CN110188997A - A kind of construction quality cruising resource content evaluation method and its system - Google Patents

A kind of construction quality cruising resource content evaluation method and its system Download PDF

Info

Publication number
CN110188997A
CN110188997A CN201910393047.1A CN201910393047A CN110188997A CN 110188997 A CN110188997 A CN 110188997A CN 201910393047 A CN201910393047 A CN 201910393047A CN 110188997 A CN110188997 A CN 110188997A
Authority
CN
China
Prior art keywords
inspection
standard
score
quality
situation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910393047.1A
Other languages
Chinese (zh)
Inventor
胡昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ganzhou Heyong Software Development Co Ltd
Original Assignee
Ganzhou Heyong Software Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ganzhou Heyong Software Development Co Ltd filed Critical Ganzhou Heyong Software Development Co Ltd
Priority to CN201910393047.1A priority Critical patent/CN110188997A/en
Publication of CN110188997A publication Critical patent/CN110188997A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The present invention provides a kind of construction quality cruising resource content evaluation method and its systems, the system comprises: foundation includes quality examination index and the BIM model for checking standard of deducting point, checks that standard of deducting point includes important indicator standard of deducting point and routine inspection standard of deducting point;The corresponding inspection lot performance of acquisition quality Index for examination and routine inspection situation;BIM model is according to inspection lot performance and routine inspection situation according to inspection standard of deducting point output quality examination appraisal result to provide foundation for construction quality cruising.The present invention is by uploading the corresponding inspection lot performance of quality examination index and routine inspection situation, the deduction of points value that the output corresponding content of automation obtains compared with standards of grading, and projects final score is calculated in comprehensive deduction of points situation.

