CN108625375A - A kind of foundation pit slope construction order and construction method - Google Patents

A kind of foundation pit slope construction order and construction method Download PDF

Info

Publication number
CN108625375A
CN108625375A CN201810666753.4A CN201810666753A CN108625375A CN 108625375 A CN108625375 A CN 108625375A CN 201810666753 A CN201810666753 A CN 201810666753A CN 108625375 A CN108625375 A CN 108625375A
Authority
CN
China
Prior art keywords
layer
construction
excavation
bracing members
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810666753.4A
Other languages
Chinese (zh)
Inventor
岳仁峰
张永军
史军军
孙明臣
于娇娇
高腾
孟庆昕
武文波
郭忠
信博岩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201810666753.4A priority Critical patent/CN108625375A/en
Publication of CN108625375A publication Critical patent/CN108625375A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a kind of foundation pit slope construction order and construction methods, earth excavation including cheating slope, the earth excavation layer and section for cheating slope carry out, and each layer digs 2.5m down by original ground, it to be dug to this layer of bracing members bottom 500mm at bracing members position, sequence of excavation is:From east to west, from top to bottom, the order of layer and section is excavated, meanwhile, carry out corresponding waist rail and bracing members construction operation;Excavating principle is:Vertical layered, longitudinal divisions, intermediate kerve excavate;Its earth excavation layer and section carries out, and sequence of excavation is:From east to west, from top to bottom, the order of layer and section is excavated, meanwhile, corresponding waist rail and bracing members construction operation are carried out, excavating principle is:Vertical layered, longitudinal divisions, intermediate kerve excavate;And vertical, the horizontal transport of middle part grooving and foundation pit are carried out successively, foundation pit slope is excavated orderly so that foundation pit can crack or cave in, and shorten the construction period, reduce construction cost and difficulty of construction.

Description

A kind of foundation pit slope construction order and construction method
Technical field
The present invention relates to the technical fields of earth excavation, more specifically, it relates to which a kind of foundation pit slope excavation construction is suitable Sequence and construction method.
Background technology
Along subway and when the construction and excavation earthwork of protection zone, when earth excavation, it can inevitably lead to the protuberance in soil, because This applies man-hour requirement and takes certain safeguard measure, reduces the adverse effect to subway, especially in subway work, foundation pit is put The processing that slope is excavated is particularly important.Nowadays during practice of construction, the foundation construction difficulty such as Collapsible Loess District is big, Long construction period, and the quality of its construction quality directly affects the safe to use of built works.Such as in collapsible loess When area carries out extensive Deep Foundation Ditch Construction of Metro, the formation to construction area collapsible loess and Collapsing Deformation are needed first Characteristic index carries out comprehensive analysis, and on the basis of comprehensive analysis, in conjunction with the design structure of constructed subway station and whole Body stability and service life demand, the deep basal pit foundation structure of the constructed subway station of appropriate design, and accordingly determine a set of Rational Deep Foundation Ditch Construction of Metro method, nowadays, when practical Deep Foundation Ditch Construction of Metro, generally use underground is continuous The construction method of wall is constructed.But when practice of construction, since the geological condition of Collapsible Loess District is generally all more multiple Miscellaneous, practice of construction difficulty is larger, and a variety of inevitable undesirable elements appeared in practice of construction process influence in addition, make The deep foundation pit construction quality for obtaining subway station hardly results in guarantee.
Invention content
In view of the deficiencies of the prior art, the present invention intends to provide a kind of foundation pit slope construction order and Construction method, to solve the problems mentioned in the above background technology.
To achieve the above object, the present invention provides the following technical solutions:
A kind of foundation pit slope construction order and construction method, include the following steps:
Step 1: the earth excavation of hole slope:
The earth excavation layer and section for cheating slope carries out, and each layer digs 2.5m by original ground, wanted at bracing members position down It digs to this layer of bracing members bottom 500mm, sequence of excavation is:From east to west, from top to bottom, the order of layer and section is excavated, together When, carry out corresponding waist rail and bracing members construction operation;
Earth excavation sequence:
Excavating principle is:Vertical layered, longitudinal divisions, intermediate kerve excavate;
Vertical layered, longitudinal divisions:
Under first layer earth excavation to first layer bracing members at 50cm, first layer bracing members of constructing;It excavates deeply for every layer below Degree is that 3.5m performs step, step height 1.5m, to below second layer bracing members at every layer close to slope protection pile position simultaneously When 50cm, construct second layer bracing members and its waist rail;Then 3.5m is excavated in the earthwork again, and spray Anchor Care slope is excavated to third layer steel branch When the 50cm of support lower section, construct third layer bracing members and its waist rail, and so on last earth excavation to substrate;
Step 2: middle part grooving:
When earth excavation, flat excavation construction is taken in slope protection pile cap depth bounds, is 1.5m per layer thickness;
The platform of 6.0m wide, platform is respectively stayed to block up the percolating water of building enclosure and carry out bracing members installation along fender post both sides, Excavate the earthwork at reserved platform position again before carrying out following one layer of earth excavation;
Step 3: vertical, the horizontal transport of foundation pit:
Earthwork horizontal transport in foundation pit is transported with truck, is transported outward through riding track, and part is under bracing members and slope protection pile Neighbouring mechanical excavation less than place transported outward at trolley muck haulage to mechanical excavation, then by mechanical excavation by hand excavation, Riding track ending takes excavator to cut the earth, and last surplus earth is by hand excavation, truck crane lifting outward transport;
When cubic metre of earth ending vertical transport, truck crane should be greater than 2m close to foundation pit side leg apart from foundation pit, according to live needs, It is 2.4t that work range, which selects 14m, brachium 24.9m, lifting weight, and dress native hanging basket in scene holds earthwork 0.8m3, use automobile It hangs.
Further, in the step 1, earth excavation is backacter.
Further, in the step one, the region that earth excavation is divided according to structure construction, from the foundation pit south, head is fallen back It excavates, each section of excavation is unearthed by interior riding track, riding track width 7-8m, and the gradient is 20 degree, ramp both sides slope 1:0.75.
Further, with excavator relay, soil, the receipts soil of the increasing riding track earthwork, surplus earth pass through when the riding track receives soil Hand fit's crane is unearthed and entrucking outward transport.
Further, the scene is quasi- arranges 2 excavators construction operation simultaneously, it is contemplated that be unearthed 1000m daily3, when peak Phase is 1200m3/ day.
Further, in the step 1, vertical layered height by agent structure size, supporting depth and bracing members array pitch with And excavator maximum is excavated ability and is determined, elder generation's center kerve when earth excavation, after install bracing members, then clear up both sides step soil Side.
In conclusion the present invention has the advantages that compared with prior art:
The foundation pit slope construction order and construction method of the present invention, earth excavation layer and section carry out, and excavate suitable Sequence is:From east to west, from top to bottom, the order of layer and section is excavated, meanwhile, carry out corresponding waist rail and bracing members construction Operation, excavating principle is:Vertical layered, longitudinal divisions, intermediate kerve excavate;And successively carry out middle part grooving and foundation pit hang down Directly, horizontal transport, foundation pit slope are excavated orderly so that foundation pit can crack or cave in, and shorten the construction period, reduce and be constructed into Sheet and difficulty of construction.
More clearly to illustrate the structure feature and effect of the present invention, come below in conjunction with the accompanying drawings to this hair with specific embodiment It is bright to be described in detail.
Description of the drawings
Fig. 1 is that the foundation pit slope of the present invention excavates schematic diagram.
Reference numeral:1- first layers bracing members, 2- second layers bracing members, 3- third layer bracing members, 4- platforms.
Specific implementation mode
The following further describes the technical solution of the present invention in the following with reference to the drawings and specific embodiments.
Referring to Fig. 1, a kind of foundation pit slope construction order and construction method include the following steps:
Step 1: the earth excavation of hole slope:
The earth excavation layer and section for cheating slope carries out, and each layer digs 2.5m by original ground, wanted at bracing members position down It digs to this layer of bracing members bottom 500mm, earth excavation is using backacter, sequence of excavation:From east to west, from top to bottom, divide The order of layer segmentation is excavated.Meanwhile the orderly corresponding waist rail of carry out and bracing members construction operation according to plan.Earth excavation According to the region that structure construction divides, from the foundation pit south, head, which is fallen back, excavates, and each section of excavation is unearthed by interior riding track.Riding track width 7- 8m, the gradient are 20 degree, ramp both sides slope 1:0.75.It is native that riding track uses excavator relay to fall when receiving soil, and increases riding track as possible The receipts soil of the earthwork, last surplus earth is unearthed using hand fit's crane and entrucking is transported outward.
Scene is quasi- to arrange 2 excavators construction operation simultaneously, it is contemplated that be unearthed 1000m daily3, peak time 1200m3/ It.
Specifically, earth excavation sequence:
Mainly excavating principle is:Vertical layered, longitudinal divisions, intermediate kerve excavate.
Vertical layered, longitudinal divisions:
Vertical layered height excavates ability by agent structure size, supporting depth and bracing members array pitch and excavator maximum It determines.At first layer earth excavation to 1 time 50cm of first layer bracing members, construction first layer bracing members 1;Every layer of cutting depth below For 3.5m (while performing step close to slope protection pile position at every layer, step height 1.5m, convenient for spray anchor slope protection construction), to the When two layers of 2 lower section 50cm of bracing members, construction second layer bracing members 2 and its waist rail;Then 3.5m is excavated in the earthwork again, sprays Anchor Care slope, When being excavated to 3 lower section 50cm of third layer bracing members, construction third layer bracing members 3 and its waist rail, and so on last earth excavation To substrate.Elder generation center kerve when earth excavation, after install bracing members, then clear up the both sides step earthwork.Bracing members are constructed and the earthwork Excavation forms continuous productive process, and to achieve the purpose that shorten the construction period, foundation pit slope excavation is shown in Fig. 1.
Step 2: middle part grooving:
When earth excavation, flat excavation construction is taken in slope protection pile cap depth bounds, is 1.5m or so per layer thickness, to protect Demonstrate,prove the safety of construction and performing for stake top cap.
The platform 4 that 6.0m wide is respectively stayed along fender post both sides makes full use of its resistance of soil to ensure the stabilization of building enclosure, again It can carry out blocking the percolating water of building enclosure in time using this platform 4 and carry out bracing members installation, it is ensured that be applied in bracing members Working hour earth excavation carries out as usual, to accelerate construction progress.4, reserved platform is excavated again before carrying out following one layer of earth excavation The earthwork of position.
Step 3: vertical, the horizontal transport of foundation pit:
Earthwork horizontal transport in foundation pit is transported using truck, is transported outward through riding track.Part is under bracing members and bank protection Stake nearby mechanical excavation less than place, by hand excavation, at trolley muck haulage to mechanical excavation, then by mechanical excavation outside Fortune.Riding track ending takes excavator to cut the earth, and last surplus earth is by hand excavation, truck crane lifting outward transport.
When cubic metre of earth ending vertical transport, truck crane should be greater than 2m close to foundation pit side leg apart from foundation pit, according to live needs, 14m may be selected in work range, and brachium can be 24.9m, and lifting weight is 2.4t.Dress native hanging basket in scene holds earthwork 0.8m3, automobile Live needs can be met by hanging.
It should be strongly noted that following earth excavation working measure:
Section for that cannot apply support in time should be noted that kerve excavates, stays native retaining wall.It is answered during earthwork evacuation Pay attention to cheating the protection of internal drainage facility, it is ensured that the normal operation of drainage system.Transport sidewalk should set special messenger's finishing, it is ensured that transport peace Entirely, efficiency is improved.The soil layer that 15~30cm of hand fit, especially substrate or more should be aided with while mechanical excavation should be with artificial Based on excavation, to reduce the original state structure for hole subsoil body of backbreaking, keep.
During earth excavation, observation and monitoring measurement work should be reinforced, to find construction safety hidden danger, and passed through Monitoring feedback adjusts excavation sequence in time.
For weight away from slight slope safe distance, automobile is not less than 3m, and the earthwork, which is stacked, is not less than 1m, and mound height is no more than 1.5m, material Material heap is put not less than 1m.
The technical principle that the present invention is described above in association with specific embodiment, is only the preferred embodiment of the present invention.This The protection domain of invention is not limited merely to above-described embodiment, and all technical solutions belonged under thinking of the present invention belong to the present invention Protection domain.Those skilled in the art would not require any inventive effort the other specific realities that can associate the present invention Mode is applied, these modes are fallen within protection scope of the present invention.

Claims (6)

1. a kind of foundation pit slope construction order and construction method, which is characterized in that include the following steps:
Step 1: the earth excavation of hole slope:
The earth excavation layer and section for cheating slope carries out, and each layer digs 2.5m down by original ground, bracing members position to dig to This layer of bracing members bottom 500mm, sequence of excavation are:From east to west, from top to bottom, the order of layer and section is excavated, meanwhile, into The corresponding waist rail of row and bracing members construction operation;
Earth excavation sequence:
Excavating principle is:Vertical layered, longitudinal divisions, intermediate kerve excavate;
Vertical layered, longitudinal divisions:
Under first layer earth excavation to first layer bracing members at 50cm, first layer bracing members of constructing;Every layer of cutting depth is below 3.5m performs step at every layer close to slope protection pile position simultaneously, step height 1.5m, to second layer bracing members below 50cm when, Construction second layer bracing members and its waist rail;Then 3.5m is excavated in the earthwork again, and spray Anchor Care slope is excavated to below third layer bracing members When 50cm, construct third layer bracing members and its waist rail, and so on last earth excavation to substrate;
Step 2: middle part grooving:
When earth excavation, flat excavation construction is taken in slope protection pile cap depth bounds, is 1.5m per layer thickness;
Respectively stay the platform of 6.0m wide along fender post both sides, platform blocks up the percolating water of building enclosure and carries out bracing members installation, into The earthwork at reserved platform position is excavated before the following one layer of earth excavation of row again;
Step 3: vertical, the horizontal transport of foundation pit:
Earthwork horizontal transport in foundation pit is transported with truck, is transported outward through riding track, and part is under bracing members and near slope protection pile Mechanical excavation less than place transported outward at trolley muck haulage to mechanical excavation, then by mechanical excavation, riding track by hand excavation Ending takes excavator to cut the earth, and last surplus earth is by hand excavation, truck crane lifting outward transport;
When earthwork ending vertical transport, truck crane should be greater than 2m close to foundation pit side leg apart from foundation pit, according to live needs, work It is 2.4t that amplitude, which selects 14m, brachium 24.9m, lifting weight, and dress native hanging basket in scene holds earthwork 0.8m3, use truck crane.
2. a kind of foundation pit slope construction order according to claim 1 and construction method, which is characterized in that described In step 1, earth excavation is backacter.
3. a kind of foundation pit slope construction order according to claim 1 and construction method, which is characterized in that described In step 1, the region that earth excavation is divided according to structure construction, from the foundation pit south, head, which is fallen back, excavates, and each section is excavated by interior riding track It is unearthed, riding track width 7-8m, the gradient is 20 degree, ramp both sides slope 1:0.75.
4. a kind of foundation pit slope construction order according to claim 3 and construction method, which is characterized in that the horse With excavator relay, soil, the receipts soil of the increasing riding track earthwork, surplus earth are unearthed and are filled by hand fit's crane when soil is received in road Vehicle is transported outward.
5. a kind of foundation pit slope construction order according to claim 4 and construction method, which is characterized in that scene is quasi- Arrange 2 excavators construction operation simultaneously, it is contemplated that be unearthed 1000m daily3, peak time 1200m3/ day.
6. a kind of foundation pit slope construction order according to claim 1 and construction method, which is characterized in that the step In rapid one, vertical layered height excavates ability by agent structure size, supporting depth and bracing members array pitch and excavator maximum Determine, elder generation's center kerve when earth excavation, after install bracing members, then clear up the both sides step earthwork.
CN201810666753.4A 2018-06-26 2018-06-26 A kind of foundation pit slope construction order and construction method Pending CN108625375A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810666753.4A CN108625375A (en) 2018-06-26 2018-06-26 A kind of foundation pit slope construction order and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810666753.4A CN108625375A (en) 2018-06-26 2018-06-26 A kind of foundation pit slope construction order and construction method

Publications (1)

Publication Number Publication Date
CN108625375A true CN108625375A (en) 2018-10-09

Family

ID=63688426

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810666753.4A Pending CN108625375A (en) 2018-06-26 2018-06-26 A kind of foundation pit slope construction order and construction method

Country Status (1)

Country Link
CN (1) CN108625375A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109594564A (en) * 2019-01-22 2019-04-09 中铁建大桥工程局集团第五工程有限公司 A kind of anti-collapse construction method of Metro Deep Excavation open cut
CN109914478A (en) * 2019-04-02 2019-06-21 中交铁道设计研究总院有限公司 A kind of Blasting Excavation continued access diaphram wall construction subway station method
CN110158603A (en) * 2019-06-14 2019-08-23 北京翔鲲水务建设有限公司 Long and narrow deep foundation pit earthwork digging method
CN111778984A (en) * 2020-06-28 2020-10-16 苏州建设(集团)有限责任公司 Construction method of deep foundation pit and intelligent detection system thereof
CN112922028A (en) * 2021-02-02 2021-06-08 中铁四局集团有限公司 Construction method suitable for oversized circular subway station
CN113235603A (en) * 2021-05-21 2021-08-10 中建七局安装工程有限公司 Civil air defense engineering foundation pit earthwork construction method
CN114908761A (en) * 2022-06-08 2022-08-16 中国二十冶集团有限公司 Excavation construction method of foundation pit
CN114991159A (en) * 2022-05-16 2022-09-02 中铁六局集团有限公司 Subway station deep foundation pit riding track type rapid unearthing construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
561233: "熊猫环岛站土方工程施工方案", 《360DOC》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109594564A (en) * 2019-01-22 2019-04-09 中铁建大桥工程局集团第五工程有限公司 A kind of anti-collapse construction method of Metro Deep Excavation open cut
CN109914478A (en) * 2019-04-02 2019-06-21 中交铁道设计研究总院有限公司 A kind of Blasting Excavation continued access diaphram wall construction subway station method
CN110158603A (en) * 2019-06-14 2019-08-23 北京翔鲲水务建设有限公司 Long and narrow deep foundation pit earthwork digging method
CN111778984A (en) * 2020-06-28 2020-10-16 苏州建设(集团)有限责任公司 Construction method of deep foundation pit and intelligent detection system thereof
CN111778984B (en) * 2020-06-28 2021-10-29 苏州建设(集团)有限责任公司 Construction method of deep foundation pit and intelligent detection system thereof
CN112922028A (en) * 2021-02-02 2021-06-08 中铁四局集团有限公司 Construction method suitable for oversized circular subway station
CN113235603A (en) * 2021-05-21 2021-08-10 中建七局安装工程有限公司 Civil air defense engineering foundation pit earthwork construction method
CN114991159A (en) * 2022-05-16 2022-09-02 中铁六局集团有限公司 Subway station deep foundation pit riding track type rapid unearthing construction method
CN114908761A (en) * 2022-06-08 2022-08-16 中国二十冶集团有限公司 Excavation construction method of foundation pit
CN114908761B (en) * 2022-06-08 2023-07-21 中国二十冶集团有限公司 Excavation construction method for foundation pit

Similar Documents

Publication Publication Date Title
CN108625375A (en) A kind of foundation pit slope construction order and construction method
CN106761778B (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN108914941A (en) A kind of station pit earthwork digging one step process
CN106759366B (en) The construction method of soil excavation and riding track arrangement in a kind of foundation pit
CN103255771B (en) Method for excavating super-deep foundation pit engineering piles in graded mode and graded composite supporting of supporting piles
CN104131565B (en) A kind of against making the construction method that the earthwork is just made to excavate
CN108643231A (en) A kind of inner city subway station half range structure roof cover and cut construction method
CN105587320B (en) Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method
CN110017144A (en) A kind of three step construction method of loess tunnel considering bottom stab ilization processing
CN102704401A (en) Multizone pre-pressing technology for full framing
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN105350526B (en) Method for setting up steel platform
CN107023027A (en) A kind of building concentration zones large-scale well-sinking construction method
CN103015431B (en) Foundation pit supporting method for manual dig-hole cement-soil steel pile
CN109356169A (en) Foundation pit row pile supporting system and construction method thereof
CN104895087B (en) Chemical powder soil texture deep foundation pit construction method
CN1605679A (en) Anchor cable retaining wall road bank and cantilevered structured combined road
CN108842820A (en) A kind of subway station transfer node section foundation ditch construction method
CN110159296A (en) Structural system for controlling deformation of subway shield tunnel and construction method thereof
CN108560572A (en) A kind of construction method of extra-high support system
CN106567391B (en) A kind of flat building enclosure of rocky stratum subway entrance sectional type molten steel and construction method
CN101994314A (en) Longhole rectangular terraced antiskid pile jump-preventing excavating construction
CN109113045A (en) A kind of soft-soil foundation treatment method
CN111677530B (en) Safe construction method for three-step temporary inverted arch at tunnel through section
CN105241320B (en) A kind of both sides, Gao Dou valley, scenic spot bridge abutment controlled blasting and means of defence

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181009

RJ01 Rejection of invention patent application after publication