloses one kind and installs elevator and existing building buffer device for collision additional without foundation pit for outdoor, including wall, collision prevention girders have been bolted in the side of the wall, the outer surface of the collision prevention girders offers sliding slot, and there are two sliding blocks for the internal slide connection of the sliding slot.This be used for it is outdoor install elevator and existing building buffer device for collision additional without foundation pit, the cost of construction cost and material is relatively low, is conducive to push process of industrialization, and easy to produce, be easily installed, construction quickly, does not influence the normal life of people, practical;When natural or artificial disaster arrives, the elevator of installation is likely to the generation destruction that collides with existing building, threat is brought to the safety of life and property of people, the present apparatus can absorb the impact force for slowing down and generating when colliding well, prevent the generation of collision, the safety that ensure that people makes the personal safety as well as the property safety of people be guaranteed.
Description
Technical field
The present invention relates to building renovation safeguard procedures technical field, it is specially a kind of for it is outdoor without foundation pit install additional elevator with
Existing building buffer device for collision.
Background technique
With the quickening of Urbanization in China, Building Trade in China development is very fast, at present, national existing building area
Nearly 50,000,000,000 square metres are amounted to, a large amount of existing buildings have been unable to meet modern development since building function is backward, safety is insufficient
It needs, is especially built in the nineteen ninety pervious anti-seismic performance requirement that current specifications is mostly not achieved, meanwhile, a large amount of existing buildings
For non-energy saving building, reducing energy consumption is urgently carried out, it is quite huge that these, which all show that existing building needs the project amount being transformed,
's.
The dwelling construction in China is progressed into from the economical of the phase early 1980s to 21st century
Fairly well-off level, improving existing living quality becomes the primary demand of resident.Due to historical reasons, China still has
Many six, seven layers even higher than seven layers of house is fitted without elevator, and with the arriving of aging society, existing apartment installs electricity additional
The concern for the middle and old age residents that ladder increasingly causes the common people especially to live in walk-up building, become one it is anxious to be resolved
Social concern.
Social resources are nervous now, and many countries have all entered aging ranks, for the speed and matter for improving urban development
Amount, we are to the improvement project of old town existing building also in progress like a raging fire.Do not pacify for many existing buildings
Elevator is filled, this has been unable to satisfy people's lives needs, especially with the propulsion of aging of population, in the old room of not elevator
In son, the action of the elderly is highly inconvenient, and China is also carrying out the transformation that old house installs elevator additional.So how to guarantee to add
How the safety for filling elevator guarantees the safety of people, then designing a kind of installation when nature or artificial disaster occurs
Elevator and existing building buffer device for collision are necessary.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, the present invention provides one kind touches without foundation pit installation elevator with existing building for outdoor
Buffer unit is hit, mainly for playing the role of buffering, reducing and prevent when installing elevator additional will collide in existing building
Collide the harm generated.
(2) technical solution
It is above-mentioned in order to play the role of buffering when installing elevator additional will collide in existing building to realize, reduce and
The purpose for the harm for preventing collision from generating, the invention provides the following technical scheme: it is a kind of for it is outdoor without foundation pit install additional elevator with
Collision prevention girders have been bolted in existing building buffer device for collision, including wall, the side of the wall, the collision prevention girders
Outer surface offers sliding slot, the internal slide connection of the sliding slot there are two sliding block, the opposite sides of two sliding blocks it
Between be fixedly connected with adjustable spring, the adjustable spring is located at the inside of the sliding slot, and the outer surface of two sliding blocks is cut with scissors
It is connected to connecting rod, the left side of the collision prevention girders is fixedly connected with jingle bell, there are two the left side of the collision prevention girders is fixedly connected
Telescopic rod, the telescopic rod is symmetrical about the jingle bell, and the outer surface of two telescopic rods is arranged with support spring,
Two telescopic rods are fixedly connected with connecting plate far from one end of the collision prevention girders, and the right side of the connecting plate is fixedly connected
There is impact block, the impact block matches with the jingle bell, the one end of the connecting rod far from the sliding block and the connecting plate
It is hinged, the left side of the connecting plate is fixedly connected with two groups of buffer connecting rods, and the left end of the buffer connecting rods is solid
Surely it is connected with Crashworthy plate.
Preferably, the buffer connecting rods include arc-shaped spring piece, hydraulic telescopic rod, bump rubber and buffering elastic
Spring, the arc-shaped spring piece are located at the top of the hydraulic telescopic rod, and the hydraulic telescopic rod is located at the bump rubber
Top, the bump rubber are located at the top of the buffer spring.
Preferably, the collision prevention girders, the connecting rod, the connecting plate, the buffer connecting rods and the Crashworthy plate
Outer surface carry out waterproof and preservative treatment.
Preferably, the included angle range between the connecting rod and the connecting plate is 30 degree to 60 degree.
Preferably, the left side of the Crashworthy plate is fixedly connected with cushion rubber layer.
Preferably, the connecting plate side opposite with the Crashworthy plate is fixedly connected to connection card slot, the buffering
Rubber block is bolted to connection with the connection card slot.
(3) beneficial effect
Compared with prior art, the present invention provides one kind for outdoor slow without foundation pit installation elevator and existing building collision
Flushing device, have it is following the utility model has the advantages that
(1) this be used for it is outdoor install elevator and existing building buffer device for collision additional without foundation pit, construction is simple, construction cost with
The cost of material is relatively low, is conducive to push process of industrialization, and easy to produce, be easily installed, construction quickly, does not influence people
Normal life, it is practical;When natural or artificial disaster arrives, the elevator of installation is likely to and existing building
Collide generation destruction, brings threat to the safety of life and property of people, the present apparatus can absorb well slows down generation
The impact force generated when collision prevents the generation of collision, ensure that the safety of people, obtain the personal safety as well as the property safety of people
Guarantee.
(2) this is used for outdoor and installs elevator and existing building buffer device for collision additional without foundation pit, by the way that connecting plate is arranged, is sending out
When raw shock, connecting plate drives impact block mobile, hits jingle bell, plays the effect of alarm.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the schematic enlarged-scale view of A in Fig. 1 of the invention.
In figure: 1 wall, 2 collision prevention girders, 3 sliding slots, 4 sliding blocks, 5 adjustable springs, 6 connecting rods, 7 jingle bells, 8 telescopic rods, 9 supports
Spring, 10 connecting plates, 11 buffer connecting rods, 12 Crashworthy plates, 13 cushion rubber layers, 14 impact blocks, 1101 arc-shaped spring pieces,
1102 hydraulic telescopic rods, 1103 bump rubbers, 1104 buffer springs.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
It is a kind of referring to FIG. 1-2, to install elevator and existing building buffer device for collision, including wall additional without foundation pit for outdoor
1, collision prevention girders 2 have been bolted in the side of wall 1, and the outer surface of collision prevention girders 2 offers sliding slot 3, the internal slide of sliding slot 3
Connection is fixedly connected with adjustable spring 5 there are two sliding block 4 between the opposite side of two sliding blocks 4, adjustable spring 5, which is located at, to be slided
The inside of slot 3, the outer surface of two sliding blocks 4 are hinged with connecting rod 6, and the left side of collision prevention girders 2 is fixedly connected with jingle bell 7, prevent
The left side for hitting beam 2 is fixedly connected there are two telescopic rod 8, and telescopic rod 8 is symmetrical about jingle bell 7, the appearance of two telescopic rods 8
Face is arranged with support spring 9, and two telescopic rods 8 are fixedly connected with connecting plate 10 far from one end of collision prevention girders 2, connecting plate 10
Right side is fixedly connected with impact block 14, and impact block 14 matches with jingle bell 7, connecting rod 6 one end and connecting plate far from sliding block 4
10 are hinged, and the left side of connecting plate 10 is fixedly connected with two groups of buffer connecting rods 11, and the left end of buffer connecting rods 11 is solid
Surely it is connected with Crashworthy plate 12.
Further, buffer connecting rods 11 include arc-shaped spring piece 1101, hydraulic telescopic rod 1102, bump rubber
1103 and buffer spring 1104, arc-shaped spring piece 1101 be located at the top of hydraulic telescopic rod 1102, hydraulic telescopic rod 1102 is located at
The top of bump rubber 1103, bump rubber 1103 are located at the top of buffer spring 1104.
Further, the outer surface of collision prevention girders 2, connecting rod 6, connecting plate 10, buffer connecting rods 11 and Crashworthy plate 12 is equal
Waterproof and preservative treatment are carried out, waterproof and preservative treatment can be carried out by modes such as japannings, service using life can be extended.
Further, the included angle range between connecting rod 6 and connecting plate 10 is 30 degree to 60 degree, guarantees device
Stable operation.
Further, the left side of Crashworthy plate 12 is fixedly connected with cushion rubber layer 13, plays absorption and slows down impact force
Effect.
Further, the side opposite with Crashworthy plate 12 of connecting plate 10 is fixedly connected to connection card slot, bump rubber
1103 are bolted to connection with card slot is connect, and play the effect for facilitating installation.
This is used for outdoor without foundation pit installation elevator and existing building buffer device for collision, construction method are as follows: connects buffering
Device is welded between more than 12 connecting plate 10 of Crashworthy plate, then collision prevention girders 2 is opened up sliding slot 3, and sliding block 4 is installed in sliding slot 3 and is stretched
Contracting spring 5, is fixedly connected in the side of collision prevention girders 2 by more than 8 connecting plate 10 of telescopic rod, and connecting plate 10 is passed through connecting rod more than 6
Sliding block 4 is hinged, is combined into prefabricated component, finally, after carrying out the processing such as waterproof to the surface of existing wall 1, it is pre- by what is made
Product is fixed the top of existing wall 1 and side by bolt.
Working principle: this be used for it is outdoor install elevator and existing building buffer device for collision additional without foundation pit, by Crashworthy plate 12,
It when colliding, is played by the cushion rubber layer 13 of setting and absorbs the effect for slowing down impact force, Crashworthy plate 12 drives buffering
Attachment device 11 shakes, and passes through the arc-shaped spring piece 1101 of setting, hydraulic telescopic rod 1102, bump rubber 1103 and buffering elastic
The effect for further absorbing and slowing down impact force is played in the deformation of spring 1104, and buffer connecting rods 11 drive connecting plate 10 to shake, even
Fishplate bar 10 drives two sliding blocks 4 to be moved away from by hinged connecting rod 6, and two sliding blocks 4 stretch adjustable spring 5, adjustable spring 5
Deformation generates elastic force, further absorbs and slows down impact force, while connecting plate 10 drives impact block 14 mobile, hits jingle bell 7,
Play the effect of alarm.
In conclusion this, which is used for outdoor, installs elevator and existing building buffer device for collision, construction is simple, construction additional without foundation pit
Cost and the cost of material are relatively low, are conducive to push process of industrialization, and easy to produce, be easily installed, construction is quick, not shadow
The normal life of people is rung, it is practical;When natural or artificial disaster arrives, the elevator of installation be likely to both
There is building to collide and generate destruction, brings threat to the safety of life and property of people, the present apparatus can absorb well to be subtracted
Delay the impact force generated when colliding, prevents the generation of collision, ensure that the safety of people, make the personal safety as well as the property safety of people
It is guaranteed.
This is used for outdoor and installs elevator and existing building buffer device for collision additional without foundation pit, by the way that connecting plate 10 is arranged, is sending out
When raw shock, connecting plate 10 drives impact block 14 mobile, hits jingle bell 7, plays the effect of alarm.
It should be noted that the terms "include", "comprise" or its any other variant are intended to the packet of nonexcludability
Contain, so that the process, method, article or equipment for including a series of elements not only includes those elements, but also including
Other elements that are not explicitly listed, or further include for elements inherent to such a process, method, article, or device.
In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including the element
Process, method, article or equipment in there is also other identical elements.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding
And modification, the scope of the present invention is defined by the appended.
Claims (6)
1. one kind installs elevator and existing building buffer device for collision, including wall (1) additional without foundation pit for outdoor, feature exists
In: the side of the wall (1) has been bolted collision prevention girders (2), and the outer surface of the collision prevention girders (2) offers sliding slot
(3), solid between the opposite side of two sliding blocks (4) there are two the internal slide connections of the sliding slot (3) sliding block (4)
Surely be connected with adjustable spring (5), the adjustable spring (5) is located at the inside of the sliding slot (3), two sliding blocks (4) it is outer
Surface is hinged with connecting rod (6), and the left side of the collision prevention girders (2) is fixedly connected with jingle bell (7), the collision prevention girders (2)
Left side is fixedly connected there are two telescopic rod (8), and the telescopic rod (8) is symmetrical about the jingle bell (7), stretches described in two
The outer surface of contracting bar (8) is arranged with support spring (9), and the one end of two telescopic rods (8) far from the collision prevention girders (2) is solid
Surely it is connected with connecting plate (10), the right side of the connecting plate (10) is fixedly connected with impact block (14), the impact block (14)
It matching with the jingle bell (7), the connecting rod (6) is hinged far from the one end of the sliding block (4) with the connecting plate (10),
The left side of the connecting plate (10) is fixedly connected with two groups of buffer connecting rods (11), a left side for the buffer connecting rods (11)
End is fixedly connected with Crashworthy plate (12).
2. one kind according to claim 1 installs elevator and existing building buffer device for collision additional without foundation pit for outdoor,
Be characterized in that: the buffer connecting rods (11) include arc-shaped spring piece (1101), hydraulic telescopic rod (1102), bump rubber
(1103) and buffer spring (1104), the arc-shaped spring piece (1101) are located at the top of the hydraulic telescopic rod (1102), institute
The top that hydraulic telescopic rod (1102) are located at the bump rubber (1103) is stated, the bump rubber (1103) is located at described
The top of buffer spring (1104).
3. one kind according to claim 1 installs elevator and existing building buffer device for collision additional without foundation pit for outdoor,
It is characterized in that: the collision prevention girders (2), the connecting rod (6), the connecting plate (10), the buffer connecting rods (11) and institute
The outer surface for stating Crashworthy plate (12) carries out waterproof and preservative treatment.
4. one kind according to claim 1 installs elevator and existing building buffer device for collision additional without foundation pit for outdoor,
Be characterized in that: the included angle range between the connecting rod (6) and the connecting plate (10) is 30 degree to 60 degree.
5. one kind according to claim 1 installs elevator and existing building buffer device for collision additional without foundation pit for outdoor,
Be characterized in that: the left side of the Crashworthy plate (12) is fixedly connected with cushion rubber layer (13).
6. one kind according to claim 2 installs elevator and existing building buffer device for collision additional without foundation pit for outdoor,
Be characterized in that: the connecting plate (10) and the Crashworthy plate (12) opposite side are fixedly connected to connection card slot, described slow
Rubber block (1103) is rushed to be bolted to connection with the connection card slot.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910739126.3A CN110342374A (en) | 2019-08-12 | 2019-08-12 | One kind installing elevator and existing building buffer device for collision additional without foundation pit for outdoor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910739126.3A CN110342374A (en) | 2019-08-12 | 2019-08-12 | One kind installing elevator and existing building buffer device for collision additional without foundation pit for outdoor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110342374A true CN110342374A (en) | 2019-10-18 |
Family
ID=68184681
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910739126.3A Pending CN110342374A (en) | 2019-08-12 | 2019-08-12 | One kind installing elevator and existing building buffer device for collision additional without foundation pit for outdoor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110342374A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110862000A (en) * | 2019-11-26 | 2020-03-06 | 天津京龙工程机械有限公司 | Thing networking remote monitoring construction elevator |
CN111101984A (en) * | 2020-01-17 | 2020-05-05 | 淮阴工学院 | Tunnel supporting mechanism |
CN113338466A (en) * | 2021-05-26 | 2021-09-03 | 中国五冶集团有限公司 | Anti-collision device of shockproof building structure |
CN114212647A (en) * | 2021-11-16 | 2022-03-22 | 中国建筑第八工程局有限公司 | Construction elevator |
CN115520742A (en) * | 2022-10-27 | 2022-12-27 | 中国城市建设研究院有限公司 | Constant force device, connecting equipment and building |
-
2019
- 2019-08-12 CN CN201910739126.3A patent/CN110342374A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110862000A (en) * | 2019-11-26 | 2020-03-06 | 天津京龙工程机械有限公司 | Thing networking remote monitoring construction elevator |
CN111101984A (en) * | 2020-01-17 | 2020-05-05 | 淮阴工学院 | Tunnel supporting mechanism |
CN113338466A (en) * | 2021-05-26 | 2021-09-03 | 中国五冶集团有限公司 | Anti-collision device of shockproof building structure |
CN114212647A (en) * | 2021-11-16 | 2022-03-22 | 中国建筑第八工程局有限公司 | Construction elevator |
CN115520742A (en) * | 2022-10-27 | 2022-12-27 | 中国城市建设研究院有限公司 | Constant force device, connecting equipment and building |
CN115520742B (en) * | 2022-10-27 | 2023-08-18 | 中国城市建设研究院有限公司 | Building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110342374A (en) | One kind installing elevator and existing building buffer device for collision additional without foundation pit for outdoor | |
CN206143946U (en) | Use particle damping technical promotion core cylinder structure anti -collapse capability 's device | |
CN215977925U (en) | Building curtain exempts from to support installation device | |
CN109024959A (en) | A kind of Antiseismic house builds structure | |
CN206941856U (en) | A kind of home-use environment friendly wall acoustic material | |
CN208440126U (en) | Install elevator and existing building buffer device for collision additional | |
CN108657900A (en) | Install elevator and existing building buffer device for collision additional | |
CN215925892U (en) | Dam body floats energy dissipation mechanism | |
CN102296641A (en) | Anti-seismic building structure | |
CN213297220U (en) | Brake mechanism for high-altitude anti-falling protection | |
CN105178435B (en) | A kind of damping type steel structure node component | |
CN204940530U (en) | A kind of damping type steel structure node component | |
CN210421395U (en) | Assembled light steel frame | |
CN113863710A (en) | Energy-consuming swing substructure and method for reinforcing existing building | |
CN207378060U (en) | A kind of aluminum alloy doors and windows shock absorbing apparatus | |
CN104612292A (en) | Hanging plate type earthquake reduction envelope structure of frame type structure building | |
CN206738486U (en) | A kind of novel building equipment damping device | |
CN201232385Y (en) | Anti-earthquake building | |
CN206518356U (en) | Antivibrating bed stead and its bed body | |
CN218580997U (en) | Building energy-saving outer wall prefabricated part | |
CN214302961U (en) | Be used for integral anticollision guard plate of green building | |
CN208441508U (en) | Existing building installs elevator shearing resistance cutting apparatus additional | |
CN219060631U (en) | Roof structure for preventing stone falling | |
CN108545571A (en) | Existing building installs elevator drawing-resisting device additional | |
CN209705172U (en) | Energy dissipation shock pad |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191018 |
|