CN110185076A CN201910419840.4A CN201910419840A CN110185076A CN 110185076 A CN110185076 A CN 110185076A CN 201910419840 A CN201910419840 A CN 201910419840A CN 110185076 A CN110185076 A CN 110185076A
Authority
CN
China
Prior art keywords
stake
reinforcement
existing building
rectification method
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910419840.4A
Other languages
Chinese (zh)
Inventor
贾国平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910419840.4A priority Critical patent/CN110185076A/en
Publication of CN110185076A publication Critical patent/CN110185076A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of reinforcement and rectification methods of existing building, comprising the following steps: axis location positions engineering according to cell general arrangement plan, determines axial location;Stake positioning, according to design on axis guide pile position, and each position is numbered;Check and correction, is proofreaded according to the stake numbered, also, one by one repeatedly after collated correct, confirms stake position;It excavates, according to demand first vertical cut, then inclination, which is excavated, arrives ground beneath, rear vertical cut;It checks and accepts, stops after excavating projected depth, checked and accepted via related personnel, until reaching the depth of requirement;First time molding, formwork according to the design needs, also, steel reinforcement cage is placed in template;It pours for the first time, is making casting concrete between template, be shaped to bottom stake to it, and be embedded with steel bar end.The utility model has the advantages that can effectively guarantee that existing foundation strength increases, while it can rectify a deviation to building, construction area is small, simple process.

