CN110158603A - Long and narrow deep foundation pit earthwork digging method - Google Patents

Long and narrow deep foundation pit earthwork digging method Download PDF

Info

Publication number
CN110158603A
CN110158603A CN201910513532.8A CN201910513532A CN110158603A CN 110158603 A CN110158603 A CN 110158603A CN 201910513532 A CN201910513532 A CN 201910513532A CN 110158603 A CN110158603 A CN 110158603A
Authority
CN
China
Prior art keywords
foundation pit
long
steel pipe
layer
pipe support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910513532.8A
Other languages
Chinese (zh)
Inventor
孙久存
张建
王鹏
周兴
赵志峰
李长华
董杰
葛凤凯
李嘉鑫
王百仲
刘金明
孟宪春
任超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING XIANGKUN WATER CONSERVANCY PROJECT Co Ltd
Original Assignee
BEIJING XIANGKUN WATER CONSERVANCY PROJECT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING XIANGKUN WATER CONSERVANCY PROJECT Co Ltd filed Critical BEIJING XIANGKUN WATER CONSERVANCY PROJECT Co Ltd
Priority to CN201910513532.8A priority Critical patent/CN110158603A/en
Publication of CN110158603A publication Critical patent/CN110158603A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Abstract

The present invention provides a kind of long and narrow deep foundation pit earthwork digging methods, adequately utilize the strength and stiffness of ground-connecting-wall supporting construction, earth excavation suitable for long and narrow deep basal pit form, pit earthwork, which excavates, selects large excavator construction, vertically press the vertical spaced divisions of steel pipe support, horizontal direction is layered by steel pipe support horizontal space, and the upper layer soil body is excavated by the way of mechanical heavy excavation;Lower layer's soil body is regressed using step-like layering and is excavated, and indwelling mounting platform, after the installation is completed to same vertical layered steel pipe support, then excavates the platform soil body, and is continued next layered soil and excavated, until all construction is completed.The present invention can be obviously shortened construction period;The construction machinery used is less, can reduce exhaust emissions, mitigates the pollution to atmosphere;Supporting construction and the middle kerve soil body are made full use of, it is excavated using function, creates convenience for construction.

Description

Long and narrow deep foundation pit earthwork digging method
Technical field
The present invention relates to a kind of long and narrow deep foundation pit earthwork digging methods, are taking diaphram wall to add more particularly, to one kind The long and narrow deep foundation pit earthwork digging method of steel pipe inner supporting support pattern.
Background technique
With the development of society and the progress of construction technology, depth that building, structures etc. are expanded space to underground and Range is gradually increasing, these are all inevitably related to the earth excavation construction of deep basal pit.It is limited to engineering geology, the hydrology Complexity, be limited to construction machinery (swing arm height, radius of gyration etc.), construction method (the especially form of supporting construction) Selection need to comprehensively consider all kinds of influence factors in deep foundation pit earthwork digging, could accomplish in construction safety, it is economical, Quickly, environmentally friendly.
In the patent of 103410152 B of patent No. CN, a kind of construction for long and narrow deep foundation pit earthwork digging is provided Method, comprising the following steps:
1) foundation pit part is integrally excavated using large excavator, slot is stayed in foundation pit center, installs steel pipe diagonal brace;
2) slope is longitudinally drawn into foundation pit soil layer top surface using large excavator, forms bull-dozer soil-shifting condition;
3) bull-dozer is longitudinally drawing upslope formula dozing in slope that it is mountable to reach bracing members from low side to high-end soil-shifting Height after, in time follow-up installation steel shotcrete support structure;
4) the fender post soil that nearby reserved soil or bull-dozer can not construct behind is fed native using mini-excavator, bull-dozer to One end is bulldozed, and outward transport is concentrated;
5) after the completion of long and narrow deep foundation pit earthwork digging, excavating equipment is hung out from deep basal pit with crane.
B. the construction method of long and narrow deep foundation pit earthwork digging is used for according to scheme requirement a, it is characterised in that: step 1) before, operation of loosening the soil is carried out according to the selection of engineering site condition.
C. the construction method of long and narrow deep foundation pit earthwork digging is used for according to scheme requirement b, it is characterised in that: described The machinery of operation of loosening the soil is mini-excavator, and the scraper bowl in the mini-excavator backhoe is only hook ridge buster.
D. the construction method of long and narrow deep foundation pit earthwork digging is used for according to scheme requirement c, it is characterised in that: step 1) in, the method for soil is fallen using large excavator, dump truck changes the miscellaneous fill sidewalk filled out from rock ballast and is unearthed.
E. the construction method of long and narrow deep foundation pit earthwork digging is used for according to scheme requirement d, it is characterised in that: step 2) in, at longitudinal place for drawing slope that can enter at present to dump truck.
F. the construction method of long and narrow deep foundation pit earthwork digging is used for according to scheme requirement e, it is characterised in that: step 3) in, bull-dozer is since being stayed among slot foundation pit center along longitudinal direction from low side to high-end soil-shifting.
G. the construction method of long and narrow deep foundation pit earthwork digging is used for according to scheme requirement f, which is characterized in that step 4) it further includes steps of
(1) bull-dozer by soil be pushed into can entrucking position, then pulled away on the dump truck with large excavator;
(2) after reaching second bracing members installable height, second bracing members are installed in time;
(3) after being installed, pit earthwork excavation once sees the bottom, first of bracing members and second bracing members install with It successively follows up forward in digging face.
H. the described in any item construction methods for long and narrow deep foundation pit earthwork digging of a-g, feature are required according to scheme Be: long and narrow deep basal pit length range is 130m~200m.
The program is longitudinally drawn using excavator in excavation of foundation pit and stays slot among slope, forms bull-dozer soil-shifting condition, then Excavator and bull-dozer cooperation shoveling are native, and as the intensification of cutting depth installs bracing members simultaneously, and the closing slope that regresses is unearthed, directly It is completed to earth excavation.
The patent there are the shortcomings that:
1, the unearthed limited speed of above scheme is in the mechanical performance of excavator in foundation pit and bull-dozer, due to propping up in construction It supports vertical spacing and is generally 3~5m, the excavator of operation and bull-dozer type selecting are limited to support vertical spacing again in foundation pit, can only Small-sized machine is selected, is unearthed relatively slow;
2, in above scheme, slot is stayed in centre behind longitudinal drawing slope, soil is only used as balance foundation pit lateral pressure more than two sides, not sufficiently Utilize its effect.
Summary of the invention
The present invention provides a kind of long and narrow deep foundation pit earthwork digging method, overcoming can only be using mini-excavator, soil-shifting Machine causes earth excavation to be unearthed slow-footed disadvantage, while the second layer soil body being made full use of to act on, and guarantees that foundation pit is stable and conveniently Horizontal support installation.It is described that its technical solution is as follows:
A kind of long and narrow deep foundation pit earthwork digging method, comprising the following steps:
(1) horizontal slice and vertical division block are carried out to long and narrow Deep Foundation Pit Excavation according to horizontal, the vertical distribution of steel pipe support, Horizontal direction is layered by the horizontal space of steel pipe support, the vertical vertical spaced divisions for pressing steel pipe support;
(2) horizontal direction is divided into the first layer soil body and the second layer soil body, and the first layer soil body directly excavates and do not need vertical division block;
(3) second layer soil bodies are a subregion according to the every twice of horizontal distance of bracing members, are regressed using step-like subregion It excavates;
(4) below second layer steel pipe support bracket in indwelling mounting platform by the way of kerve, to same vertical division block Steel pipe support after the installation is completed, then excavate the platform soil body, and continue next subregion soil excavation;
(5) earth excavation is to the section that finishes up, and when earthmoving vehicle can not be down toward foundation pit, using extension arm excavator, soil is filled Vehicle, until the earthwork is all excavated.
Further, in step (2), the first layer soil body is directly dug by the way of mechanical heavy excavation to first floor steel pipe support Lower 1.5m, in the foundation pit other end, there are unearthed ramps.
Further, in step (3), the length of subregion is 10m.
Further, step-like to be formed by the way of kerve in step (3).
Further, in step (4), first layer, the second layer steel pipe support immediately following subregion excavate progress with dig with branch.
Further, in step (4), according to the height reasonable disposition excavator of second layer steel pipe support to bottom of foundation ditch, Second layer excavator is cooperated to be unearthed when construction, the slope at excavator both ends is the slope ratio of 1:1.
The present invention adequately utilizes the strength and stiffness of ground-connecting-wall supporting construction, the earthwork suitable for long and narrow deep basal pit form It excavates, pit earthwork, which excavates, selects large excavator construction, vertically presses the vertical spaced divisions of steel pipe support, horizontal direction presses steel pipe branch Horizontal space layering is supportted, the upper layer soil body is excavated by the way of mechanical heavy excavation;Lower layer's soil body is opened using the room for manoeuvre of step-like subregion It digs, and indwelling mounting platform, the steel pipe support to same vertical division block after the installation is completed, then are excavated flat by the way of kerve in The platform soil body, and continue next subregion soil excavation, until all construction is completed;Soil at both sides after intermediate kerve is filled Point utilize, which is accomplished platform by the present invention, be used as horizontal support mounting operation platform, platform section be it is trapezoidal, top width 1.2~ 1.5m is highly lower than bracing members 1.5m, and slope is compared on the oblique slope by 1:1.Platform predominantly balances foundation pit soil lateral pressure and use Make bracing members mounting platform, excavates again after the completion of operation.
Technical solution of the present invention bring the utility model has the advantages that
1, the program is excavated because directly being regressed using large excavator subregion piecemeal, accelerates the progress of earth excavation, Construction period can be obviously shortened;
2, the construction machinery that the program uses is less, can reduce exhaust emissions, mitigates the pollution to atmosphere;
3, the program makes full use of supporting construction and the middle kerve soil body, excavates it using function, creates convenience for construction.
Detailed description of the invention
Fig. 1 is that pit earthwork excavates horizontal slice figure;
Fig. 2 is that pit earthwork excavates vertical layered figure;
Fig. 3 is that 1. layer soil body excavates schematic diagram;
Fig. 4 is that 2. layer soil body excavates schematic diagram;
Fig. 5 is steel pipe inner supporting scheme of installation;
Fig. 6 is that 2. layer soil body excavates schematic diagram cross-section diagram.
Specific embodiment
The present invention provides a kind of in the long and narrow Deep Foundation Pit Excavation for taking diaphram wall to add steel pipe inner supporting support pattern Excavation method, including the following steps:
As shown in Figure 1, horizontal direction is layered by steel pipe support horizontal space, horizontal direction is divided into 1. layer soil body and 2. layer soil body. 1. layer soil body directly excavates and does not need vertical division block.
Shown in Fig. 2, pit earthwork excavation is vertical, and by the vertical spaced divisions of steel pipe support, (design drawing has the water of bracing members Flat, vertical distribution design, horizontal, the vertical spacing between bracing members that when construction requires according to design drawing is layered, point Area), it is divided into the area the A multiple subregions in the area-I.2. layer soil body is a subregion according to the horizontal distance every 2 of bracing members.Partition length 10 meters, it can satisfy the swing arm length of big machinery.
The Regionalization basis of vertical division block is as deep as possible below first layer Horizontal steelwork bracing after designing unit calculates safely Depth.Primarily to reduce by the earth volume that 2. layer excavates, the 2. layer earth excavation influenced by installation support, excavate efficiency Compared with, 1. layer is much lower.
It is the practical value in real case in figure.1. the depth of layer soil body is 3m, 2. the depth of layer soil body is 4.55m.
Steel pipe support is divided into first layer, the second layer, and the layout structure of steel pipe support installation, which is generally provided by designing unit, to be set Drawing is counted to determine.Steel pipe support horizontal space 5m, two layers of steel pipe support longitudinal pitch 2.5m, two layers of steel pipe support vertical non-alignment.
Wherein, as shown in Figure 3 and Figure 4, the length of long and narrow deep basal pit is 83m, and 1. layer soil body uses the side of mechanical heavy excavation Formula is directly dug to 1.5m below first layer bracing members, and bracket and purlin are installed;In the technical solution, 1. layer soil body uses machine 1.5m under the mode of tool heavy excavation is directly dug to first floor steel pipe support is stayed in the foundation pit other end and is unearthed as shown on the right side of Fig. 3 Ramp.2. layer soil body is regressed using step-like layering and excavated, step-like is mode such as Fig. 6 of middle kerve.
Also, in the long mounting platform step-like to indwelling of foundation pit.As shown in figure 5, second layer steel pipe support bracket with It is lower that indwelling mounting platform, the steel pipe support to same vertical division block after the installation is completed, then excavate platform by the way of kerve in The soil body, and continue next subregion soil excavation.
The mode of middle kerve is long to first excavating the middle part soil body along foundation pit i.e. in soil mass of foundation pit excavation, soil at both sides indwelling, The digging mode of the earthwork is excavated after complete bracing members to be installed again.
As shown in fig. 6,2. kerve mode is excavated in the use of layer soil body excavation, which need to be in strict accordance with steel branch The horizontal space of support, which regresses, to be excavated, and first and second layer of steel pipe support is immediately following stage excavation progress with digging with branch, and steel pipe support is also the 2. being layered installation when layer stage excavation.This section excavation need to rationally match according to the height of second layer steel pipe support to bottom of foundation ditch Set excavator, 2. layer excavator is unearthed for cooperation when construction.1 meter of width of the expression of level 1 in figure, the oblique slope ratio for indicating 1:1.
Earth excavation is to the section that finishes up, and when earthmoving vehicle can not be down toward foundation pit, falls native entrucking using extension arm excavator, Until the earthwork is all excavated.
Technical solution of the present invention bring the utility model has the advantages that
1, the program is excavated because directly being regressed using large excavator subregion piecemeal, accelerates the progress of earth excavation, Construction period can be obviously shortened;
2, the construction machinery that the program is selected is less, can reduce exhaust emissions, mitigates the pollution to atmosphere;
3, the program makes full use of supporting construction and the middle kerve soil body, excavates it using function, creates convenience for construction.

Claims (7)

1. a kind of long and narrow deep foundation pit earthwork digging method, comprising the following steps:
(1) horizontal slice and vertical division block are carried out to long and narrow Deep Foundation Pit Excavation according to horizontal, the vertical distribution of steel pipe support, it is horizontal Direction is layered by the horizontal space of steel pipe support, the vertical vertical spaced divisions for pressing steel pipe support;
(2) horizontal direction is divided into the first layer soil body and the second layer soil body, and the first layer soil body directly excavates and do not need vertical division block;
(3) second layer soil bodies are a subregion according to the every twice of horizontal distance of bracing members, are regressed and are excavated using step-like subregion;
(4) below second layer steel pipe support bracket in indwelling mounting platform, the steel to same vertical division block by the way of kerve Pipe supports after the installation is completed, then excavates the platform soil body, and continue next subregion soil excavation;
(5) earth excavation is to the section that finishes up, and when earthmoving vehicle can not be down toward foundation pit, falls native entrucking using extension arm excavator, Until the earthwork is all excavated.
2. long and narrow deep foundation pit earthwork digging method according to claim 1, comprising the following steps: in step (2), first layer The soil body is directly dug to 1.5m under first floor steel pipe support by the way of mechanical heavy excavation, and in the foundation pit other end, there are unearthed ramps.
3. long and narrow deep foundation pit earthwork digging method according to claim 1, comprising the following steps: in step (3), subregion Length is 10m.
4. long and narrow deep foundation pit earthwork digging method according to claim 1, comprising the following steps: step-like in step (3) It is formed by the way of kerve in.
5. long and narrow deep foundation pit earthwork digging method according to claim 1, comprising the following steps: in step (4), first Layer, the second layer steel pipe support immediately following subregion excavate progress with dig with branch.
6. long and narrow deep foundation pit earthwork digging method according to claim 1, comprising the following steps: in step (4), according to Two layers of steel pipe support are to the height reasonable disposition excavator of bottom of foundation ditch, and cooperation second layer excavator is unearthed when construction, excavator The slope at both ends is the slope ratio of 1:1.
7. long and narrow deep foundation pit earthwork digging method according to claim 1, comprising the following steps: second layer soil excavation is applied Work is by the way of intermediate kerve two sides indwelling platform.Platform section is trapezoidal, top width 1.5m, is highly lower than bracing members 1.5m, Compare slope in the oblique slope by 1:1.Platform predominantly balances foundation pit soil lateral pressure and is used as bracing members and installs.
CN201910513532.8A 2019-06-14 2019-06-14 Long and narrow deep foundation pit earthwork digging method Pending CN110158603A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910513532.8A CN110158603A (en) 2019-06-14 2019-06-14 Long and narrow deep foundation pit earthwork digging method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910513532.8A CN110158603A (en) 2019-06-14 2019-06-14 Long and narrow deep foundation pit earthwork digging method

Publications (1)

Publication Number Publication Date
CN110158603A true CN110158603A (en) 2019-08-23

Family

ID=67628779

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910513532.8A Pending CN110158603A (en) 2019-06-14 2019-06-14 Long and narrow deep foundation pit earthwork digging method

Country Status (1)

Country Link
CN (1) CN110158603A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114086566A (en) * 2021-11-10 2022-02-25 中铁第四勘察设计院集团有限公司 Long and narrow soft soil foundation pit excavation support and soil transportation method
CN114703860A (en) * 2022-03-18 2022-07-05 北京住总集团有限责任公司 Foundation pit supporting structure and construction method thereof
CN114908761A (en) * 2022-06-08 2022-08-16 中国二十冶集团有限公司 Excavation construction method of foundation pit

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH668790A5 (en) * 1988-04-11 1989-01-31 Vincent Boban Erecting building foundations with surrounding support work - starts with bottom slab within surrounding support work, made of several layer, coupled to support
CN105887889A (en) * 2016-04-20 2016-08-24 中铁上海工程局集团有限公司 Excavation construction method for super-wide low-permeability silty deep foundation pit
CN106759366A (en) * 2017-01-25 2017-05-31 北京市政建设集团有限责任公司 The construction method that soil excavation is arranged with packway in a kind of foundation ditch
CN108625375A (en) * 2018-06-26 2018-10-09 北京市政建设集团有限责任公司 A kind of foundation pit slope construction order and construction method
CN108914941A (en) * 2018-08-15 2018-11-30 北京市政建设集团有限责任公司 A kind of station pit earthwork digging one step process

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH668790A5 (en) * 1988-04-11 1989-01-31 Vincent Boban Erecting building foundations with surrounding support work - starts with bottom slab within surrounding support work, made of several layer, coupled to support
CN105887889A (en) * 2016-04-20 2016-08-24 中铁上海工程局集团有限公司 Excavation construction method for super-wide low-permeability silty deep foundation pit
CN106759366A (en) * 2017-01-25 2017-05-31 北京市政建设集团有限责任公司 The construction method that soil excavation is arranged with packway in a kind of foundation ditch
CN108625375A (en) * 2018-06-26 2018-10-09 北京市政建设集团有限责任公司 A kind of foundation pit slope construction order and construction method
CN108914941A (en) * 2018-08-15 2018-11-30 北京市政建设集团有限责任公司 A kind of station pit earthwork digging one step process

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
罗桂军等: "繁华地段穿越运营地铁车站基坑开挖施工技术 ", 《山西建筑》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114086566A (en) * 2021-11-10 2022-02-25 中铁第四勘察设计院集团有限公司 Long and narrow soft soil foundation pit excavation support and soil transportation method
CN114703860A (en) * 2022-03-18 2022-07-05 北京住总集团有限责任公司 Foundation pit supporting structure and construction method thereof
CN114908761A (en) * 2022-06-08 2022-08-16 中国二十冶集团有限公司 Excavation construction method of foundation pit
CN114908761B (en) * 2022-06-08 2023-07-21 中国二十冶集团有限公司 Excavation construction method for foundation pit

Similar Documents

Publication Publication Date Title
CN103195158B (en) Municipal drainage pipeline slurry balance pipe-jacking construction method
CN102535474B (en) A kind of construction method of deep-foundation pit excavation
CN105887889B (en) A kind of ultra-wide hyposmosis mud method of excavation of deep foundation pit
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN103410152B (en) A kind of construction method for long and narrow deep foundation pit earthwork digging
CN110158603A (en) Long and narrow deep foundation pit earthwork digging method
CN108914941A (en) A kind of station pit earthwork digging one step process
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN102691300A (en) Construction method of foundation pit earthwork
CN101634375B (en) Construction device and method for underground pipeline installation
CN105953078B (en) The protective device of high-pressure gas pipeline and guard method
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN101597888B (en) Construction method of municipal drainage culvert sinking trough
CN112064751A (en) Deep groove construction method for drainage pipeline
CN109403332A (en) The wide shallow river valley deep basal pit layering bench of sandy gravel thick-covering combines excavation method
CN101824825B (en) Deep foundation pit open cutting construction method
CN112227401A (en) Method for constructing bearing platform by filling stones in underwater stone abrupt slope area
CN108560572A (en) A kind of construction method of extra-high support system
CN101532586A (en) Underground pipeline installation construction device and method thereof
CN106869165A (en) City integrated prefabricated piping lane open cut formula is from construction of prevention work method and self-propelled laydown machine
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN115506382A (en) Construction method for pile plate wall of island building platform
CN110485471A (en) It is a kind of sliding rear by the recyclable rectangle active well of the integrated assembled of wall and its construction method
CN110485469A (en) Round-seal reservoir and its construction method can be recycled by the integrated assembled of wall after one kind
CN209211389U (en) Bank slump repairs structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190823

RJ01 Rejection of invention patent application after publication