CN110273576A - Rail member and its construction method - Google Patents
Rail member and its construction method Download PDFInfo
- Publication number
- CN110273576A CN110273576A CN201910488277.6A CN201910488277A CN110273576A CN 110273576 A CN110273576 A CN 110273576A CN 201910488277 A CN201910488277 A CN 201910488277A CN 110273576 A CN110273576 A CN 110273576A
- Authority
- CN
- China
- Prior art keywords
- reinforcing bar
- connection
- pedestal
- connection reinforcing
- lamp holder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 8
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 78
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 44
- 238000005452 bending Methods 0.000 claims abstract description 13
- 238000003466 welding Methods 0.000 claims abstract description 13
- 239000000725 suspension Substances 0.000 claims abstract description 8
- 230000002787 reinforcement Effects 0.000 claims abstract description 5
- 229910001335 Galvanized steel Inorganic materials 0.000 claims description 17
- 239000008397 galvanized steel Substances 0.000 claims description 17
- 239000004567 concrete Substances 0.000 claims description 14
- 239000011248 coating agent Substances 0.000 claims description 12
- 238000000576 coating method Methods 0.000 claims description 12
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 12
- 229910000831 Steel Inorganic materials 0.000 claims description 9
- 239000010959 steel Substances 0.000 claims description 9
- 239000004576 sand Substances 0.000 claims description 8
- 239000000463 material Substances 0.000 claims description 7
- 239000011398 Portland cement Substances 0.000 claims description 6
- 238000004078 waterproofing Methods 0.000 claims description 6
- 150000001732 carboxylic acid derivatives Chemical class 0.000 claims description 3
- 239000003638 chemical reducing agent Substances 0.000 claims description 3
- 239000011178 precast concrete Substances 0.000 claims description 3
- 210000003205 muscle Anatomy 0.000 claims description 2
- 238000009434 installation Methods 0.000 description 12
- 241001465382 Physalis alkekengi Species 0.000 description 11
- 230000035882 stress Effects 0.000 description 9
- 238000010586 diagram Methods 0.000 description 8
- 239000004744 fabric Substances 0.000 description 3
- BPQQTUXANYXVAA-UHFFFAOYSA-N Orthosilicate Chemical compound [O-][Si]([O-])([O-])[O-] BPQQTUXANYXVAA-UHFFFAOYSA-N 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 239000002253 acid Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000004643 material aging Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000035699 permeability Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B1/00—Producing shaped prefabricated articles from the material
- B28B1/14—Producing shaped prefabricated articles from the material by simple casting, the material being neither forcibly fed nor positively compacted
-
- C—CHEMISTRY; METALLURGY
- C04—CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
- C04B—LIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
- C04B28/00—Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
- C04B28/02—Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
- C04B28/04—Portland cements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F11/00—Stairways, ramps, or like structures; Balustrades; Handrails
- E04F11/18—Balustrades; Handrails
- E04F11/181—Balustrades
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H17/00—Fencing, e.g. fences, enclosures, corrals
- E04H17/14—Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H17/00—Fencing, e.g. fences, enclosures, corrals
- E04H17/14—Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
- E04H17/20—Posts therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H17/00—Fencing, e.g. fences, enclosures, corrals
- E04H17/14—Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
- E04H17/20—Posts therefor
- E04H17/22—Anchoring means therefor, e.g. specially-shaped parts entering the ground; Struts or the like
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F21—LIGHTING
- F21V—FUNCTIONAL FEATURES OR DETAILS OF LIGHTING DEVICES OR SYSTEMS THEREOF; STRUCTURAL COMBINATIONS OF LIGHTING DEVICES WITH OTHER ARTICLES, NOT OTHERWISE PROVIDED FOR
- F21V33/00—Structural combinations of lighting devices with other articles, not otherwise provided for
- F21V33/006—General building constructions or finishing work for buildings, e.g. roofs, gutters, stairs or floors; Garden equipment; Sunshades or parasols
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F11/00—Stairways, ramps, or like structures; Balustrades; Handrails
- E04F11/18—Balustrades; Handrails
- E04F2011/1868—Miscellaneous features of handrails not otherwise provided for
- E04F2011/1872—Miscellaneous features of handrails not otherwise provided for illuminated
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Inorganic Chemistry (AREA)
- Physics & Mathematics (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Materials Engineering (AREA)
- Organic Chemistry (AREA)
- Manufacturing & Machinery (AREA)
- Electromagnetism (AREA)
- General Engineering & Computer Science (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of rail members, including pedestal, the body of rod set on the pedestal side and the steelframe inside pedestal and the body of rod, the top of the pedestal is equipped with lamp holder embedded hole, pvc pipe is embedded in the pedestal, one end of the pvc pipe is connected to the lamp holder embedded hole, and the other end extends from the side wall of pedestal;The top of the body of rod is equipped with joint bar preformed hole and groove, is preset with lifting built-in fitting in the groove;The bottom of the rod piece is equipped with demoulding suspension hook;The steelframe includes horizontally disposed more first connections reinforcing bar, more second connection reinforcing bars and the connection reinforcing bar of Duo Gen the 4th, more third connection reinforcing bars are evenly distributed on the first connection reinforcing bar, four angles of the third connection reinforcing bar are in the first connection reinforcement welding;The second connection reinforcing bar and the 4th connection equal bending of reinforcing bar are in rectangle.Have the advantages that be easily installed.The invention also discloses a kind of construction methods of rail member.
