CN110259096A - The certainly mobile operation platform of civil engineering and its application method - Google Patents
The certainly mobile operation platform of civil engineering and its application method Download PDFInfo
- Publication number
- CN110259096A CN110259096A CN201910563348.4A CN201910563348A CN110259096A CN 110259096 A CN110259096 A CN 110259096A CN 201910563348 A CN201910563348 A CN 201910563348A CN 110259096 A CN110259096 A CN 110259096A
- Authority
- CN
- China
- Prior art keywords
- operation platform
- construction
- twisted wire
- hawser
- civil engineering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/20—Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
- E04G2003/286—Mobile scaffolds; Scaffolds with mobile platforms mobile vertically
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The invention discloses a kind of certainly mobile operation platforms of civil engineering, including the guide assembly being fixedly installed on wall and the mobile platform component being slidably mounted on guide assembly, the mobile platform component includes the movable supporting frame being slidably mounted on the guide assembly and the operation platform that is installed on movable supporting frame, the operation platform for carry construction personnel carry out on it wall construction and the operation platform can with the sliding of movable supporting frame synchronizing moving.A kind of certainly mobile operation platform of civil engineering disclosed by the invention and its application method, it can be from mobile operation platform by being arranged inside and outside in wall, when can satisfy aedicula construction, especially rural housing construction when can flexible operating installation platform, the safe ready in construction in later period, and the installation save the cost of entire operation platform, it is easy-to-use, and can achieve inner-outer wall and meanwhile construction effect, effectively shorten working hour improve work efficiency, save the cost of being more convenient for.
Description
Technical field
The present invention relates to civil construction operating platform technical fields, and in particular to a kind of certainly mobile construction of civil engineering external wall construction
Platform.
Background technique
Civil engineering generally refers to civil engineering, civil engineering refer to all He Shui, soil, the related infrastructure of culture meter
It draws, build and repairs, current general civil engineering project includes: house, road, water utilities, canal business, flood control works and traffic
Deng, the civil engineering said now mostly generally refers exclusively to small Civil Specialities, the primary construction including house, public building, structures etc.,
It is readily seen that the construction of many high buildings and large mansions, wherein external wall construction is very important plate in construction in our daily lifes
Block is built a wall first, then is inside and outside wall floating, is finally the decoration of exterior wall, and the construction of each procedure carries out requiring height
Do-nothing operation is needed in the overhead upper completion process of exterior wall, our common exterior wall scaffolds are all by a large amount of steel pipes and scaffold
Fastener is climbed always building since bottom along story height along the huge steel frame construction built is risen, in such outer wall stand
Need to expend a large amount of steel pipe and scaffold clasp during setting up, it is huge to build construction work amount, steel consumption nor
Chang Ju great needs to form comprehensive operation platform, and some heavy constructions and construction party can bear so big expense cost,
But the extremely large amount of wasting of resources is also resulted in, not very practical on some small buildings, cost is excessively high.
Therefore, in order to solve the above problem, need a kind of civil engineering to move operation platform and its application method certainly, can satisfy small
When type building construction, especially rural housing construction when can flexible operating installation platform, it is safe in construction in later period
It is convenient, and the installation save the cost of entire operation platform, it is easy-to-use.
Summary of the invention
In view of this, the purpose of the present invention is overcoming defect in the prior art, provide civil engineering from mobile operation platform and
Its application method, can satisfy aedicula build when, especially rural housing construction when being capable of flexible operating installation
Platform, the safe ready in construction in later period, and the installation save the cost of entire operation platform, it is easy-to-use, and can achieve
Inner-outer wall simultaneously construct effect, effectively shorten working hour improve work efficiency, save the cost of being more convenient for.
Civil engineering of the invention including the guide assembly being fixedly installed on wall and is slidably installed from mobile operation platform
In the mobile platform component on guide assembly, the mobile platform component includes the movement being slidably mounted on the guide assembly
Support frame and the operation platform being installed on movable supporting frame, the operation platform carry out wall for carrying construction personnel on it
Surface construction and the operation platform can with the sliding of movable supporting frame synchronizing moving.
Further, the guide assembly includes being fixedly installed in the intracorporal pre- buried column of wall and being fixedly connected with pre- buried column
Slide rail, the slide rail length are adapted to the length of construction wall and are arranged inside multiple for described in mobile support
The idler wheel of movable supporting frame, the idler wheel are arranged in the guide groove of the slide rail.
Further, it is provided on the idler wheel for providing the bracket of mobile support, the shifting to the movable supporting frame
The corresponding bracket is provided with riveting column on dynamic support frame, and the riveting column is installed in the bracket and can be synchronous with the bracket
It is mobile.
Further, the pre- buried column both ends are symmetrically arranged with the slide rail, can be convenient for carrying out both sides inside and outside wall
Synchronous construction.
Further, the movable supporting frame is upside-down triangle shape, is provided with the abutting foot being connected on wall on base angle.
It further, further include the driving assembly of mobile platform component slippage described in drive control.
Further, the driving component includes being set to above the slide rail both ends first to pull rope fixing end and the
Two pull rope fixing end, the first twisted wire wheel and the second twisted wire wheel being fixed on operation platform, and described first, which pulls rope fixing end, passes through
First, which pulls rope, is connected to the first twisted wire wheel, and the first hawser fixing end is fixed in first hawser one end, and the other end is twisted in
In hank line wheel and the first twisted wire wheel can be realized relative to opposite between the first hawser fixing end by the first twisted wire wheel of rotation
The diminution of distance;Described second, which pulls rope fixing end, pulls rope by second and is connected to the second twisted wire wheel, and second hawser one end is solid
Due to the second hawser fixing end, the other end is twisted on the second twisted wire wheel and can passing through the second twisted wire wheel of rotation and realize the second twisted wire
Take turns the diminution relative to the relative distance between the second hawser fixing end.
Further, the first twisted wire wheel and the second twisted wire wheel are installed on the operation platform by mounting post, and the
One hawser fixing end, the first twisted wire wheel, the second twisted wire wheel and the second hawser fixing end are located along the same line.
Further, the first hawser fixing end, the second hawser fixing end are installed on the sliding by bending mounting rack
The both ends of guide rail.
A kind of application method using the certainly mobile operation platform of civil engineering,
A. it according to the installation site of the size design slide rail of construction wall, is installed by guide rail installation site and pre- buried column
Quantity determines the pre-buried position of pre- buried column;
B. pre- buried column is buried in corresponding position, the installation foundation as slide rail;
C. slide rail is lifted in place by the way of lifting, slide rail is installed on to the both ends of pre- buried column;
D. movable supporting frame is lifted in place by the way of lifting, and its riveting column is installed on positioned at slide rail guide groove
In the bracket of interior idler wheel, bolt is plugged on riveting column extension end, movable supporting frame abuts foot and is supported in the wall below slide rail
On face;
E. operation platform is lifted in place by the way of lifting, is installed on more than two movable supporting frames;
F., driving assembly, the first hawser fixing end of installation, the second hawser fixing end, the first twisted wire wheel and the second twisted wire are installed
Wheel installs the first hawser, the second hawser, installs the construction behaviour that Construction of Supporting personnel can be realized on mobile operation platform
Make, and construction personnel can operate the movement that driving assembly drives mobile operation platform.
The beneficial effects of the present invention are: a kind of civil engineering disclosed by the invention is led to from mobile operation platform and its application method
It crosses and is arranged inside and outside the operation platform that can be moved certainly in wall, when can satisfy aedicula construction, especially grange is built
If when can flexible operating installation platform, the safe ready in construction in later period, and the installation saving of entire operation platform at
This, it is easy-to-use, and can achieve inner-outer wall simultaneously construct effect, effectively shorten working hour raising work efficiency, be more convenient for saving
Cost.
Detailed description of the invention
The invention will be further described with reference to the accompanying drawings and examples:
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the side view of Fig. 1;
Fig. 3 is the enlarged drawing of operation platform.
Specific embodiment
Fig. 1 is the structural diagram of the present invention, and Fig. 2 is the side view of Fig. 1, and Fig. 3 is the enlarged drawing of operation platform, as schemed institute
Show, the civil engineering in the present embodiment including the guide assembly being fixedly installed on wall and is slidably installed from mobile operation platform
In the mobile platform component on guide assembly, the mobile platform component includes the movement being slidably mounted on the guide assembly
Support frame 21 and the operation platform 22 being installed on movable supporting frame 21, the operation platform 22 is for carrying construction personnel at it
Upper progress wall construction and the operation platform 22 can with the sliding of movable supporting frame 21 synchronizing moving, in the construction process,
It is voluntarily determined by construction personnel and starts to drive the moving direction of operation platform 22 to meet construction demand, and flexibly switching construction
Position.
In the present embodiment, the guide assembly includes being fixedly installed in the intracorporal pre- buried column 11 of wall and consolidating with pre- buried column 11
Surely the slide rail 12 connected, 12 length of slide rail are adapted to the length of construction wall and multiple be used for are arranged inside
The mobile idler wheel 13 for supporting the movable supporting frame 21, the idler wheel 13 are arranged in the guide groove of the slide rail 12, are constructed
Platform 22 realizes that, from movement, 13 stainless steel materials of idler wheel are made by the idler wheel 13 being located in slide rail 12, can be in room
Long-time intensive work in external environment, wearability is good, and intensity is high.
In the present embodiment, it is provided on the idler wheel 13 for providing the bracket of mobile support to the movable supporting frame 21
131, the corresponding bracket 131 is provided with riveting column 221 on the movable supporting frame 21, and the riveting column 221 is installed on the branch
In frame 131 and can with 131 synchronizing moving of bracket, with the form installation of riveting column 221 being inserted directly among bracket 131
Platform 22 is conducive to building for operation platform 22, and is locked using bolt 222 to riveting column 221, and operation platform is improved
22 reliability guarantees that the offset in other directions does not occur in the construction process for operation platform 22, can be in slide rail 12
It is free to slide under limitation.
In the present embodiment, pre- 11 both ends of buried column are symmetrically arranged with the slide rail 12, can be convenient for inside and outside to wall
Both sides synchronize construction, can be used for two sides inside and outside wall while constructing, effectively shorten the duration, improve work efficiency, reach
The synchronous construction effect that traditional scaffold is unable to reach.
In the present embodiment, the movable supporting frame 21 is upside-down triangle shape, is provided with and is connected on wall on base angle
Abut foot 211, abut foot 211 and effectively inhibit the shaking of operation platform 22, avoid operation platform 22 teetertotter or side
Rolling is dynamic, guarantees to provide a metastable aerial construction environment to construction personnel.
It further include the driving assembly of mobile platform component slippage described in drive control in the present embodiment.
In the present embodiment, the driving component include be set to above 12 both ends of slide rail first pull rope fix
End 31 and second pull rope fixing end 32, the first twisted wire wheel 33 and the second twisted wire wheel 34 that are fixed on operation platform 22, described the
One, which pulls rope fixing end 31, pulls rope by first and 311 is connected to the first twisted wire wheel 33, and described first hawser, 311 one end is fixed on first
Pull rope fixing end 31, the other end it is twisted on the first twisted wire wheel 33 and can pass through rotation the first twisted wire wheel 33 realization the first twisted wire wheel
33 pull the diminution of the relative distance between rope fixing end 31 relative to first;Described second, which pulls rope fixing end 32, pulls rope by second
321 are connected to the second twisted wire wheel 34, and the second hawser fixing end 32 is fixed in described second hawser, 321 one end, the other end it is twisted in
On second twisted wire wheel 34 and the second twisted wire wheel 34 can be realized relative to the second hawser fixing end 32 by the second twisted wire wheel 34 of rotation
Between relative distance diminution, the first twisted wire wheel 33 and the second twisted wire wheel 34 can separate alone individually rotation winding hawser,
When the first twisted wire wheel 33 rotates the first hawser 311 of coiling, the second twisted wire wheel 34 is in unconfined free state, can decontrol
Second hawser 321 is to compensate the length that the first hawser 311 is shunk, and similarly, rotates the second hawser of coiling 321 in the second twisted wire wheel 34
When, the first twisted wire wheel 33 is in unconfined free state, can decontrol the first hawser 311 and be shunk with compensating the second hawser 321
Length, realize that the left and right of operation platform 22 moves freely with this.
In the present embodiment, the first twisted wire wheel 33 and the second twisted wire wheel 34 are installed on the construction by mounting post 24 and put down
On platform 22, and first pulls rope fixing end 31, the first twisted wire wheel 33, the second twisted wire wheel 34 and the second hawser fixing end 32 positioned at same
It on straight line, avoids hawser from generating angle in drawing process and component on other directions occurs, be construction personnel from driving movement
Operation platform is laborsaving.
In the present embodiment, described first pulls rope fixing end 31, the second hawser fixing end 32 is installed by bending mounting rack 23
In the both ends of the slide rail 12, generally for the convenience of construction, the both ends of sliding rail can almost reach the two of wall
Endpoint, therefore guarantee that the moving range of operation platform 22 can reach all positions of surface of wall, in the height direction can be with
Setting multilayer operation platform reaches construction demand.
A kind of application method using the certainly mobile operation platform of civil engineering,
A. according to the installation site of the size design slide rail 12 of construction wall, by guide rail installation site and pre- buried column 11
Installation number determines the pre-buried position of pre- buried column 11;
B. pre- buried column 11 is buried in corresponding position, the installation foundation as slide rail 12;
C. slide rail 12 is lifted in place by the way of lifting, slide rail 12 is installed on the two of pre- buried column 11
End;
D. movable supporting frame 21 is lifted in place by the way of lifting, and its riveting column 221 is installed on to be located to slide and is led
In the bracket 131 of idler wheel 13 in 12 guide groove of rail, bolt 222, the abutting foot of movable supporting frame 21 are plugged on 221 extension end of riveting column
211 are supported on the metope of 12 lower section of slide rail;
E. operation platform 22 is lifted in place by the way of lifting, is installed on more than two movable supporting frames 21;
F., driving assembly is installed, rope fixing end 31, the second hawser fixing end 32, the first twisted wire wheel 33 and the are pulled in installation first
Two twisted wire wheels 34 install the first hawser 311, the second hawser 321, install and Construction of Supporting personnel can be realized in mobile construction
Constructing operation on platform 22, and construction personnel can operate the movement that driving assembly drives mobile operation platform 22.
Finally, it is stated that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although referring to compared with
Good embodiment describes the invention in detail, those skilled in the art should understand that, it can be to skill of the invention
Art scheme is modified or replaced equivalently, and without departing from the objective and range of technical solution of the present invention, should all be covered at this
In the scope of the claims of invention.
Claims (10)
1. a kind of certainly mobile operation platform of civil engineering, it is characterised in that: including the guide assembly being fixedly installed on wall and cunning
The dynamic mobile platform component being installed on guide assembly, the mobile platform component include being slidably mounted on the guide assembly
Movable supporting frame and the operation platform that is installed on movable supporting frame, the operation platform is for carrying construction personnel on it
Carry out wall construction and the operation platform can with the sliding of movable supporting frame synchronizing moving.
2. the certainly mobile operation platform of civil engineering according to claim 1, it is characterised in that: the guide assembly includes fixed peace
Loaded on slide rail wall intracorporal pre- buried column and be fixedly connected with pre- buried column, the slide rail length is adapted to construction wall
The length of body and it is arranged inside multiple for the mobile idler wheels for supporting the movable supporting frame, the idler wheel is arranged in the cunning
In the guide groove of dynamic guide rail.
3. civil engineering according to claim 2 is from mobile operation platform, it is characterised in that: be provided on the idler wheel for pair
The movable supporting frame provides the bracket of mobile support, and the corresponding bracket is provided with riveting column, institute on the movable supporting frame
Riveting column is stated to be installed in the bracket and can be with the bracket synchronizing moving.
4. the certainly mobile operation platform of civil engineering according to claim 3, it is characterised in that: the pre- buried column both ends are symmetrical arranged
There is the slide rail, can be convenient for synchronizing construction to both sides inside and outside wall.
5. the certainly mobile operation platform of civil engineering according to claim 4, it is characterised in that: the movable supporting frame is inverted triangle
Shape is provided with the abutting foot being connected on wall on base angle.
6. the certainly mobile operation platform of civil engineering according to claim 5, it is characterised in that: further include being moved described in drive control
The driving assembly of platform assembly sliding.
7. the certainly mobile operation platform of civil engineering according to claim 6, it is characterised in that: the driving component includes being set to
First above the slide rail both ends pull rope fixing end and second pull rope fixing end, be fixed on operation platform first twist
Line wheel and the second twisted wire wheel, described first pulls rope fixing end pulls rope and is connected to the first twisted wire wheel, first hawser by first
The first hawser fixing end is fixed in one end, and the other end is twisted in can realize on the first twisted wire wheel and by the first twisted wire wheel of rotation the
Diminution of the hank line wheel relative to the relative distance between the first hawser fixing end;Described second pulls rope fixing end pulls by second
Rope is connected to the second twisted wire wheel, and the second hawser fixing end is fixed in second hawser one end, and the other end is twisted in the second twisted wire
On wheel and the second twisted wire wheel can be realized relative to the relative distance between the second hawser fixing end by the second twisted wire wheel of rotation
It reduces.
8. the certainly mobile operation platform of civil engineering according to claim 7, it is characterised in that: the first twisted wire wheel and the second strand
Line wheel is installed on the operation platform by mounting post, and the first hawser fixing end, the first twisted wire wheel, the second twisted wire wheel and
Two hawser fixing ends are located along the same line.
9. civil engineering according to claim 8 is from mobile operation platform, it is characterised in that: the first hawser fixing end, the
The both ends that two hawser fixing ends are installed on the slide rail by bending mounting rack.
10. a kind of application method using the certainly mobile operation platform of civil engineering described in claim 1-9, it is characterised in that:
A. according to the installation site of the size design slide rail of construction wall, by guide rail installation site and pre- buried column installation number
Determine the pre-buried position of pre- buried column;
B. pre- buried column is buried in corresponding position, the installation foundation as slide rail;
C. slide rail is lifted in place by the way of lifting, slide rail is installed on to the both ends of pre- buried column;
D. movable supporting frame is lifted in place by the way of lifting, and its riveting column is installed in slide rail guide groove
In the bracket of idler wheel, bolt is plugged on riveting column extension end, movable supporting frame abuts foot and is supported on the metope below slide rail;
E. operation platform is lifted in place by the way of lifting, is installed on more than two movable supporting frames;
F., driving assembly is installed, the first hawser fixing end, the second hawser fixing end, the first twisted wire wheel and the second twisted wire wheel are installed,
First hawser, the second hawser are installed, the constructing operation that Construction of Supporting personnel can be realized on mobile operation platform is installed,
And construction personnel can operate the movement that driving assembly drives mobile operation platform.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910563348.4A CN110259096A (en) | 2019-06-26 | 2019-06-26 | The certainly mobile operation platform of civil engineering and its application method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910563348.4A CN110259096A (en) | 2019-06-26 | 2019-06-26 | The certainly mobile operation platform of civil engineering and its application method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110259096A true CN110259096A (en) | 2019-09-20 |
Family
ID=67921991
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910563348.4A Pending CN110259096A (en) | 2019-06-26 | 2019-06-26 | The certainly mobile operation platform of civil engineering and its application method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110259096A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113482315A (en) * | 2021-08-27 | 2021-10-08 | 南昌市凯华建筑工程有限公司 | Novel socket type self-adaptive layer climbing frame |
CN113914592A (en) * | 2021-10-29 | 2022-01-11 | 中冶建工集团有限公司 | Installation method of profiled steel sheet on wall surface of factory building |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050179507A1 (en) * | 2004-02-17 | 2005-08-18 | Samsung Electronics Co., Ltd. | Phase shifter using tunable bragg gratings and method for providing a tunable phase shift function thereof |
CN201236477Y (en) * | 2008-08-04 | 2009-05-13 | 南通英雄建筑安装工程有限公司 | Integral climbing scaffold for high-rise building |
CN202023353U (en) * | 2011-04-15 | 2011-11-02 | 江苏中原建设集团有限公司 | Integral lifting scaffold for building operations |
CN202969890U (en) * | 2012-03-23 | 2013-06-05 | 北京韬盛科技发展有限公司 | Tool type liftable material platform |
CN203412273U (en) * | 2013-08-14 | 2014-01-29 | 洪绮君 | Full-circular orbit type lifting work platform of storage tank |
CN204980891U (en) * | 2015-09-08 | 2016-01-20 | 贵州省公路工程集团有限公司 | Indulge and move hanger rope positioner of steel purlin girder segment section usefulness |
US20160312481A1 (en) * | 2015-04-27 | 2016-10-27 | Rolling Easy Platforms, LLC | Work platform rail system |
CN206128600U (en) * | 2016-08-31 | 2017-04-26 | 广西建工集团第五建筑工程有限责任公司 | Mobilizable steel construction high altitude operation platform |
CN206581141U (en) * | 2017-01-23 | 2017-10-24 | 重庆恒佳工程技术咨询有限公司 | Bridge maintenance system |
CN206616846U (en) * | 2017-03-30 | 2017-11-07 | 福建省东霖建设工程有限公司 | Exterior wall finishing engineering movable Scaffold |
-
2019
- 2019-06-26 CN CN201910563348.4A patent/CN110259096A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050179507A1 (en) * | 2004-02-17 | 2005-08-18 | Samsung Electronics Co., Ltd. | Phase shifter using tunable bragg gratings and method for providing a tunable phase shift function thereof |
CN201236477Y (en) * | 2008-08-04 | 2009-05-13 | 南通英雄建筑安装工程有限公司 | Integral climbing scaffold for high-rise building |
CN202023353U (en) * | 2011-04-15 | 2011-11-02 | 江苏中原建设集团有限公司 | Integral lifting scaffold for building operations |
CN202969890U (en) * | 2012-03-23 | 2013-06-05 | 北京韬盛科技发展有限公司 | Tool type liftable material platform |
CN203412273U (en) * | 2013-08-14 | 2014-01-29 | 洪绮君 | Full-circular orbit type lifting work platform of storage tank |
US20160312481A1 (en) * | 2015-04-27 | 2016-10-27 | Rolling Easy Platforms, LLC | Work platform rail system |
CN204980891U (en) * | 2015-09-08 | 2016-01-20 | 贵州省公路工程集团有限公司 | Indulge and move hanger rope positioner of steel purlin girder segment section usefulness |
CN206128600U (en) * | 2016-08-31 | 2017-04-26 | 广西建工集团第五建筑工程有限责任公司 | Mobilizable steel construction high altitude operation platform |
CN206581141U (en) * | 2017-01-23 | 2017-10-24 | 重庆恒佳工程技术咨询有限公司 | Bridge maintenance system |
CN206616846U (en) * | 2017-03-30 | 2017-11-07 | 福建省东霖建设工程有限公司 | Exterior wall finishing engineering movable Scaffold |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113482315A (en) * | 2021-08-27 | 2021-10-08 | 南昌市凯华建筑工程有限公司 | Novel socket type self-adaptive layer climbing frame |
CN113482315B (en) * | 2021-08-27 | 2022-06-17 | 南昌市凯华建筑工程有限公司 | Novel socket type self-adaptive layer climbing frame |
CN113914592A (en) * | 2021-10-29 | 2022-01-11 | 中冶建工集团有限公司 | Installation method of profiled steel sheet on wall surface of factory building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100572713C (en) | The large span bidirectional string stretching girders rope accumulation gliding construction method | |
CN103556817B (en) | Side wall concrete construction method employing side wall trolley | |
CN206298170U (en) | A kind of carbon cloth production winding barrel structure | |
CN112196159B (en) | Glass curtain wall construction structure and construction method thereof | |
CN110259096A (en) | The certainly mobile operation platform of civil engineering and its application method | |
CN109138431B (en) | Super high-rise pump pipe bridge crossing device and construction method thereof | |
CN105113536A (en) | Movable sidewall formwork erecting system for underground structure and construction method of system | |
CN205276842U (en) | High altitude rack in bulk is with novel bed -jig that slides | |
CN114941411B (en) | BIM-based assembled low-carbon building structure and construction connection method | |
CN116219896A (en) | Bridge substructure prefabrication and installation device and construction method | |
CN86203954U (en) | Wall bearing self-lifting scaffold | |
CN104818995A (en) | Method for assembling confined concrete arch frames | |
CN201128882Y (en) | Lifting and supporting brackets integrated construction device for bridge arch rib | |
CN115288409A (en) | Green intelligent trapezoidal horizontal sliding platform for high cornice | |
CN101818829B (en) | Construction method of cross-valley overhead pipeline | |
CN202117338U (en) | Hydraulic ejection and following sliding device | |
CN217996549U (en) | Hoisting frame for dry quenching furnace body building | |
CN112377672A (en) | Old factory dust removal pipeline reconstruction and installation method and special pipeline moving and hoisting device thereof | |
CN216038413U (en) | Safe crane is used in hoist and mount of precast concrete roof beam | |
CN214840217U (en) | Energy-conserving lighting device with adjustable construction | |
CN216006588U (en) | Intelligent assembled anchor beam device of cable hoist and mount system | |
CN111058877A (en) | Rotary type tunnel cloth hanging trolley | |
CN218966731U (en) | Contact net device in tunnel | |
CN215291280U (en) | High stability flexible formula support frame for building engineering construction | |
CN216046704U (en) | Support for externally hung sliding groove |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190920 |
|
RJ01 | Rejection of invention patent application after publication |