Description

A kind of construction quality cruising resource content evaluation method and its system
Technical field
The present invention relates to the engineering construction project management field more particularly to a kind of construction quality cruising resource content evaluation method and Its system.
Background technique
Engineering Quality Control refers to that supervising engineer organizes to participate in the contractor of construction, is built by contract standard, and The factors for forming quality are detected, are veritified, the supervision and management process of adjustment, corrective action is proposed to difference.In time and Positive implementation Engineering Quality Control can guarantee and improve construction quality.
Existing Engineering Quality Control method is to establish taking human as core perfect, does not form a set of standardization, intelligence The evaluation system of energyization.Be manually entered and statistics be easy to appear mistake, and it is artificial judge in subjective desire occupy it is main because Element, it is inconsistent that this will lead to judgment criteria each time.Therefore, a kind of intelligentized evaluation method and system are very necessary 's.
Summary of the invention
It is an object of that present invention to provide a kind of construction quality cruising resource content evaluation method and its systems, to solve conventional method Can not intelligent appraisement and judge there is technical issues that.
To achieve the above object, the present invention provides a kind of construction quality cruising resource content evaluation methods, comprising the following steps:
S1, foundation include quality examination index and the BIM model for checking standard of deducting point, check that standard of deducting point includes weight Want index standard of deducting point and routine inspection standard of deducting point;
The corresponding inspection lot performance of S2, acquisition quality Index for examination and routine inspection situation;
S3, BIM model export quality according to inspection standard of deducting point according to inspection lot performance and routine inspection situation Check appraisal result to provide foundation for construction quality cruising.
Preferably, quality examination appraisal result includes inspection lot scoring, project scoring, project leader scores, company is commented Divide and cruising personnel score.
Preferably, inspection lot performance includes inspection lot important indicator performance and routine inspection situation.
Preferably, important indicator performance deduction of points situation is referring to important indicator standard of deducting point;
The deduction of points of routine inspection situation is referring to routine inspection standard of deducting point, routine inspection standard of deducting point are as follows: routine inspection situation Check that situation and general data check that situation, main project check that situation and general data check that situation is total including main project Total score is 100 points, and the every discovery one of main project is underproof to deduct 10 points;The every discovery one of general data is underproof, It deducts points according to qualification rate.
Preferably, the standard deducted points according to qualification rate are as follows:
Qualification rate is lower than 80%, deducts points by qualification rate: when qualification rate is 70-80%, detaining 1 point, hereafter, qualification rate is every Low 10% adds 1 point of button;Qualification rate is not less than 80%, and test point occurs influencing using function or maximum deviation being more than to standardize regulation 1.5 times of tolerance, detain 1 point;Otherwise, it does not deduct points.
Preferably, inspection lot, which scores, includes:
When there is important indicator: single inspection lot score=inspection lot quality-critical index checking score * 70%+ inspection lot Quality general indicator checks score * 30%;
When no important indicator: single inspection lot score=60+ examines quality of lot general indicator to check score * 40%.
Preferably, project Rating Model are as follows:
Project score=∑ single inspection lot score/k
Wherein, k is that the item-test batch checks number.
Preferably, project leader's Rating Model are as follows:
Project leader's score=∑ single inspection lot score/m
Wherein, m is that responsible person's management project inspection lot checks number.
Preferably, cruising personnel Rating Model are as follows:
Cruising personnel score=∑ (100- single inspection lot score)+2 × j
Wherein, j is that cruising personnel's inspection lot checks number.
Above-mentioned evaluation method is relied on, the invention also provides a kind of construction quality cruising resource content evaluation systems, including deposit Reservoir, processor and storage on a memory and the computer program that can run on a processor, processor execution computer The step of any of the above-described method is realized when program.
The present invention is by uploading the corresponding inspection lot performance of quality examination index and routine inspection situation, automation The deduction of points value that is obtained compared with standards of grading of output corresponding content, and that projects are calculated is final for comprehensive deduction of points situation Point.
Other than objects, features and advantages described above, there are also other objects, features and advantages by the present invention. Below with reference to accompanying drawings, the present invention is described in further detail.
Detailed description of the invention
The attached drawing constituted part of this application is used to provide further understanding of the present invention, schematic reality of the invention It applies example and its explanation is used to explain the present invention, do not constitute improper limitations of the present invention.In the accompanying drawings:
Fig. 1 is a kind of construction quality cruising resource content evaluation method flow diagram of the preferred embodiment of the present invention.
Specific embodiment
The embodiment of the present invention is described in detail below in conjunction with attached drawing, but the present invention can be defined by the claims Implement with the multitude of different ways of covering.
The embodiment of the present invention discloses a kind of construction quality cruising resource content evaluation method first, and this method, which can run on, to be based on On the multi-clients such as mobile phone, tablet computer, the computer of the platforms such as windows platform, Android platform or IOS, specific manifestation Form includes but is not limited to the combination using APP and its hardware support kit developed and loaded based on corresponding platform.Such as Fig. 1 institute Show, the process that this method is implemented in client includes:
S1, foundation include quality examination index and the BIM model for checking standard of deducting point, check that standard of deducting point includes weight Want index standard of deducting point and routine inspection standard of deducting point.
This gives three kinds of quality Index for examination and check standard of deducting point list, respectively road engineering is examined Quality of lot important indicator and inspection standard of deducting point, science of bridge building inspection lot quality-critical index and inspection standard of deducting point and building Project quality inspection quality of lot important indicator and inspection standard of deducting point, as shown in following table 1-3.
1 road engineering inspection lot quality-critical index of table and inspection standard of deducting point
2 road engineering inspection lot quality-critical index of table and inspection standard of deducting point
3 architectural engineering inspection lot quality-critical index of table and inspection standard of deducting point
It is beyond the value except specification allowable error beyond examination scope value, upward carry is rounded in table 1-3.Due to Various industries are different for the standard of quality management.Therefore important indicator standard of deducting point is also just different.And routine inspection button Minute mark standard is all based on basis, therefore unified one kind can be used in standards of grading, to reduce the complexity of model.
The corresponding inspection lot performance of S2, acquisition quality Index for examination and routine inspection situation.