Description

A kind of reinforcement and rectification method of existing building
Technical field
The present invention relates to strengthening of foundation correction fields, it particularly relates to a kind of reinforcement and rectification method of existing building.
Background technique
Existing building be easy to cause shallow layer foundation soft when encountering lasting rainfall perhaps geologic change or Non-uniform sedimentation, existing building can be easy to happen inclination at this time, need to rectify a deviation to building at this time, but existing Technology in mostly rectified a deviation using forced settlement, forced settlement, which is broadly divided into, takes soil forced landing, immersion rectifying method, by excavating or soaking The mode of water, it is high-end to structure foundation to force-land, so that building is restored in the deviation range of permission, reach correction Purpose, this kind of processing means need to excavate basis, and construction working face is big, and intensity is high, and construction technology is cumbersome, long in time limit.
For the problems in the relevant technologies, currently no effective solution has been proposed.
Summary of the invention
The purpose of the present invention is to provide a kind of reinforcement and rectification methods of existing building, to solve in above-mentioned background technique The problem of proposition.
To achieve the above object, the invention provides the following technical scheme:
A kind of reinforcement and rectification method of existing building, comprising the following steps:
Axis location positions engineering according to cell general arrangement plan, determines axial location;
Stake positioning, according to design on axis guide pile position, and each position is numbered;
Check and correction, is proofreaded according to the stake numbered, also, one by one repeatedly after collated correct, confirms stake position;
It excavates, according to demand first vertical cut, then inclination, which is excavated, arrives ground beneath, rear vertical cut;
It checks and accepts, stops after excavating projected depth, checked and accepted via related personnel, until reaching the depth of requirement;
First time molding, formwork according to the design needs, also, steel reinforcement cage is placed in template;
It pours for the first time, is making casting concrete between template, be shaped to bottom stake to it, and be embedded with steel bar end;
Jacking is placed jack in the stake of the bottom of above-mentioned forming, according to the direction of building inclination, is jacked as requested Building;
Branch muscle measures gap therein after the completion of its jacking, intercepts several muscle according to gap;
Branch muscle is welded on the upper pre-buried steel bar end of bottom stake, while removing jack by welding;
Second of molding is reserved after the branch muscle periphery molding being welded and pours mouth;
Second of pouring carries out placing concrete by the reserved mouth that pours, and to its molding;
Backfill after the assay was approved to it backfills the earthwork, and slightly tamp.
Further, when the excavation, if encountering dangerous stratum needs to do retaining wall, retaining wall with a thickness of 150MM, wait protect Wall thickness is further continued for being excavated after reaching intensity.
Further, in above-mentioned first time pouring, the concrete strength poured is quotient's concrete of C20.
Further, it is shaped to bottom stake to it in above-mentioned first time pouring, the intensity of the bottom stake reaches design requirement 70% can be jacked.
Further, above-mentioned jacking is needed to place jack simultaneously on multiple bottom pile heads and be jacked.
Further, the outer diameter of the branch muscle is 20MM.
Further, it should be ensured that air flowing and brightness in borehole guarantee when excavation.
Further, it pours for above-mentioned second, the concrete poured is expansive concrete either dry and hard concrete therein one Kind.
Further, the diameter of the vertical muscle of the steel reinforcement cage should be not less than 14MM, and the spacing of stirrup should be lower half bottom Stake is 200MM, and the stake of the upper half bottom is 100MM.
Further, above-mentioned excavation is hand excavation, and jack-up construction follows reasonable jacking, absolutely prevents excessively to jack, and is prevented It only rectifies a deviation and secondary injury excessively is caused to building.
Compared with prior art, the invention has the following advantages: spread by carrying out multiple spot to existing ground comprehensively If stake, then jacked according to the direction of building inclination, the building after jacking can reach horizontal, then use major diameter Reinforcing bar withstand after pour expansive concrete, can effectively guarantee that existing foundation strength increases, while can carry out to building Correction, construction area is small, simple process.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is a kind of one of the flow chart of the reinforcement and rectification method of existing building according to an embodiment of the present invention;
Fig. 2 is the two of the flow chart of the reinforcement and rectification method of a kind of existing building according to an embodiment of the present invention;
Fig. 3 is the three of the flow chart of the reinforcement and rectification method of a kind of existing building according to an embodiment of the present invention.
Specific embodiment
In the following, making further description to invention in conjunction with attached drawing and specific embodiment:
Embodiment one:
Referring to Fig. 1, a kind of reinforcement and rectification method of existing building according to an embodiment of the present invention, including following step It is rapid:
Step S101, axis location position engineering according to cell general arrangement plan, determine axial location;
Step S103, stake positioning, according to design on axis guide pile position, and each position is numbered;
Step S105, check and correction, is proofreaded according to the stake numbered, also, one by one repeatedly after collated correct, confirms stake Position;
Step S107 is excavated, according to demand first vertical cut, and then inclination, which is excavated, arrives ground beneath, rear vertical cut;
Step S109 is checked and accepted, is stopped after excavating projected depth, check and accept via related personnel, until reaching requirement Depth;
Step S111, first time molding, formwork according to the design needs, also, steel reinforcement cage is placed in template;
Step S113 pours for the first time, is making casting concrete between template, is shaped to bottom stake to it, and pre-buried There is steel bar end;
Step S115, jacking are placed jack in the stake of the bottom of above-mentioned forming, according to the direction of building inclination, are pressed As requested jacks building;
Step S117, branch muscle measure gap therein after the completion of its jacking, intercept several muscle according to gap;
Branch muscle is welded on the upper pre-buried steel bar end of bottom stake, while removing jack by step S119, welding;
Step S121, second of molding are reserved after the branch muscle periphery molding being welded and pour mouth;
Step S123, second of pouring carry out placing concrete by the reserved mouth that pours, and to its molding;
Step S125, backfill after the assay was approved to it backfill the earthwork, and slightly tamp.
In Specific construction, when the excavation, if encountering dangerous stratum needs to do retaining wall, retaining wall with a thickness of 150MM, It is further continued for being excavated after dado thickness reaches intensity.
In Specific construction, in above-mentioned first time pouring, the concrete strength poured is quotient's concrete of C20.
In Specific construction, it is shaped to bottom stake to it in above-mentioned first time pouring, the intensity of the bottom stake reaches design and wants 70% asked can be jacked.
In Specific construction, above-mentioned jacking, which needs to place jack simultaneously on multiple bottom pile heads, to be jacked.
In Specific construction, the outer diameter of the branch muscle is 20MM.
In Specific construction, when excavation, should be ensured that the flowing of the air in borehole and brightness guarantee.
In Specific construction, above-mentioned second is poured, the concrete poured be expansive concrete either dry and hard concrete wherein One kind.
In Specific construction, the diameter of the vertical muscle of the steel reinforcement cage should be not less than 14MM, and the spacing of stirrup should be lower half Cutting bottom stake is 200MM, and the stake of the upper half bottom is 100MM.
In Specific construction, above-mentioned excavation is hand excavation, and jack-up construction follows reasonable jacking, absolutely prevents excessively to push up It rises, prevents correction from excessively causing secondary injury to building.
In conclusion stake is laid with comprehensively by carrying out multiple spot to existing ground, then in the side according to building inclination To being jacked, the building after jacking can reach horizontal, pour expansive concrete after then being withstood with the reinforcing bar of major diameter, can Effectively guarantee that existing foundation strength increases, while can rectify a deviation to building, construction area is small, simple process.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (10)

1. a kind of reinforcement and rectification method of existing building, which comprises the following steps:
Axis location positions engineering according to cell general arrangement plan, determines axial location;
Stake positioning, according to design on axis guide pile position, and each position is numbered;
Check and correction, is proofreaded according to the stake numbered, also, one by one repeatedly after collated correct, confirms stake position;
It excavates, according to demand first vertical cut, then inclination, which is excavated, arrives ground beneath, rear vertical cut;
It checks and accepts, stops after excavating projected depth, checked and accepted via related personnel, until reaching the depth of requirement;
First time molding, formwork according to the design needs, also, steel reinforcement cage is placed in template;
It pours for the first time, is making casting concrete between template, be shaped to bottom stake to it, and be embedded with steel bar end;
Jacking places jack in the stake of the bottom of above-mentioned forming, and according to the direction of building inclination, jacking is built as requested Object;
Branch muscle measures gap therein after the completion of its jacking, intercepts several muscle according to gap;
Branch muscle is welded on the upper pre-buried steel bar end of bottom stake, while removing jack by welding;
Second of molding is reserved after the branch muscle periphery molding being welded and pours mouth;
Second of pouring carries out placing concrete by the reserved mouth that pours, and to its molding;
Backfill after the assay was approved to it backfills the earthwork, and slightly tamp.
2. a kind of reinforcement and rectification method of existing building according to claim 1, which is characterized in that when the excavation, If encountering dangerous stratum needs to do retaining wall, retaining wall with a thickness of 150MM, be further continued for carrying out after dado thickness reaches intensity It excavates.
3. a kind of reinforcement and rectification method of existing building according to claim 1, which is characterized in that above-mentioned first time pours In filling, the concrete strength poured is quotient's concrete of C20.
4. a kind of reinforcement and rectification method of existing building according to claim 1, which is characterized in that above-mentioned first time pours It is shaped to bottom stake to it in filling, the intensity of the bottom stake, which reaches the 70% of design requirement, to be jacked.
5. a kind of reinforcement and rectification method of existing building according to claim 1, which is characterized in that above-mentioned jacking needs Jack is placed simultaneously on multiple bottom pile heads to be jacked.
6. a kind of reinforcement and rectification method of existing building according to claim 1, which is characterized in that outside the branch muscle Diameter is 20MM.
7. a kind of reinforcement and rectification method of existing building according to claim 1, which is characterized in that should be protected when excavation The air flowing and brightness demonstrate,proved in borehole guarantee.
8. a kind of reinforcement and rectification method of existing building according to claim 1, which is characterized in that above-mentioned to pour for the second time It fills, the concrete poured is that expansive concrete either dry and hard concrete is one such.
9. a kind of reinforcement and rectification method of existing building according to claim 1, which is characterized in that the steel reinforcement cage The diameter of vertical muscle should be not less than 14MM, and the spacing of stirrup should be that the stake of lower half bottom is 200MM, and the stake of the upper half bottom is 100MM.
10. a kind of reinforcement and rectification method of existing building according to claim 1, which is characterized in that above-mentioned excavation is Hand excavation, jack-up construction follow reasonable jacking, absolutely prevent excessively to jack, and prevent correction from excessively causing secondary wound to building Evil.
CN201910419840.4A 2019-05-20 2019-05-20 A kind of reinforcement and rectification method of existing building Pending CN110185076A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910419840.4A CN110185076A (en) 2019-05-20 2019-05-20 A kind of reinforcement and rectification method of existing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910419840.4A CN110185076A (en) 2019-05-20 2019-05-20 A kind of reinforcement and rectification method of existing building

Publications (1)

Publication Number Publication Date
CN110185076A true CN110185076A (en) 2019-08-30

Family

ID=67716995

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910419840.4A Pending CN110185076A (en) 2019-05-20 2019-05-20 A kind of reinforcement and rectification method of existing building

Country Status (1)

Country Link
CN (1) CN110185076A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1123353A (en) * 1994-11-19 1996-05-29 唐殿峰 Correction and reinforcing method for inclined house
JP2001262602A (en) * 2000-03-21 2001-09-26 Hisao Sakuraba Building sill structure and method of executing building foundation
CN109706987A (en) * 2019-02-25 2019-05-03 山东建筑大学 A kind of frame structure building inside lifting inclination-correcting method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1123353A (en) * 1994-11-19 1996-05-29 唐殿峰 Correction and reinforcing method for inclined house
JP2001262602A (en) * 2000-03-21 2001-09-26 Hisao Sakuraba Building sill structure and method of executing building foundation
CN109706987A (en) * 2019-02-25 2019-05-03 山东建筑大学 A kind of frame structure building inside lifting inclination-correcting method

Similar Documents

Publication Publication Date Title
CN104196034B (en) A kind of utilize steel sheet pile as the foundation ditch construction method in supporting cofferdam
CN110080318B (en) Deviation rectifying method for local settlement of pile foundation building
CN107059667B (en) Door shape assembled armored concrete box culvert and its construction method
CN108643935A (en) The construction method in tunnel under rich water shallow embedding geology
CN109505229A (en) Highway high gradient slope stress equilibrium and vibration damping are taken precautions against natural calamities high bridge pier structure and construction method
CN106759439B (en) Tower crane foundation for foundation pit and construction method thereof
CN108894214A (en) A kind of solution cavity geological environment bored concrete pile and its bore forming method
CN101343869A (en) Underground continuous wall construction method of city-across pipeline
CN102430277B (en) Coarse grid sunk well for physically processing waste water and construction method thereof
CN104563146A (en) Construction method for open caisson engineering of fixed and direct burial type rainwater and sewage pumping station
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN107675704A (en) A kind of artificial digging pile assembled retaining wall and its construction technology
CN110468938A (en) A kind of municipal drain pipeline construction method
CN112695763A (en) Deep sludge stratum foundation pit excavation method
CN108316283A (en) The devices and methods therefor of influence of foundation excavation is controlled using hole rising pouring slurry ground-connecting-wall
CN206721870U (en) A kind of long auger guncreting pile steel reinforcement cage
CN106245654A (en) Deposited reinforced concrete pile exempts from inter-pile soil excavation construction method
CN101798823B (en) Construction method of performing remote deviation rectification by passageway method
CN110016919A (en) A kind of aging blocks install the minimally invasive foundation pit structure of elevator and construction method additional
CN205617390U (en) A softer side of sears layer excavation supporting system for loess area
CN106120793A (en) A kind of tilt the method for correcting error of pile for prestressed pipe and structure
CN113216215A (en) Deep groove support reverse construction method in complex environment
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN207878451U (en) A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation
CN108625368A (en) A kind of Deep Thick Soft Ground Area Rigid Long-Short-Pile Composite Foundation construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190830