CN110082618A - A kind of optimization method of area's power-off event concentrator active reporting - Google Patents

A kind of optimization method of area's power-off event concentrator active reporting Download PDF

Info

Publication number
CN110082618A
CN110082618A CN201910306441.7A CN201910306441A CN110082618A CN 110082618 A CN110082618 A CN 110082618A CN 201910306441 A CN201910306441 A CN 201910306441A CN 110082618 A CN110082618 A CN 110082618A
Authority
CN
China
Prior art keywords
concentrator
power
voltage
event
area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910306441.7A
Other languages
Chinese (zh)
Inventor
肖湘奇
陈向群
黄瑞
杨茂涛
肖湘晨
胡军华
柳青
熊德智
陈福胜
吴志勇
陈浩
申丽曼
贺星
王智
杨静
徐慧婷
余敏琪
韦淑敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hunan Electric Power Co Ltd
Metering Center of State Grid Hunan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hunan Electric Power Co Ltd
Metering Center of State Grid Hunan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hunan Electric Power Co Ltd, Metering Center of State Grid Hunan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201910306441.7A priority Critical patent/CN110082618A/en
Publication of CN110082618A publication Critical patent/CN110082618A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere

Abstract

The present invention relates to electric power network field more particularly to the optimization methods of a kind of area's power-off event concentrator active reporting.The present invention carries out the screening of effective outage information using concentrator monitoring voltage abnormal conditions, concentrator monitors that one group of concentrator friendship is resurveyed after electric voltage exception adopts voltage, after first judgement power-off event, quasi- record power-off event simultaneously actively calls scaffold tower area summary table voltage together, it studies and judges for the first time to report main website after platform area power-off event, after acquisition main website receives, transparent area's summary table voltage carries out secondary study and judge, if the secondary area judgement Reng Weitai has a power failure, then main website sends power-off event to distribution and repairs platform, arrange corresponding repairing staff, the present invention can be improved the reliability that platform area power-off event reports, save main website resource, to have a power failure, repairing work is raced against time.

Description

A kind of optimization method of area's power-off event concentrator active reporting
Technical field
The present invention relates to electric power network field more particularly to the optimization sides of a kind of area's power-off event concentrator active reporting Method.
Background technique
Power distribution station is the intermediate link for connecting height voltage electric grid, and distribution transformer comes as low-voltage electricity user electric energy Source, once distribution transformer has a power failure, will result directly in all users under platform area can not electricity consumption.Therefore, reinforce stopping platform area Scene rush to repair is rushed towards in the monitoring of electric event at once after distribution transformer has a power failure, and shortens customer outage hours especially as far as possible It is important.Previous distribution transforming power-off event is complained after having a power failure mainly by user to power department, arrives at power distribution station by repair personnel Scene just can confirm that not only recovery time is long for this passive repairing, and user satisfaction is poor.Relatively advanced at present is to pass through Public affairs become concentrator and report power-off event, but acquiring the power-off event that main website receives and reporting includes too many invalid information in information, It is reported by mistake as caused by voltage instability and frequently reports outage information, occupy main website resource, affect acquisition main station system its His business, more affects the timely processing of effective platform area power-off event.Therefore a kind of area's power-off event concentrator is needed actively The optimization method reported improves the validity that platform area power-off event reports.
Summary of the invention
Based on the above issues, the present invention provides the optimization method of a kind of area's power-off event concentrator active reporting, to mention The validity that plateau area power-off event reports.
The optimization method of a kind of area's power-off event concentrator active reporting, this method are abnormal using concentrator monitoring voltage Situation carries out the screening of effective outage information, the optimization method the following steps are included:
Step 01: concentrator operates normally;
Step 02: monitor whether to occur concentrator voltage lower than critical voltage, if the result is negative, then return step 01;
Step 03: if the monitoring result of step 02 be it is yes, concentrator at least acquires 5 friendships in 10 seconds and adopts voltage, institute It states friendship and adopts the voltage that voltage refers to AC sampling concentrator;
Step 04: whether the friendship of last time and 80% probability adopts voltage lower than critical voltage to detection collection result, If it is not, then concentrator does not record power-off event, return step 01;
Step 05: if the testing result of step 04 is yes, the quasi- record power-off event of concentrator;
Step 06: concentrator actively calls scaffold tower area summary table voltage together;
Step 07: whether successfully calling together and survey summary table voltage, if the result is negative, then concentrator generates platform area power-off event and reports Main website, and then execute step 10;
Step 08: if the result of step 07 be it is yes, detection calls the summary table voltage of survey together and whether is lower than critical voltage, if detection As a result be it is no, then determine that platform area does not have a power failure;
Step 09: if the testing result of step 08 be it is yes, concentrator generate platform area power-off event simultaneously report main website;
Step 10: acquisition transparent area's summary table voltage of main website;
Step 11, whether: succeed transparent summary table voltage, if result whether, determines that platform area has a power failure, and executes step 14;
Step 12: if the result of step 11 be it is yes, detect whether transparent summary table voltage is lower than critical voltage, if detection As a result be it is no, then determine that platform area does not have a power failure;
Step 13: if the testing result of step 12 be it is yes, determine platform area have a power failure;
Step 14: main website sending station area power-off event to distribution repairs platform;
Step 15: distribution repairs platform and sends work order to corresponding repairing staff.
Preferably, the critical voltage is the 60% of reference voltage.
Preferably, after the power-off event reports main website, if main website is unresponsive, concentrator report 3 times to avoid communication Signal is bad to be caused to fail to report.
The beneficial effect of the technical program is: (1) high reliablity, and by the first screening of concentrator and main website is secondary grinds Sentence, effectively increases the validity that platform area power-off event reports;(2) outage information that main website receives has been subjected to screening, effectively Main website resource is saved;(3) real-time is high, compared to manual report's power-off event, concentrator real-time monitoring electric voltage exception, can and Shi Faxian platform area power-off event makes corresponding arrangement, and to have a power failure, the time has been striven in repairing work;(4) actively transparent compared to main website Platform area or concentrator voltage greatly reduce the data collection task amount and acquisition time of main website;(5) critical voltage and more is used Kind voltage value is compared (such as " concentrator exchanges collection voltages, the summary table voltage for calling survey together, transparent platform area summary table voltage "), and Rule of thumb reasonably setting critical voltage value is " the 60% of reference voltage ", the criterion of the quasi- record power-off event of concentrator For " voltage is adopted in the friendship of the concentrator of last time and 80% probability acquisition ", to judge from all angles and sequence level The validity of power off time greatly reduces the probability of power-off event wrong report.
Detailed description of the invention
The features and advantages of the present invention will be more clearly understood by referring to the accompanying drawings, and attached drawing is schematically without that should manage Solution is carries out any restrictions to the present invention, in the accompanying drawings:
Fig. 1 is the relational graph of main website, concentrator, platform area summary table and electric supply meter.
Fig. 2 is the method flow diagram of the effective screening of outage information.
Specific embodiment
Specific embodiments of the present invention will be described in further detail with reference to the accompanying drawings of the specification.
As shown in Figure 1, one concentrator for having power-off event reporting functions is installed in 10KV step down side exit, Concentrator reports information to main website by wireless public network, and main website, which has, receives concentrator reporting functions, and concentrator passes through RS485 bus Communication connection electric supply meter, platform area summary table.Each area is only installed by one concentrator.
The present invention carries out the screening of effective outage information using concentrator monitoring voltage abnormal conditions, as shown in Fig. 2, described Optimization method the following steps are included:
Step 01: concentrator operates normally;
Step 02: monitor whether to occur concentrator voltage lower than critical voltage, if the result is negative, then return step 01;
Step 03: if the monitoring result of step 02 be it is yes, concentrator at least acquires 5 friendships in 10 seconds and adopts voltage, institute It states friendship and adopts the voltage that voltage refers to AC sampling concentrator;
Step 04: whether the friendship of last time and 80% probability adopts voltage lower than critical voltage to detection collection result, If it is not, then concentrator does not record power-off event, return step 01;
Step 05: if the testing result of step 04 is yes, the quasi- record power-off event of concentrator;
Step 06: concentrator actively calls scaffold tower area summary table voltage together;
Step 07: whether successfully calling together and survey summary table voltage, if the result is negative, then concentrator generates platform area power-off event and reports Main website, and then execute step 10;
Step 08: if the result of step 07 be it is yes, detection calls the summary table voltage of survey together and whether is lower than critical voltage, if detection As a result be it is no, then determine that platform area does not have a power failure;
Step 09: if the testing result of step 08 be it is yes, concentrator generate platform area power-off event simultaneously report main website;
Step 10: acquisition transparent area's summary table voltage of main website;
Step 11, whether: succeed transparent summary table voltage, if result whether, determines that platform area has a power failure, and executes step 14;
Step 12: if the result of step 11 be it is yes, detect whether transparent summary table voltage is lower than critical voltage, if detection As a result be it is no, then determine that platform area does not have a power failure;
Step 13: if the testing result of step 12 be it is yes, determine platform area have a power failure;
Step 14: main website sending station area power-off event to distribution repairs platform;
Step 15: distribution repairs platform and sends work order to corresponding repairing staff.
The critical voltage is the 60% of reference voltage.
After the power-off event reports main website, if main website is unresponsive, concentrator report 3 times it is bad to avoid communication signal Cause to fail to report.
In summary, by above-mentioned method, the validity and timeliness for enabling to this method platform area power-off event to report Property is higher, and reduces the resource occupation of main website.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the invention The normally understood meaning of technical staff is identical.Term as used herein in the specification of the present invention is intended merely to description tool The purpose of the embodiment of body, it is not intended that in the limitation present invention.Each technical characteristic of embodiment described above can carry out arbitrarily Combination, for simplicity of description, it is not all possible to each technical characteristic in above-described embodiment combination be all described, so And as long as there is no contradiction in the combination of these technical features, it all should be considered as described in this specification.
Although the embodiments of the invention are described in conjunction with the attached drawings, but those skilled in the art can not depart from this hair Various modifications and variations are made in the case where bright spirit and scope, such modifications and variations are each fallen within by appended claims Within limited range.

Claims (3)

1. the optimization method of a kind of area's power-off event concentrator active reporting, this method utilizes concentrator monitoring voltage exception feelings Condition carries out the screening of effective outage information, the optimization method the following steps are included:
Step 01: concentrator operates normally;
Step 02: monitor whether to occur concentrator voltage lower than critical voltage, if the result is negative, then return step 01;
Step 03: if the monitoring result of step 02 be it is yes, concentrator at least acquires 5 friendships in 10 seconds and adopts voltage;
Step 04: whether the friendship of last time and 80% probability adopts voltage lower than critical voltage to detection collection result, if it is not, Then concentrator does not record power-off event, return step 01;
Step 05: if the testing result of step 04 is yes, the quasi- record power-off event of concentrator;
Step 06: concentrator actively calls scaffold tower area summary table voltage together;
Step 07: whether successfully calling together and survey summary table voltage, if the result is negative, then concentrator generates platform area power-off event and reports master It stands, and then executes step 10;
Step 08: if the result of step 07 be it is yes, detection calls the summary table voltage of survey together and whether is lower than critical voltage, if testing result Be it is no, then determine that platform area does not have a power failure;
Step 09: if the testing result of step 08 be it is yes, concentrator generate platform area power-off event simultaneously report main website;
Step 10: acquisition transparent area's summary table voltage of main website;
Step 11, whether: succeed transparent summary table voltage, if result whether, determines that platform area has a power failure, and then executes step 14;
Step 12: if the result of step 11 be it is yes, detect whether transparent summary table voltage is lower than critical voltage, if testing result Be it is no, then determine that platform area does not have a power failure;
Step 13: if the testing result of step 12 be it is yes, determine platform area have a power failure;
Step 14: main website sending station area power-off event to distribution repairs platform;
Step 15: distribution repairs platform and sends work order to corresponding repairing staff.
2. the optimization method of power-off event concentrator active reporting in platform area as described in claim 1, wherein the critical electricity Pressure is the 60% of reference voltage.
3. the optimization method of power-off event concentrator active reporting in platform area as described in claim 1, wherein the power failure thing After part reports main website, if main website is unresponsive, concentrator reports 3 times to cause to fail to report to avoid communication signal is bad.
CN201910306441.7A 2019-04-16 2019-04-16 A kind of optimization method of area's power-off event concentrator active reporting Pending CN110082618A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910306441.7A CN110082618A (en) 2019-04-16 2019-04-16 A kind of optimization method of area's power-off event concentrator active reporting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910306441.7A CN110082618A (en) 2019-04-16 2019-04-16 A kind of optimization method of area's power-off event concentrator active reporting

Publications (1)

Publication Number Publication Date
CN110082618A true CN110082618A (en) 2019-08-02

Family

ID=67415339

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910306441.7A Pending CN110082618A (en) 2019-04-16 2019-04-16 A kind of optimization method of area's power-off event concentrator active reporting

Country Status (1)

Country Link
CN (1) CN110082618A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113189437A (en) * 2021-06-30 2021-07-30 武汉中原电子信息有限公司 Detection method for power-off and power-on fault areas of transformer area

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008140316A (en) * 2006-12-05 2008-06-19 Chugoku Electric Power Co Inc:The Operation support system
CN103926485A (en) * 2014-03-26 2014-07-16 国家电网公司 Power failure event judging method based on electric energy collecting terminal
CN104779699A (en) * 2014-01-13 2015-07-15 国网上海市电力公司 Multifunctional station line loss management system
CN105071539A (en) * 2015-08-25 2015-11-18 国网北京市电力公司 Monitoring method and apparatus for distribution network
CN106483406A (en) * 2016-09-30 2017-03-08 国家电网公司 A kind of method of low-voltage power client's outage information data acquisition
CN107506849A (en) * 2017-07-24 2017-12-22 国网江西省电力公司电力科学研究院 A kind of intelligent optimization distribution transforming, which has a power failure, studies and judges system
CN107862626A (en) * 2017-11-03 2018-03-30 广东电网有限责任公司电力科学研究院 A kind of real-time power failure monitoring method and device based on measuring terminal warning information
CN108152578A (en) * 2017-12-15 2018-06-12 国网陕西省电力公司电力科学研究院 Taiwan area intelligent electric energy meter power-off event active reporting and analysis method
CN108765187A (en) * 2018-04-11 2018-11-06 国网山东省电力公司 A kind of power-off fault auxiliary analysis method, apparatus and system
CN109919328A (en) * 2019-01-31 2019-06-21 国网浙江省电力有限公司 A kind of low pressure branch line power failure analysis method based on multi-source power-off event

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008140316A (en) * 2006-12-05 2008-06-19 Chugoku Electric Power Co Inc:The Operation support system
CN104779699A (en) * 2014-01-13 2015-07-15 国网上海市电力公司 Multifunctional station line loss management system
CN103926485A (en) * 2014-03-26 2014-07-16 国家电网公司 Power failure event judging method based on electric energy collecting terminal
CN105071539A (en) * 2015-08-25 2015-11-18 国网北京市电力公司 Monitoring method and apparatus for distribution network
CN106483406A (en) * 2016-09-30 2017-03-08 国家电网公司 A kind of method of low-voltage power client's outage information data acquisition
CN107506849A (en) * 2017-07-24 2017-12-22 国网江西省电力公司电力科学研究院 A kind of intelligent optimization distribution transforming, which has a power failure, studies and judges system
CN107862626A (en) * 2017-11-03 2018-03-30 广东电网有限责任公司电力科学研究院 A kind of real-time power failure monitoring method and device based on measuring terminal warning information
CN108152578A (en) * 2017-12-15 2018-06-12 国网陕西省电力公司电力科学研究院 Taiwan area intelligent electric energy meter power-off event active reporting and analysis method
CN108765187A (en) * 2018-04-11 2018-11-06 国网山东省电力公司 A kind of power-off fault auxiliary analysis method, apparatus and system
CN109919328A (en) * 2019-01-31 2019-06-21 国网浙江省电力有限公司 A kind of low pressure branch line power failure analysis method based on multi-source power-off event

Non-Patent Citations (7)

* Cited by examiner, † Cited by third party
Title
MYGBFE336: "《智能电能表及采集终端事件记录采集规则》", 《道客巴巴》 *
冯素玲: "《上市公司违规处罚信息市场反应研究》", 《山东人民出版社》 *
河南电力技师学院: "《装表接电工》", 《中国电力出版社》 *
耿俊成等: "《基于多源信息的配电网停电故障研判》", 《上海电力学院学报》 *
赵永生等: "《基于大数据技术的供电可靠性中压停电事件实时智能分析研判与增益研究》", 《电力大数据》 *
邬宽明: "《现场总线技术应用选编 3》", 《北京航空航天大学出版社》 *
钱立军等: "《基于采集终端的台区停电监测功能实现及应用》", 《电气应用》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113189437A (en) * 2021-06-30 2021-07-30 武汉中原电子信息有限公司 Detection method for power-off and power-on fault areas of transformer area
CN113189437B (en) * 2021-06-30 2021-09-21 武汉中原电子信息有限公司 Detection method for power-off and power-on fault areas of transformer area

Similar Documents

Publication Publication Date Title
CN107909295B (en) Power failure information monitoring and analyzing system
CN104410067B (en) Zone area power failure analyzing method based on common transformer and analysis of big data acquired by users
CN110212645B (en) Power consumption information acquisition terminal power failure event reporting method and device
CN105427039A (en) Efficient processing method of distribution network repair work orders based on responsibility areas
CN104410163B (en) A kind of safety in production based on electric energy management system and power-economizing method
CN107844880A (en) A kind of electric network fault grade automatic identifying method based on multisource data fusion
CN106651643A (en) Power security management and control method for whole process based on distribution and adjustment
CN107153151B (en) Quick response method and system for power failure fault of low-voltage power grid user line
CN106646057A (en) Power-off and power-on active judgment method
CN108110893A (en) A kind of electric network fault grade automatic identifying method of transmission & distribution collaboration
CN105719062B (en) A kind of power grid risk considering double probability of malfunction characteristic and weak link appraisal procedure
CN109345786A (en) A kind of non-resident user power utilization abnormal conditions automatic alarm system of low pressure
CN202939301U (en) Remote monitoring diagnosis system of electric energy metering device
CN110083640A (en) A kind of recognition methods of platform area and device based on power failure data
CN110363422A (en) One kind stopping power transmission information management system, method and electronic equipment
CN105911424A (en) Identification method based on fault indicator false alarm signal
CN103197200B (en) Method and system for rapidly collecting and transmitting fault ranging information of power grid line
CN110082618A (en) A kind of optimization method of area's power-off event concentrator active reporting
CN104714206A (en) Remote monitoring and diagnosing method for electric energy metering device capable of finding faults timely
CN105913126A (en) Transformer station intelligent alarm model method for big data and cloud environment
CN107453481B (en) Method for rapidly discovering power failure of low-voltage transformer area
CN109523422A (en) A kind of method for digging of distribution network failure influence factor
Zhang et al. Development of the monitoring system in the smart distribution substation in Guangzhou, China
CN111585350A (en) Power control station communication and analysis system
CN105335824A (en) Power distribution network fault first-aid repair commanding method and system based on data center

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190802