Inspection lot quality examination is usually completed by cruising staff, and according to the requirement input checking feelings in above table Condition.It can such as have been described at 3 for this important indicator item of coiled material construction quality, cruising staff in waterproofing work in table 3 Bubble directly uploads shooting picture at this.BIM model is beaten according to the description situation of upload or the picture of shooting Divide and deduct points, to provide last evaluation result.
S3, BIM model export quality according to inspection standard of deducting point according to inspection lot performance and routine inspection situation Check appraisal result to provide foundation for construction quality cruising.
Preferably, quality examination appraisal result includes inspection lot scoring, project scoring, project leader scores, company is commented Divide and cruising personnel score.
Preferably, inspection lot performance includes inspection lot important indicator performance and routine inspection situation.
Preferably, important indicator performance deduction of points situation is referring to important indicator standard of deducting point;
The deduction of points of routine inspection situation is referring to routine inspection standard of deducting point, routine inspection standard of deducting point are as follows: routine inspection situation Check that situation and general data check that situation, main project check that situation and general data check that situation is total including main project Total score is 100 points, and the every discovery one of main project is underproof to deduct 10 points;The every discovery one of general data is underproof, It deducts points according to qualification rate.
Preferably, the standard deducted points according to qualification rate are as follows:
Qualification rate is lower than 80%, deducts points by qualification rate: when qualification rate is 70-80%, detaining 1 point, hereafter, qualification rate is every Low 10% adds 1 point of button;Qualification rate is not less than 80%, and test point occurs influencing using function or maximum deviation being more than to standardize regulation 1.5 times of tolerance, detain 1 point;Otherwise, it does not deduct points.
Preferably, inspection lot, which scores, includes:
When there is important indicator: single inspection lot score=inspection lot quality-critical index checking score * 70%+ inspection lot Quality general indicator checks score * 30%;
When no important indicator: single inspection lot score=60+ examines quality of lot general indicator to check score * 40%.
Preferably, project Rating Model are as follows:
Project score=∑ single inspection lot score/k
Wherein, k is that the item-test batch checks number.
Preferably, project leader's Rating Model are as follows:
Project leader's score=∑ single inspection lot score/m
Wherein, m is that responsible person's management project inspection lot checks number.
Preferably, cruising personnel Rating Model are as follows:
Cruising personnel score=∑ (100- single inspection lot score)+2 × j
Wherein, j is that cruising personnel's inspection lot checks number.
Above-mentioned evaluation method is relied on, the invention also provides a kind of construction quality cruising resource content evaluation systems, including deposit Reservoir, processor and storage on a memory and the computer program that can run on a processor, processor execution computer The step of any of the above-described method is realized when program.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of construction quality cruising resource content evaluation method, which comprises the following steps:
S1, foundation include quality examination index and the BIM model for checking standard of deducting point, and the inspection standard of deducting point includes weight Want index standard of deducting point and routine inspection standard of deducting point;
S2, the corresponding inspection lot performance of the acquisition quality examination index and routine inspection situation;
S3, the BIM model are deducted points according to the inspection lot performance and the routine inspection situation according to the inspection Standard output quality examination appraisal result is to provide foundation for construction quality cruising.
2. a kind of engineering quality supervision personnel ability to supervise evaluation method according to claim 1, which is characterized in that described Quality examination appraisal result includes that inspection lot scoring, project scoring, project leader's scoring, company's scoring and cruising personnel comment Point.
3. a kind of engineering quality supervision personnel ability to supervise evaluation method according to claim 1, which is characterized in that examine Criticizing performance includes inspection lot important indicator performance and routine inspection situation.
4. a kind of engineering quality supervision personnel ability to supervise evaluation method according to claim 3, which is characterized in that described Important indicator performance deducts points situation referring to the important indicator standard of deducting point;
The routine inspection situation deduction of points is referring to the routine inspection standard of deducting point, the routine inspection standard of deducting point are as follows: described Routine inspection situation includes that main project checks that situation and general data check situation, and the main project checks situation and described General data checks that situation adds up to total score to be 100 points, and the every discovery one of main project is underproof to deduct 10 points;It is described The every discovery one of general data is underproof, deducts points according to qualification rate.
5. a kind of engineering quality supervision personnel ability to supervise evaluation method according to claim 4, which is characterized in that according to The standard that qualification rate is deducted points are as follows:
Qualification rate is lower than 80%, deducts points by qualification rate: when qualification rate is 70-80%, detaining 1 point, hereafter, qualification rate is per low 10% adds 1 point of button;Qualification rate is not less than 80%, and test point occurs influencing being more than to standardize regulation to permit using function or maximum deviation Perhaps 1.5 times of deviation, 1 point is detained;Otherwise, it does not deduct points.
6. a kind of engineering quality supervision personnel ability to supervise evaluation method according to claim 4 or 5, which is characterized in that The inspection lot scores
When there is the important indicator: single inspection lot score=inspection lot quality-critical index checking score * 70%+ inspection lot Quality general indicator checks score * 30%;
When without the important indicator: single inspection lot score=60+ examines quality of lot general indicator to check score * 40%.
7. a kind of engineering quality supervision personnel ability to supervise evaluation method according to claim 6, which is characterized in that described Project Rating Model are as follows:
Project score=∑ single inspection lot score/k
Wherein, k is that the item-test batch checks number.
8. a kind of engineering quality supervision personnel ability to supervise evaluation method according to claim 6, which is characterized in that described Project leader's Rating Model are as follows:
Project leader's score=∑ single inspection lot score/m
Wherein, m is that responsible person's management project inspection lot checks number.
9. a kind of engineering quality supervision personnel ability to supervise evaluation method according to claim 6, which is characterized in that described Cruising personnel's Rating Model are as follows:
Cruising personnel score=∑ (100- single inspection lot score)+2 × j
Wherein, j is that cruising personnel's inspection lot checks number.
10. a kind of construction quality cruising resource content evaluation system, including memory, processor and storage are on a memory and can be The computer program run on processor, which is characterized in that the processor realizes above-mentioned power when executing the computer program Benefit requires the step of 1 to 9 any the method.
CN201910393047.1A 2019-05-13 2019-05-13 A kind of construction quality cruising resource content evaluation method and its system Pending CN110188997A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910393047.1A CN110188997A (en) 2019-05-13 2019-05-13 A kind of construction quality cruising resource content evaluation method and its system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910393047.1A CN110188997A (en) 2019-05-13 2019-05-13 A kind of construction quality cruising resource content evaluation method and its system

Publications (1)

Publication Number Publication Date
CN110188997A true CN110188997A (en) 2019-08-30

Family

ID=67714490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910393047.1A Pending CN110188997A (en) 2019-05-13 2019-05-13 A kind of construction quality cruising resource content evaluation method and its system

Country Status (1)

Country Link
CN (1) CN110188997A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113449615A (en) * 2021-06-16 2021-09-28 新安洁环境卫生股份有限公司 Intelligent inspection method and system for cleaning operation quality and storage medium
CN113934751A (en) * 2021-12-16 2022-01-14 深圳市明源云科技有限公司 Index value measuring method, equipment and computer readable storage medium
CN114519498A (en) * 2022-01-10 2022-05-20 湖北国际物流机场有限公司 Quality evaluation method and system based on BIM (building information modeling)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106295998A (en) * 2016-08-10 2017-01-04 广州市微柏软件股份有限公司 A kind of quality-controlsystem in management built based on traffic engineering
CN106997511A (en) * 2017-04-05 2017-08-01 中铁四局集团有限公司 Railway beam course management system and railway beam a management method based on BIM technology
CN207517058U (en) * 2017-07-14 2018-06-19 江苏南工科技集团有限公司 A kind of wisdom safety grade of architecture assessment system based on BIM and cloud computing
CN108564207A (en) * 2018-03-30 2018-09-21 合肥工业大学 Architectural engineering intelligence Authorize to Bid based on BIM manages system
CN108564283A (en) * 2018-04-16 2018-09-21 南京金寓信息科技有限公司 Construction quality rating database construction method based on BIM
CN108959736A (en) * 2018-06-19 2018-12-07 厦门大学 A kind of bridge technology status assessment method based on BIM
KR101909996B1 (en) * 2017-08-22 2018-12-28 주식회사 연우테크놀러지 Construction Quantity take-off system based on the BIM and method therefor

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106295998A (en) * 2016-08-10 2017-01-04 广州市微柏软件股份有限公司 A kind of quality-controlsystem in management built based on traffic engineering
CN106997511A (en) * 2017-04-05 2017-08-01 中铁四局集团有限公司 Railway beam course management system and railway beam a management method based on BIM technology
CN207517058U (en) * 2017-07-14 2018-06-19 江苏南工科技集团有限公司 A kind of wisdom safety grade of architecture assessment system based on BIM and cloud computing
KR101909996B1 (en) * 2017-08-22 2018-12-28 주식회사 연우테크놀러지 Construction Quantity take-off system based on the BIM and method therefor
CN108564207A (en) * 2018-03-30 2018-09-21 合肥工业大学 Architectural engineering intelligence Authorize to Bid based on BIM manages system
CN108564283A (en) * 2018-04-16 2018-09-21 南京金寓信息科技有限公司 Construction quality rating database construction method based on BIM
CN108959736A (en) * 2018-06-19 2018-12-07 厦门大学 A kind of bridge technology status assessment method based on BIM

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113449615A (en) * 2021-06-16 2021-09-28 新安洁环境卫生股份有限公司 Intelligent inspection method and system for cleaning operation quality and storage medium
CN113934751A (en) * 2021-12-16 2022-01-14 深圳市明源云科技有限公司 Index value measuring method, equipment and computer readable storage medium
CN113934751B (en) * 2021-12-16 2022-03-01 深圳市明源云科技有限公司 Index value measuring method, equipment and computer readable storage medium
CN114519498A (en) * 2022-01-10 2022-05-20 湖北国际物流机场有限公司 Quality evaluation method and system based on BIM (building information modeling)

Similar Documents

Publication Publication Date Title
CN110188997A (en) A kind of construction quality cruising resource content evaluation method and its system
CN109858828B (en) Power distribution network fixed value automatic setting method and device and distribution network system
CN113256102B (en) High-risk technological process risk control method and system
CN104281523B (en) A kind of demand Testability Analysis method and system
CN108038616A (en) A kind of work transmission line analysis of prices method
CN106384399A (en) IOT (Internet of Things)-office-oriented network attendance method
CN110232445A (en) A kind of historical relic authenticity identification method of knowledge based distillation
CN110907883A (en) Metering supervision method and system for automatic verification system of electric energy meter
CN107391452A (en) A kind of software defect estimated number method based on data lack sampling and integrated study
CN104598584A (en) Method and equipment for processing assessment data of information system
CN108320112A (en) A kind of method and device of determining equipment health status
CN111340257A (en) Optimization method and system for maintenance plan of power transmission equipment based on risk analysis
CN111047157A (en) Construction scheme comparing and selecting method in building engineering
CN109522517A (en) A kind of ammeter crash rate calculation method and system
CN112595346A (en) Automatic temperature cycle testing method, system and control device for liquid floating gyroscope
Zhou et al. Issues in dependency modeling in multi-unit seismic PRA
CN108197424A (en) E-learning behavior power-law distribution modelling method of probabilistic in large scale network education
CN116032016B (en) Intelligent wind power plant running state on-line monitoring and early warning system and early warning method
CN116739147A (en) BIM-based intelligent energy consumption management and dynamic carbon emission calculation combined method and system
CN110096797A (en) A kind of group system mission reliability modeling and simulating method
CN105488521B (en) A kind of dilatation screening sample method based on kernel function
CN114240061A (en) Task matching method and device for manufacturing workshop
CN111063226A (en) Power simulation training scoring method, system and storage medium
CN108776925A (en) A kind of concrete order control method
CN109658014A (en) A kind of construction overall management method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination