CN110306584A - A kind of follow-up casing pile foundation drilling construction method - Google Patents

A kind of follow-up casing pile foundation drilling construction method Download PDF

Info

Publication number
CN110306584A
CN110306584A CN201910604830.8A CN201910604830A CN110306584A CN 110306584 A CN110306584 A CN 110306584A CN 201910604830 A CN201910604830 A CN 201910604830A CN 110306584 A CN110306584 A CN 110306584A
Authority
CN
China
Prior art keywords
pile
casing
pile foundation
follow
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910604830.8A
Other languages
Chinese (zh)
Inventor
王欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Sui Shi Civil Polytron Technologies Inc
Original Assignee
Guangzhou Sui Shi Civil Polytron Technologies Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Sui Shi Civil Polytron Technologies Inc filed Critical Guangzhou Sui Shi Civil Polytron Technologies Inc
Priority to CN201910604830.8A priority Critical patent/CN110306584A/en
Publication of CN110306584A publication Critical patent/CN110306584A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Abstract

The invention discloses a kind of follow-up casing pile foundation drilling construction methods, the method specifically includes following steps: step 1, before pile foundation construction, levelling of the land construction is carried out to the place for needing pile foundation by laser leveling machine, form smooth job platform, after the completion of construction, accurately measure by survey crew and put a little, determine pile center position, and cross pile is squeezed into and surveys measured position, step 2, measured pile center position is surveyed in step 1, it is loosened the soil using loosenning tiller to the center, the range diameter to loosen the soil is 400-450cm, the present invention relates to existing driven cast-in-place pile technical fields.The follow-up casing pile foundation drilling construction method, it is covered using noise abatement and supports the cooperation between annulus can be when punching, absorb the noise that punching generates, avoid the living environment that excessive noise effect surrounding resident is generated when punching, simultaneously using the mud in double pump alternately replacement hole, it can avoid occurring the phenomenon that punching offset because of soil property.

Description

A kind of follow-up casing pile foundation drilling construction method
Technical field
The present invention relates to existing driven cast-in-place pile technical field, specially a kind of follow-up casing pile foundation drilling construction method.
Background technique
Existing driven cast-in-place pile is one of numerous type pile foundations in civil construction project.System is using the design ruler with stake Very little adaptable steel pipe (i.e. casing), after sinking in soil after pile top in end sleeve, hangs framework of steel reinforcement, then side in casing The vibration of casting concrete side or hammering tube drawing, mechanical pudding concrete when using tube drawing and form required bored concrete pile.This Kind construction method is suitable for having the case where underground water, quicksand, mud.Using hammer piling equipment immersed tube, tube drawing pile, referred to as Hammer hidden pipe caisson pile.Utilize vibrator vibration sinking tube, tube drawing pile, referred to as vibrator pipe sinking cast-in-place pile.According to immersed tube method and Difference is vibrated when tube drawing, casing pipe hole forming bored concrete pile can be divided into hammer hidden pipe caisson pile, vibrator pipe sinking cast-in-place pile.The former is chiefly used in one As cohesive soil, muck soil, sand and artificial earth fill's ground, the latter is in addition to range above, it may also be used for it is slightly close and in it is close broken Stone soil base.In order to improve the quality and bearing capacity of stake, driven cast-in-place pile is applied frequently with singles' method, strike-on method, anti-plug method etc. Work technique.
Follow-up casing pile foundation pore-forming can generate biggish noise when construction, and construction can all influence residence nearby every time The living environment of the people, and Chang Tuzhi is harder when embedded casing, and casing is damaged, schedule delays, while in block stamp The case where causing punching to shift vulnerable to the influence of underground soil property when punching, and can not carry out following Work.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, it the present invention provides a kind of follow-up casing pile foundation drilling construction method, solves every Secondary construct can all influence the living environment of neighbouring resident, and Chang Tuzhi is harder when embedded casing, and damage shield Cylinder, schedule delays, while causing punching to shift vulnerable to the influence of underground soil property when block stamp is punched The case where, and the problem of working below can not be carried out.
(2) technical solution
In order to achieve the above object, the present invention is achieved by the following technical programs: a kind of follow-up casing pile foundation pore-forming is applied Work method, specifically includes the following steps:
Step 1: carrying out levelling of the land construction, shape to the place for needing pile foundation by laser leveling machine before pile foundation construction At smooth job platform, after the completion of construction, accurately measure by survey crew and put a little, determine pile center position, and by ten Word stake, which is squeezed into, surveys measured position;
Step 2: surveying measured pile center position in step 1, is loosened the soil, loosened the soil to the center using loosenning tiller Range diameter be 400-450cm, after the completion of loosening the soil, using hoisting machine by shield-tube embedment in the position of pile center;
Step 3: having buried the outer surface above casing in step 2 is socketed a noise abatement set, and in noise abatement set inner ring Lower section is installed with support annulus, adjusts the block stamp that hoisting machine has been hung, and makes the position control of centre weight and pile center fortunately 1.5cm interior;
It is impacted Step 4: hoisting machine begins through block stamp, mud off is used when impact, when block stamp is down toward casing 3- After 3.5m, tup 2-3m is improved, and accelerate speed and be transferred to normal impact.
Step 5: improving tup again after impact depth is 7-8m, support annulus is taken out, then remove noise abatement set, will located The one end for the mud managed is attached by feed pipe and tup, and is connected to waste tank by drainage conduit in the other side;
Step 6: impacting again by hoisting machine to it, and start the draining pump connecting with drainage conduit simultaneously, and The suction pump that the starting of connecing property is connect with feed pipe makes the work of draining pump and suction pump alternately, head pressure in retaining hole Balance, until punching reaches projected depth;
Step 7: punching, which reaches projected depth, to be made, hole depth is checked, hole location is checked, confirmation meets design It is required that the registration that can fill in a form.
Preferably, the material of the casing is steel casing, and the internal diameter of casing is greater than cross pile 15cm, is higher by construction ground Face 20-25cm.
Preferably, the support annulus is spring steel ring, has outside extensibility, and easily shrink.
Preferably, the bracing wire centre deviation of the end face center of the casing and cross pile is less than 5cm.
Preferably, the noise abatement set is fixedly connected with the junction of casing using screw.
(3) beneficial effect
The present invention provides a kind of follow-up casing pile foundation drilling construction methods.Have following the utility model has the advantages that the follow-up casing Pile foundation drilling construction method, specifically includes the following steps: Step 1: before pile foundation construction, by laser leveling machine to needing stake The place of base carries out levelling of the land construction, forms smooth job platform, after the completion of construction, is accurately measured by survey crew It puts a little, determines pile center position, and cross pile is squeezed into and surveys measured position, Step 2: surveying measured pile center in step 1 Position loosens the soil to the center using loosenning tiller, and the range diameter to loosen the soil is 400-450cm, after the completion of loosening the soil, uses Hoisting machine by shield-tube embedment in the position of pile center, Step 3: step 2 buried the outer surface above casing be socketed one Noise abatement set, and noise abatement set inner ring below be installed with support annulus, adjust the block stamp that hoisting machine has been hung, make centre weight and The position control of pile center in 1.5cm, is impacted fortunately Step 4: hoisting machine begins through block stamp, and mud is used when impact Retaining wall improves tup 2-3m, and accelerate speed and be transferred to normal impact after block stamp is down toward casing 3-3.5m, Step 5: when impact After depth is 7-8m, tup is improved again, takes out support annulus, then remove noise abatement set, the one end for the mud handled well is passed through Feed pipe is attached with tup, and is connected to waste tank by drainage conduit in the other side, Step 6: again by hoisting machine pair It is impacted, and starts the draining pump connecting with drainage conduit simultaneously, and the suction pump that the starting of indirect is connect with feed pipe, Make the work of draining pump and suction pump alternately, head pressure balances in retaining hole, until punching reaches projected depth, step Seven, punching reaches projected depth and makes, and checks hole depth, checks hole location, and confirmation meets design requirement, can fill in a form Registration is covered using noise abatement and supports the cooperation between annulus that can absorb the noise that punching generates when punching, avoids beating The living environment of excessive noise effect surrounding resident is generated when hole, while using the mud in double pump alternately replacement hole, can be kept away Exempt from occur the phenomenon that punching offset because of soil property.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation Example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without making creative work belongs to the model that the present invention protects It encloses.
