CN110306584A - A kind of follow-up casing pile foundation drilling construction method - Google Patents
A kind of follow-up casing pile foundation drilling construction method Download PDFInfo
- Publication number
- CN110306584A CN110306584A CN201910604830.8A CN201910604830A CN110306584A CN 110306584 A CN110306584 A CN 110306584A CN 201910604830 A CN201910604830 A CN 201910604830A CN 110306584 A CN110306584 A CN 110306584A
- Authority
- CN
- China
- Prior art keywords
- pile
- casing
- pile foundation
- follow
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
Abstract
The invention discloses a kind of follow-up casing pile foundation drilling construction methods, the method specifically includes following steps: step 1, before pile foundation construction, levelling of the land construction is carried out to the place for needing pile foundation by laser leveling machine, form smooth job platform, after the completion of construction, accurately measure by survey crew and put a little, determine pile center position, and cross pile is squeezed into and surveys measured position, step 2, measured pile center position is surveyed in step 1, it is loosened the soil using loosenning tiller to the center, the range diameter to loosen the soil is 400-450cm, the present invention relates to existing driven cast-in-place pile technical fields.The follow-up casing pile foundation drilling construction method, it is covered using noise abatement and supports the cooperation between annulus can be when punching, absorb the noise that punching generates, avoid the living environment that excessive noise effect surrounding resident is generated when punching, simultaneously using the mud in double pump alternately replacement hole, it can avoid occurring the phenomenon that punching offset because of soil property.
Description
Technical field
The present invention relates to existing driven cast-in-place pile technical field, specially a kind of follow-up casing pile foundation drilling construction method.
Background technique
Existing driven cast-in-place pile is one of numerous type pile foundations in civil construction project.System is using the design ruler with stake
Very little adaptable steel pipe (i.e. casing), after sinking in soil after pile top in end sleeve, hangs framework of steel reinforcement, then side in casing
The vibration of casting concrete side or hammering tube drawing, mechanical pudding concrete when using tube drawing and form required bored concrete pile.This
Kind construction method is suitable for having the case where underground water, quicksand, mud.Using hammer piling equipment immersed tube, tube drawing pile, referred to as
Hammer hidden pipe caisson pile.Utilize vibrator vibration sinking tube, tube drawing pile, referred to as vibrator pipe sinking cast-in-place pile.According to immersed tube method and
Difference is vibrated when tube drawing, casing pipe hole forming bored concrete pile can be divided into hammer hidden pipe caisson pile, vibrator pipe sinking cast-in-place pile.The former is chiefly used in one
As cohesive soil, muck soil, sand and artificial earth fill's ground, the latter is in addition to range above, it may also be used for it is slightly close and in it is close broken
Stone soil base.In order to improve the quality and bearing capacity of stake, driven cast-in-place pile is applied frequently with singles' method, strike-on method, anti-plug method etc.
Work technique.
Follow-up casing pile foundation pore-forming can generate biggish noise when construction, and construction can all influence residence nearby every time
The living environment of the people, and Chang Tuzhi is harder when embedded casing, and casing is damaged, schedule delays, while in block stamp
The case where causing punching to shift vulnerable to the influence of underground soil property when punching, and can not carry out following
Work.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, it the present invention provides a kind of follow-up casing pile foundation drilling construction method, solves every
Secondary construct can all influence the living environment of neighbouring resident, and Chang Tuzhi is harder when embedded casing, and damage shield
Cylinder, schedule delays, while causing punching to shift vulnerable to the influence of underground soil property when block stamp is punched
The case where, and the problem of working below can not be carried out.
(2) technical solution
In order to achieve the above object, the present invention is achieved by the following technical programs: a kind of follow-up casing pile foundation pore-forming is applied
Work method, specifically includes the following steps:
Step 1: carrying out levelling of the land construction, shape to the place for needing pile foundation by laser leveling machine before pile foundation construction
At smooth job platform, after the completion of construction, accurately measure by survey crew and put a little, determine pile center position, and by ten
Word stake, which is squeezed into, surveys measured position;
Step 2: surveying measured pile center position in step 1, is loosened the soil, loosened the soil to the center using loosenning tiller
Range diameter be 400-450cm, after the completion of loosening the soil, using hoisting machine by shield-tube embedment in the position of pile center;
Step 3: having buried the outer surface above casing in step 2 is socketed a noise abatement set, and in noise abatement set inner ring
Lower section is installed with support annulus, adjusts the block stamp that hoisting machine has been hung, and makes the position control of centre weight and pile center fortunately
1.5cm interior;
It is impacted Step 4: hoisting machine begins through block stamp, mud off is used when impact, when block stamp is down toward casing 3-
After 3.5m, tup 2-3m is improved, and accelerate speed and be transferred to normal impact.
Step 5: improving tup again after impact depth is 7-8m, support annulus is taken out, then remove noise abatement set, will located
The one end for the mud managed is attached by feed pipe and tup, and is connected to waste tank by drainage conduit in the other side;
Step 6: impacting again by hoisting machine to it, and start the draining pump connecting with drainage conduit simultaneously, and
The suction pump that the starting of connecing property is connect with feed pipe makes the work of draining pump and suction pump alternately, head pressure in retaining hole
Balance, until punching reaches projected depth;
Step 7: punching, which reaches projected depth, to be made, hole depth is checked, hole location is checked, confirmation meets design
It is required that the registration that can fill in a form.
Preferably, the material of the casing is steel casing, and the internal diameter of casing is greater than cross pile 15cm, is higher by construction ground
Face 20-25cm.
Preferably, the support annulus is spring steel ring, has outside extensibility, and easily shrink.
Preferably, the bracing wire centre deviation of the end face center of the casing and cross pile is less than 5cm.
Preferably, the noise abatement set is fixedly connected with the junction of casing using screw.
(3) beneficial effect
The present invention provides a kind of follow-up casing pile foundation drilling construction methods.Have following the utility model has the advantages that the follow-up casing
Pile foundation drilling construction method, specifically includes the following steps: Step 1: before pile foundation construction, by laser leveling machine to needing stake
The place of base carries out levelling of the land construction, forms smooth job platform, after the completion of construction, is accurately measured by survey crew
It puts a little, determines pile center position, and cross pile is squeezed into and surveys measured position, Step 2: surveying measured pile center in step 1
Position loosens the soil to the center using loosenning tiller, and the range diameter to loosen the soil is 400-450cm, after the completion of loosening the soil, uses
Hoisting machine by shield-tube embedment in the position of pile center, Step 3: step 2 buried the outer surface above casing be socketed one
Noise abatement set, and noise abatement set inner ring below be installed with support annulus, adjust the block stamp that hoisting machine has been hung, make centre weight and
The position control of pile center in 1.5cm, is impacted fortunately Step 4: hoisting machine begins through block stamp, and mud is used when impact
Retaining wall improves tup 2-3m, and accelerate speed and be transferred to normal impact after block stamp is down toward casing 3-3.5m, Step 5: when impact
After depth is 7-8m, tup is improved again, takes out support annulus, then remove noise abatement set, the one end for the mud handled well is passed through
Feed pipe is attached with tup, and is connected to waste tank by drainage conduit in the other side, Step 6: again by hoisting machine pair
It is impacted, and starts the draining pump connecting with drainage conduit simultaneously, and the suction pump that the starting of indirect is connect with feed pipe,
Make the work of draining pump and suction pump alternately, head pressure balances in retaining hole, until punching reaches projected depth, step
Seven, punching reaches projected depth and makes, and checks hole depth, checks hole location, and confirmation meets design requirement, can fill in a form
Registration is covered using noise abatement and supports the cooperation between annulus that can absorb the noise that punching generates when punching, avoids beating
The living environment of excessive noise effect surrounding resident is generated when hole, while using the mud in double pump alternately replacement hole, can be kept away
Exempt from occur the phenomenon that punching offset because of soil property.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation
Example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common
Technical staff's every other embodiment obtained without making creative work belongs to the model that the present invention protects
It encloses.
The embodiment of the present invention provides a kind of technical solution: a kind of follow-up casing pile foundation drilling construction method, specifically include with
Lower embodiment:
Embodiment 1
Step 1: carrying out levelling of the land construction, shape to the place for needing pile foundation by laser leveling machine before pile foundation construction
At smooth job platform, after the completion of construction, accurately measure by survey crew and put a little, determine pile center position, and by ten
Word stake, which is squeezed into, surveys measured position;
Step 2: surveying measured pile center position in step 1, is loosened the soil, loosened the soil to the center using loosenning tiller
Range diameter be 400cm, after the completion of loosening the soil, using hoisting machine by shield-tube embedment in the position of pile center;
Step 3: having buried the outer surface above casing in step 2 is socketed a noise abatement set, and in noise abatement set inner ring
Lower section is installed with support annulus, adjusts the block stamp that hoisting machine has been hung, and makes the position control of centre weight and pile center fortunately
1.5cm interior;
It is impacted Step 4: hoisting machine begins through block stamp, mud off is used when impact, when block stamp is down toward casing 3m
Afterwards, tup 2m is improved, and accelerates speed and is transferred to normal impact.
Step 5: improving tup again after impact depth is 7m, support annulus is taken out, then remove noise abatement set, will handled
One end of good mud is attached by feed pipe with tup, and is connected to waste tank by drainage conduit in the other side;
Step 6: impacting again by hoisting machine to it, and start the draining pump connecting with drainage conduit simultaneously, and
The suction pump that the starting of connecing property is connect with feed pipe makes the work of draining pump and suction pump alternately, head pressure in retaining hole
Balance, until punching reaches projected depth;
Step 7: punching, which reaches projected depth, to be made, hole depth is checked, hole location is checked, confirmation meets design
It is required that the registration that can fill in a form.
Embodiment 2
Step 1: carrying out levelling of the land construction, shape to the place for needing pile foundation by laser leveling machine before pile foundation construction
At smooth job platform, after the completion of construction, accurately measure by survey crew and put a little, determine pile center position, and by ten
Word stake, which is squeezed into, surveys measured position;
Step 2: surveying measured pile center position in step 1, is loosened the soil, loosened the soil to the center using loosenning tiller
Range diameter be 425cm, after the completion of loosening the soil, using hoisting machine by shield-tube embedment in the position of pile center;
Step 3: having buried the outer surface above casing in step 2 is socketed a noise abatement set, and in noise abatement set inner ring
Lower section is installed with support annulus, adjusts the block stamp that hoisting machine has been hung, and makes the position control of centre weight and pile center fortunately
1.3cm interior;
It is impacted Step 4: hoisting machine begins through block stamp, mud off is used when impact, when block stamp is down toward casing
After 3.2m, tup 2.5m is improved, and accelerate speed and be transferred to normal impact.
Step 5: improving tup again after impact depth is 7.5m, support annulus is taken out, then remove noise abatement set, will located
The one end for the mud managed is attached by feed pipe and tup, and is connected to waste tank by drainage conduit in the other side;
Step 6: impacting again by hoisting machine to it, and start the draining pump connecting with drainage conduit simultaneously, and
The suction pump that the starting of connecing property is connect with feed pipe makes the work of draining pump and suction pump alternately, head pressure in retaining hole
Balance, until punching reaches projected depth;
Step 7: punching, which reaches projected depth, to be made, hole depth is checked, hole location is checked, confirmation meets design
It is required that the registration that can fill in a form.
Embodiment 3
Step 1: carrying out levelling of the land construction, shape to the place for needing pile foundation by laser leveling machine before pile foundation construction
At smooth job platform, after the completion of construction, accurately measure by survey crew and put a little, determine pile center position, and by ten
Word stake, which is squeezed into, surveys measured position;
Step 2: surveying measured pile center position in step 1, is loosened the soil, loosened the soil to the center using loosenning tiller
Range diameter be 450cm, after the completion of loosening the soil, using hoisting machine by shield-tube embedment in the position of pile center;
Step 3: having buried the outer surface above casing in step 2 is socketed a noise abatement set, and in noise abatement set inner ring
Lower section is installed with support annulus, adjusts the block stamp that hoisting machine has been hung, and makes the position control of centre weight and pile center fortunately
1.5cm interior;
It is impacted Step 4: hoisting machine begins through block stamp, mud off is used when impact, when block stamp is down toward casing
After 3.5m, tup 3m is improved, and accelerate speed and be transferred to normal impact.
Step 5: improving tup again after impact depth is 8m, support annulus is taken out, then remove noise abatement set, will handled
One end of good mud is attached by feed pipe with tup, and is connected to waste tank by drainage conduit in the other side;
Step 6: impacting again by hoisting machine to it, and start the draining pump connecting with drainage conduit simultaneously, and
The suction pump that the starting of connecing property is connect with feed pipe makes the work of draining pump and suction pump alternately, head pressure in retaining hole
Balance, until punching reaches projected depth;
Step 7: punching, which reaches projected depth, to be made, hole depth is checked, hole location is checked, confirmation meets design
It is required that the registration that can fill in a form.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality
Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation
In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to
Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those
Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment
Intrinsic element.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding
And modification, the scope of the present invention is defined by the appended.
Claims (5)
1. a kind of follow-up casing pile foundation drilling construction method, it is characterised in that: specifically includes the following steps:
Step 1: carrying out levelling of the land construction before pile foundation construction to the place for needing pile foundation by laser leveling machine, being formed flat
Whole job platform after the completion of construction, accurately measure by survey crew and be put a little, determines pile center position, and by cross pile
It squeezes into and surveys measured position;
Step 2: surveying measured pile center position in step 1, loosened the soil using loosenning tiller to the center, the model to loosen the soil
Enclosing diameter is 400-450cm, after the completion of loosening the soil, using hoisting machine by shield-tube embedment in the position of pile center;
Step 3: having buried the outer surface above casing in step 2 is socketed a noise abatement set, and in the lower section of noise abatement set inner ring
It is installed with support annulus, adjusts the block stamp that hoisting machine has been hung, makes the position control of centre weight and pile center 1.5cm fortunately
It is interior;
It is impacted Step 4: hoisting machine begins through block stamp, mud off is used when impact, when block stamp is down toward casing 3-3.5m
Afterwards, tup 2-3m is improved, and accelerates speed and is transferred to normal impact.
Step 5: improving tup again after impact depth is 7-8m, support annulus is taken out, then remove noise abatement set, will handled well
One end of mud be attached by feed pipe and tup, and waste tank is connected to by drainage conduit in the other side;
Step 6: impacting again by hoisting machine to it, and start the draining pump connecting with drainage conduit simultaneously, and indirect
The suction pump that is connect with feed pipe of starting, make the work of draining pump and suction pump alternately, head pressure balances in retaining hole,
Until punching reaches projected depth;
Step 7: punching, which reaches projected depth, to be made, hole depth is checked, hole location is checked, confirmation meets design requirement,
Can fill in a form registration.
2. a kind of follow-up casing pile foundation drilling construction method according to claim 1, it is characterised in that: the material of the casing
Matter is steel casing, and the internal diameter of casing is greater than cross pile 15cm, is higher by construction ground 20-25cm.
3. a kind of follow-up casing pile foundation drilling construction method according to claim 1, it is characterised in that: the support annulus
For spring steel ring, there is outside extensibility, and easily shrink.
4. a kind of follow-up casing pile foundation drilling construction method according to claim 1, it is characterised in that: the top of the casing
The bracing wire centre deviation of face center and cross pile is less than 5cm.
5. a kind of follow-up casing pile foundation drilling construction method according to claim 1, it is characterised in that: noise abatement set with
The junction of casing is fixedly connected using screw.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910604830.8A CN110306584A (en) | 2019-07-05 | 2019-07-05 | A kind of follow-up casing pile foundation drilling construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910604830.8A CN110306584A (en) | 2019-07-05 | 2019-07-05 | A kind of follow-up casing pile foundation drilling construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110306584A true CN110306584A (en) | 2019-10-08 |
Family
ID=68079174
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910604830.8A Pending CN110306584A (en) | 2019-07-05 | 2019-07-05 | A kind of follow-up casing pile foundation drilling construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110306584A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2478362A (en) * | 2010-03-06 | 2011-09-07 | Shire Structures Ltd | A pile with a tube extending lengthwise of the pile |
CN102808407A (en) * | 2012-08-14 | 2012-12-05 | 天津二十冶建设有限公司 | Construction method of soft-foundation reinforced concrete cast-in-place pile |
CN103774669A (en) * | 2014-01-27 | 2014-05-07 | 广东明阳风电产业集团有限公司 | Vacuum metal ball noise reduction net for constructing offshore draught fan foundation |
CN107938658A (en) * | 2017-11-17 | 2018-04-20 | 重庆交通建设(集团)有限责任公司 | A kind of construction method of fender post |
CN207846432U (en) * | 2018-01-04 | 2018-09-11 | 王兵 | Foundation pit enclosure pile driving construction casing device |
-
2019
- 2019-07-05 CN CN201910604830.8A patent/CN110306584A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2478362A (en) * | 2010-03-06 | 2011-09-07 | Shire Structures Ltd | A pile with a tube extending lengthwise of the pile |
CN102808407A (en) * | 2012-08-14 | 2012-12-05 | 天津二十冶建设有限公司 | Construction method of soft-foundation reinforced concrete cast-in-place pile |
CN103774669A (en) * | 2014-01-27 | 2014-05-07 | 广东明阳风电产业集团有限公司 | Vacuum metal ball noise reduction net for constructing offshore draught fan foundation |
CN107938658A (en) * | 2017-11-17 | 2018-04-20 | 重庆交通建设(集团)有限责任公司 | A kind of construction method of fender post |
CN207846432U (en) * | 2018-01-04 | 2018-09-11 | 王兵 | Foundation pit enclosure pile driving construction casing device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107246006B (en) | The pile-filling method of concrete-pile | |
CN102635120B (en) | Circular deep foundation ditch is without Construction of Supporting structure and construction method | |
CN109555116A (en) | A kind of high density karst intense development area fully-sleeved filled pile construction method | |
CN102644275A (en) | Rotary-digging combined pile-forming construction method in complicated geological conditions | |
CN109440762A (en) | A kind of construction method of drainage pumping plant bored concrete pile | |
JP2022528743A (en) | Wall subsidence construction method | |
CN111794205B (en) | Anti-collapse rotary digging pile construction device and construction method thereof | |
CN110387879A (en) | A kind of concrete filling pile construction method of hydraulic vibration hammer hidden pipe | |
CN105953078A (en) | Protection device and protection method of high-pressure gas pipeline | |
CN112030956A (en) | Karst stratum bored pile construction method | |
CN106522191A (en) | Transformer substation foundation treatment method and application thereof | |
CN108589711A (en) | A kind of construction method of bead string type solution cavity development area fender post | |
CN110409433A (en) | The construction system and method for basement process are carried out using the bored concrete pile with steel bushing | |
CN113431039A (en) | Construction method of bridge implanted pile | |
CN106032667A (en) | Technology of large-energy dynamic-compaction-treated foundation | |
CN102817349B (en) | Method for consolidating soft soil foundations through fine dynamic compaction replacement | |
CN109989346B (en) | Bridge large-diameter precast concrete tubular column foundation and construction method thereof | |
CN110067205A (en) | A kind of permanent protecting tube embedding construction method of bridge pier column outsourcing | |
CN106869038A (en) | Prevent servicing unit and its construction method that overpass is settled | |
CN110306584A (en) | A kind of follow-up casing pile foundation drilling construction method | |
CN109113054A (en) | A kind of reclaimation area complex geological condition cast-in-situ bored pile multimachine combined construction method | |
CN113235640B (en) | Steel pipe group pile vibration piling method and positioning tool | |
CN109385997A (en) | The construction method of PHC tubular pole under narrow site condition | |
CN212656218U (en) | Heavy pile machine load underpinning structure | |
CN211816394U (en) | Retaining wall structure without drainage in bedrock area |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191008 |
|
RJ01 | Rejection of invention patent application after publication |