CN104358251A - Main reinforcement distance control device during pile foundation project reinforcement cage manufacturing and pile foundation project reinforcement cage manufacturing method - Google Patents

Main reinforcement distance control device during pile foundation project reinforcement cage manufacturing and pile foundation project reinforcement cage manufacturing method Download PDF

Info

Publication number
CN104358251A
CN104358251A CN201410671470.0A CN201410671470A CN104358251A CN 104358251 A CN104358251 A CN 104358251A CN 201410671470 A CN201410671470 A CN 201410671470A CN 104358251 A CN104358251 A CN 104358251A
Authority
CN
China
Prior art keywords
reinforcement
manufacturing
pile foundation
main muscle
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410671470.0A
Other languages
Chinese (zh)
Inventor
范金财
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201410671470.0A priority Critical patent/CN104358251A/en
Publication of CN104358251A publication Critical patent/CN104358251A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21FWORKING OR PROCESSING OF METAL WIRE
    • B21F31/00Making meshed-ring network from wire
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a main reinforcement distance control device during pile foundation project reinforcement cage manufacturing. The main reinforcement distance control device during the pile foundation project reinforcement cage manufacturing comprises a straight rod, a straight-line-shaped cross beam and a right angle arm. According to a technical scheme, a pile foundation project reinforcement cage manufacturing method comprises the following steps of firstly manufacturing a reinforcement manufacturing platform according to the design length of a reinforcement cage, wherein the length of the reinforcement manufacturing platform is slightly smaller than the design length of the reinforcement cage, the reinforcement manufacturing platform comprises a supporting part and a manufacturing platform surface, the manufacturing platform surface is integrally in a rectangular shape, and the manufacturing platform surface is a horizontal surface; secondly arranging two main reinforcements on the reinforcement manufacturing platform surface, manufacturing the main reinforcement distance control device through a pile foundation project reinforcement cage and sequentially welding the main reinforcements; thirdly welding a reinforcing reinforcement and the main reinforcements and achieving the manufacture. The foundation project reinforcement cage manufacturing method is simple in operation, quickens the reinforcement cage manufacturing efficiency, improves the reinforcement cage forming quality, enables the reinforcement cage to pass the acceptance inspection in one time, avoids secondary reworking and saves work hours and the labor.

Description

The main muscle pitch control unit of pile foundation engineering fabrication of reinforcing cage and pile foundation engineering fabrication of reinforcing cage method
Technical field
The present invention relates to pile foundation engineering fabrication of reinforcing cage field, particularly the main muscle pitch control unit of pile foundation engineering fabrication of reinforcing cage and pile foundation engineering fabrication of reinforcing cage method.
Background technology
In practice of construction, often because reinforcing cage main muscle spacing controls not in place, do not reach design specifications requirement, cause the shaping examination of reinforcing cage defective, carry out secondary and do over again, affect the pile foundation engineering construction period.Current reinforcing cage main muscle spacing controls generally to adopt on every root Reinforced Hoop by the method for paintbrush by design size mark.The deviation that this construction method causes often beyond design specifications requirement, and wastes labour to a certain extent.
Summary of the invention
Technical problem to be solved by this invention is to provide the main muscle pitch control unit of pile foundation engineering fabrication of reinforcing cage and pile foundation engineering fabrication of reinforcing cage method, easy and simple to handle, accelerate reinforcing cage processing and fabricating efficiency, and reinforcing cage Forming Quality can be improved, once by checking and accepting, avoid secondary to do over again, save man-hour, save labour.
For achieving the above object, the main muscle pitch control unit of pile foundation engineering fabrication of reinforcing cage that the present invention proposes, it comprises straight-bar, " one " font transverse arm and right angle arm, " one " font transverse arm and right angle arm are arranged on straight-bar the same side by being welded and fixed, the horizon bar of " one " font transverse arm and right angle arm is all perpendicular with straight-bar, " Qian " shape space is constituted between described right angle arm and straight-bar, the length of described " one " font transverse arm is slightly larger than the diameter of the main muscle of reinforcing bar to be installed, right angle arm and the orthogonal and spacing between the two of straight-bar are slightly larger than the diameter of the main muscle of reinforcing bar to be installed, spacing between " one " font transverse arm and the horizon bar of right angle arm is the spacing between two main muscle of reinforcing bar to be installed.
 
Pile foundation engineering fabrication of reinforcing cage method, its concrete technical scheme is:
One, make reinforcement fabrication platform according to reinforcing cage design length, reinforcement fabrication platform length is slightly less than reinforcing bar
Cage design length, reinforcement fabrication platform comprises support member and makes platform table top, and make platform table top entirety rectangular, making platform table top is horizontal plane;
Two, first two main muscle are placed on reinforcement fabrication table top, by reinforcing rib and a wherein main muscle
Welding, use the main muscle pitch control unit of described pile foundation engineering fabrication of reinforcing cage, main muscle is placed on " one " font transverse arm, is placed in " Qian " shape space of forming between right angle arm with straight-bar needing the main muscle of welding and it is welded, successively all the other main muscle being welded;
Three, spiral hoop is welded with main muscle, complete making.
The main muscle pitch control unit of pile foundation engineering fabrication of reinforcing cage proposed by the invention and pile foundation engineering fabrication of reinforcing cage method, easy and simple to handle, accelerate reinforcing cage processing and fabricating efficiency, and reinforcing cage Forming Quality can be improved, once by checking and accepting, avoiding secondary to do over again, saving man-hour, saving labour.
Accompanying drawing explanation
Fig. 1 is pile foundation engineering fabrication of reinforcing cage main muscle pitch control unit structural representation proposed by the invention.
Fig. 2 is pile foundation engineering fabrication of reinforcing cage schematic diagram proposed by the invention.
Fig. 3 is pile foundation engineering fabrication of reinforcing cage main muscle pitch control unit using state enlarged diagram proposed by the invention.
Detailed description of the invention
See accompanying drawing, the main muscle pitch control unit 1 of pile foundation engineering fabrication of reinforcing cage, it comprises straight-bar 1-1, " one " font transverse arm 1-2 and right angle arm 1-3, " one " font transverse arm and right angle arm are arranged on straight-bar the same side by being welded and fixed, the horizon bar of " one " font transverse arm and right angle arm is all perpendicular with straight-bar, " Qian " shape space is constituted between described right angle arm and straight-bar, the length of described " one " font transverse arm is slightly larger than the diameter of the main muscle 2 of reinforcing bar to be installed, right angle arm and the orthogonal and spacing between the two of straight-bar are slightly larger than the diameter of the main muscle of reinforcing bar to be installed, spacing between " one " font transverse arm and the horizon bar of right angle arm is the spacing between two main muscle of reinforcing bar to be installed.
 
Pile foundation engineering fabrication of reinforcing cage method, its concrete technical scheme is:
One, make reinforcement fabrication platform 4 according to reinforcing cage design length, reinforcement fabrication platform length is slightly less than steel
Muscle cage design length, reinforcement fabrication platform comprises support member and makes platform table top, and make platform table top entirety rectangular, making platform table top is horizontal plane;
Two, first two main muscle are placed on reinforcement fabrication table top, by reinforcing rib 3 and a wherein main muscle
Welding, use the main muscle pitch control unit of described pile foundation engineering fabrication of reinforcing cage, main muscle is placed on " one " font transverse arm, is placed in " Qian " shape space of forming between right angle arm with straight-bar needing the main muscle of welding and it is welded, successively all the other main muscle being welded;
Three, spiral hoop is welded with main muscle, complete making.
The main muscle pitch control unit of pile foundation engineering fabrication of reinforcing cage proposed by the invention and pile foundation engineering fabrication of reinforcing cage method, easy and simple to handle, accelerate reinforcing cage processing and fabricating efficiency, and reinforcing cage Forming Quality can be improved, once by checking and accepting, avoiding secondary to do over again, saving man-hour, saving labour.

Claims (2)

1. the main muscle pitch control unit of pile foundation engineering fabrication of reinforcing cage, it is characterized in that it comprises straight-bar, " one " font transverse arm and right angle arm, " one " font transverse arm and right angle arm are arranged on straight-bar the same side by being welded and fixed, the horizon bar of " one " font transverse arm and right angle arm is all perpendicular with straight-bar, " Qian " shape space is constituted between described right angle arm and straight-bar, the length of described " one " font transverse arm is slightly larger than the diameter of the main muscle of reinforcing bar to be installed, right angle arm and the orthogonal and spacing between the two of straight-bar are slightly larger than the diameter of the main muscle of reinforcing bar to be installed, spacing between " one " font transverse arm and the horizon bar of right angle arm is the spacing between two main muscle of reinforcing bar to be installed.
2. pile foundation engineering fabrication of reinforcing cage method, its concrete technical scheme is:
One, make reinforcement fabrication platform according to reinforcing cage design length, reinforcement fabrication platform length is smaller
In reinforcing cage design length, reinforcement fabrication platform comprises support member and makes platform table top, and make platform table top entirety rectangular, making platform table top is horizontal plane;
Two, first two main muscle are placed on reinforcement fabrication table top, by reinforcing rib and wherein one
Main muscle welding, use the main muscle pitch control unit of described pile foundation engineering fabrication of reinforcing cage, main muscle is placed on " one " font transverse arm, is placed in " Qian " shape space of forming between right angle arm with straight-bar needing the main muscle of welding and it is welded, successively all the other main muscle being welded;
Three, spiral hoop is welded with main muscle, complete making.
CN201410671470.0A 2014-11-21 2014-11-21 Main reinforcement distance control device during pile foundation project reinforcement cage manufacturing and pile foundation project reinforcement cage manufacturing method Pending CN104358251A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410671470.0A CN104358251A (en) 2014-11-21 2014-11-21 Main reinforcement distance control device during pile foundation project reinforcement cage manufacturing and pile foundation project reinforcement cage manufacturing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410671470.0A CN104358251A (en) 2014-11-21 2014-11-21 Main reinforcement distance control device during pile foundation project reinforcement cage manufacturing and pile foundation project reinforcement cage manufacturing method

Publications (1)

Publication Number Publication Date
CN104358251A true CN104358251A (en) 2015-02-18

Family

ID=52525550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410671470.0A Pending CN104358251A (en) 2014-11-21 2014-11-21 Main reinforcement distance control device during pile foundation project reinforcement cage manufacturing and pile foundation project reinforcement cage manufacturing method

Country Status (1)

Country Link
CN (1) CN104358251A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106040921A (en) * 2016-05-24 2016-10-26 中交第航务工程局有限公司 Cylindrical steel reinforcement cage quick precise connection machining formwork and manufacturing method for steel reinforcement cages
CN112091132A (en) * 2020-08-25 2020-12-18 中交路桥建设有限公司 Method for quickly positioning main reinforcement of pile foundation reinforcement cage
CN113369424A (en) * 2021-06-04 2021-09-10 云南建投第十一建设有限公司 Method for quickly manufacturing reinforcement cage
CN113756291A (en) * 2021-10-12 2021-12-07 上海东华建设管理有限公司 Assembling construction method for cast-in-place pile reinforcement cage

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3731408B2 (en) * 1999-10-05 2006-01-05 株式会社大林組 Reinforcing rod production method
CN201380464Y (en) * 2009-04-16 2010-01-13 中铁六局集团有限公司 Spacing control clamping device used for manufacturing and mounting steel reinforcement cage
CN203209591U (en) * 2012-11-14 2013-09-25 中建三局建设工程股份有限公司 Standard processing device for big-diameter extra-long pile foundation full pre-assembly reinforcement cage
CN203380304U (en) * 2013-06-28 2014-01-08 中铁上海工程局有限公司 Tiled processing device for bored pile reinforcement cage
CN203526850U (en) * 2013-10-10 2014-04-09 中铁十九局集团有限公司 Processing tool for welding reinforcement cage
CN203737903U (en) * 2014-02-13 2014-07-30 山东寿光第一建筑有限公司 Longitudinal bar positioning tool for reinforcement cage
CN203900779U (en) * 2014-05-23 2014-10-29 中铁三局集团有限公司 F-shaped positioning fixture for control of distance between main reinforcements of reinforcement cage

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3731408B2 (en) * 1999-10-05 2006-01-05 株式会社大林組 Reinforcing rod production method
CN201380464Y (en) * 2009-04-16 2010-01-13 中铁六局集团有限公司 Spacing control clamping device used for manufacturing and mounting steel reinforcement cage
CN203209591U (en) * 2012-11-14 2013-09-25 中建三局建设工程股份有限公司 Standard processing device for big-diameter extra-long pile foundation full pre-assembly reinforcement cage
CN203380304U (en) * 2013-06-28 2014-01-08 中铁上海工程局有限公司 Tiled processing device for bored pile reinforcement cage
CN203526850U (en) * 2013-10-10 2014-04-09 中铁十九局集团有限公司 Processing tool for welding reinforcement cage
CN203737903U (en) * 2014-02-13 2014-07-30 山东寿光第一建筑有限公司 Longitudinal bar positioning tool for reinforcement cage
CN203900779U (en) * 2014-05-23 2014-10-29 中铁三局集团有限公司 F-shaped positioning fixture for control of distance between main reinforcements of reinforcement cage

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106040921A (en) * 2016-05-24 2016-10-26 中交第航务工程局有限公司 Cylindrical steel reinforcement cage quick precise connection machining formwork and manufacturing method for steel reinforcement cages
CN112091132A (en) * 2020-08-25 2020-12-18 中交路桥建设有限公司 Method for quickly positioning main reinforcement of pile foundation reinforcement cage
CN113369424A (en) * 2021-06-04 2021-09-10 云南建投第十一建设有限公司 Method for quickly manufacturing reinforcement cage
CN113756291A (en) * 2021-10-12 2021-12-07 上海东华建设管理有限公司 Assembling construction method for cast-in-place pile reinforcement cage

Similar Documents

Publication Publication Date Title
CN103350165B (en) Processing device and method capable of manufacturing reinforcement cages with different diameters
CN104358251A (en) Main reinforcement distance control device during pile foundation project reinforcement cage manufacturing and pile foundation project reinforcement cage manufacturing method
CN202570872U (en) Cold bending correction device for steel pipe rods
CN104532829B (en) A kind of pile foundation reinforcement cage preparation method
CN109226601B (en) Reinforcing mesh forming process
CN203679102U (en) Full-automatic hydraulic mesh bending device
CN204524120U (en) The vertical loopful of large diameter pile foundation steel reinforcement cage is to location moulding bed device
CN105421341A (en) Large-diameter pile foundation reinforcement cage manufacturing method
CN203900346U (en) Bracket device for manufacturing reinforcement cage
CN204343550U (en) Washroom water stopping thresholds jig
CN203924039U (en) A kind of filling pile cage of reinforcement topping control structure
CN203755696U (en) Rectangular cross section column vertical rebar positioning device
CN210132636U (en) Whole ligature device of precast box girder hogging moment notch reinforcing bar
CN106583603A (en) Manufacturing method for sprayed concrete reinforcing mesh and bracket used in manufacturing method
CN105364291A (en) Bridge reinforcement cage ground mold roll welding frame and application thereof
CN211171938U (en) Quick distance instrument of stake owner muscle
CN205200789U (en) Bridge reinforcing bar cage topotype roll welding frame
CN205363119U (en) A welding stent system that be used for waterproof wall body engineering to drawing screw rod
CN212271406U (en) Steel reinforcement cage stirrup interval controlling means
CN210317347U (en) Tunnel grid bow member bed-jig
CN204326063U (en) A kind of pile foundation reinforcement cage producing device
CN204982671U (en) Automatic adjustment tool of pier shaft reinforcing bar
CN205733497U (en) A kind of rapid welding fixes the mold of bolt group
CN105317056A (en) Reinforced inspection well cover plate
CN205614240U (en) Bored concrete pile steel reinforcement cage owner muscle interval fixing tool

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150218