The embodiment of the present invention provides a kind of technical solution: a kind of follow-up casing pile foundation drilling construction method, specifically include with Lower embodiment:
Embodiment 1
Step 1: carrying out levelling of the land construction, shape to the place for needing pile foundation by laser leveling machine before pile foundation construction At smooth job platform, after the completion of construction, accurately measure by survey crew and put a little, determine pile center position, and by ten Word stake, which is squeezed into, surveys measured position;
Step 2: surveying measured pile center position in step 1, is loosened the soil, loosened the soil to the center using loosenning tiller Range diameter be 400cm, after the completion of loosening the soil, using hoisting machine by shield-tube embedment in the position of pile center;
Step 3: having buried the outer surface above casing in step 2 is socketed a noise abatement set, and in noise abatement set inner ring Lower section is installed with support annulus, adjusts the block stamp that hoisting machine has been hung, and makes the position control of centre weight and pile center fortunately 1.5cm interior;
It is impacted Step 4: hoisting machine begins through block stamp, mud off is used when impact, when block stamp is down toward casing 3m Afterwards, tup 2m is improved, and accelerates speed and is transferred to normal impact.
Step 5: improving tup again after impact depth is 7m, support annulus is taken out, then remove noise abatement set, will handled One end of good mud is attached by feed pipe with tup, and is connected to waste tank by drainage conduit in the other side;
Step 6: impacting again by hoisting machine to it, and start the draining pump connecting with drainage conduit simultaneously, and The suction pump that the starting of connecing property is connect with feed pipe makes the work of draining pump and suction pump alternately, head pressure in retaining hole Balance, until punching reaches projected depth;
Step 7: punching, which reaches projected depth, to be made, hole depth is checked, hole location is checked, confirmation meets design It is required that the registration that can fill in a form.
Embodiment 2
Step 1: carrying out levelling of the land construction, shape to the place for needing pile foundation by laser leveling machine before pile foundation construction At smooth job platform, after the completion of construction, accurately measure by survey crew and put a little, determine pile center position, and by ten Word stake, which is squeezed into, surveys measured position;
Step 2: surveying measured pile center position in step 1, is loosened the soil, loosened the soil to the center using loosenning tiller Range diameter be 425cm, after the completion of loosening the soil, using hoisting machine by shield-tube embedment in the position of pile center;
Step 3: having buried the outer surface above casing in step 2 is socketed a noise abatement set, and in noise abatement set inner ring Lower section is installed with support annulus, adjusts the block stamp that hoisting machine has been hung, and makes the position control of centre weight and pile center fortunately 1.3cm interior;
It is impacted Step 4: hoisting machine begins through block stamp, mud off is used when impact, when block stamp is down toward casing After 3.2m, tup 2.5m is improved, and accelerate speed and be transferred to normal impact.
Step 5: improving tup again after impact depth is 7.5m, support annulus is taken out, then remove noise abatement set, will located The one end for the mud managed is attached by feed pipe and tup, and is connected to waste tank by drainage conduit in the other side;
Step 6: impacting again by hoisting machine to it, and start the draining pump connecting with drainage conduit simultaneously, and The suction pump that the starting of connecing property is connect with feed pipe makes the work of draining pump and suction pump alternately, head pressure in retaining hole Balance, until punching reaches projected depth;
Step 7: punching, which reaches projected depth, to be made, hole depth is checked, hole location is checked, confirmation meets design It is required that the registration that can fill in a form.
Embodiment 3
Step 1: carrying out levelling of the land construction, shape to the place for needing pile foundation by laser leveling machine before pile foundation construction At smooth job platform, after the completion of construction, accurately measure by survey crew and put a little, determine pile center position, and by ten Word stake, which is squeezed into, surveys measured position;
Step 2: surveying measured pile center position in step 1, is loosened the soil, loosened the soil to the center using loosenning tiller Range diameter be 450cm, after the completion of loosening the soil, using hoisting machine by shield-tube embedment in the position of pile center;
Step 3: having buried the outer surface above casing in step 2 is socketed a noise abatement set, and in noise abatement set inner ring Lower section is installed with support annulus, adjusts the block stamp that hoisting machine has been hung, and makes the position control of centre weight and pile center fortunately 1.5cm interior;
It is impacted Step 4: hoisting machine begins through block stamp, mud off is used when impact, when block stamp is down toward casing After 3.5m, tup 3m is improved, and accelerate speed and be transferred to normal impact.
Step 5: improving tup again after impact depth is 8m, support annulus is taken out, then remove noise abatement set, will handled One end of good mud is attached by feed pipe with tup, and is connected to waste tank by drainage conduit in the other side;
Step 6: impacting again by hoisting machine to it, and start the draining pump connecting with drainage conduit simultaneously, and The suction pump that the starting of connecing property is connect with feed pipe makes the work of draining pump and suction pump alternately, head pressure in retaining hole Balance, until punching reaches projected depth;
Step 7: punching, which reaches projected depth, to be made, hole depth is checked, hole location is checked, confirmation meets design It is required that the registration that can fill in a form.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (5)

1. a kind of follow-up casing pile foundation drilling construction method, it is characterised in that: specifically includes the following steps:
Step 1: carrying out levelling of the land construction before pile foundation construction to the place for needing pile foundation by laser leveling machine, being formed flat Whole job platform after the completion of construction, accurately measure by survey crew and be put a little, determines pile center position, and by cross pile It squeezes into and surveys measured position;
Step 2: surveying measured pile center position in step 1, loosened the soil using loosenning tiller to the center, the model to loosen the soil Enclosing diameter is 400-450cm, after the completion of loosening the soil, using hoisting machine by shield-tube embedment in the position of pile center;
Step 3: having buried the outer surface above casing in step 2 is socketed a noise abatement set, and in the lower section of noise abatement set inner ring It is installed with support annulus, adjusts the block stamp that hoisting machine has been hung, makes the position control of centre weight and pile center 1.5cm fortunately It is interior;
It is impacted Step 4: hoisting machine begins through block stamp, mud off is used when impact, when block stamp is down toward casing 3-3.5m Afterwards, tup 2-3m is improved, and accelerates speed and is transferred to normal impact.
Step 5: improving tup again after impact depth is 7-8m, support annulus is taken out, then remove noise abatement set, will handled well One end of mud be attached by feed pipe and tup, and waste tank is connected to by drainage conduit in the other side;
Step 6: impacting again by hoisting machine to it, and start the draining pump connecting with drainage conduit simultaneously, and indirect The suction pump that is connect with feed pipe of starting, make the work of draining pump and suction pump alternately, head pressure balances in retaining hole, Until punching reaches projected depth;
Step 7: punching, which reaches projected depth, to be made, hole depth is checked, hole location is checked, confirmation meets design requirement, Can fill in a form registration.
2. a kind of follow-up casing pile foundation drilling construction method according to claim 1, it is characterised in that: the material of the casing Matter is steel casing, and the internal diameter of casing is greater than cross pile 15cm, is higher by construction ground 20-25cm.
3. a kind of follow-up casing pile foundation drilling construction method according to claim 1, it is characterised in that: the support annulus For spring steel ring, there is outside extensibility, and easily shrink.
4. a kind of follow-up casing pile foundation drilling construction method according to claim 1, it is characterised in that: the top of the casing The bracing wire centre deviation of face center and cross pile is less than 5cm.
5. a kind of follow-up casing pile foundation drilling construction method according to claim 1, it is characterised in that: noise abatement set with The junction of casing is fixedly connected using screw.
CN201910604830.8A 2019-07-05 2019-07-05 A kind of follow-up casing pile foundation drilling construction method Pending CN110306584A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910604830.8A CN110306584A (en) 2019-07-05 2019-07-05 A kind of follow-up casing pile foundation drilling construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910604830.8A CN110306584A (en) 2019-07-05 2019-07-05 A kind of follow-up casing pile foundation drilling construction method

Publications (1)

Publication Number Publication Date
CN110306584A true CN110306584A (en) 2019-10-08

Family

ID=68079174

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910604830.8A Pending CN110306584A (en) 2019-07-05 2019-07-05 A kind of follow-up casing pile foundation drilling construction method

Country Status (1)

Country Link
CN (1) CN110306584A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2478362A (en) * 2010-03-06 2011-09-07 Shire Structures Ltd A pile with a tube extending lengthwise of the pile
CN102808407A (en) * 2012-08-14 2012-12-05 天津二十冶建设有限公司 Construction method of soft-foundation reinforced concrete cast-in-place pile
CN103774669A (en) * 2014-01-27 2014-05-07 广东明阳风电产业集团有限公司 Vacuum metal ball noise reduction net for constructing offshore draught fan foundation
CN107938658A (en) * 2017-11-17 2018-04-20 重庆交通建设(集团)有限责任公司 A kind of construction method of fender post
CN207846432U (en) * 2018-01-04 2018-09-11 王兵 Foundation pit enclosure pile driving construction casing device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2478362A (en) * 2010-03-06 2011-09-07 Shire Structures Ltd A pile with a tube extending lengthwise of the pile
CN102808407A (en) * 2012-08-14 2012-12-05 天津二十冶建设有限公司 Construction method of soft-foundation reinforced concrete cast-in-place pile
CN103774669A (en) * 2014-01-27 2014-05-07 广东明阳风电产业集团有限公司 Vacuum metal ball noise reduction net for constructing offshore draught fan foundation
CN107938658A (en) * 2017-11-17 2018-04-20 重庆交通建设(集团)有限责任公司 A kind of construction method of fender post
CN207846432U (en) * 2018-01-04 2018-09-11 王兵 Foundation pit enclosure pile driving construction casing device

Similar Documents

Publication Publication Date Title
CN107246006B (en) The pile-filling method of concrete-pile
CN102635120B (en) Circular deep foundation ditch is without Construction of Supporting structure and construction method
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN102644275A (en) Rotary-digging combined pile-forming construction method in complicated geological conditions
CN109440762A (en) A kind of construction method of drainage pumping plant bored concrete pile
JP2022528743A (en) Wall subsidence construction method
CN111794205B (en) Anti-collapse rotary digging pile construction device and construction method thereof
CN110387879A (en) A kind of concrete filling pile construction method of hydraulic vibration hammer hidden pipe
CN105953078A (en) Protection device and protection method of high-pressure gas pipeline
CN112030956A (en) Karst stratum bored pile construction method
CN106522191A (en) Transformer substation foundation treatment method and application thereof
CN108589711A (en) A kind of construction method of bead string type solution cavity development area fender post
CN110409433A (en) The construction system and method for basement process are carried out using the bored concrete pile with steel bushing
CN113431039A (en) Construction method of bridge implanted pile
CN106032667A (en) Technology of large-energy dynamic-compaction-treated foundation
CN102817349B (en) Method for consolidating soft soil foundations through fine dynamic compaction replacement
CN109989346B (en) Bridge large-diameter precast concrete tubular column foundation and construction method thereof
CN110067205A (en) A kind of permanent protecting tube embedding construction method of bridge pier column outsourcing
CN106869038A (en) Prevent servicing unit and its construction method that overpass is settled
CN110306584A (en) A kind of follow-up casing pile foundation drilling construction method
CN109113054A (en) A kind of reclaimation area complex geological condition cast-in-situ bored pile multimachine combined construction method
CN113235640B (en) Steel pipe group pile vibration piling method and positioning tool
CN109385997A (en) The construction method of PHC tubular pole under narrow site condition
CN212656218U (en) Heavy pile machine load underpinning structure
CN211816394U (en) Retaining wall structure without drainage in bedrock area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191008

RJ01 Rejection of invention patent application after publication