Description
Technical field
The present invention relates to assembled architecture technical fields, it particularly relates to a kind of rail member.
Background technique
Most of traditional rail member is all metal structure, will appear material aging or corrosion etc. after a period of use
Phenomenon, while installation and maintenance cost is larger.
Summary of the invention
To solve problems of the prior art, the present invention provides a kind of rail member, has and is easy for installation and maintenance
The advantages of.
To achieve the above object, the technical solution adopted by the present invention is that: a kind of rail member, including pedestal, be set to it is described
The top of the body of rod of base top and the steelframe inside pedestal and the body of rod, the pedestal is equipped with lamp holder embedded hole, the bottom
It is embedded with pvc pipe in seat, one end of the pvc pipe is connected to the lamp holder embedded hole, and the other end extends from the side wall of pedestal;
The top of the body of rod is equipped with joint bar preformed hole and groove, is preset with lifting built-in fitting in the groove;The bottom of the rod piece
Equipped with demoulding suspension hook;
The steelframe includes horizontally disposed more first connections reinforcing bar, more second connection reinforcing bars and the connection of Duo Gen the 4th
Reinforcing bar, described first connects the third connection reinforcing bars that more bendings are evenly distributed on reinforcing bar in rectangle, and the third connects steel
Four angles of muscle are in the first connection reinforcement welding;The second connection reinforcing bar and the 4th connection equal bending of reinforcing bar are in square
Shape, the second connection reinforcement welding form cube after welding between the 4th connection reinforcing bar, cube weldering
It is connected to one end of the first connection reinforcing bar.
Rail member is poured in advance in factory, the scene of being transported to directly is installed, while being constructed in railing
Pedestal and the body of rod in setting steelframe be whole stress condition in order to further ensure rail member, for the ease of later period installation
Lamps and lanterns preset value lamp holder embedded hole at the top of the base, the pvc pipe one end being embedded in pedestal is stretched out from lamp holder embedded hole, another
End is stretched out from the side wall of pedestal, and the power supply line for installing lamps and lanterns convenient for the later period can extend out of pvc pipe, is connected with outer cloth power supply
It connects, setting joint bar preformed hole is steel pipe railing in order to facilitate the installation of, and setting groove is to lift built-in fitting in order to facilitate the installation of, is convenient for
The lifting in later period, setting demoulding suspension hook is to demould after factory pours for convenience.
Preferably, the pedestal and the body of rod are divided into 3 layers, successively include the outer waterproof for wrapping up setting from outside to inside
Layer, inner waterproofing layer and stress layer.
Setting three-decker is while exterior waterproof coating and interior anti-to be arranged in order to enable rail member overall structure is more stable
Water layer is that rail member inside carries out in order to prevent, influences service life.
Preferably, lamp holder built-in fitting is equipped in the lamp holder embedded hole, the lamp holder built-in fitting includes precast concrete
With the galvanized steel plain sheet being set at the top of the concrete embedded part, the galvanized steel plain sheet is equipped with the through-hole to match with the pvc pipe,
It is opposite on the side wall that the galvanized steel plain sheet is bonded with concrete to be equipped with J section steel plate.
It is equipped with lamp holder built-in fitting in lamp holder embedded hole, is the installation of later period lamps and lanterns for convenience;Lamp holder built-in fitting includes mixed
Solidifying soil built-in fitting and the galvanized steel plain sheet being arranged on concrete embedded part, setting galvanized steel plain sheet be in order to improve lamp holder built-in fitting by
Power.
Preferably, the top of the lamp holder built-in fitting is concordant with the top of the pedestal.
The top of lamp holder built-in fitting and the top of pedestal be concordantly for the ease of make after mounted lamp the bottom of lamps and lanterns with
The top of pedestal is concordant, keeps it more beautiful.
A kind of construction method of rail member as described above, includes the following steps:
S10, the reinforcing bar for choosing steelframe, wherein the diameter of the first connection reinforcing bar is the diameter of 8-10mm, the second connection reinforcing bar
It is 6-10mm for the diameter that the diameter that 8-10mm, third connect reinforcing bar is the connection reinforcing bar of 6-10mm and the 4th;
S20, the second connection of bending reinforcing bar, third connection reinforcing bar and the 4th connection reinforcing bar, so that the second connection reinforcing bar, third
Connecting reinforcing bar and the 4th connection reinforcing bar bending is in rectangle;
S30, each reinforcing bar of welding, form it into steelframe;
S40, the concrete material for choosing following components by weight percent ratio are mixed: intensity is not less than the silicate of 42.5 grades
Cement or 600-900 parts of ordinary portland cement;
50-60 parts of poly carboxylic acid series water reducer;
600-850 parts of middle sand river sand;
20-45 parts of inert material;
300-350 parts of water;
S50, fixed steelframe carry out concreting to pouring in mold;
S60, it is demoulded after standing prefabricated component 3-5 days.
Preferably, which further includes following steps:
S70, waterproof layer processing, then the prefabricated component outer surface poured coat one layer of waterproof layer, and the waterproof layer is interior anti-
Water layer;
S80, the coating that exterior waterproof coating is carried out after standing prefabricated component 4-5 hours.
So that the overall structure of the rail member is more firm, while waterproof performance is more preferable when in use.
The beneficial effects of the present invention are:
(1) rail member is poured in advance in factory, the scene of being transported to directly is installed, while in railing structure
Setting steelframe is the whole stress condition in order to further ensure rail member in the pedestal and the body of rod built, for the ease of later period peace
Lamps and lanterns preset value lamp holder embedded hole at the top of the base is filled, the pvc pipe one end being embedded in pedestal is stretched out from lamp holder embedded hole, separately
One end is stretched out from the side wall of pedestal, and the power supply line for installing lamps and lanterns convenient for the later period can extend out of pvc pipe, is connected with outer cloth power supply
It connects, setting joint bar preformed hole is steel pipe railing in order to facilitate the installation of, and setting groove is to lift built-in fitting in order to facilitate the installation of, is convenient for
The lifting in later period, setting demoulding suspension hook is to demould after factory pours for convenience.
(2) setting three-decker be in order to enable rail member overall structure is more stable, while be arranged exterior waterproof coating and
Inner waterproofing layer is that rail member inside carries out in order to prevent, influences service life.
(3) it is equipped with lamp holder built-in fitting in lamp holder embedded hole, is the installation of later period lamps and lanterns for convenience;Lamp holder built-in fitting includes
Concrete embedded part and the galvanized steel plain sheet being arranged on concrete embedded part, setting galvanized steel plain sheet is to improve lamp holder built-in fitting
Stress.
(4) top of lamp holder built-in fitting and the top of pedestal it is concordant be bottom for the ease of making lamps and lanterns after mounted lamp
It is concordant with the top of pedestal, keep it more beautiful.
(5) make the overall structure of the rail member more firm, while waterproof performance is more preferable when in use.
Detailed description of the invention
Fig. 1 is the overlooking structure diagram of the embodiment of rail member of the present invention;
Fig. 2 is the schematic view of the front view of the embodiment of rail member of the present invention;
Fig. 3 is the backsight structural representation of the embodiment of rail member of the present invention;
Fig. 4 is the present invention looks up structural representation of the embodiment of rail member of the present invention;
Fig. 5 is the inside overall structure diagram of the embodiment of rail member of the present invention;
Fig. 6 be in Fig. 5 1-1 to structural schematic diagram;
Fig. 7 be in Fig. 5 2-2 to structural schematic diagram;
Fig. 8 be in Fig. 5 3-3 to structural schematic diagram;
Fig. 9 is the overall structure stratiform schematic diagram of the embodiment of rail member of the present invention;
Figure 10 is the galvanized steel plain sheet structural schematic diagram of the embodiment of rail member of the present invention;
Figure 11 is the structural schematic diagram of the lamp holder built-in fitting of the embodiment of rail member of the present invention;
Description of symbols:
1, pedestal;2, the body of rod;3, steelframe;1-1, lamp holder embedded hole;1-2, pvc pipe;2-1, joint bar preformed hole;It is 2-2, recessed
Slot;2-3, lifting built-in fitting;2-4, demoulding suspension hook;3-1, the first connection reinforcing bar;3-2, the second connection reinforcing bar;3-3, third connection
Reinforcing bar;3-4, the 4th connection reinforcing bar;4, exterior waterproof coating;5, inner waterproofing layer;6, stress layer;7, lamp holder built-in fitting;7-1, concrete
Built-in fitting;7-2, galvanized steel plain sheet;7-3, through-hole;7-4, J section steel plate.
Specific embodiment
The embodiment of the present invention is described in detail with reference to the accompanying drawing.
Embodiment 1:
As shown in figures 1-8, a kind of rail member, including pedestal 1, set on the body of rod 2 of 1 side of pedestal and set on pedestal
1 and the body of rod 2 inside steelframe 3, the top of the pedestal 1 is equipped with lamp holder embedded hole 1-1, is embedded with pvc pipe 1- in the pedestal 1
2, one end of the pvc pipe 1-2 is connected to the lamp holder embedded hole 1-1, and the other end extends from the side wall of pedestal 1;The bar
The top of body 2, which is equipped in joint bar preformed hole 2-1 and groove 2-2, the groove 2-2, is preset with lifting built-in fitting 2-3;The rod piece
Bottom be equipped with demoulding suspension hook 2-4;
The steelframe 3 includes horizontally disposed more first connection reinforcing bars 3-1, more second connection reinforcing bars 3-2 and Duo Gen
More bendings are evenly distributed in the third connection reinforcing bar 3- of rectangle on 4th connection reinforcing bar 3-4, the first connection reinforcing bar 3-1
3, four angles of the third connection reinforcing bar 3-3 are in the first connection reinforcing bar 3-1 welding;The second connection reinforcing bar 3-2
It is in rectangle with the 4th connection equal bending of reinforcing bar 3-4, the second connection reinforcing bar 3-2 is welded in the 4th connection reinforcing bar 3-4's
Between, and cube is formed after welding, which is welded in one end of the first connection reinforcing bar 3-1.
Rail member is poured in advance in factory, the scene of being transported to directly is installed, while being constructed in railing
Pedestal 1 and the body of rod 2 in setting steelframe 3 be whole stress condition in order to further ensure rail member, for the ease of the later period
For mounted lamp in the top preset value lamp holder embedded hole 1-1 of pedestal 1, the one end pvc pipe 1-2 being embedded in pedestal 1 is pre- from lamp holder
Buried via hole 1-1 stretches out, and the other end is stretched out from the side wall of pedestal 1, and the power supply line for installing lamps and lanterns convenient for the later period can be out of pvc pipe 1-2
Extend, connect with outer cloth power supply, setting joint bar preformed hole 2-1 is steel pipe 1-2 railing in order to facilitate the installation of, and groove 2-2 is arranged
It is to lift built-in fitting 2-3 in order to facilitate the installation of, convenient for the lifting in later period, setting demoulding suspension hook 2-4 is to pour for convenience in factory
It is demoulded after building.
Embodiment 2:
As shown in figure 9, the present embodiment is on the basis of embodiment 1, the pedestal 1 and the body of rod 2 are divided into 3 layers, according to
Secondary includes the exterior waterproof coating 4, inner waterproofing layer 5 and stress layer 6 for wrapping up setting from outside to inside.
Setting three-decker is while exterior waterproof coating 4 and interior to be arranged in order to enable rail member overall structure is more stable
Waterproof layer 5 is that rail member inside carries out in order to prevent, influences service life.
Embodiment 3:
As shown in Figure 8 and Figure 9, the present embodiment on the basis of embodiment 1, is equipped with lamp holder in the lamp holder embedded hole 1-1
Built-in fitting 7, the lamp holder built-in fitting 7 include precast concrete and the galvanized steel at the top of the concrete embedded part 7-1
Plate 7-2, the galvanized steel plain sheet 7-2 are equipped with the through-hole 7-3, the galvanized steel plain sheet 7-2 and coagulation to match with the pvc pipe 1-2
It is opposite on the side wall of soil fitting to be equipped with J section steel plate 7-4.
It is equipped with lamp holder built-in fitting 7 in lamp holder embedded hole 1-1, is the installation of later period lamps and lanterns for convenience;Lamp holder built-in fitting 7 wraps
The galvanized steel plain sheet 7-2 for including concrete embedded part 7-1 and being arranged on concrete embedded part 7-1, setting galvanized steel plain sheet 7-2 be in order to
Improve 7 stress of lamp holder built-in fitting.
Embodiment 4:
As shown in figs 1-9, the present embodiment on the basis of embodiment 1, the top of the lamp holder built-in fitting 7 and the pedestal
1 top is concordant.
It is bottom for the ease of making lamps and lanterns after mounted lamp that the top of lamp holder built-in fitting 7 is concordant with the top of pedestal 1
It is concordant with the top of pedestal 1, keep it more beautiful.
Embodiment 5:
As shown in figs 1-9, a kind of construction method of the rail member as described in embodiment 1-4 any one, including it is as follows
Step:
S10, the reinforcing bar for choosing steelframe 3, wherein the diameter of the first connection reinforcing bar 3-1 is 8-10mm, the second connection reinforcing bar 3-2
Diameter be 8-10mm, third connection reinforcing bar 3-3 diameter be 6-10mm and the 4th connection reinforcing bar 3-4 diameter be 6-10mm;
S20, the second connection of bending reinforcing bar 3-2, the third connection reinforcing bar 3-4 of connection reinforcing bar 3-3 and the 4th, so that the second connection
Reinforcing bar 3-2, the third connection reinforcing bar 3-4 bending of connection reinforcing bar 3-3 and the 4th are in rectangle;
S30, each reinforcing bar of welding, form it into steelframe 3;
S40, the concrete material for choosing following components by weight percent ratio are mixed: intensity is not less than the silicate of 42.5 grades
Cement or 600-900 parts of ordinary portland cement;
50-60 parts of poly carboxylic acid series water reducer;
600-850 parts of middle sand river sand;
20-45 parts of inert material;
300-350 parts of water;
S50, fixed steelframe 3 carry out concreting to pouring in mold;
S60, it is demoulded after standing prefabricated component 3-5 days.
Embodiment 6:
As shown in figs 1-9, for the present embodiment on the basis of embodiment 5, which further includes following steps:
S70, waterproof layer processing, then the prefabricated component outer surface poured coat one layer of waterproof layer, and the waterproof layer is interior anti-
Water layer 5;
S80, the coating that exterior waterproof coating 4 is carried out after standing prefabricated component 4-5 hours.
So that the overall structure of the rail member is more firm, while waterproof performance is more preferable when in use;Rail member
Stress layer 6 selects intensity not less than the portland cement of 42.5 grades or 600-900 parts of ordinary portland cement;Polycarboxylic-acid subtracts
50-60 parts of aqua;600-850 parts of middle sand river sand;20-45 parts of inert material;300-350 parts of water, so that rail member pours
There is better water permeability later, while two layers of waterproof layer is set, water is avoided quickly to penetrate into inside rail member, cause railing
The service life of component reduces.
A specific embodiment of the invention above described embodiment only expresses, the description thereof is more specific and detailed, but simultaneously
Limitations on the scope of the patent of the present invention therefore cannot be interpreted as.It should be pointed out that for those of ordinary skill in the art
For, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to guarantor of the invention
Protect range.
Claims (6)
1. a kind of rail member, which is characterized in that including pedestal, set on the body of rod of the base top and set on pedestal and the body of rod
Internal steelframe, the top of the pedestal are equipped with lamp holder embedded hole, are embedded with pvc pipe, one end of the pvc pipe in the pedestal
It is connected to the lamp holder embedded hole, the other end extends from the side wall of pedestal;The top of the body of rod be equipped with joint bar preformed hole and
Groove is preset with lifting built-in fitting in the groove;The bottom of the rod piece is equipped with demoulding suspension hook;
The steelframe includes horizontally disposed more first connections reinforcing bar, more second connection reinforcing bars and the connection steel of Duo Gen the 4th
Muscle, described first connects the third connection reinforcing bars that more bendings are evenly distributed on reinforcing bar in rectangle, and the third connects reinforcing bar
Four angles be in it is described first connection reinforcement welding;The second connection reinforcing bar and the 4th connection equal bending of reinforcing bar are in rectangle,
The second connection reinforcement welding forms cube after welding between the 4th connection reinforcing bar, cube welding
In one end of the first connection reinforcing bar.
2. rail member according to claim 1, which is characterized in that the pedestal and the body of rod are divided into 3 layers, successively
Exterior waterproof coating, inner waterproofing layer and stress layer including wrapping up setting from outside to inside.
3. rail member according to claim 1, which is characterized in that lamp holder built-in fitting is equipped in the lamp holder embedded hole,
The lamp holder built-in fitting includes precast concrete and the galvanized steel plain sheet at the top of the concrete embedded part, the galvanized steel
Plate is equipped with the through-hole to match with the pvc pipe, is equipped with J section steel relatively on the side wall that the galvanized steel plain sheet is bonded with concrete
Plate.
4. rail member according to claim 3, which is characterized in that the top of the lamp holder built-in fitting and the pedestal
Top is concordant.
5. a kind of construction method of the rail member as described in claim 1-4 any one, which is characterized in that including walking as follows
It is rapid:
S10, the reinforcing bar for choosing steelframe, wherein the diameter of the first connection reinforcing bar is 8-10mm, the diameter of the second connection reinforcing bar is 8-
10mm, third connection reinforcing bar diameter be 6-10mm and the 4th connection reinforcing bar diameter be 6-10mm;
S20, the second connection of bending reinforcing bar, third connection reinforcing bar and the 4th connection reinforcing bar, so that the second connection reinforcing bar, third connection
Reinforcing bar and the 4th connection reinforcing bar bending are in rectangle;
S30, each reinforcing bar of welding, form it into steelframe;
S40, the concrete material for choosing following components by weight percent ratio are mixed: intensity is not less than the portland cement of 42.5 grades
Or 600-900 parts of ordinary portland cement;
50-60 parts of poly carboxylic acid series water reducer;
600-850 parts of middle sand river sand;
20-45 parts of inert material;
300-350 parts of water;
S50, fixed steelframe carry out concreting to pouring in mold;
S60, it is demoulded after standing prefabricated component 3-5 days.
6. the construction method of rail member according to claim 5, which is characterized in that the construction method further includes walking as follows
It is rapid:
S70, waterproof layer processing, then the prefabricated component outer surface poured coat one layer of waterproof layer, and the waterproof layer is inner waterproofing layer;
S80, the coating that exterior waterproof coating is carried out after standing prefabricated component 4-5 hours.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910488277.6A CN110273576A (en) | 2019-06-05 | 2019-06-05 | Rail member and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910488277.6A CN110273576A (en) | 2019-06-05 | 2019-06-05 | Rail member and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110273576A true CN110273576A (en) | 2019-09-24 |
Family
ID=67960562
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910488277.6A Pending CN110273576A (en) | 2019-06-05 | 2019-06-05 | Rail member and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110273576A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111005654A (en) * | 2019-11-15 | 2020-04-14 | 四川中至耀辉建设有限公司 | Underground pump house inlet sealing device and pouring method thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030113161A1 (en) * | 2001-12-19 | 2003-06-19 | Yodock Leo J. | Barrier device with external reinforcement structure |
CN201649003U (en) * | 2010-04-21 | 2010-11-24 | 北京惠诚基业工程技术有限责任公司 | Active powder concrete column and steel pipe combination rail structure |
CN104482490A (en) * | 2014-12-22 | 2015-04-01 | 上海倍瑞太阳能设备有限公司 | Solar street lamp |
CN205678615U (en) * | 2016-06-02 | 2016-11-09 | 上海华城工程建设管理有限公司 | The pre-buried pedestal of viaduct bridge guardrail lamp stand |
CN108623251A (en) * | 2018-04-23 | 2018-10-09 | 东南大学 | A kind of ultra-high performance concrete and preparation method thereof for abyssal environment |
CN208870498U (en) * | 2018-08-20 | 2019-05-17 | 中建八局第四建设有限公司 | A kind of enclosing basis and enclosing |
CN210659503U (en) * | 2019-06-05 | 2020-06-02 | 成都建工工业化建筑有限公司 | Railing component |
-
2019
- 2019-06-05 CN CN201910488277.6A patent/CN110273576A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030113161A1 (en) * | 2001-12-19 | 2003-06-19 | Yodock Leo J. | Barrier device with external reinforcement structure |
CN201649003U (en) * | 2010-04-21 | 2010-11-24 | 北京惠诚基业工程技术有限责任公司 | Active powder concrete column and steel pipe combination rail structure |
CN104482490A (en) * | 2014-12-22 | 2015-04-01 | 上海倍瑞太阳能设备有限公司 | Solar street lamp |
CN205678615U (en) * | 2016-06-02 | 2016-11-09 | 上海华城工程建设管理有限公司 | The pre-buried pedestal of viaduct bridge guardrail lamp stand |
CN108623251A (en) * | 2018-04-23 | 2018-10-09 | 东南大学 | A kind of ultra-high performance concrete and preparation method thereof for abyssal environment |
CN208870498U (en) * | 2018-08-20 | 2019-05-17 | 中建八局第四建设有限公司 | A kind of enclosing basis and enclosing |
CN210659503U (en) * | 2019-06-05 | 2020-06-02 | 成都建工工业化建筑有限公司 | Railing component |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111005654A (en) * | 2019-11-15 | 2020-04-14 | 四川中至耀辉建设有限公司 | Underground pump house inlet sealing device and pouring method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206467922U (en) | A kind of module-assembled component stair | |
CN204326300U (en) | A kind of collar tie beam shell for building steel tube Combined concrete system | |
CN104947719B (en) | The rear pouring tape construction method of formwork erecting structure is hung in basement roof post-cast strip | |
CN106499092A (en) | A kind of lightgage steel joist composite concrete wallboard hoisting structure and its installation method | |
CN108726348B (en) | Horizontal prefabrication, overturning and hoisting method for pipe gallery segments | |
CN109914644A (en) | A kind of assembled heat insulation masonry wall and preparation method thereof | |
CN103938767B (en) | Trough type energy-saving bearing wall externally wrapped by steel wire mesh mortar plates and foamed concrete | |
CN110103316A (en) | A kind of sandwich heat preservation non-bearing wallboard and its production technology with hole | |
CN110273576A (en) | Rail member and its construction method | |
CN209163217U (en) | Exposed Prefabricated concrete-filled steel tube column and foundation connection structure | |
CN110344535A (en) | A kind of prefabricated assembled combined wall board and construction method realized concealed beam and exempt from formwork | |
CN106639166A (en) | Cushion block for controlling floor thickness | |
CN111395570B (en) | Fair-faced concrete composite external wall panel and construction method thereof | |
CN106223460B (en) | The prefabricated construction method of large scale wallboard | |
CN211499320U (en) | Prefabricated partition plate structure of assembled balcony | |
CN208701734U (en) | Plug-in type precast assembly isolated footing | |
CN204753834U (en) | Partition plate of scissors stair and connection structure of floor roof beam | |
CN2207418Y (en) | Block pouring shaping and automatic demoulding form for box-like room member | |
CN206570989U (en) | A kind of assembled architecture locking device | |
CN107859164A (en) | A kind of sill bolt plate precast wall body and its construction method | |
CN205367457U (en) | Cast member installs special hoist | |
CN110306683B (en) | Outer wall of fabricated building structure and pouring method | |
CN210659503U (en) | Railing component | |
CN107268755A (en) | A kind of construction method of inlet for stom water | |
CN104563281B (en) | A kind of prefabricated balcony structure and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |