CN106759366A - The construction method that soil excavation is arranged with packway in a kind of foundation ditch - Google Patents

The construction method that soil excavation is arranged with packway in a kind of foundation ditch Download PDF

Info

Publication number
CN106759366A
CN106759366A CN201710060601.5A CN201710060601A CN106759366A CN 106759366 A CN106759366 A CN 106759366A CN 201710060601 A CN201710060601 A CN 201710060601A CN 106759366 A CN106759366 A CN 106759366A
Authority
CN
China
Prior art keywords
foundation ditch
packway
soil
excavation
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710060601.5A
Other languages
Chinese (zh)
Other versions
CN106759366B (en
Inventor
孔恒
卢长炯
张树
赵福元
朱子龙
田行宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201710060601.5A priority Critical patent/CN106759366B/en
Publication of CN106759366A publication Critical patent/CN106759366A/en
Application granted granted Critical
Publication of CN106759366B publication Critical patent/CN106759366B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/08Restraining of underground water by employing open ditches arranged below the level of the water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Foundations (AREA)

Abstract

The present invention relates to the construction method that earth excavation in a kind of many close long and narrow foundation ditches of support in rainfall area is arranged with packway, it is mainly achieved through the following technical solutions:(1) packway is arranged on foundation ditch middle part by smooth location, earthwork layer and section, excavate packway soil at both sides, the foundation ditch middle part soil body for leaving and foundation ditch both sides form " W " shape bathtub construction so that rainfall can be pooled to " W " shape bathtub construction bottom near the building enclosure soil body.(2) construction foundation pit gutter and sump is set, the water in gutter is pooled in sump, taken away the water in sump in time with water pumper.The present invention solves the long and narrow foundation ditch in many rainfall areas due to packway damage problem caused by rainfall, there is safe and reliable, convenient construction, shorten the construction period, be a kind of preferred construction method of the earthwork construction for solving the long and narrow foundation ditch packway damage in many rainfall areas.

Description

The construction method that soil excavation is arranged with packway in a kind of foundation ditch
【Technical field】
The present invention relates to soil excavation in a kind of foundation ditch and the construction method of packway arrangement, and in particular to a kind of many rainfalls Soil excavation and the construction method of packway arrangement in the close long and narrow foundation ditch of support in area, belong to ground foundation engineering technical field.
【Background technology】
As economic continues to develop, subway and tunnel are built in increasing city, wherein many subways and tunnel are all Using cut and cover tunneling.When using cut and cover tunneling, the flat shape of subway foundation pit and tunnel foundation ditch is all long and narrow rectangle. Due to mostly hundreds of meters of foundation ditch length, earth volume is big, then the excavation of foundation ditch is into a great problem.The arrangement of foundation ditch packway It is the key problem in technology point of foundation pit construction.
Traditional excavation of foundation pit is mostly arranged on foundation ditch middle part using basin excavation and by packway, and the benefit of basin excavation exists Play a part of the stabilization that horizontal support ensures side slope jointly with campshed in the passive earth pressure of basin side local products life can be utilized.But It is that, in many rainfalls ground area, basin excavation causes rainwater to concentrate on foundation ditch middle part, and packway is soaked due to rainwater, causes packway Damage, and it is unfavorable for drainage of foundation pit, this all influences being normally carried out for construction.Foundation ditch can not construct after being soaked, bearing capacity and Soil property does not meet design requirement.Pit water accumulation can also make supporting course intensity in foundation ditch wreck.
Therefore, in order to solve the above technical problems, it is necessory to provide soil excavation and packway cloth in a kind of foundation ditch of innovation The construction method put, to overcome the defect of the prior art.
【The content of the invention】
It is an object of the invention to provide soil excavation in a kind of foundation ditch and the construction method of packway arrangement, it is used " W " Groove profile is excavated, and foundation ditch middle part is packway, and the back-pressure soil that foundation ditch both sides are reserved near building enclosure is interim to substitute support, it is ensured that base Hole stabilization, not only can guarantee that packway and building enclosure safety but also can guarantee that drainage of foundation pit was smooth.
To achieve the above object, the technical scheme taken of the present invention is:Soil excavation and packway arrangement in a kind of foundation ditch Construction method, it includes following construction procedure:
(1) after long and narrow foundation ditch city's roads are finished, the project situation according to long and narrow foundation ditch is entered from top to bottom in deep basal pit The earthwork layering of the row earthwork, and the segmentation of the earthwork is carried out according to project situation, each section of each layer is one piece of soil body;
(2) excavation of foundation pit is symmetrically excavated from centre to both sides, that is, the excavation first since long and narrow foundation ditch side middle part long The layer earthwork, earth excavation to concrete support beam bottom, cutting depth is 1m or so;Excavation formula is moved back using segmentation, to foundation ditch both sides Digging is moved back, excavator directly fills soil and gets on the bus, transported outward spoir by dump truck, dug one section of construct immediately concrete Guan Liang and branch Support, ground floor soil excavation depth only 1m or so is not required to set packway;
(3) during each piece of soil excavation of the second layer and following soil layer, foundation ditch packway is arranged in foundation ditch middle part, using small Type digging machine first carries out packway soil at both sides excavation, leaves the part foundation ditch middle part soil body and is reserved near building enclosure in foundation ditch both sides Back-pressure soil, forms " W " shape bathtub construction, and the back-pressure soil that foundation ditch both sides are reserved near building enclosure is interim to substitute support;
(4) when excavating each layer of earthwork, some substratums are divided into by 1.5m or so depth per big layer, are carried out using Miniature digging machine Earth excavation, is unearthed by high-front shovel or electricity grab bucket, is dug during to 0.5m~1.0m below bracing members, carries out the peace of bracing members Dress;
(5) the step of repeating (3), (4) after, carries out each layer of excavation of foundation pit and the arrangement of construction packway, that is, Soil excavation after being carried out in the way of being segmented point step and moving back digging, first supports and digs afterwards;
(6) in Excavation Process, foundation ditch sets gutter or directly utilizes head fall draining, sets sump and takes out Water;
(7) when backacter does not have enough spaces to be applied, use high-front shovel station instead is carried out on foundation ditch side It is unearthed;Foundation ditch depth below the 12m earthwork coordinates high-front shovel to be vertically unearthed using Miniature digging machine, and Miniature digging machine finally is hung out into base Hole.
The construction method that soil excavation is arranged with packway in foundation ditch of the invention is further:The long and narrow foundation ditch is width 35~45m, depth 6m~16m, foundation ditch of the length in more than 150m.
The construction method that soil excavation is arranged with packway in foundation ditch of the invention is further:The layering is according to concrete branch Come what is be layered, layer height scope is 3m~5m to the arrangement of support or bracing members, and described its length range of segmentation is 20m~30m.
The construction method that soil excavation is arranged with packway in foundation ditch of the invention is further:Packway width is 5m, packway The gradient is 1:5~10, packway grade of side slope is 1:1.5~2.
The construction method that soil excavation is arranged with packway in foundation ditch of the invention is further:Reserving back-pressure soil width is 3m, it is 1 to reserve back-pressure slight slope degree:1.5~2.
The construction method that soil excavation is arranged with packway in foundation ditch of the invention is also:Gutter is arranged on " W " shape bottom land Portion, rather than foundation ditch both sides at building enclosure;Head fall represents head fall in tunnel.
Compared with prior art, the present invention has the advantages that:Soil excavation and packway cloth in foundation ditch of the invention The construction method put by " W " shape slot type excavate, it is ensured that foundation ditch packway not by rainwater soak and damage, accelerate construct into Degree.Back-pressure is reserved simultaneously so that the passive earth pressure of back-pressure local products life plays a part of horizontal support jointly with campshed, it is ensured that side The stabilization on slope, has the advantages that safe and reliable, convenient construction, shortens the construction period, is that a kind of many rainfall areas of solution are long and narrow The preferred construction method of the earthwork construction of foundation ditch packway damage.
【Brief description of the drawings】
Fig. 1 is that excavation of foundation pit of the invention is segmented and sequence of excavation schematic diagram.
Fig. 2 is foundation pit supporting construction figure of the invention.
Fig. 3 is the excavation of foundation pit drawing in side sectional elevation drawn by taking second segment second layer earth excavation as an example in the present invention.
Fig. 4 and Fig. 5 is excavation of foundation pit skiagraph in the present invention.
【Specific embodiment】
Refer to shown in Figure of description 1 to accompanying drawing 5, the present invention is a kind of air channel road tunneling segment structure construction method, especially It is applied to annual rainfall more than 1000mm, and rainy season rainfall accounts for many rainfalls area of the annual rainfall more than 70%.This hair The bright construction machinery being related to mainly has mini-excavator, large excavator, high-front shovel, electricity grab bucket and dump truck, relates to And the pattern foundation pit supporting structure facility for arriving mainly cast-in-situ bored pile, concrete support, steel pipe support and lattice column.
The concrete construction method of the construction method that soil excavation is arranged with packway is comprised the following steps in foundation ditch of the invention:
(1) after long and narrow foundation ditch city's roads are finished, the project situation according to long and narrow foundation ditch is entered from top to bottom in deep basal pit The earthwork layering of the row earthwork, and the segmentation of the earthwork is carried out according to project situation, each section of each layer is one piece of soil body.Described Long and narrow foundation ditch is 35~45m of width, and depth 6m~16m, length is particularly suited for open cut big cross section tunnel in the foundation ditch of more than 150m Road base pit engineering.Described layering is layered according to the arrangement of concrete support or bracing members, and layer height scope is 3m~5m, Its length range of described segmentation is 20m~30m.
(2) excavation of foundation pit is symmetrically excavated from centre to both sides, that is, the excavation first since long and narrow foundation ditch side middle part long The layer earthwork, earth excavation to concrete support beam bottom, cutting depth is 1m or so;Excavation formula is moved back using segmentation, to foundation ditch both sides Digging is moved back, excavator directly fills soil and gets on the bus, transported outward spoir by dump truck, dug one section of construct immediately concrete Guan Liang and branch Support, ground floor soil excavation depth only 1m or so is not required to set packway.
(3) during each piece of soil excavation of the second layer and following soil layer, foundation ditch packway is arranged in foundation ditch middle part, using small Type digging machine first carries out packway soil at both sides excavation, leaves the part foundation ditch middle part soil body and is reserved near building enclosure in foundation ditch both sides Back-pressure soil, forms " W " shape bathtub construction, and the back-pressure soil that foundation ditch both sides are reserved near building enclosure is interim to substitute support, it is ensured that base Hole stabilization.In the present embodiment, the packway width is 5m, and the packway gradient is 1:5~10, packway grade of side slope is 1:1.5 ~2, it is ensured that the stabilization of support pile and foundation ditch and leave working face, the earthwork of both sides support pile side 3m wide scopes to bracing members are installed Must not excavate, 1 is built beyond 3m scopes:1.5~2 slope ratio.Reserved back-pressure soil width is 3m, and it is 1 to reserve back-pressure slight slope degree: 1.5~2.
(4) when excavating each layer of earthwork, some substratums are divided into by 1.5m or so depth per big layer, are carried out using Miniature digging machine Earth excavation, is unearthed by high-front shovel or electricity grab bucket, is dug during to 0.5m~1.0m below bracing members, carries out the peace of bracing members Dress.
(5) the step of repeating (3), (4) after, carries out each layer of excavation of foundation pit and the arrangement of construction packway, that is, Soil excavation after being carried out in the way of being segmented point step and moving back digging, first supports and digs afterwards.Simultaneously in strict accordance with " tau-effect " and " first Dug after support " theoretical and principle instructs pit earthwork to excavate and propping, accomplish in digging process " layering, piecemeal, it is symmetrical, balance, Excavate in limited time " and propping, base is followed first to support and dug afterwards, forbids to backbreak;
(6) in Excavation Process, foundation ditch sets gutter or directly utilizes head fall draining, sets sump and takes out Water.The gutter is arranged on " W " shape trench bottom, rather than foundation ditch both sides at building enclosure;Head fall is represented in tunnel Head fall.
(7) when backacter does not have enough spaces to be applied, use high-front shovel station instead is carried out on foundation ditch side It is unearthed;Foundation ditch depth below the 12m earthwork coordinates high-front shovel to be vertically unearthed using Miniature digging machine, and Miniature digging machine finally is hung out into base Hole.
Specific embodiment above is only the preferred embodiment of this creation, is not used to limit this creation, all in this wound Any modification, equivalent substitution and improvements for being done etc. within the spirit and principle of work, should be included in this creation protection domain it It is interior.

Claims (6)

1. the construction method that soil excavation is arranged with packway in a kind of foundation ditch, it is characterised in that:Including following construction procedure:
(1) after long and narrow foundation ditch city's roads are finished, the project situation according to long and narrow foundation ditch carries out soil from top to bottom in deep basal pit The earthwork layering of side, and the segmentation of the earthwork is carried out according to project situation, each section of each layer is one piece of soil body;
(2) excavation of foundation pit is symmetrically excavated from centre to both sides, that is, excavates ground floor soil since long and narrow foundation ditch side middle part long Side, earth excavation to concrete support beam bottom, cutting depth is 1m or so;Excavation formula is moved back using segmentation, digging is moved back to foundation ditch both sides, Excavator directly fills soil and gets on the bus, and is transported outward spoir by dump truck, has dug one section of construct immediately concrete Guan Liang and support, first Layer soil body cutting depth only 1m or so, is not required to set packway;
(3) during each piece of soil excavation of the second layer and following soil layer, foundation ditch packway is arranged in foundation ditch middle part, using small-sized digging Machine first carries out packway soil at both sides excavation, leaves the part foundation ditch middle part soil body and reserves back-pressure near building enclosure in foundation ditch both sides Soil, forms " W " shape bathtub construction, and the back-pressure soil that foundation ditch both sides are reserved near building enclosure is interim to substitute support;
(4) when excavating each layer of earthwork, some substratums are divided into by 1.5m or so depth per big layer, the earthwork is carried out using Miniature digging machine Excavate, be unearthed by high-front shovel or electricity grab bucket, dig during to 0.5m~1.0m below bracing members, carry out the installation of bracing members;
(5) the step of repeating (3), (4) after, carries out each layer of excavation of foundation pit and the arrangement of construction horse, that is, to be segmented Point step move back digging mode carry out after soil excavation, first support and dig afterwards;
(6) in Excavation Process, foundation ditch sets gutter or directly utilizes head fall draining, sets sump and draws water;
(6) when backacter does not have enough spaces to be applied, use high-front shovel station instead and be unearthed on foundation ditch side; Foundation ditch depth below the 12m earthwork coordinates high-front shovel to be vertically unearthed using Miniature digging machine, and Miniature digging machine finally is hung out into foundation ditch.
2. the construction method that soil excavation is arranged with packway in foundation ditch as claimed in claim 1, it is characterised in that:It is described long and narrow Foundation ditch is 35~45m of width, depth 6m~16m, foundation ditch of the length in more than 150m.
3. the construction method that soil excavation is arranged with packway in foundation ditch as claimed in claim 1, it is characterised in that:The layering It is to be layered according to the arrangement of concrete support or bracing members, layer height scope is 3m~5m, described its length range of segmentation It is 20m~30m.
4. the construction method that soil excavation is arranged with packway in foundation ditch as claimed in claim 1, it is characterised in that:Packway width It is 5m, the packway gradient is 1:5~10, packway grade of side slope is 1:1.5~2.
5. the construction method that soil excavation is arranged with packway in foundation ditch as claimed in claim 1, it is characterised in that:Reserved back-pressure Native width is 3m, and it is 1 to reserve back-pressure slight slope degree:1.5~2.
6. the construction method that soil excavation is arranged with packway in foundation ditch as claimed in claim 1, it is characterised in that:Gutter sets Put in " W " shape trench bottom, rather than foundation ditch both sides at building enclosure;Head fall represents head fall in tunnel.
CN201710060601.5A 2017-01-25 2017-01-25 The construction method of soil excavation and riding track arrangement in a kind of foundation pit Active CN106759366B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710060601.5A CN106759366B (en) 2017-01-25 2017-01-25 The construction method of soil excavation and riding track arrangement in a kind of foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710060601.5A CN106759366B (en) 2017-01-25 2017-01-25 The construction method of soil excavation and riding track arrangement in a kind of foundation pit

Publications (2)

Publication Number Publication Date
CN106759366A true CN106759366A (en) 2017-05-31
CN106759366B CN106759366B (en) 2018-10-09

Family

ID=58941962

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710060601.5A Active CN106759366B (en) 2017-01-25 2017-01-25 The construction method of soil excavation and riding track arrangement in a kind of foundation pit

Country Status (1)

Country Link
CN (1) CN106759366B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700493A (en) * 2017-07-14 2018-02-16 腾达建设集团股份有限公司 Basin earthwork excavation method in the small yardstick block of weak soil subway foundation pit
CN107938680A (en) * 2017-11-20 2018-04-20 重庆交通建设(集团)有限责任公司 A kind of excavation of foundation pit safe construction method
CN108643198A (en) * 2018-04-18 2018-10-12 中国十七冶集团有限公司 Excavation of earthwork structure and its construction method between a kind of long and narrow foundation pit pile of ultra-deep
CN109750825A (en) * 2018-12-29 2019-05-14 杭州江润科技有限公司 The construction method of foundation pit suspension type riding track
CN110158603A (en) * 2019-06-14 2019-08-23 北京翔鲲水务建设有限公司 Long and narrow deep foundation pit earthwork digging method
CN110158604A (en) * 2019-06-19 2019-08-23 北京城建北方集团有限公司 Support construction method at foundation pit riding track
CN114086566A (en) * 2021-11-10 2022-02-25 中铁第四勘察设计院集团有限公司 Long and narrow soft soil foundation pit excavation support and soil transportation method
CN114991159A (en) * 2022-05-16 2022-09-02 中铁六局集团有限公司 Subway station deep foundation pit riding track type rapid unearthing construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05287746A (en) * 1992-04-07 1993-11-02 Fujita Corp Back driving earth retaining method
CN103410152A (en) * 2013-09-05 2013-11-27 中交公路养护工程技术有限公司 Construction method for long, narrow and deep foundation pit soil excavation

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05287746A (en) * 1992-04-07 1993-11-02 Fujita Corp Back driving earth retaining method
CN103410152A (en) * 2013-09-05 2013-11-27 中交公路养护工程技术有限公司 Construction method for long, narrow and deep foundation pit soil excavation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
孙志华等: "超长深基坑土方开挖方法", 《城市勘测》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700493A (en) * 2017-07-14 2018-02-16 腾达建设集团股份有限公司 Basin earthwork excavation method in the small yardstick block of weak soil subway foundation pit
CN107700493B (en) * 2017-07-14 2019-08-16 腾达建设集团股份有限公司 Basin earthwork excavation method in the small scale block of weak soil subway foundation pit
CN107938680A (en) * 2017-11-20 2018-04-20 重庆交通建设(集团)有限责任公司 A kind of excavation of foundation pit safe construction method
CN108643198A (en) * 2018-04-18 2018-10-12 中国十七冶集团有限公司 Excavation of earthwork structure and its construction method between a kind of long and narrow foundation pit pile of ultra-deep
CN109750825A (en) * 2018-12-29 2019-05-14 杭州江润科技有限公司 The construction method of foundation pit suspension type riding track
CN110158603A (en) * 2019-06-14 2019-08-23 北京翔鲲水务建设有限公司 Long and narrow deep foundation pit earthwork digging method
CN110158604A (en) * 2019-06-19 2019-08-23 北京城建北方集团有限公司 Support construction method at foundation pit riding track
CN110158604B (en) * 2019-06-19 2021-07-02 北京城建北方集团有限公司 Construction method of supporting structure at underpass of foundation pit
CN114086566A (en) * 2021-11-10 2022-02-25 中铁第四勘察设计院集团有限公司 Long and narrow soft soil foundation pit excavation support and soil transportation method
CN114991159A (en) * 2022-05-16 2022-09-02 中铁六局集团有限公司 Subway station deep foundation pit riding track type rapid unearthing construction method

Also Published As

Publication number Publication date
CN106759366B (en) 2018-10-09

Similar Documents

Publication Publication Date Title
CN106759366B (en) The construction method of soil excavation and riding track arrangement in a kind of foundation pit
CN103321230B (en) The deep big foundation pit excavation method in place is passed through in the long distance of operation shallow embedding subway
CN108914941A (en) A kind of station pit earthwork digging one step process
CN102505695B (en) Construction method for deep foundation pit of three-dimensional garage
CN105887889B (en) A kind of ultra-wide hyposmosis mud method of excavation of deep foundation pit
CN102966108B (en) Construction method of deep foundation pit close to building and adopting underground structure as internal support
CN102535474B (en) A kind of construction method of deep-foundation pit excavation
CN105041349A (en) Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN102704957A (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN109322330A (en) A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN108625375A (en) A kind of foundation pit slope construction order and construction method
CN207003499U (en) A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN108612117A (en) A kind of seabed water-retaining structure across municipal tunnel greatly and construction method
CN103290847A (en) Inner oblique beam supporting structure for oversized-area deep foundation pit and construction method
CN105370288A (en) Construction method of shallow-buried large-span tunnels
CN103410152B (en) A kind of construction method for long and narrow deep foundation pit earthwork digging
CN111236241B (en) Weak water-rich stratum subway foundation pit reinforcing excavation method based on half-cover excavation method
CN102758442A (en) Earth excavation method and open-cut tunnel construction method
CN104653188A (en) Method for arranging large-diameter shield receiving and originating well in underground-excavated air duct
CN108867692A (en) The protection of city big cross section open trench tunnel Nearby Structure and tunnel foundation pit method for digging
CN108457277A (en) A kind of a wide range of deep & thick silt excavation construction method
CN108842820A (en) A kind of subway station transfer node section foundation ditch construction method
CN109056810A (en) The transverse direction that open cut or lid dig underground main structure below existing building digs construction and its construction method
CN106761771A (en) A kind of construction method for crossing native shallow tunnel on rock under the location of mountain valley

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant