CN106869038A - Prevent servicing unit and its construction method that overpass is settled - Google Patents

Prevent servicing unit and its construction method that overpass is settled Download PDF

Info

Publication number
CN106869038A
CN106869038A CN201710170403.4A CN201710170403A CN106869038A CN 106869038 A CN106869038 A CN 106869038A CN 201710170403 A CN201710170403 A CN 201710170403A CN 106869038 A CN106869038 A CN 106869038A
Authority
CN
China
Prior art keywords
support
overpass
bridge
cushion cap
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710170403.4A
Other languages
Chinese (zh)
Other versions
CN106869038B (en
Inventor
叶锡钧
孙卓
陈炳聪
曹飒飒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou University
Original Assignee
Guangzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou University filed Critical Guangzhou University
Priority to CN201710170403.4A priority Critical patent/CN106869038B/en
Publication of CN106869038A publication Critical patent/CN106869038A/en
Application granted granted Critical
Publication of CN106869038B publication Critical patent/CN106869038B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to Urban Bridge field, disclose a kind of servicing unit for preventing overpass from settling and its construction method, the device has the function of preventing overpass from settling, it includes aiding in cushion cap and lateral Displacement support member, the auxiliary cushion cap is in the pile foundation of overpass, and the outside of the former cushion cap of overpass is coated on, the pier stud of overpass passes through the auxiliary cushion cap;The lateral Displacement support member includes support base and support frame, the support base is on ground and positioned at the outside of pier stud, the joint chair end of support frame as described above is connected on the support base, and the beam-ends that connects of support frame as described above is connected at the position that the bent cap of overpass is connected with pier stud.Be coated on auxiliary cushion cap outside former cushion cap by the present invention so that pier stud lower end more consolidates, and is prevented from bridge and settles, and can effectively prevent bridge from laterally offset occurring using lateral Displacement support member, further prevents the differential settlement of bridge from continuing to increase.

Description

Prevent servicing unit and its construction method that overpass is settled
Technical field
The present invention relates to Urban Bridge field, more particularly to a kind of servicing unit for preventing overpass from settling and its construction Method.
Background technology
Most of urban viaduct is mostly using this base form of pile foundation.However, Urban Bridge is normal Multifactor influence can be faced during operation, so as to cause the differential settlement of bridge foundation.And, when urban viaduct When basis differential settlement occurs and needs to carry out maintenance and reinforcement, because newly-built pile foundation is nearer with original structure pile foundations, if need to add Solid pier stud old pile foundation and old cushion cap working condition it is poor, greater risk is had when pile driving construction is bored, just in case collapse The accidents such as hole, will produce the influence for being difficult to estimate to original structure.
The content of the invention
It is an object of the invention to provide a kind of servicing unit for preventing overpass from settling and its construction method, to solve city There is the problem of foundation uneven settlement in overpass.
In order to solve the above-mentioned technical problem, the present invention provides a kind of servicing unit for preventing overpass from settling, and it includes auxiliary Help cushion cap and lateral Displacement support member, the auxiliary cushion cap to be located in the pile foundation of overpass, and be coated on the original of overpass and hold The outside of platform, the pier stud of overpass passes through the auxiliary cushion cap;The lateral Displacement support member includes support base and support frame, institute Support base is stated on ground and positioned at the outside of pier stud, the joint chair end of support frame as described above is connected on the support base, described The beam-ends that connects of support frame is connected at the position that the bent cap of overpass is connected with pier stud.
Preferably, support frame as described above is obliquely installed relative to level ground, and the beam-ends that connects of support frame as described above is provided with First backing plate, support frame as described above is connected at the position that bent cap is connected with pier stud by first backing plate;Support frame as described above, pier Post and ground form triangular structure.
Preferably, support frame as described above includes the first support tube, the second support tube and the 3rd support tube, described first Support tube and the second support tube are set in angle, and the beam-ends that connects of first support tube is connected with the beam-ends that connects of the second support tube, The joint chair end of first support tube and the joint chair end interval setting of the second support tube, the 3rd support tube are connected to described the Between one support tube and the second support tube.
Preferably, the support base includes brace foundation and limit base, and the brace foundation is located on ground, or Subsurface is embedded in, on the brace foundation, the joint chair end of support frame as described above is connected to the limit base to the limit base On.
Preferably, the limit base includes barricade and ruggedized construction, and the ruggedized construction is located at the barricade Outside, is provided with the second backing plate on the inside of institute's barricade, the joint chair end of support frame as described above is connected to the gear by second backing plate The inner side of wall.
A kind of construction method of the servicing unit for preventing overpass from settling, comprises the following steps:
(1) girder falling temporary support structure is installed
Temporary support component is installed in the bridge pier both sides under the girder of overpass or Bailey bracket is faced as girder falling When supporting construction, specifically, the bottom of temporary support component or Bailey bracket to be fixed on the top of the former cushion cap of overpass, and will The top of temporary support component or Bailey bracket acts against the bottom of girder.
(2) lateral limited support part is installed
In support base of being constructed out on the ground on the outside of pier stud, the joint chair end of support frame is fixed on support base, and The beam-ends that connects of support frame is connected at the position that bent cap is connected with pier stud.
(3) steel pipe T beam support systems are installed
First many steel-pipe piles are squeezed into compartment of terrain on the ground between adjacent pier stud, then again on the ground on pier stud periphery Squeeze into many steel-pipe piles;
The upper end of these steel-pipe piles is extended close into bent cap bottom, and connector, the company are set in the upper end of steel-pipe pile Fitting includes that direction across bridge I-beam, steel plate and vertical bridge, to I-beam, the direction across bridge I-beam are located at the top of the steel-pipe pile Portion, and steel plate is set at the top of direction across bridge I-beam, the vertical bridge is then connected to the steel plate to the lower end of I-beam On, and then vertical bridge is set into bridging to the bent cap bottom is withstood at the top of I-beam between adjacent steel-pipe pile;
(4) girder falling temporary support structure is removed
(5) construction auxiliary cushion cap
The foundation ditch that construction aids in cushion cap is excavated out on ground first above pile foundation, it is ensured that the side slope and level of foundation ditch The angle in face is in 45 degree, until excavation spills more than 30cm to the former cushion cap upper surface of overpass;In digging process, first carry out Thick to dig, thick digging after 20~30cm, is dug to more than the bottom absolute altitude of design hole using essence;After excavation is finished, foundation ditch surfacing is overhauled;
Foundation ditch setting-out is carried out, according to auxiliary cushion cap and foundation ditch baseplane size, foundation ditch baseplane contour line is surveyed and is set to original On ground;Section survey is carried out along 4 edge directions of the foundation ditch Planar Contours on ground;It is determined that excavating the depth of skirt piles, press The width of slope is determined according to lower digging depth, center pile layout will be excavated to ground, and arrangement mark in this place;Carry out at chisel pile crown Reason and draining, after the completion of draining, the assembling reinforcement in foundation ditch, cover to reinforcement uses rubber blanket;In polylith template surface brushing Mould oil, and the installation form in foundation ditch, are blocked in the joint of adjacent forms using sponge strip or two-sided tape;
Dirt on cleaning template, reinforcing bar, then concrete is poured into a mould, after concrete setting, conserved and form removal, finally return Foundation ditch is filled out, auxiliary bearing platform construction is completed.
Preferably, include the step of construction lateral Displacement support member in step (2):
First backing plate is fixed at the position that bent cap is connected with pier stud, and is injected between the first backing plate and the position Adhesive;
Second backing plate is fixed on the inner side of barricade, and adhesive is injected between the second backing plate and barricade;
The beam-ends pretension that connects of support frame is supported on the first backing plate, and the joint chair end pretension of support frame is supported to second On backing plate, then the beam-ends that connects of support frame is welded on the first backing plate, and the joint chair end of support frame is welded to the second backing plate On.
Preferably, temporary support component includes temporary support seat, many support columns, crossbeam, stulls in step (1) Part and bracing element, located at the top of the former cushion cap of overpass, the bottom of many support columns is connected to the temporary support seat On temporary support seat, and the top of many support columns is in the same plane, and the bottom of the crossbeam is connected to many The top of support column described in root, and the top of the crossbeam acts against the bottom of girder, the Cross stay is connected to adjacent branch Between dagger and vertical with the support column, the bracing element is connected between adjacent support column, and between the Cross stay Every.
Preferably, during step (3) construction steel pile tube, with the heavy of the frequency monitoring bridge of every 2 hours 1 time Drop;Specifically, first choose a pier stud as measuring basis, then in the measuring basis left and right sides and other each pier studs 2 monitoring points are each side set, datum mark are set in the range of 10~20m of distance construction region, by the skill of second grade leveling Art requirement is measured;
With the horizontal displacement of the frequency monitoring bridge of every 2 hours 1 time;Specifically, in measuring basis and other each pier studs Place left and right respectively sets 2 prisms, while embedded 2 have the survey station point of observation pier and forced centering instrument as monitoring criteria point, 2 More than 1/,250,000, the horizontal displacement to bridge on survey station point is monitored relative accuracy between survey station point;
With the fracture width of the frequency monitoring bridge of every 2 hours 1 time, first occur depicting crack at the position in crack on bridge Distribution and and mark out the characteristic point position in crack, and measure the average crack width in these cracks;Then 5 width are selected The standard specimen crack that maximum crack is monitored as construction period, measures this 5 length in standard specimen crack, width and depth.
Preferably, the monitoring result according to work progress calculate the accumulative settling amount of bridge, accumulative horizontal displacement, The rate of settling and horizontal displacement-pattern;When the rate of settling is more than 0.3mm/d, or horizontal displacement rate of change is more than 0.3mm/d, or Accumulative settling amount is more than 6mm, or accumulative horizontal displacement is more than 2mm, should encrypt monitoring frequency;
When the rate of settling or horizontal displacement-pattern are more than 0.3mm/d for three days on end, or accumulative settling amount is more than 10mm, or tired Meter horizontal displacement is more than 3mm, should immediately stop construction, improves monitoring frequency, and take measures to prevent pier stud from continuing water Prosposition is moved or settled;
When sedimentation produces mutation to be more than 5mm/d, or horizontal displacement produces mutation to be more than 2mm/d, or accumulative settling amount exceedes 20mm, or accumulative horizontal displacement is more than 5mm, should immediately stop construction, and take measures to mitigate bridge load.
Preferably, during step (5) excavation pit, when digging to the position for having underground water, in foundation ditch Vicinity construct out sump, and having gutter of being constructed out between the position of underground water and sump, introduce the water into sump; Wherein, the bottom width in gutter is 20cm, and the ditch depth in gutter is 20cm, and the sump sets one, the collection at interval of 20m The length and width of well and respectively 30cm, 30cm and 40cm high;When Local topography can not set gutter and sump, use Water pumper carries out draining.
Preferably, the length and width of auxiliary cushion cap and respectively 12.45m, 0.51m and 1.3m high in step (5), the The strength grade of two cushion caps is C40.
Preferably, in step (3) steel-pipe pile work progress, steel-pipe pile is first squeezed into by ground using vibration hammer, when When driving depth is to 8-9m, steel-pipe pile is continued using reaction frame be pressed into ground.
A kind of servicing unit for preventing overpass from settling provided by the present invention and its construction method, auxiliary cushion cap is located at In the pile foundation of overpass, and the outside of the former cushion cap of overpass is coated on, the pier stud of overpass is through auxiliary cushion cap and grafting To in former cushion cap so that the lower end of pier stud more consolidates, and is prevented from bridge and settles, additionally, on the ground and positioned at pier Support base is set on the outside of post, the joint chair end of support frame is connected on support base, and the beam-ends that connects of support frame is connected to bent cap At the position being connected with pier stud, can effectively prevent bridge from laterally offset occurring, further prevent the differential settlement of bridge Continue to increase.
Brief description of the drawings
Fig. 1 is a kind of structural representation of the servicing unit for preventing overpass from settling of the embodiment of the present invention;
Fig. 2 is the structural representation of the support frame of the embodiment of the present invention;
Fig. 3 is a kind of flow chart of the construction method of the servicing unit for preventing overpass from settling in the embodiment of the present invention;
Fig. 4 is the structural representation of steel pipe T beam support systems in the embodiment of the present invention.
Wherein, 1, bent cap;2nd, cushion cap is aided in;3rd, pier stud;4th, lateral Displacement support member, 41, support base;411st, branch support group Plinth;412nd, limit base;4121st, barricade;4122nd, ruggedized construction;42nd, support frame;421st, the first support tube;422nd, the second support Pipe;423rd, the 3rd support tube;5th, pile foundation;6th, steel-pipe pile component;61st, steel-pipe pile;62nd, connector;63rd, bridging;7th, original is held Platform.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiment of the invention is described in further detail.Hereinafter implement Example is not limited to the scope of the present invention for illustrating the present invention.
As shown in figure 1, a kind of servicing unit for preventing overpass from settling of the preferred embodiment of the present invention, it includes that auxiliary is held Platform 2 and lateral Displacement support member 4, auxiliary cushion cap 2 are located in the pile foundation 5 of overpass, and be coated on the former cushion cap 7 of overpass Outside, the pier stud 3 of overpass passes through auxiliary cushion cap 2 and is plugged in former cushion cap 7 so that the lower end of pier stud 3 more consolidates, can Prevent bridge from settling;Lateral Displacement support member 4 includes support base 41 and support frame 42, and support base 41 is located on ground and position In the outside of pier stud 3, the joint chair end of support frame 42 is connected on support base 41, and the beam-ends that connects of support frame 42 is connected to overpass At the position that bent cap 1 is connected with pier stud 3, in use, lateral Displacement support member 4 can effectively prevent bridge from side occurring To skew, the differential settlement of bridge is further prevented to continue to increase.
In order that support frame 42 can effectively prevent bridge laterally offset, support frame 42 is inclined relative to level ground and set Put, and support frame 42, pier stud 3 and ground form triangular structure, to cause that supporting construction is more consolidated, it is preferred that in support The beam-ends that connects of frame 42 is provided with the first backing plate, and support frame 42 is connected at the position that bent cap 1 is connected with pier stud 3 by the first backing plate.
As shown in Fig. 2 support frame 42 includes the first support tube 421, the second support tube 422 and the 3rd support tube 423, first The support tube 422 of support tube 421 and second is set in angle, the first support tube 421 connect beam-ends and the second support tube 422 connect beam The joint chair end interval setting of end connection, the joint chair end of the first support tube 421 and the second support tube 422, the 3rd support tube 423 is connected Between the first support tube 421 and the second support tube 422, the first support tube 421, the second support tube 422 and the 3rd support tube 423 Composition " A " character form structure so that support frame 42 itself is more consolidated, improves the ability of resistance bridge laterally offset.Preferably, The material that first support tube, the second support tube and the 3rd support tube are used for steel pipe, specifically, be the seamless steel pipes of Φ 325 × 12. Further, it is also possible to set other support tubes between pier stud 3 and support frame 42, one end of other support tubes is connected to pier stud 3 On, the other end is connected on support frame 42, to strengthen the steadiness of lateral Displacement support member 4.
In order to improve the intensity of support base 41, support base 41 includes brace foundation 411 and limit base 412, brace foundation 411 For support limit seat 412, brace foundation 411 can be on ground, it is also possible to is embedded in subsurface, limit base 412 is located at On brace foundation 411, the joint chair end of support frame 42 is connected on limit base 412, specifically, limit base 412 includes barricade 4121 With ruggedized construction 4122, ruggedized construction 4122 is located at the outside of barricade 4121, to improve the resistance lateral force of barricade 4121 Ability, the inner side of barricade 4121 is provided with the second backing plate, and the joint chair end of support frame 42 is connected to barricade 4121 by the second backing plate Inner side.
As shown in figure 3, preventing the construction method of the servicing unit of overpass sedimentation from comprising the following steps:
(1) girder falling temporary support structure is installed
Temporary support component is installed in the bridge pier both sides under the girder of overpass or Bailey bracket is faced as girder falling When supporting construction, specifically, the bottom of temporary support component or Bailey bracket to be fixed on the top of the former cushion cap 7 of overpass, and The top of temporary support component or Bailey bracket is acted against the bottom of girder.
Temporary support component includes temporary support seat, many support columns, crossbeam, Cross stay and bracing elements, temporary support seat Located at the top of the former cushion cap 7 of overpass, the bottom of many support columns is connected on temporary support seat, and many tops of support column End is in the same plane, and the bottom of crossbeam is connected to many tops of support column, and the top of crossbeam acts against the bottom of girder End, Cross stay is connected between adjacent support column, and vertical with support column, and bracing element is connected between adjacent support column, and It is spaced with Cross stay, to improve the stability of supporting construction.In order that temporary support component has enough strength supports, support column Using the steel pipes of φ 480 × 10, crossbeam uses I-shaped gooseneck, specially I25B models I-steel, and size is φ 219 × 10, is faced When support base formed using 10mm and 18mm steel plate combinations, model I36B, Cross stay and bracing element are using [16 channel-section steels, and horizontal Support member uses welding to be connected on support column with bracing element.
(2) lateral limited support part 4 is installed
In support base 41 of being constructed out on the ground on the outside of pier stud 3, the joint chair end of support frame 42 is fixed on support base On 41, and the beam-ends that connects of support frame 41 is connected at the position that bent cap 1 is connected with pier stud 3.
Specifically, the step of construction lateral Displacement support member 4 include:
First backing plate is fixed at the position that bent cap 1 is connected with pier stud 3, and is noted between the first backing plate and the position Enter adhesive, it is preferred that using the first steel plate as the first backing plate, first passing through the first high-strength bolt will be arranged on the first steel plate At the position that bent cap 1 is connected with pier stud 3, steel bonding glue is injected between concrete then at the position and the first steel plate;
Second backing plate is fixed on the inner side of barricade, and adhesive is injected between the second backing plate and barricade, it is preferred that Using the second steel plate as the second backing plate, first pass through the second high-strength bolt and the second steel plate be installed on the inner side of barricade 4121, And steel bonding glue is injected between the concrete of the second steel plate and barricade 4121;
The beam-ends pretension that connects of support frame 42 is supported on the first backing plate, and the joint chair end pretension of support frame 42 is supported to On second backing plate, then the beam-ends that connects of support frame 42 is welded on the first backing plate, and the joint chair end of support frame 42 is welded to On second backing plate.
(3) steel pipe T beam support systems are installed
As shown in figure 4, install steel pipe T beam support systems comprising the following steps:
First many steel-pipe piles 61 are squeezed into compartment of terrain on the ground between adjacent pier stud 3, and the quantity of steel-pipe pile 61 is 3~6 Root, the bottom of bent cap 1 is extended close to by the upper end of steel-pipe pile 61, and sets connector 62 in the upper end of steel-pipe pile 61, specifically, According to force analysis, the connector 62 of use includes direction across bridge I-beam, steel plate and vertical bridge to I-beam, by direction across bridge I-beam The top of steel-pipe pile 61 is located at, and steel plate is set at the top of direction across bridge I-beam, then connect vertical bridge to the lower end of I-beam It is connected on steel plate, and by vertical bridge to the bottom that bent cap 1 is withstood at the top of I-beam;Then set between adjacent steel-pipe pile 61 Skewed horizontal load part, it is preferred that be located between adjacent steel-pipe pile 61 using bridging 63.
Many steel are squeezed on the ground of side then again on the ground on the periphery of pier stud 3 or opposite with other pier studs 3 Pile tube, likewise, the upper end of these steel-pipe piles to be extended close to the bottom of bent cap 1, is then located at steel by direction across bridge I-beam The top of pile tube 61, and steel plate is set at the top of direction across bridge I-beam, vertical bridge is then connected to steel to the lower end of I-beam On plate, and by vertical bridge to the bottom that bent cap 1 is withstood at the top of I-beam;Then scissors is set between adjacent steel-pipe pile 61 Support.
In steel-pipe pile work progress, cause construction space not enough in order to avoid being limited by bridge base space, first use and shake Steel-pipe pile is squeezed into ground by hammer, when driving depth is to 8-9m, continues steel-pipe pile using reaction frame to be pressed into ground, and reaction frame is needed Carry out forcing checking, it is ensured that anti-overturning energy of the internal force, bearing anchor force and concrete foundation of reversed beam etc. meets specification will Ask.
Because in work progress, gene vibrations in ground are likely to result in bridge foundation local subsidence or skew, therefore in construction During steel-pipe pile, with the sedimentation of the frequency monitoring bridge of every 2 hours 1 time;Specifically, first choosing a pier stud as measurement base Standard, then in 2 monitoring points of each side setting of the measuring basis left and right sides and other each pier studs, in distance construction Datum mark is set in the range of 10~20m of region, is measured by the technical requirements of second grade leveling, specifically, using LeicaN3 essences Quasi- spirit level and indium watt chi are measured;
With the horizontal displacement of the frequency monitoring bridge of every 2 hours 1 time;Specifically, in measuring basis and other each pier studs Place left and right respectively sets 2 prisms, while embedded 2 have the survey station point of observation pier and forced centering instrument as monitoring criteria point, 2 More than 1/,250,000, the horizontal displacement to bridge on survey station point is monitored relative accuracy between survey station point, specifically, surveying Measured using total powerstation and its supporting prism on website;
With the fracture width of the frequency monitoring bridge of every 2 hours 1 time, first occur depicting crack at the position in crack on bridge Distribution and and mark out the characteristic point position in crack, and measure the average crack width in these cracks;Then 5 width are selected The standard specimen crack that maximum crack is monitored as construction period, measures this 5 length in standard specimen crack, width and depth, has Body, width is measured using Si Weier crack observers or scale microscope, it is true to be aided with core pulling detection using ultrasonic wave detector Depthkeeping degree.
Monitoring result according to work progress calculates the accumulative settling amount of bridge, accumulative horizontal displacement, the rate of settling and water Flat rate of displacement;When the rate of settling is big more than 0.3mm/d, or accumulative settling amount more than 0.3mm/d, or horizontal displacement rate of change It is more than 2mm in 6mm, or accumulative horizontal displacement, monitoring frequency should be encrypted;
When the rate of settling or horizontal displacement-pattern are more than 0.3mm/d for three days on end, or accumulative settling amount is more than 10mm, or tired Meter horizontal displacement is more than 3mm, should immediately stop construction, improves monitoring frequency, and take measures to prevent pier stud from continuing water Prosposition is moved or settled;
When sedimentation produces mutation to be more than 5mm/d, or horizontal displacement produces mutation to be more than 2mm/d, or accumulative settling amount exceedes 20mm, or accumulative horizontal displacement is more than 5mm, should immediately stop construction, and take measures to mitigate bridge load, such as to be handed over Siphunculus system.
(4) girder falling temporary support structure is removed
The temporary support at bent cap bottom is removed, and the larger block concrete produced during by steel pipe pile driving construction carries out without friction cutting Cut piecemeal, then demolition reduction will be carried out outside the concrete handling after cutting to bridge, specifically, using core pulling bore after dicing it is mixed Hole for hoist is bored on solidifying soil block, job site is left in then handling.
(5) construction auxiliary cushion cap 2
The foundation ditch that construction aids in cushion cap 2 is excavated out on the ground of the top of pile foundation 5 first, it is ensured that the side slope and water of foundation ditch The angle of plane is in 45 degree, until excavate to the former upper surface of cushion cap 7 spilling more than 30cm;In digging process, first slightly dug, Specifically, can slightly be dug using heavy-duty machinery, thick digging after 20~30cm, is dug, tool to more than the bottom absolute altitude of design hole using essence Body, dug by artificial essence;After excavation is finished, foundation ditch surfacing is overhauled;
During excavation pit, when digging to the position for having underground water, constructed out sump in the vicinity of foundation ditch, and There is gutter of being constructed out between the position of underground water and sump, introduce the water into sump;Wherein, the bottom width in gutter is 20cm, the ditch depth in gutter is 20cm, and the sump sets one at interval of 20m, and the length and width and height of sump are respectively 30cm, 30cm and 40cm;When Local topography can not set gutter and sump, draining is carried out using water pumper.
Foundation ditch setting-out is carried out, according to auxiliary cushion cap 2 and foundation ditch baseplane size, foundation ditch baseplane contour line is surveyed and is set to original On ground;Section survey is carried out along 4 edge directions of the foundation ditch Planar Contours on ground;It is determined that excavating the depth of skirt piles, press The width of side slope is determined according to lower digging depth, center pile layout will be excavated to ground, and arrangement mark in this place, specifically, at this Place sprinkles lime;Then carry out digging Stake head handling and draining, after the completion of draining, the assembling reinforcement in foundation ditch, before colligation, to foundation ditch Cleaned, cover to reinforcement uses rubber blanket, specifically, the thickness of protective layer is not less than 50mm, and protected by quincuncial arrangement Sheath;In polylith template surface brushing mould oil, and the installation form in foundation ditch, sponge strip is used in the joint of adjacent forms Or two-sided tape is blocked, with mortar leakage prevention, and holding template surface is smooth, and inner side line style is straight;Template and bracing reinforcement are firm Afterwards, the dirt on cleaning template, reinforcing bar, then concrete is poured into a mould, after concrete setting, conserved and form removal, finally backfill base Hole, the auxiliary construction of cushion cap 2 is completed.Preferably, the length and width of auxiliary cushion cap 2 and respectively 12.45m, 0.51m and 1.3m high, auxiliary The strength grade of cushion cap 2 is C40.
To sum up, a kind of servicing unit for preventing overpass from settling provided by the present invention and its construction method, auxiliary is held Platform is located in the pile foundation of overpass, and is coated on the outside of the former cushion cap of overpass, and the pier stud of overpass passes through auxiliary cushion cap And be plugged into former cushion cap so that pier stud lower end more consolidates, and is prevented from bridge and settles, additionally, on the ground and position Support base is set on the outside of pier stud, the joint chair end of support frame is connected on support base, and the beam-ends that connects of support frame is connected to At the position that bent cap is connected with pier stud, can effectively prevent bridge from laterally offset occurring, further prevent the uneven of bridge Sedimentation continues to increase.
In work progress, avoided to bridge using temporary support structure, steel pipe T beams support system and set of monitoring method Girder construction causes to damage, and is conducive to construction safety.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, on the premise of the technology of the present invention principle is not departed from, some improvement and replacement can also be made, these improve and replace Also should be regarded as protection scope of the present invention.

Claims (13)

1. it is a kind of prevent overpass settle servicing unit, it is characterised in that including auxiliary cushion cap and lateral Displacement support member, institute Auxiliary cushion cap is stated in the pile foundation of overpass, and is coated on the outside of the former cushion cap of overpass, the pier stud of overpass is passed through The auxiliary cushion cap;The lateral Displacement support member includes support base and support frame, and the support base is on ground and is located at The outside of pier stud, the joint chair end of support frame as described above is connected on the support base, support frame as described above connect beam-ends be connected to it is overhead At the position that the bent cap of bridge is connected with pier stud.
2. the servicing unit for preventing overpass from settling as claimed in claim 1, it is characterised in that support frame as described above is relative to water Plane earth is obliquely installed, and the beam-ends that connects of support frame as described above is provided with the first backing plate, and support frame as described above is connected by first backing plate At the position being connected with pier stud to bent cap;Support frame as described above, pier stud and ground form triangular structure.
3. the servicing unit for preventing overpass from settling as claimed in claim 1, it is characterised in that support frame as described above includes first Support tube, the second support tube and the 3rd support tube, first support tube and the second support tube are set in angle, described first The beam-ends that connects of stay tube is connected with the beam-ends that connects of the second support tube, the joint chair end of first support tube and the joint chair of the second support tube End interval setting, the 3rd support tube is connected between first support tube and the second support tube.
4. the servicing unit for preventing overpass from settling as claimed in claim 1, it is characterised in that the support base includes support Basis and limit base, the brace foundation is on ground, or is embedded in subsurface, and the limit base is located at the brace foundation On, the joint chair end of support frame as described above is connected on the limit base.
5. the servicing unit for preventing overpass from settling as claimed in claim 4, it is characterised in that the limit base includes barricade And ruggedized construction, the ruggedized construction located at the barricade outside, be provided with the second backing plate, support frame as described above on the inside of institute's barricade Joint chair end the inner side of the barricade is connected to by second backing plate.
6. it is a kind of as described in any one of claim 1 to 5 prevent overpass settle servicing unit construction method, its feature It is to comprise the following steps:
(1) girder falling temporary support structure is installed
Temporary support component is installed in the bridge pier both sides under the girder of overpass or Bailey bracket is propped up temporarily as girder falling Support structure, specifically, the bottom of temporary support component or Bailey bracket is fixed on the top of the former cushion cap of overpass, and will be interim The top of support component or Bailey bracket acts against the bottom of girder.
(2) lateral limited support part is installed
Support base is being set on the ground on the outside of pier stud, the joint chair end of support frame is being fixed on support base, and will support The beam-ends that connects of frame is connected at the position that bent cap is connected with pier stud.
(3) steel pipe T beam support systems are installed
First many steel-pipe piles are squeezed into compartment of terrain on the ground between adjacent pier stud, are then squeezed on the ground on pier stud periphery again Many steel-pipe piles;
The upper end of these steel-pipe piles is extended close into bent cap bottom, and connector, the connector are set in the upper end of steel-pipe pile Including direction across bridge I-beam, steel plate and vertical bridge to I-beam, the direction across bridge I-beam is located at the top of the steel-pipe pile, and Steel plate is set at the top of direction across bridge I-beam, then the vertical bridge is connected on the steel plate to the lower end of I-beam, and By vertical bridge to the bent cap bottom is withstood at the top of I-beam, bridging then is set between adjacent steel-pipe pile;
(4) girder falling temporary support structure is removed
(5) construction auxiliary cushion cap
The foundation ditch that construction aids in cushion cap is excavated out on ground first above pile foundation, it is ensured that the side slope of foundation ditch and horizontal plane Angle is in 45 degree, until excavation spills more than 30cm to the former cushion cap upper surface of overpass;In digging process, first carry out thick Dig, thick digging after 20~30cm, is dug to more than the bottom absolute altitude of design hole using essence;After excavation is finished, foundation ditch surfacing is overhauled;
Foundation ditch setting-out is carried out, according to auxiliary cushion cap and foundation ditch baseplane size, foundation ditch baseplane contour line is surveyed and is set to original ground On;Section survey is carried out along 4 edge directions of the foundation ditch Planar Contours on ground;It is determined that the depth of skirt piles is excavated, under The width that depth determines slope is dug, center pile layout will be excavated to ground, and arrangement mark in this place;Carry out chisel Stake head handling with Draining, after the completion of draining, the assembling reinforcement in foundation ditch, cover to reinforcement uses rubber blanket;In the polylith template surface brushing demoulding Oil, and the installation form in foundation ditch, are blocked in the joint of adjacent forms using sponge strip or two-sided tape;
Dirt on cleaning template, reinforcing bar, then concrete is poured into a mould, after concrete setting, conserved and form removal, finally backfill base Hole, auxiliary bearing platform construction is completed.
7. the construction method of the servicing unit of overpass sedimentation is prevented as claimed in claim 6, it is characterised in that step (2) The step of middle construction lateral Displacement support member, includes:
First backing plate is fixed at the position that bent cap is connected with pier stud, and gluing is injected between the first backing plate and the position Agent;
Second backing plate is fixed on the inner side of barricade, and adhesive is injected between the second backing plate and barricade;
The beam-ends pretension that connects of support frame is supported on the first backing plate, and the joint chair end pretension of support frame is supported into the second backing plate On, then the beam-ends that connects of support frame is welded on the first backing plate, and the joint chair end of support frame is welded on the second backing plate.
8. the construction method of the servicing unit of overpass sedimentation is prevented as claimed in claim 6, it is characterised in that step (1) Middle temporary support component includes temporary support seat, many support columns, crossbeam, Cross stay and bracing elements, and the temporary support seat sets In the top of the former cushion cap of overpass, the bottom of many support columns is connected on the temporary support seat, and described in many The top of support column is in the same plane, and the bottom of the crossbeam is connected to many tops of the support column, and the horizontal stroke The top of beam acts against the bottom of girder, and the Cross stay is connected between adjacent support column, and vertical with the support column, The bracing element is connected between adjacent support column, and is spaced with the Cross stay.
9. the construction method of the servicing unit of overpass sedimentation is prevented as claimed in claim 6, it is characterised in that in step (3) during construction steel pile tube, with the sedimentation of the frequency monitoring bridge of every 2 hours 1 time;Specifically, first choose a pier stud making It is measuring basis, then in 2 monitoring points of each side setting of the measuring basis left and right sides and other each pier studs, Datum mark is set in the range of 10~20m of distance construction region, is measured by the technical requirements of second grade leveling;
With the horizontal displacement of the frequency monitoring bridge of every 2 hours 1 time;Specifically, left at measuring basis and other each pier studs The right side respectively sets 2 prisms, while embedded 2 have the survey station point of observation pier and forced centering instrument as monitoring criteria point, 2 survey stations More than 1/,250,000, the horizontal displacement to bridge on survey station point is monitored relative accuracy between point;
With the fracture width of the frequency monitoring bridge of every 2 hours 1 time, first occur depicting fractue spacing at the position in crack on bridge And and mark out the characteristic point position in crack, and measure the average crack width in these cracks;Then 5 width maximums are selected The standard specimen crack monitored as construction period of crack, measure this 5 length in standard specimen crack, width and depth.
10. the construction method of the as claimed in claim 9 servicing unit for preventing overpass from settling, it is characterised in that according to applying The monitoring result of work process calculates the accumulative settling amount of bridge, accumulative horizontal displacement, the rate of settling and horizontal displacement-pattern;When heavy Reduction of speed rate is more than 0.3mm/d, or horizontal displacement rate of change is more than 0.3mm/d, or accumulative settling amount is more than 6mm, or accumulative water Prosposition is moved and is more than 2mm, should encrypt monitoring frequency;
When the rate of settling or horizontal displacement-pattern are more than 0.3mm/d for three days on end, or accumulative settling amount is more than 10mm, or accumulative water Prosposition is moved and is more than 3mm, should immediately stop construction, improves monitoring frequency, and take measures to prevent pier stud from continuing occurred level position Move or settle;
When sedimentation produces mutation to be more than 5mm/d, or horizontal displacement produces mutation to be more than 2mm/d, or accumulative settling amount is more than 20mm, Or accumulative horizontal displacement is more than 5mm, should immediately stop construction, and take measures to mitigate bridge load.
The construction method of 11. servicing units for preventing overpass from settling as claimed in claim 6, it is characterised in that step (5) During excavation pit, when digging to the position for having underground water, constructed out sump in the vicinity of foundation ditch, and having underground water Position and sump between construct out gutter, introduce the water into sump;Wherein, the bottom width in gutter is 20cm, gutter Ditch depth be 20cm, the sump sets one at interval of 20m, the length and width of the sump and high is respectively 30cm, 30cm And 40cm;When Local topography can not set gutter and sump, draining is carried out using water pumper.
The construction method of 12. servicing units for preventing overpass from settling as claimed in claim 6, it is characterised in that step (5) The length and width of middle auxiliary cushion cap and respectively 12.45m, 0.51m and 1.3m high, the strength grade of the second cushion cap is C40.
The construction method of 13. servicing units for preventing overpass from settling as claimed in claim 6, it is characterised in that in step (3) in steel-pipe pile work progress, steel-pipe pile is first squeezed into by ground using vibration hammer, when driving depth is to 8-9m, using reaction frame Steel-pipe pile is continued to be pressed into ground.
CN201710170403.4A 2017-03-21 2017-03-21 The auxiliary device and its construction method for preventing overpass from settling Active CN106869038B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710170403.4A CN106869038B (en) 2017-03-21 2017-03-21 The auxiliary device and its construction method for preventing overpass from settling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710170403.4A CN106869038B (en) 2017-03-21 2017-03-21 The auxiliary device and its construction method for preventing overpass from settling

Publications (2)

Publication Number Publication Date
CN106869038A true CN106869038A (en) 2017-06-20
CN106869038B CN106869038B (en) 2019-06-14

Family

ID=59172719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710170403.4A Active CN106869038B (en) 2017-03-21 2017-03-21 The auxiliary device and its construction method for preventing overpass from settling

Country Status (1)

Country Link
CN (1) CN106869038B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110619177A (en) * 2019-09-18 2019-12-27 广州大学 Automatic identification method and device for structure operation modal parameters and storage medium
CN111287069A (en) * 2020-02-23 2020-06-16 郑州市公路工程公司 Connecting member for overcoming non-uniform settlement of bridge
CN114737626A (en) * 2022-04-15 2022-07-12 中铁十六局集团路桥工程有限公司 Foundation reinforcement construction method during bridge operation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101858055A (en) * 2010-06-04 2010-10-13 中交第一航务工程局有限公司 Setting steel pipe bracket support system of cover beam and construction method thereof
CN103147402A (en) * 2013-03-27 2013-06-12 上海建工集团股份有限公司 Support device for constructing continuous box girder bridge and elevation adjusting method
CN103981816A (en) * 2014-04-15 2014-08-13 河南省公路工程局集团有限公司 Construction method for underpinning of overpass framework pier columns
CN105155431A (en) * 2015-10-22 2015-12-16 河南省公路工程局集团有限公司 Rapid repair method for three-stand-column structure bridge with damaged lateral stand columns and undamaged beam and slab structure
KR20160085086A (en) * 2015-01-07 2016-07-15 주식회사 포스코건설 Settlement adjusting apparatus and settlement adjusting maintenance method for earthwork connecting portion

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101858055A (en) * 2010-06-04 2010-10-13 中交第一航务工程局有限公司 Setting steel pipe bracket support system of cover beam and construction method thereof
CN103147402A (en) * 2013-03-27 2013-06-12 上海建工集团股份有限公司 Support device for constructing continuous box girder bridge and elevation adjusting method
CN103981816A (en) * 2014-04-15 2014-08-13 河南省公路工程局集团有限公司 Construction method for underpinning of overpass framework pier columns
KR20160085086A (en) * 2015-01-07 2016-07-15 주식회사 포스코건설 Settlement adjusting apparatus and settlement adjusting maintenance method for earthwork connecting portion
CN105155431A (en) * 2015-10-22 2015-12-16 河南省公路工程局集团有限公司 Rapid repair method for three-stand-column structure bridge with damaged lateral stand columns and undamaged beam and slab structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110619177A (en) * 2019-09-18 2019-12-27 广州大学 Automatic identification method and device for structure operation modal parameters and storage medium
CN110619177B (en) * 2019-09-18 2023-03-31 广州大学 Automatic identification method and device for structure operation modal parameters and storage medium
CN111287069A (en) * 2020-02-23 2020-06-16 郑州市公路工程公司 Connecting member for overcoming non-uniform settlement of bridge
CN114737626A (en) * 2022-04-15 2022-07-12 中铁十六局集团路桥工程有限公司 Foundation reinforcement construction method during bridge operation

Also Published As

Publication number Publication date
CN106869038B (en) 2019-06-14

Similar Documents

Publication Publication Date Title
Finno et al. Performance of a stiff support system in soft clay
CN1837506B (en) Construction method for excavating box-shape structure over an operating tunnel
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN106088127A (en) Open caisson construction method
CN105953078B (en) The protective device of high-pressure gas pipeline and guard method
CN110485429A (en) A kind of prestressing force fashioned iron assembled combination inner support construction method
CN106930319A (en) A kind of high slope framed revetment and its construction method
CN110258582B (en) Inclined support foundation pit supporting structure based on steel pipe pile and Lassen steel plate and construction method
CN204738556U (en) A device for landmark is whole to shift
CN106869038B (en) The auxiliary device and its construction method for preventing overpass from settling
CN112064751A (en) Deep groove construction method for drainage pipeline
CN115199288A (en) Construction method for mud-water balanced circular jacking pipe penetrating railway roadbed stratum downwards
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
Powderham The observational method-application through progressive modification
CN113216215A (en) Deep groove support reverse construction method in complex environment
CN108625368A (en) A kind of Deep Thick Soft Ground Area Rigid Long-Short-Pile Composite Foundation construction method
KR20210078779A (en) Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same
KR20210055980A (en) Underground roadway by top-down method using steel continuous wall in the earth without traffic control and temporary road and method for constructing the same
CN114482014B (en) Construction method for hammering pile sinking of precast pile in deep foundation pit in offshore ultra-thick silt region
CN113529830B (en) Isolation-underpinning combined reinforcement structure of adjacent building of shallow tunnel and construction process thereof
CN210621709U (en) Inclined support foundation pit supporting structure based on steel pipe pile and Larsen steel plate
Evans et al. Modified sheet pile abutments for low-volume road bridges
Stallings Implementation of Geosynthetic Reinforced Soil-Integrated Bridge System (GRS-IBS) Technology in Alabama
KR20210055981A (en) Underground roadway using steel continuous wall in the earth with minimum traffic control in constructing by top-down method and method for constructing the same
CN111455979A (en) PHC pile construction process for bottom mud treatment plant

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant