CN110173102A - The more work surface synchronous construction foot hand systems of super high-rise building and construction method - Google Patents

The more work surface synchronous construction foot hand systems of super high-rise building and construction method Download PDF

Info

Publication number
CN110173102A
CN110173102A CN201910382136.6A CN201910382136A CN110173102A CN 110173102 A CN110173102 A CN 110173102A CN 201910382136 A CN201910382136 A CN 201910382136A CN 110173102 A CN110173102 A CN 110173102A
Authority
CN
China
Prior art keywords
construction
scaffold
layers
work surface
super high
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910382136.6A
Other languages
Chinese (zh)
Inventor
陈思睿
白小刚
黄国华
孙鹏鹏
宋全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 1 Group Co Ltd
Original Assignee
Shanghai Construction No 1 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 1 Group Co Ltd filed Critical Shanghai Construction No 1 Group Co Ltd
Priority to CN201910382136.6A priority Critical patent/CN110173102A/en
Publication of CN110173102A publication Critical patent/CN110173102A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/001Safety or protective measures against falling down relating to scaffoldings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

A kind of more work surface synchronous construction foot hand systems of super high-rise building of the invention and construction method, are related to formwork system technical field, and single for solving traditional construction foot hand system work surface, total construction time is long, the higher problem of construction cost., by two sets of lifted scaffolds above and below setting, frame body height and promotion number of floor levels are different for it, and the main function of top lifted scaffold is to carry out major structure of construction construction, edge list masonry and external wall plastering etc. to construct;The main function of lower lift formula scaffold is carried out for the alien invasions ornamental work such as lacquer in a small amount of plastering of exterior wall completion, surface brick adherence, shutter;Therebetween it is spaced certain floor, thus Optimizing construction process, so that each working procedure cross construction, substantially reduces total construction time, improves construction efficiency.

Description

The more work surface synchronous construction foot hand systems of super high-rise building and construction method
Technical field
The present invention relates to formwork system technical field, in particular to a kind of more work surface synchronous construction foot hands of super high-rise building System and construction method.
Background technique
Currently, well known skyscraper external scaffolding is generally using traditional console mode+overhanging scaffold or a promotion Formula scaffold, work surface is single, and no fado work surface is constructed simultaneously.Cause so not only total construction time it is long, and need to put into big The human and material resources of amount, construction cost are higher.
Therefore, how a kind of more work surface synchronous construction foot hand systems of super high-rise building and construction method are provided, is ability The technical issues of field technique personnel's urgent need to resolve.
Summary of the invention
In order to overcome traditional construction foot hand system work surface single, total construction time is long, the higher problem of construction cost, this Invention is designed to provide a kind of more work surface synchronous construction foot hand systems of super high-rise building and construction method, by using two Portion's lifted scaffold, Optimizing construction process, the setting floor system that intercepts water guarantee more work surface synchronous constructions, are greatly saving Maltilevel security isolated system is constructed while manpower and material resources to guarantee the safety of itself.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of more work surface synchronous construction foot hand systems of super high-rise building, the foot hand system include two sets of hoisting type foot hands Frame, respectively top lifted scaffold and lower lift formula scaffold, the lifted scaffold include guide rail main frame, water Flat scaffold, attachment supporting arrangement and lifting means, the top lifted scaffold, which is also matched, to be arranged with floor and intercepts water knot Structure;
The guide rail main frame includes guide rail and vertical main framework interconnected, the vertical main framework be preceding upright bar, The frame structure that upright bar, horizon bar and brace are formed afterwards;
The horizontal supporting frame is assembled by the standard knot and connecting rod of steel-pipe welding, and horizontal supporting frame passes through bolt It is mounted on the bottom of scaffold frame body;
The attachment supporting arrangement includes fixed guide seat and balancing point type fall-preventing safety interconnected, and the fixation is led It is fixed to seat by through-wall bolt and major structure of construction;
The lifting means includes the electric block and suspender member being equipped with, and the lifting means passes through suspender member and builds Build main structure connection.
Compared with prior art, the present invention is beneficial has the technical effect that
One, the more work surface synchronous construction foot hand systems of super high-rise building of the invention, by the way that top hoisting type foot hand is arranged Frame and lower lift formula scaffold, the frame body height of two sets of lifted scaffolds is different with number of floor levels is promoted, top hoisting type foot The main function of hand cradle is to carry out the constructions such as major structure of construction construction, edge list masonry and external wall plastering, the interspersed door in centre Window and railing construction, the vivid progress after climbing are that major structure of construction interior wall essence masonry is completed, interior wall thin-coat plaster is completed, exterior wall The float work of masonry, exterior wall large area in upper edge list and lines;The main function of lower lift formula scaffold is to carry out Vivid progress for alien invasions ornamental works such as lacquers in a small amount of plastering of exterior wall completion, surface brick adherence, shutter, after climbing For alien invasion molding (removing construction elevator, tower crane attached wall position), it is spaced certain floor therebetween, thus Optimizing construction process, So that each working procedure cross construction, substantially reduces total construction time, improves construction efficiency.
Two, the construction method of the more work surface synchronous construction foot hand systems of super high-rise building of the invention, top hoisting type foot Hand cradle, which is also matched, to be arranged with floor and intercepts water structure, guarantees more work surface synchronous constructions, structure while greatly using manpower and material resources sparingly Maltilevel security isolated system is built to guarantee the safety of foot hand system itself.
Further, the fixed guide seat includes the orienting roll wheel seat of several adjustable movements, each orienting roll There are four guide roller, two upright bars of guide rail to be inserted in orienting roll wheel seat for wheel seat, and four guide rollers constrain guide rail upright bar, It is formed and rolls sliding sleeve connection.Fixed guide seat can be in the WidFin of preformed hole vertical plane, to adapt to preformed hole vertical line direction Error, the adjustable distance in the front-back direction with major structure of construction surface of orienting roll wheel seat.The effect of fixed guide seat is constraint The movement of the horizontal portraitlandscape of guide rail main frame;The load that the transmitting of guide rail main frame comes is born, and transfers the load to building master Body structure is the anti-dumping for adhering to supporting arrangement, load component.
Further, the balancing point type fall-preventing safety includes balancing point axis and balancing point, and the balancing point is by balancing point axis and admittedly The axle bed being scheduled on orienting roll wheel seat is connected, and the both ends of balancing point spring are connected on balancing point and axle bed, and guide rail can led It is slided up and down in way roller seat.Present apparatus structure is simple, ingenious, is not required to manual operation, at any time can be with macroscopic examination, maintenance side Just, when occurring such as the problems such as balancing point swings not flexible or spring failure, the present apparatus does not lose function of safety protection, safe and reliable Property it is good, be adhere to supporting arrangement anti-fall component.
Further, it in order to guarantee more work surface synchronous constructions, needs to carry out floor and intercepts water, it is contemplated that water energy is trickled down Hole and few, the floor main positions that intercept water include: elevator, staircase pump line hole, interim feed pipe box out, big interspersed to apply Various piping shafts, flue on work floor are all closed with top lifted scaffold substantially;The floor intercepts water structure Including get water bucket and water blocking sill.Wherein, get water bucket is mainly set in elevator, is connect by installing pvc pipe in get water bucket lower part Enter in vertical tube, floor ponding is introduced into gutter;Water blocking sill be mainly set to staircase pump line hole, interim feed pipe hole, At staircase door opening and elevator door opening, floor ponding row sinuous flow is prevented.
Further, it is bolted in order to facilitate the installation of with disassembly, the get water bucket with elevator inner wall.Elevator water receiving Bucket is made into a monolith, with a thickness of 1mm, can disposably move, and material is galvanized iron sheet, is moved easily.
The present invention also provides the construction method of the more work surface synchronous construction foot hand systems of aforementioned super high-rise building, the constructions Method includes:
S1: installation lifted scaffold is spare;
S2: it is used to install wearing for suspender member and fixed guide seat in the pre-buried embedded part of design position when major structure of construction is constructed Wall screw hole after installing suspender member and fixed guide seat, lifts top lifted scaffold, and pass through according to project progress Suspender member and fixed guide seat are fixed on the outside of major structure of construction;
S3: hydropower installation is carried out on the major structure of construction below the top lifted scaffold and main structure is tested Receive construction;
S4: step S2, lifting and fixed lower lift formula scaffold are referred to, wherein between the lifted scaffold of upper and lower part Floor between at a distance of three layers to four layers.
Further, the step S1 includes:
Horizontal supporting frame is assembled, hoisting guiding rail main frame simultaneously corrects verticality, respectively by the bottom of guide rail main frame, outer Side, inboard are connect with the corresponding position of horizontal supporting frame;
After guide rail main frame is fixed fixed guide cover for seat is moved to the position that will be installed on guide rail, is fixed temporarily, And the verticality of the aspect of corrective rail main frame two, interim drawknot is installed, and with the construction of main structure engineering into Degree is installed remaining fixed guide seat and remaining frame body and is used for main building engineering construction;Lifting means is installed and is set up and is unloaded Expect platform.As the construction frame body of main body is set up upwards, fixed guide seat is installed upwards one by one, until frame body assembling finishes.Frame Body is set up the rising with main body and is risen, and is always ensured that more than one step frame of operation layer.Turnover panel, turnover panel is arranged in frame body bottom inside It should effectively be connect with frame body, guarantee the leakproofness under lifting and applying working condition, to prevent material from falling.Frame body bottom completely spreads foot Palm nails on woodwork plate and carries out secondary seal.Bottom turnover panel is welded into the outline border of 1.5m*1m using L40 angle bar, welds 2mm above Thick checkered steel plate, turnover panel and frame body bottom scaffold board hinge are hinged, and with wire rope inclined drawknot.
Further, the top lifted scaffold is N layers, and wherein n-th layer is major structure of construction construction layer, N- 1 layer is that demoulding turns over, floor is cleared up, the construction layer of closure screw hole;N-2 layers are snap the line, bar planting, Pipe installing and anti-bank The construction layer poured;N-3 layers built for decoration of exterior wall column, the construction layer that indoor masonry is built;N-4 layers are building body knot The construction layer of structure external wall plastering, masonry stuff up a crack and the installation of aluminium door window frame.The lower lift formula scaffold is M layers, wherein M Layer is the plastering of major structure of construction decoration of exterior wall column, local construction of exterior insulation system layer, and M-1 layers are to play ash cake bracing wire, facing tile The construction layer of stickup and deformation joint cover plate;M-2 layers for putty at major structure of construction exterior-wall heat insulation and are polished, install cooperation The monitoring of each pipeline and construction layer at hand;M-3 layers are lacquer, face brick jointing, shutter is installed, door and window ointment blocks Construction layer.
In practice of construction, the design number of plies of upper and lower part lifted scaffold and lower part layers more most than the practice of construction number of plies. That is, the number of plies that can be constructed is five layers when the design number of plies of the top lifted scaffold of design is five and half, it should Five layers of independently work compound, realize more work surface synchronous constructions, greatly improve construction efficiency.Similarly, lower lift formula When the number of plies of scaffold design is four and half, the number of plies that can be constructed is four layers.In view of upper and lower part lifted scaffold is constructed The contents of a project of operation are different, it is necessary to the examination for the major structure of construction constructed to top lifted scaffold and maintenance work After the completion, therefore the alien invasion ornamental work that can just carry out corresponding floor needs to keep between the lifted scaffold of upper and lower part Certain spacing, moreover, the climbing speed of upper and lower part lifted scaffold and the number of plies of climbing also are different.
Detailed description of the invention
Fig. 1 is the scheme of installation of the more work surface synchronous construction foot hand systems of one embodiment of the invention super high-rise building;
Fig. 2 is escalator and staircase in the more work surface synchronous construction foot hand systems of one embodiment of the invention super high-rise building Intercept water floor map;
Fig. 3 is escalator and staircase in the more work surface synchronous construction foot hand systems of one embodiment of the invention super high-rise building Intercept water elevational schematic view;
Fig. 4 is that the installation of get water bucket in the more work surface synchronous construction foot hand systems of one embodiment of the invention super high-rise building is shown It is intended to;
Fig. 5 is the schematic diagram of the more work surface synchronous construction foot hand system turnover panels of one embodiment of the invention super high-rise building.Figure In:
The top 1- lifted scaffold;2- lower lift formula scaffold;4- get water bucket;5- water blocking sill;6- turnover panel;7- frame body Bottom scaffold board;8- wirerope;9- feed pipe box out;10- pump line hole;11- vertical tube.
Specific embodiment
Below in conjunction with the drawings and specific embodiments to a kind of more work surface synchronous constructions of super high-rise building proposed by the present invention Foot hand system and construction method are described in further detail.According to following explanation, advantages and features of the invention will be become apparent from. Below will be by cited embodiment combination attached drawing, the technology contents and feature that the present invention will be described in detail.Need in addition it illustrate, Attached drawing is all made of very simplified form and using non-accurate ratio, only to convenient, lucidly aid illustration is of the invention The purpose of embodiment.For sake of convenience, "upper" described below, "lower" are consistent with the upper and lower direction of attached drawing, but this cannot Limitation as technical solution of the present invention.
Embodiment one
Illustrate the structure composition of the more work surface synchronous construction foot hand systems of super high-rise building of the invention in conjunction with Fig. 1 to Fig. 5.
Fig. 1 to Fig. 5, a kind of more work surface synchronous construction foot hand systems of super high-rise building are please referred to, which includes Two sets of lifted scaffolds, respectively top lifted scaffold 1 and lower lift formula scaffold 2, lifted scaffold include Guide rail main frame, horizontal supporting frame, attachment supporting arrangement and lifting means, top lifted scaffold 1, which is also matched, to be arranged with Floor intercepts water structure;Guide rail main frame includes guide rail and vertical main framework interconnected, and vertical main framework is preceding upright bar, stands afterwards The frame structure that bar, horizon bar and brace are formed;Horizontal supporting frame is assembled by the standard knot and connecting rod of steel-pipe welding, Horizontal supporting frame is mounted on the bottom of scaffold frame body by bolt;Adhering to supporting arrangement includes fixed guide interconnected Seat and balancing point type fall-preventing safety, fixed guide seat are fixed by through-wall bolt and major structure of construction;Lifting means includes matching The electric block and suspender member of setting are closed, lifting means is connect by suspender member with major structure of construction.
Specifically, the more work surface synchronous construction foot hand systems of super high-rise building of the invention are promoted by setting top Formula scaffold 1 and lower lift formula scaffold 2, the frame body height of two sets of lifted scaffolds is different with number of floor levels is promoted, top The main function of lifted scaffold is to carry out the constructions such as major structure of construction construction, edge list masonry and external wall plastering, in Between intert door and window and railing construction, vivid progress after climbing be major structure of construction interior wall essence masonry complete, interior wall thin-coat plaster It completes, the float work of the masonry on exterior wall in edge list and lines, exterior wall large area;Lower lift formula scaffold 2 it is main Effect is carried out for the alien invasions ornamental work such as lacquer in a small amount of plastering of exterior wall completion, surface brick adherence, shutter, after climbing Vivid progress be alien invasion molding (remove construction elevator, tower crane attached wall position), certain floor is spaced therebetween, to optimize Construction process, so that each working procedure cross construction, substantially reduces total construction time, improve construction efficiency.
In the present embodiment, it is highly preferred that fixed guide seat includes the orienting roll wheel seat of several adjustable movements, Mei Gesuo Orienting roll wheel seat is stated there are four guide roller, two upright bars of guide rail are inserted in orienting roll wheel seat, and four guide rollers constrain Guide rail upright bar forms and rolls sliding sleeve connection.Fixed guide seat can be hung down in the WidFin of preformed hole vertical plane with adapting to preformed hole The error in line direction, the adjustable distance in the front-back direction with major structure of construction surface of orienting roll wheel seat.The work of fixed guide seat With the movement for being the constraint horizontal portraitlandscape of guide rail main frame;The load that the transmitting of guide rail main frame comes is born, and load is transmitted It is the anti-dumping for adhering to supporting arrangement, load component to major structure of construction.
In the present embodiment, it is highly preferred that balancing point type fall-preventing safety includes balancing point axis and balancing point, balancing point passes through balancing point axis It is connected with the axle bed being fixed on orienting roll wheel seat, the both ends of balancing point spring are connected on balancing point and axle bed, and guide rail can It is slided up and down in orienting roll wheel seat.When guide holder is fixed, guide rail is under the constraint of guide holder and when downward microinching, movement In guide rail connecting rod enter in guide holder and contacted with the bottom of balancing point pushing after, balancing point occur rotationally clockwise, when After connecting rod moves downward the bottom for crossing balancing point, balancing point generates under the elastic force effect of reset spring and rotates counterclockwise moment bullet Position is replied, balancing point is restored to original original state before swinging, completes primary swing.And then another connecting rod enters again In guide holder, above procedure is repeated, connecting rod will be passed downwardly through constantly in guide holder at a slow speed, repeat above procedure, multiple connections Bar will smoothly decline, and guide rail is made to pass through guide holder.It is different from descending at slow speed when guide rail sharp downward movement or when falling When being descending at slow speed after balancing point, which is completed once to swing up and down, to be returned to original state, and then another connecting rod just enters again In the range of balancing point is swung, and when guide rail rapid decrease or when falling, balancing point, which does not complete also once to swing, restores initial shape Before state, another connecting rod has entered in the range of balancing point swing at this time, makes balancing point that can not rebound, the upper end of balancing point is in connecting rod After rotating clockwise certain angle under pushing, it will finally stop connecting rod and pass downwardly through, i.e., guide rail is stuck, and plays under preventing Rail guide piece is lifted up about 5cm height, balancing point will spring back into original state, at this time entirely after troubleshooting by the purpose of pendant Device is restored to normal operating conditions again.Present apparatus structure is simple, ingenious, is not required to manual operation, can be tieed up at any time with macroscopic examination It repairs conveniently, when occurring such as the problems such as balancing point swings not flexible or spring failure, the present apparatus does not lose function of safety protection, safety Good reliability is the anti-fall component for adhering to supporting arrangement.
In the present embodiment, it is highly preferred that in order to guarantee more work surface synchronous constructions, needs to carry out floor and intercepts water, consider The hole trickled down to water energy is simultaneously few, floor intercept water main positions include: elevator, staircase pump line hole 10, temporarily to Water pipe box out 9, the big various piping shafts interted on construction floor, flue are all sealed with top lifted scaffold 1 substantially It closes;The floor structure that intercepts water includes get water bucket 4 and water blocking sill 5.Wherein, get water bucket 4 is mainly set in elevator, by water receiving It struggles against in 4 lower parts installation pvc pipe access vertical tube 11, floor ponding is introduced into gutter;Water blocking sill 5 are mainly set to staircase pump At pipe hole 10, interim feed pipe hole 9, staircase door opening and elevator door opening, floor ponding row sinuous flow is prevented.
In the present embodiment, it is highly preferred that being bolted in order to facilitate the installation of with disassembly, get water bucket 4 with elevator inner wall. Elevator get water bucket 4 is made into a monolith, with a thickness of 1mm, can disposably move, and material is galvanized iron sheet, is moved easily.
Please continue to refer to Fig. 1 to Fig. 5, the present invention also provides the more work surface synchronous construction foot hand bodies of aforementioned super high-rise building The construction method of system, the construction method include:
Step S1: installation lifted scaffold is spare;
Step S2: in the pre-buried embedded part of design position for installing suspender member and fixed guide seat when major structure of construction is constructed Through-wall bolt hole, according to project progress, after installing suspender member and fixed guide seat, lift top lifted scaffold, and It is fixed on the outside of major structure of construction by suspender member and fixed guide seat;
Step S3: hydropower installation and main structure are carried out on the major structure of construction below top lifted scaffold 1 Check and accept construction;
Step S4: step S2, lifting and fixed lower lift formula scaffold 2 are referred to, wherein upper and lower part hoisting type foot hand At a distance of three layers to four layers between floor between frame.
In the present embodiment, it is highly preferred that step S1 includes:
Horizontal supporting frame is assembled, hoisting guiding rail main frame simultaneously corrects verticality, respectively by the bottom of guide rail main frame, outer Side, inboard are connect with the corresponding position of horizontal supporting frame;
After guide rail main frame is fixed fixed guide cover for seat is moved to the position that will be installed on guide rail, is fixed temporarily, And the verticality of the aspect of corrective rail main frame two, interim drawknot is installed, and with the construction of main structure engineering into Degree is installed remaining fixed guide seat and remaining frame body and is used for main building engineering construction;Lifting means is installed and is set up and is unloaded Expect platform.As the construction frame body of main body is set up upwards, fixed guide seat is installed upwards one by one, until frame body assembling finishes.Frame Body is set up the rising with main body and is risen, and is always ensured that more than one step frame of operation layer.Turnover panel, turnover panel is arranged in frame body bottom inside It should effectively be connect with frame body, guarantee the leakproofness under lifting and applying working condition, to prevent material from falling.Frame body bottom completely spreads foot Palm nails on woodwork plate and carries out secondary seal.Bottom turnover panel is welded into the outline border of 1.5m*1m using L40 angle bar, welds 2mm above Thick checkered steel plate, turnover panel and frame body bottom scaffold board hinge are hinged, and with wire rope inclined drawknot.
In the present embodiment, it is highly preferred that top lifted scaffold 1 is N layers, wherein n-th layer is major structure of construction Construction layer, N-1 layers are that demoulding turns over, floor is cleared up, the construction layer of closure screw hole;N-2 layers are snap the line, bar planting, pipeline The construction layer that installation and anti-bank pour;N-3 layers built for decoration of exterior wall column, the construction layer that indoor masonry is built;N-4 layers For the construction layer of major structure of construction external wall plastering, masonry stuff up a crack and aluminium door window frame installation.Lower lift formula scaffold 2 is M Layer, wherein M layers are the plastering of major structure of construction decoration of exterior wall column, local construction of exterior insulation system layer, M-1 layers are to play ash cake drawing Line, facing tile are pasted and the construction layer of deformation joint cover plate;M-2 layers for putty at major structure of construction exterior-wall heat insulation and are beaten The monitoring and construction layer at hand that mill, installation cooperate each pipeline;M-3 layers are lacquer, face brick jointing, shutter installation, door The construction layer that window ointment blocks.In the present embodiment, M, N respectively represent top lifted scaffold 1 and lower lift formula foot hand The difference of frame 2 can construct the number of plies simultaneously.
In practice of construction, the design number of plies of upper and lower part lifted scaffold and lower part layers more most than the practice of construction number of plies. That is, the number of plies that can be constructed is five layers when the design number of plies of the top lifted scaffold of design is five and half, it should Five layers of independently work compound, realize more work surface synchronous constructions, greatly improve construction efficiency.Similarly, lower lift formula When the number of plies of scaffold design is four and half, the number of plies that can be constructed is four layers.In view of upper and lower part lifted scaffold is constructed The contents of a project of operation are different, it is necessary to the examination for the major structure of construction constructed to top lifted scaffold and maintenance work After the completion, therefore the alien invasion ornamental work that can just carry out corresponding floor needs to keep between the lifted scaffold of upper and lower part Certain spacing, moreover, the climbing speed of upper and lower part lifted scaffold and the number of plies of climbing also are different.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Range.

Claims (10)

1. a kind of more work surface synchronous construction foot hand systems of super high-rise building, which is characterized in that the foot hand system includes two sets Lifted scaffold, respectively top lifted scaffold and lower lift formula scaffold, the lifted scaffold include leading Rail main frame, horizontal supporting frame, attachment supporting arrangement and lifting means, the top lifted scaffold, which is also matched, to be arranged with Floor intercepts water structure;
The guide rail main frame includes guide rail and vertical main framework interconnected, and the vertical main framework is preceding upright bar, stands afterwards The frame structure that bar, horizon bar and brace are formed;
The horizontal supporting frame is assembled by the standard knot and connecting rod of steel-pipe welding, and horizontal supporting frame is installed by bolt In the bottom of scaffold frame body;
The attachment supporting arrangement includes fixed guide seat and balancing point type fall-preventing safety interconnected, the fixed guide seat It is fixed by through-wall bolt and major structure of construction;
The lifting means includes the electric block and suspender member being equipped with, and the lifting means is led by suspender member and building The connection of body structure.
2. the more work surface synchronous construction foot hand systems of super high-rise building according to claim 1, which is characterized in that described solid Determine the orienting roll wheel seat that guide holder includes several adjustable movements, there are four guide roller, guide rails for each orienting roll wheel seat Two upright bars be inserted in orienting roll wheel seat, four guide rollers constrain guide rail upright bar, are formed and roll sliding sleeve connection.
3. the more work surface synchronous construction foot hand systems of super high-rise building according to claim 1, which is characterized in that the pendulum Pin type anti-falling safety device includes balancing point axis and balancing point, and the balancing point passes through balancing point axis and the axle bed phase that is fixed on orienting roll wheel seat Connection, the both ends of balancing point spring are connected on balancing point and axle bed, and guide rail can slide up and down in orienting roll wheel seat.
4. the more work surface synchronous construction foot hand systems of super high-rise building according to claim 1, which is characterized in that the building The layer structure that intercepts water includes get water bucket and water blocking sill.
5. the more work surface synchronous construction foot hand systems of super high-rise building according to claim 4, which is characterized in that described to connect Bucket is bolted with elevator inner wall.
6. the more work surface synchronous construction foot hand systems of super high-rise building according to claim 4, which is characterized in that the gear Water sill are respectively arranged at staircase pump line hole, feed pipe hole hole and staircase door opening, at elevator door opening.
7. a kind of more work surface synchronous construction foot hand systems of super high-rise building according to any one of claims 1 to 6 are applied Work method characterized by comprising
S1: installation lifted scaffold is spare;
S2: it is used to install the spiral shell through walls of suspender member and fixed guide seat when major structure of construction is constructed in the pre-buried embedded part of design position Keyhole after installing suspender member and fixed guide seat, lifts top lifted scaffold, and pass through hanging according to project progress Part and fixed guide seat are fixed on the outside of major structure of construction;
S3: carrying out hydropower installation on the major structure of construction below the top lifted scaffold and main structure examination is applied Work;
S4: step S2, lifting and fixed lower lift formula scaffold are referred to, wherein the building between the lifted scaffold of upper and lower part At a distance of three layers to four layers between layer.
8. construction method according to claim 7, which is characterized in that the step S1 includes:
Assemble horizontal supporting frame, hoisting guiding rail main frame simultaneously corrects verticality, respectively by the bottom of guide rail main frame, outside, Inboard is connect with the corresponding position of horizontal supporting frame;
After guide rail main frame is fixed fixed guide cover for seat is moved to the position that will be installed on guide rail, is fixed temporarily, and school The verticality of two aspects of positive guide rail main frame installs interim drawknot, and with the construction speed of main structure engineering, peace Remaining fixed guide seat and remaining frame body is filled to use for main building engineering construction;Lifting means is installed and sets up discharging and is put down Platform.
9. construction method according to claim 7, which is characterized in that the top lifted scaffold is N layers, wherein the N layers are major structure of construction construction layer, and N-1 layers are that demoulding turns over, floor is cleared up, the construction layer of closure screw hole;N-2 layers The construction layer poured for snap the line, bar planting, Pipe installing and anti-bank;N-3 layers are decoration of exterior wall column masonry, indoor masonry is built Construction layer;N-4 layers for major structure of construction external wall plastering, masonry stuff up a crack and aluminium door window frame installation construction layer.
10. construction method according to claim 7, which is characterized in that the lower lift formula scaffold is M layers, wherein M layers are the plastering of major structure of construction decoration of exterior wall column, local construction of exterior insulation system layer, and M-1 layers are to play ash cake bracing wire, wall face Brick is pasted and the construction layer of deformation joint cover plate;M-2 layers for putty at major structure of construction exterior-wall heat insulation and are polished, install and match The monitoring for closing each pipeline and construction layer at hand;M-3 layers are lacquer, face brick jointing, shutter is installed, door and window ointment blocks Construction layer.
CN201910382136.6A 2019-05-09 2019-05-09 The more work surface synchronous construction foot hand systems of super high-rise building and construction method Pending CN110173102A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910382136.6A CN110173102A (en) 2019-05-09 2019-05-09 The more work surface synchronous construction foot hand systems of super high-rise building and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910382136.6A CN110173102A (en) 2019-05-09 2019-05-09 The more work surface synchronous construction foot hand systems of super high-rise building and construction method

Publications (1)

Publication Number Publication Date
CN110173102A true CN110173102A (en) 2019-08-27

Family

ID=67690643

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910382136.6A Pending CN110173102A (en) 2019-05-09 2019-05-09 The more work surface synchronous construction foot hand systems of super high-rise building and construction method

Country Status (1)

Country Link
CN (1) CN110173102A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111502277A (en) * 2020-04-23 2020-08-07 安徽省第一建筑工程有限公司 Efficient alternate running water construction method for high-rise building construction
CN112696021A (en) * 2020-11-30 2021-04-23 中国一冶集团有限公司 Water-stopping and drainage construction method for floor pipe hole
CN113216625A (en) * 2021-04-14 2021-08-06 凯第建筑集团有限公司 Construction method of building main body and floor slab pouring auxiliary device
CN113323396A (en) * 2021-06-15 2021-08-31 南京工业大学 Integrated construction method for external wall of fabricated building
CN114541625A (en) * 2022-01-05 2022-05-27 中国建筑第二工程局有限公司 Cast-in-place building outer wall construction method and outer vertical surface waterproof protection structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203603439U (en) * 2013-12-03 2014-05-21 贵州兴茂建筑工程有限公司 Guiding seat type lifting scaffold
US20150211205A1 (en) * 2014-01-29 2015-07-30 Guangzhou Jishi Construction Group Co., Ltd. Construction system for subway station
CN206667773U (en) * 2017-04-21 2017-11-24 云南建投第六建设有限公司 The climbing type concrete spreader being arranged in high-rise building elevator shaft
CN208267002U (en) * 2017-10-26 2018-12-21 山河建设集团有限公司 A kind of floor intercepts water device
CN109488030A (en) * 2018-11-07 2019-03-19 中建三局第建设工程有限责任公司 Quick interspersed construction method for frame structure
CN210713745U (en) * 2019-05-09 2020-06-09 上海建工一建集团有限公司 Synchronous construction scaffold system for multiple working faces of super high-rise building

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203603439U (en) * 2013-12-03 2014-05-21 贵州兴茂建筑工程有限公司 Guiding seat type lifting scaffold
US20150211205A1 (en) * 2014-01-29 2015-07-30 Guangzhou Jishi Construction Group Co., Ltd. Construction system for subway station
CN206667773U (en) * 2017-04-21 2017-11-24 云南建投第六建设有限公司 The climbing type concrete spreader being arranged in high-rise building elevator shaft
CN208267002U (en) * 2017-10-26 2018-12-21 山河建设集团有限公司 A kind of floor intercepts water device
CN109488030A (en) * 2018-11-07 2019-03-19 中建三局第建设工程有限责任公司 Quick interspersed construction method for frame structure
CN210713745U (en) * 2019-05-09 2020-06-09 上海建工一建集团有限公司 Synchronous construction scaffold system for multiple working faces of super high-rise building

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杜会军: "双爬架在超高层建筑施工中的应用", 才智, 28 May 2011 (2011-05-28), pages 354 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111502277A (en) * 2020-04-23 2020-08-07 安徽省第一建筑工程有限公司 Efficient alternate running water construction method for high-rise building construction
CN112696021A (en) * 2020-11-30 2021-04-23 中国一冶集团有限公司 Water-stopping and drainage construction method for floor pipe hole
CN112696021B (en) * 2020-11-30 2022-07-15 中国一冶集团有限公司 Water-stopping and drainage construction method for floor slab pipeline opening
CN113216625A (en) * 2021-04-14 2021-08-06 凯第建筑集团有限公司 Construction method of building main body and floor slab pouring auxiliary device
CN113323396A (en) * 2021-06-15 2021-08-31 南京工业大学 Integrated construction method for external wall of fabricated building
CN114541625A (en) * 2022-01-05 2022-05-27 中国建筑第二工程局有限公司 Cast-in-place building outer wall construction method and outer vertical surface waterproof protection structure

Similar Documents

Publication Publication Date Title
CN110173102A (en) The more work surface synchronous construction foot hand systems of super high-rise building and construction method
CA2900392C (en) Mounting facade elements for multi-storey buildings
CN111287353B (en) Unit curtain wall hoisting process
CN208792758U (en) A kind of huge column climbing apparatus
ITFI20100096A1 (en) "A COMPLEX OF PREFABRICATED ELEMENTS TO FORM A PREFABRICATED BUILDING AT AT LEAST TWO PLANS AND RELATED BUILDING AND INSTALLATION PROCEDURE"
CN102877637B (en) Method for implementing operating platform in bottom wall construction of cantilever beam
CN112112418B (en) Construction method of high-rise building aluminum formwork climbing frame combined system
CN113789948B (en) Large-span atrium side wall sliding rail hanging basket with roof and construction method thereof
CN201826516U (en) Novel attached lifting scaffold
CN210713745U (en) Synchronous construction scaffold system for multiple working faces of super high-rise building
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN110397261A (en) A kind of overhanging eaves gutter Sloping roof hanging basket installation method
CN202017335U (en) Hydraulic mutual-climbing type lifting scaffold
CN102287045B (en) Square steel tube lifting outside scaffold
CN210622278U (en) Portable all-steel lifting climbing frame with triple anti-falling mechanism
CN209568688U (en) A kind of elevating construction platform
CN109653484B (en) Roofing superelevation faces external hanging flower basket mounting structure of empty curtain engineering
CN208380058U (en) Removable hanging basket suspension scaffold
CN111119368A (en) Construction method for externally-hung metal rock wool sandwich board of autoclaved sand aerated concrete wallboard
CN108894509B (en) Steel structure assembly type house prefabricated sandwich heat-insulation external wall panel construction method without external frame
CN105776092A (en) Stretching type basket device and construction method thereof
RU146691U1 (en) INTERTEST FOLDING RESCUE PLATFORM
CN207003989U (en) External hanging type scaffold is climbed in one kind
CN202808127U (en) Platform frame-free external construction elevator
CN207658895U (en) Working at height glass hanging equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination