CN110242333A - A kind of tunnel grillage moulding bed and its processing method - Google Patents

A kind of tunnel grillage moulding bed and its processing method Download PDF

Info

Publication number
CN110242333A
CN110242333A CN201910611015.4A CN201910611015A CN110242333A CN 110242333 A CN110242333 A CN 110242333A CN 201910611015 A CN201910611015 A CN 201910611015A CN 110242333 A CN110242333 A CN 110242333A
Authority
CN
China
Prior art keywords
moulding bed
main reinforcement
grillage
steel plate
beam frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910611015.4A
Other languages
Chinese (zh)
Inventor
杨中才
王根宝
陈文山
张勇
郝少峰
张春喜
张玉玮
徐川
白学勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Construction and Investment Holding Group Co Ltd
Original Assignee
Yunnan Construction and Investment Holding Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Construction and Investment Holding Group Co Ltd filed Critical Yunnan Construction and Investment Holding Group Co Ltd
Priority to CN201910611015.4A priority Critical patent/CN110242333A/en
Publication of CN110242333A publication Critical patent/CN110242333A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K31/00Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
    • B23K31/02Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
    • B23K37/04Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work
    • B23K37/0426Fixtures for other work
    • B23K37/0435Clamps
    • B23K37/0443Jigs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • E21D11/183Supporting means for arch members, not provided for in E21D11/22

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of tunnel grillage moulding beds, and moulding bed support frame 3, the i-beam frame 2 positioned at middle part and the superposed main reinforcement fixing steel plate 1 by being located at lower part form;The moulding bed support frame 3 is arranged one every a length according to the design length of grillage.The i-beam frame 2 is identical as the design lines shape parameter of grillage.The main reinforcement fixing steel plate 1 is divided into 9 sections of positioning according to 2 length of i-beam frame.Support frame as described above 3, the connection between the i-beam frame 2 and superposed main reinforcement fixing steel plate 1 at middle part are welding.The invention also discloses a kind of processing methods of tunnel grillage moulding bed, it is characterised in that checked comprising preparation, surveying setting-out, moulding bed assembling, moulding bed and etc..Fixation for frame moulding bed to reinforcing bar of the invention, accurate positioning, welding quality is good, reduces unqualified arch quantity, reduces waste, has saved cost.

Description

A kind of tunnel grillage moulding bed and its processing method
Technical field
The invention discloses a kind of tunnel grillage moulding bed and its processing method, specifically a kind of Tunnel institute With grillage moulding bed and its processing method, belong to highway tunnel construction technical field.
Background technique
Traditional grillage processing flow are as follows:
Arch full-page proof → welding stirrup and other components → scene examination spelling → check are put in preparation of construction → debugging forming mill → → installation.
From above-mentioned grillage traditional processing process, it can be found that:
1) setting-out is repeated.Carry out arch processing every time and be required to relay arch full-page proof, and full-page proof cannot to reinforcing bar into Row is effectively fixed;
2) of poor quality.In welding process, arch top bars are easy to shake, and the welding is not firm, and easy deviation, quality are not easy Guarantee;
3) limited space.To place space requirement height during setting-out, it is easy to be limited by processing factory space;
4) inefficiency.For guarantee reinforcing rib quantity, there can only be a worker successively to weld reinforcing rib from left to right every time, According to each reinforcing rib size, rough estimate reinforcing rib position;
5) at high cost, processing quality is not easy to guarantee.Easily cause main reinforcement deviation, stirrup position skew, reinforcing rib spacing inclined Technical requirements are not met greatly and cause phenomenon of doing over again, and are generated the wasting phenomenon in artificial and financial resources, are unfavorable for cost control.
In conclusion traditional grillage processing due to repeating setting-out, causes, work efficiency is low, quality is difficult to ensure.
Summary of the invention
The technical problem to be solved by the present invention is being provided in order to avoid above-mentioned conventional grates arch processes existing deficiency It is a kind of can the pinpoint moulding bed of main reinforcement and its processing method to grillage.
The technical solution of present invention solution above-mentioned technical problem are as follows:
A kind of tunnel grillage moulding bed, by being located at the moulding bed support frame 3 of lower part, positioned at the i-beam frame 2 at middle part and position Main reinforcement fixing steel plate 1 in top forms.
The main reinforcement fixing steel plate 1 on the top is processed to be formed together according to the quantity and geometric dimension of grillage spacer bar The width of the main reinforcement locating slot 4 of quantity, same parameter, main reinforcement locating slot 4 is identical as the diameter of grillage main reinforcement.
The moulding bed support frame 3 is arranged one every certain length according to the design length of grillage, sets 4~6 altogether.
The i-beam frame 2 is identical as the radian of grid shelf's design on arch bridge, length and width parameter.
The main reinforcement fixing steel plate 1 is divided into 7~11 sections of positioning according to 2 length of i-beam frame, and totally 6~10.
Support frame as described above 3, welding is solid between the i-beam frame 2 and superposed main reinforcement fixing steel plate 1 at middle part It is fixed.
A kind of processing method of tunnel grillage moulding bed, it is characterised in that: the processing method comprises the steps of:
1) prepare
According to the radian of grillage design, the i-beam frame 2 of length and width parameter processing identical parameters;According to grid Shelf's design on arch bridge width, height, bar diameter process main reinforcement fixing steel plate 1;Suitable height and i-beam frame 2 are processed according to worker Width produce moulding bed support frame 3;
2) surveying setting-out
With total station, setting-out goes out the temporary holding location of moulding bed support frame 3 on reinforcement yard ground, in i-beam frame 2 On according to 9 equal part of carry out of length, determine the fixation position of main reinforcement fixing steel plate 1;
3) moulding bed assembles
According to setting-out position, first in processing factory's ground fixing moulding bed structure support frame 3, then welded on moulding bed support frame 3 Fixed i-beam frame 2, finally according to the fixed main reinforcement fixing steel plate 1 of Along ent on i-beam frame 2, fixed point is fixed for each main reinforcement Position 1 lower part of steel plate and 2 junction of i-beam frame, fixing means are spot welding consolidation;
4) moulding bed is checked
After being completed, fixation position of the main reinforcement fixing steel plate 1 on i-beam frame 2 is checked, after confirmation is qualified To the spot welding position of main reinforcement fixing steel plate 1 and i-beam frame 2 again reinforcement of weld, the processing of moulding bed is completed.
The beneficial effects of the present invention are:
1) main reinforcement fixing steel plate 1 is processed according to the design size of grillage, 1 spacing of every two pieces of main reinforcement fixing steel plates is small, It can quick and precisely be positioned according to the relative position of reinforcing rib and main reinforcement fixing steel plate 1 when welding;
2) four main reinforcements of grillage are fixed in main reinforcement locating slot 4, are not easy to shake, are improved welding quality;
3) reinforcing rib position is quickly positioned according to steel plate position, can be welded simultaneously with several workers, be improved the life of arch Produce efficiency;
4) moulding bed interior in a limited space can be placed, and not have to repeat setting-out space, easy to operate;
5) by fixation of the moulding bed to reinforcing bar, accurate positioning, welding quality is good, reduces unqualified arch quantity, reduces Waste, has saved cost.
Detailed description of the invention
Fig. 1 is top view of the present invention;
Fig. 2 is skiagraph of the present invention;
Fig. 3 is cross-sectional view of the present invention;
In figure: 1- main reinforcement fixing steel plate;2- i-beam frame;3- moulding bed support frame;4- main reinforcement locating slot.
Specific embodiment
A kind of 1~3 pair of tunnel grillage moulding bed of the invention and its processing method carry out specifically with reference to the accompanying drawing It is bright.
A kind of tunnel grillage moulding bed, by being located at the moulding bed support frame 3 of lower part, positioned at the i-beam frame 2 at middle part and position Main reinforcement fixing steel plate 1 in top forms.
The main reinforcement fixing steel plate 1 on the top is processed to be formed together according to the quantity and geometric dimension of grillage spacer bar The width of the main reinforcement locating slot 4 of quantity, same parameter, main reinforcement locating slot 4 is identical as the diameter of grillage main reinforcement.
The moulding bed support frame 3 is arranged one every certain length according to the design length of grillage, sets 4~6 altogether.
The i-beam frame 2 is identical as the radian of grid shelf's design on arch bridge, length and width parameter.
Preferably, the main reinforcement fixing steel plate 1 is divided into 9 sections of positioning according to 2 length of i-beam frame, and totally 8.
Support frame as described above 3, welding is solid between the i-beam frame 2 and superposed main reinforcement fixing steel plate 1 at middle part It is fixed.
A kind of processing method of tunnel grillage moulding bed, it is characterised in that: the processing method comprises the steps of:
1) prepare
According to the radian of grillage design, the i-beam frame 2 of length and width parameter processing identical parameters;According to grid Shelf's design on arch bridge width, height, bar diameter process main reinforcement fixing steel plate 1;Suitable height and i-beam frame 2 are processed according to worker Width produce moulding bed support frame 3;
2) surveying setting-out
With total station, setting-out goes out the temporary holding location of moulding bed support frame 3 on reinforcement yard ground, in i-beam frame 2 On according to 9 equal part of carry out of length, determine the fixation position of main reinforcement fixing steel plate 1;
3) moulding bed assembles
According to setting-out position, first in processing factory's ground fixing moulding bed structure support frame 3, then welded on moulding bed support frame 3 Fixed i-beam frame 2, finally according to the fixed main reinforcement fixing steel plate 1 of Along ent on i-beam frame 2, fixed point is fixed for each main reinforcement Position 1 lower part of steel plate and 2 junction of i-beam frame, fixing means are spot welding consolidation;
4) moulding bed is checked
After being completed, fixation position of the main reinforcement fixing steel plate 1 on i-beam frame 2 is checked, after confirmation is qualified To the spot welding position of main reinforcement fixing steel plate 1 and i-beam frame 2 again reinforcement of weld, the processing of moulding bed is completed.
Grille arch moulding bed provides very big help to the production of grillage, reduces the production difficulty of arch, Gong Renshi Work is convenient, easy to operate, improves the quality of production and production efficiency, and the construction cost of saving achieves good effect.

Claims (5)

1. a kind of tunnel grillage moulding bed, by be located at lower part moulding bed support frame (3), positioned at middle part i-beam frame (2) and Superposed main reinforcement fixing steel plate (1) composition;It is characterized by:
The main reinforcement fixing steel plate (1) on the top is processed to form same number according to the quantity and geometric dimension of grillage spacer bar The main reinforcement locating slot (4) of amount, same parameter, the width of main reinforcement locating slot (4) are identical as the diameter of grillage main reinforcement;
The moulding bed support frame (3) is arranged one every a length according to the design length of grillage (5), sets 4~6 altogether.
2. grillage moulding bed according to claim 1, it is characterised in that: the i-beam frame (2) sets with grillage The radian of meter, length and width parameter are identical.
3. grillage moulding bed according to claim 1, it is characterised in that: the main reinforcement fixing steel plate (1) is according to work Word steelframe (2) length is divided into 7~11 sections of positioning, and totally 6~10.
4. grillage moulding bed according to claim 1 or 2 or 3, it is characterised in that: support frame as described above (3) is located at middle part I-beam frame (2) and superposed main reinforcement fixing steel plate (1) between connection be welding.
5. a kind of processing method of tunnel grillage moulding bed, it is characterised in that: the processing method comprises the steps of:
1) prepare
According to the radian of grillage design, the i-beam frame (2) of length and width parameter processing identical parameters;According to grille arch It sets up meter width, height, bar diameter and processes main reinforcement fixing steel plate (1);Suitable height and i-beam frame are processed according to worker (2) width produces moulding bed support frame (3);
2) surveying setting-out
With total station, setting-out goes out the temporary holding location of moulding bed support frame (3) on reinforcement yard ground, in i-beam frame (2) On according to progress (9) equal part of length, determine the fixation position of main reinforcement fixing steel plate (1);
3) moulding bed assembles
According to setting-out position, first in processing factory's ground fixing moulding bed structure support frame (3), then welded on moulding bed support frame (3) Fixed i-beam frame (2) (fix main reinforcement fixing steel plate (1) according to Along ent on 2, fixed point is each main reinforcement in i-beam frame Fixing steel plate (1) lower part and i-beam frame (2) junction, fixing means are spot welding consolidation;
4) moulding bed is checked
After being completed, fixation position of the main reinforcement fixing steel plate (1) on i-beam frame (2) is checked, after confirmation is qualified To the spot welding position of main reinforcement fixing steel plate (1) and i-beam frame (2) again reinforcement of weld, the processing of moulding bed is completed.
CN201910611015.4A 2019-07-08 2019-07-08 A kind of tunnel grillage moulding bed and its processing method Pending CN110242333A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910611015.4A CN110242333A (en) 2019-07-08 2019-07-08 A kind of tunnel grillage moulding bed and its processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910611015.4A CN110242333A (en) 2019-07-08 2019-07-08 A kind of tunnel grillage moulding bed and its processing method

Publications (1)

Publication Number Publication Date
CN110242333A true CN110242333A (en) 2019-09-17

Family

ID=67891360

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910611015.4A Pending CN110242333A (en) 2019-07-08 2019-07-08 A kind of tunnel grillage moulding bed and its processing method

Country Status (1)

Country Link
CN (1) CN110242333A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111673007A (en) * 2020-07-14 2020-09-18 中国十七冶集团有限公司 Device for processing main ribs of grid arch center in shallow-buried excavation method construction
CN112570865A (en) * 2020-12-18 2021-03-30 涪特智能装备(重庆)有限公司 Continuous welding production method and production line for grid type arch centering
CN115781151A (en) * 2022-10-26 2023-03-14 中铁九局集团第三建设有限公司 Positioning die suitable for processing of grating arch frame

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101037860B1 (en) * 2010-07-16 2011-05-31 이병택 A assemble type mold construction structure for tunnel building
CN203383835U (en) * 2013-06-28 2014-01-08 中铁上海工程局有限公司 Tunnel grille arch frame jig
CN206732432U (en) * 2017-04-16 2017-12-12 中铁三局集团有限公司 Tunnel reinforcement centering processing mold
CN207606458U (en) * 2017-12-27 2018-07-13 中铁十二局集团有限公司 A kind of tunnel grillage positioning mould for processing
CN208528386U (en) * 2018-04-23 2019-02-22 中铁十六局集团第二工程有限公司 It is a kind of for making the positioning device of three limb arch of railway tunnel
CN109707414A (en) * 2018-12-29 2019-05-03 中铁五局集团有限公司 A kind of adjustable grillage processing tool in tunnel
CN210317347U (en) * 2019-07-08 2020-04-14 云南省建设投资控股集团有限公司 Tunnel grid bow member bed-jig

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101037860B1 (en) * 2010-07-16 2011-05-31 이병택 A assemble type mold construction structure for tunnel building
CN203383835U (en) * 2013-06-28 2014-01-08 中铁上海工程局有限公司 Tunnel grille arch frame jig
CN206732432U (en) * 2017-04-16 2017-12-12 中铁三局集团有限公司 Tunnel reinforcement centering processing mold
CN207606458U (en) * 2017-12-27 2018-07-13 中铁十二局集团有限公司 A kind of tunnel grillage positioning mould for processing
CN208528386U (en) * 2018-04-23 2019-02-22 中铁十六局集团第二工程有限公司 It is a kind of for making the positioning device of three limb arch of railway tunnel
CN109707414A (en) * 2018-12-29 2019-05-03 中铁五局集团有限公司 A kind of adjustable grillage processing tool in tunnel
CN210317347U (en) * 2019-07-08 2020-04-14 云南省建设投资控股集团有限公司 Tunnel grid bow member bed-jig

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111673007A (en) * 2020-07-14 2020-09-18 中国十七冶集团有限公司 Device for processing main ribs of grid arch center in shallow-buried excavation method construction
CN112570865A (en) * 2020-12-18 2021-03-30 涪特智能装备(重庆)有限公司 Continuous welding production method and production line for grid type arch centering
CN112570865B (en) * 2020-12-18 2023-09-15 涪特智能装备(重庆)有限公司 Continuous welding production method and production line for grid type arch centering
CN115781151A (en) * 2022-10-26 2023-03-14 中铁九局集团第三建设有限公司 Positioning die suitable for processing of grating arch frame

Similar Documents

Publication Publication Date Title
CN110242333A (en) A kind of tunnel grillage moulding bed and its processing method
CN103317292B (en) Novel connecting and assembling jig and method for pipe flanges
CN205058277U (en) Prefabricated T girder iron muscle mould
CN104070316B (en) A kind of assembled group of welded H section steel is to device and using method thereof
CN104652284A (en) Reverse splicing construction method for steel box girder
CN106271461A (en) A kind of steel plate shear force wall packaging technology
CN201301520Y (en) Prestressed beam drilling bellow positioning reinforced net
CN113718648A (en) Special-shaped curve structure steel-concrete combined tower segment and manufacturing process
CN115319911A (en) Digital production process of concrete prefabricated part with complex shape
CN111636303A (en) Cross baseline control method for block assembly manufacturing of curved steel box structure
CN104028875B (en) Aluminum electrolytic cell manufacturing method
CN210317347U (en) Tunnel grid bow member bed-jig
CN110629782B (en) Adjusting method of anchor bolt offline assembly device
CN104358251A (en) Main reinforcement distance control device during pile foundation project reinforcement cage manufacturing and pile foundation project reinforcement cage manufacturing method
CN204825945U (en) A fixture for fixing buried bolt in advance
CN111218991A (en) Installation method of large embedded part
CN104196153B (en) A kind of slab L-shaped steel plate shear force wall post and preparation method thereof
CN202527885U (en) Pedestal for manufacturing framework of subway pipe piece
CN209850218U (en) Reinforcing bar net piece welding and placing integrated frame
CN105798479A (en) Length-unlimited continuous H structural steel production method
CN108457679A (en) Grid steel frame, the assembled device of grid steel frame examination and grid steel frame production method
CN106583603A (en) Manufacturing method for sprayed concrete reinforcing mesh and bracket used in manufacturing method
CN210621745U (en) Foundation bolt fixing frame assembly
CN206839006U (en) A kind of processing unit (plant) of bridge reinforcement cage transverse steel circle
CN113732626B (en) Manufacturing method of X-shaped waist cylindrical structure

Legal Events