CN106651643A CN201611039074.1A CN201611039074A CN106651643A CN 106651643 A CN106651643 A CN 106651643A CN 201611039074 A CN201611039074 A CN 201611039074A CN 106651643 A CN106651643 A CN 106651643A
Authority
CN
China
Prior art keywords
electric
distribution
power
control method
guarantor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611039074.1A
Other languages
Chinese (zh)
Inventor
谢琳
吴�琳
杜红卫
王坚俊
陶涛
王达
王一达
姜辰
乔松博
韩韬
王丙文
宋英华
谭志军
周养浩
张佳琪
吴雪琼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Nari Technology Co Ltd
Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Nanjing NARI Group Corp
Original Assignee
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Nari Technology Co Ltd
Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Nanjing NARI Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Zhejiang Electric Power Co Ltd, Nari Technology Co Ltd, Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd, Nanjing NARI Group Corp filed Critical State Grid Corp of China SGCC
Priority to CN201611039074.1A priority Critical patent/CN106651643A/en
Publication of CN106651643A publication Critical patent/CN106651643A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a power security management and control method for the whole process based on distribution and adjustment. The method employs the existing construction achievements (the conventional scheduling automation system and power distribution automation system), takes land-saving power distribution network integrated scheduling monitoring as the basis, closely guarantees the power supply safety of an important user during power security, achieves the formulation of a power security scheme, the execution monitoring, the distribution and adjustment integrated analysis, the power supply path tracking, the power security region positioning, the online evaluation of the power supply risk of the important user, the management and control of a power security emergency scheme and the integrated management and control of the whole process, and guarantees the quick obtaining of the information of a power grid, the accurate analysis and judgment, the timely pre-control of an event and the quick response to the emergency.

Description

A kind of guarantor's electricity management-control method towards overall process based on auxiliary tone integration
Technical field
The present invention relates to a kind of management-control method, and in particular to a kind of guarantor's fulgurite towards overall process based on auxiliary tone integration Prosecutor method.
Background technology
The electric power system in city is one of most important public utility in city, and it is responsible for government, enterprise and the common people and supplies The mission of firm power is answered, is power producer and lifeline that all departments of the whole society are able to run well.Especially as society Informationization, modernization development, user to power reliability requirement more and more higher, once some responsible consumer systems are sent out suddenly Raw failure and interruption of power supply, it will the normal orders of life of destruction society, cause great political fallout or economic loss.Research The power supply safety problem of responsible consumer, to ensureing that it is particularly important that social stability and the national economic development play the role of.2015 November《National large-area power-cuts event emergency preplan》Promulgate, specify that the large-area power-cuts in the face of occurring and have occurred and that Event, local people's governments and its relevant department, correlation agency of Bureau of Energy, electric power enterprise are in organizational framework, monitoring and warning Dispose to information report, emergency response, later stage, disposal is assessed, safeguard each stage opens according to division of duty and related prediction scheme Exhibition disposing task.As can be seen here, farthest prevent and reduce accident and its infringement for causing, power grid security of trying hard to keep is steady Fixed operation, ensures the need for electricity of city responsible consumer, for urban safety and social stability is safeguarded, promotes economic society comprehensive Coordination, sustainable development are significant.There is presently no and a set of cover security preparedness analysis, Risk-warning, fault diagnosis With process etc. overall process guarantor electricity management-control method.
The content of the invention
In order to solve above-mentioned technical problem, the invention provides a kind of guarantor's electricity towards overall process based on auxiliary tone integration Management-control method.
In order to achieve the above object, the technical solution adopted in the present invention is:
A kind of guarantor's electricity management-control method towards overall process based on auxiliary tone integration, comprises the following steps,
Step 1, the essential information for protecting electric user is imported from marketing with extraction system, according to the importance and the electric demand of actual guarantor of user Set up and electric task is protected in typing;
Step 2, using artwork splicing, the full mould of main distribution that major network model and distribution network model are merged in electric system is protected Type, and design different message channels and be transmitted and synchronistic model data;
Step 3, according to user and main distribution full model analysis supply path;
Step 4, according to power grid risk and equipment deficiency, risk assessment is carried out to supply path, obtains all events being likely to occur Barrier collection;
Step 5, according to all fault sets being likely to occur, generates the electric scheme of some guarantors;
Step 6, in operation of power networks, protects electric system Real-time Collection profile data, the failure that analysis is produced in real time, according to different Fault correlation is corresponding to protect electric scheme, carries out guarantor's electric treatment.
Major network model includes saving the major network model that EMS system is adjusted on the peripheral transformer station's substation model for adjusting EMS system and ground, matches somebody with somebody Pessimistic concurrency control includes that the distribution network model of DMS systems is adjusted on ground.Distribution network model includes middle voltage distribution networks model and low-voltage distribution network model.
Supply path analysis process is, from user, according to the Topology connection in main distribution full model, in typical case's operation Peripheral transformer station's plant stand is traced back to from power supply point in mode, paths traversed is supply path.Supply path is closed on GIS figures Connection and display.
Protect needs to check it after electric schemes generation, i.e., the X hours before protecting electricity and formally starting, just set guarantor electricity scheme Verified with current actual operating, analyzed its reasonability and feasibility.
Protecting when electric scheme is run to verify in real time.
The beneficial effect that the present invention is reached:The present invention makes full use of existing dispatch automated system, power distribution automation system The existing construction achievement such as system, to save based on power distribution network integration dispatching and monitoring, closely surrounds guarantee responsible consumer and is protecting electricity Period power supply safety, the electric programming of realization guarantor is reviewed, protects electricity region with performing monitoring, allocating integrated analysis, supply path Positioning, responsible consumer are for risk online evaluation, the electric emergency plan management and control of guarantor and the integrated management and control of process overall process, it is ensured that electricity Net acquisition of information is fast, analysis judges standard, the timely pre-control of event, emergency disposal quick response.
Description of the drawings
Fig. 1 is the flow chart of the present invention.
Fig. 2 is the electric conceptual design figure of guarantor.
Specific embodiment
Below in conjunction with the accompanying drawings the invention will be further described.Following examples are only used for clearly illustrating the present invention Technical scheme, and can not be limited the scope of the invention with this.
As illustrated in fig. 1 and 2, a kind of guarantor's electricity management-control method towards overall process based on auxiliary tone integration, including following step Suddenly:
Step 1, the essential information for protecting electric user is imported from marketing with extraction system, according to the importance and the electric demand of actual guarantor of user Set up and electric task is protected in typing.
Step 2, using artwork splicing, the main distribution that major network model and distribution network model are merged in electric system is protected Full model, and design different message channels and be transmitted and synchronistic model data.
Major network model includes saving the major network model that EMS system is adjusted on the peripheral transformer station's substation model for adjusting EMS system and ground, matches somebody with somebody Pessimistic concurrency control includes that the distribution network model of DMS systems is adjusted on ground.
Due in original major network system not in view of mesolow model, major network and distribution network model Topology connection basis On, distribution network model is extended to into low-voltage distribution network by middle voltage distribution networks, low-voltage distribution network includes the low-voltage electricity user of 380V/220V, low Press-fitting change and its terminal device etc., i.e., distribution network model includes middle voltage distribution networks model and low-voltage distribution network model.
To ensure the main efficient process with network information, design different message channels and led the transmission with network information, together When register the message channel of distribution and major network respectively in the application, it is ensured that major network, with network information monitor it is ageing, it also avoid The main cross snoop with network information.Main distribution full model data are synchronous with main distribution data, reading, change, deleting main distribution Main distribution data successfully modified just return success value is needed to wait for during full model data.
Step 3, according to user and main distribution full model analysis supply path.
Supply path analyzes process:From user, according to the Topology connection in main distribution full model, in typical case's operation Peripheral transformer station's plant stand is traced back to from power supply point in mode, paths traversed is supply path.Generally, single supply user has one Bar supply path, dual power supply user has two supply paths.Supply path is made up of ordered cluster tool, in supply path Middle extraction key node, including user higher level's direct-furnish station, 110kV station, 220kV stations, 500kV stations, are carried out in a structured manner Storage.Supply path is associated and shown on GIS figures, is that monitoring and decision-making provide Visualization Service.
Step 4, according to power grid risk and equipment deficiency, risk assessment is carried out to supply path, obtains all being likely to occur Fault set.
Step 5, according to all fault sets being likely to occur, generates the electric scheme of some guarantors.
Protect needs to check it after electric schemes generation, i.e., the X hours before protecting electricity and formally starting, just set guarantor electricity scheme Verified with current actual operating, analyzed its reasonability and feasibility.
Step 6, in operation of power networks, protects electric system Real-time Collection profile data, the failure that analysis is produced in real time, according to not Same fault correlation is corresponding to protect electric scheme, carries out guarantor's electric treatment, can verify in real time when protecting electric scheme operation.
Above-mentioned verification and verification in real time when checking be:Section tidal current analysis is carried out, judges whether that voltage can be caused to get over Limit is transshipped.
Step 7, protect carries out protecting electric industry business overall process filing after the completion of electricity.
Said method makes full use of the existing construction achievement such as existing dispatch automated system, electrical power distribution automatization system, to save Based on ground power distribution network integration dispatching and monitoring, guarantee responsible consumer is closely surrounded in period of the protection of electricity power supply safety, realize protecting electricity Programming reviews, protects electricity zone location, responsible consumer and supply risk with performing monitoring, allocating integrated analysis, supply path Online evaluation, guarantor's electricity emergency plan management and control and the integrated management and control of process overall process, it is ensured that electric network information acquisition is fast, analyze judgement Standard, the timely pre-control of event, emergency disposal quick response.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, on the premise of without departing from the technology of the present invention principle, some improvement and deformation can also be made, these improve and deform Also should be regarded as protection scope of the present invention.

Claims (7)

1. it is a kind of based on auxiliary tone integration towards overall process guarantor electricity management-control method, it is characterised in that:Comprise the following steps,
Step 1, the essential information for protecting electric user is imported from marketing with extraction system, according to the importance and the electric demand of actual guarantor of user Set up and electric task is protected in typing;
Step 2, using artwork splicing, the full mould of main distribution that major network model and distribution network model are merged in electric system is protected Type, and design different message channels and be transmitted and synchronistic model data;
Step 3, according to user and main distribution full model analysis supply path;
Step 4, according to power grid risk and equipment deficiency, risk assessment is carried out to supply path, obtains all events being likely to occur Barrier collection;
Step 5, according to all fault sets being likely to occur, generates the electric scheme of some guarantors;
Step 6, in operation of power networks, protects electric system Real-time Collection profile data, the failure that analysis is produced in real time, according to different Fault correlation is corresponding to protect electric scheme, carries out guarantor's electric treatment.
2. it is according to claim 1 it is a kind of based on auxiliary tone integration towards overall process guarantor electricity management-control method, its feature It is:Major network model includes saving the major network model that EMS system is adjusted on the peripheral transformer station's substation model for adjusting EMS system and ground, distribution Model includes that the distribution network model of DMS systems is adjusted on ground.
3. it is according to claim 2 it is a kind of based on auxiliary tone integration towards overall process guarantor electricity management-control method, its feature It is:Distribution network model includes middle voltage distribution networks model and low-voltage distribution network model.
4. it is according to claim 1 it is a kind of based on auxiliary tone integration towards overall process guarantor electricity management-control method, its feature It is:Supply path analysis process is, from user, according to the Topology connection in main distribution full model, in typical operation side Peripheral transformer station's plant stand is traced back to from power supply point in formula, paths traversed is supply path.
5. it is according to claim 4 it is a kind of based on auxiliary tone integration towards overall process guarantor electricity management-control method, its feature It is:Supply path is associated and shown on GIS figures.
6. it is according to claim 1 it is a kind of based on auxiliary tone integration towards overall process guarantor electricity management-control method, its feature It is:Protect needs to check it after electric schemes generation, i.e., the X hours before protecting electricity and formally starting, just set guarantor electricity scheme with Current actual operating is verified, and analyzes its reasonability and feasibility.
7. it is according to claim 1 it is a kind of based on auxiliary tone integration towards overall process guarantor electricity management-control method, its feature It is:Protecting when electric scheme is run to verify in real time.
CN201611039074.1A 2016-11-21 2016-11-21 Power security management and control method for whole process based on distribution and adjustment Pending CN106651643A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611039074.1A CN106651643A (en) 2016-11-21 2016-11-21 Power security management and control method for whole process based on distribution and adjustment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611039074.1A CN106651643A (en) 2016-11-21 2016-11-21 Power security management and control method for whole process based on distribution and adjustment

Publications (1)

Publication Number Publication Date
CN106651643A true CN106651643A (en) 2017-05-10

Family

ID=58811222

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611039074.1A Pending CN106651643A (en) 2016-11-21 2016-11-21 Power security management and control method for whole process based on distribution and adjustment

Country Status (1)

Country Link
CN (1) CN106651643A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107491866A (en) * 2017-08-07 2017-12-19 国网四川省电力公司 One kind saves ground integrated electricity net safety stable integrated campaign method
CN108471115A (en) * 2018-04-26 2018-08-31 国网上海市电力公司 A kind of electric managing and control system of guarantor
CN108879792A (en) * 2018-06-27 2018-11-23 国家电网有限公司 A kind of integration auxiliary support system based on new energy management and running operation
CN109004746A (en) * 2018-07-09 2018-12-14 国网江苏省电力有限公司常州供电分公司 Power consumer occasion protects method for electrically
CN109063963A (en) * 2018-07-03 2018-12-21 国电南瑞科技股份有限公司 A kind of responsible consumer power supply methods of risk assessment based on unit style electricity distribution network model
CN109472427A (en) * 2017-12-28 2019-03-15 国网浙江省电力公司嘉兴供电公司 A kind of guarantor's power supply trouble excludes and stand-by equipment planing method
CN109598452A (en) * 2018-12-30 2019-04-09 国网北京市电力公司 Monitor the method and device of power distribution network
CN110321509A (en) * 2019-04-16 2019-10-11 国网新疆电力有限公司昌吉供电公司 A kind of guarantor's power supply management system
CN114881809A (en) * 2022-05-18 2022-08-09 广东电网有限责任公司 Topological graph analysis method and device

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102931726A (en) * 2012-10-22 2013-02-13 深圳供电局有限公司 Main network and distribution network integrated security power supply system
CN105305444A (en) * 2015-11-30 2016-02-03 国网浙江省电力公司绍兴供电公司 Distribution network intelligent alarm and processing method based on integrated allocation

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102931726A (en) * 2012-10-22 2013-02-13 深圳供电局有限公司 Main network and distribution network integrated security power supply system
CN105305444A (en) * 2015-11-30 2016-02-03 国网浙江省电力公司绍兴供电公司 Distribution network intelligent alarm and processing method based on integrated allocation

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107491866A (en) * 2017-08-07 2017-12-19 国网四川省电力公司 One kind saves ground integrated electricity net safety stable integrated campaign method
CN107491866B (en) * 2017-08-07 2021-11-05 国网四川省电力公司 Provincial and regional integrated power grid safety and stability comprehensive defense method
CN109472427A (en) * 2017-12-28 2019-03-15 国网浙江省电力公司嘉兴供电公司 A kind of guarantor's power supply trouble excludes and stand-by equipment planing method
CN108471115A (en) * 2018-04-26 2018-08-31 国网上海市电力公司 A kind of electric managing and control system of guarantor
CN108879792A (en) * 2018-06-27 2018-11-23 国家电网有限公司 A kind of integration auxiliary support system based on new energy management and running operation
CN109063963A (en) * 2018-07-03 2018-12-21 国电南瑞科技股份有限公司 A kind of responsible consumer power supply methods of risk assessment based on unit style electricity distribution network model
CN109004746A (en) * 2018-07-09 2018-12-14 国网江苏省电力有限公司常州供电分公司 Power consumer occasion protects method for electrically
CN109598452A (en) * 2018-12-30 2019-04-09 国网北京市电力公司 Monitor the method and device of power distribution network
CN110321509A (en) * 2019-04-16 2019-10-11 国网新疆电力有限公司昌吉供电公司 A kind of guarantor's power supply management system
CN114881809A (en) * 2022-05-18 2022-08-09 广东电网有限责任公司 Topological graph analysis method and device

Similar Documents

Publication Publication Date Title
CN106651643A (en) Power security management and control method for whole process based on distribution and adjustment
CN107909295B (en) Power failure information monitoring and analyzing system
CN102663240B (en) Analysis system and evaluation method for power telecommunication business risks
CN102545213B (en) System and method for managing line loss of power grid in real time
CN102930365B (en) A kind of relay protection statistical analysis and the check method of operational management data
CN103578039B (en) A kind of power networks risk prewarning analysis system
CN108110893A (en) A kind of electric network fault grade automatic identifying method of transmission & distribution collaboration
CN107194574B (en) Power grid security risk assessment method based on load loss
CN105427039A (en) Efficient processing method of distribution network repair work orders based on responsibility areas
CN105093033A (en) Power grid multi-source information-based fault integrated analysis system and analysis method
CN102938106B (en) Major network N-1 methods of risk assessment based on grid power blackout plan and system
CN105184442A (en) Power distribution network dispatching management statistical analysis system
CN110647567B (en) Power failure plan auxiliary decision system based on end data fusion
CN104463696A (en) Power grid operating risk recognition and prevention method and system
CN103488138A (en) Method and system for generating scheduling item operation order
CN105719062B (en) A kind of power grid risk considering double probability of malfunction characteristic and weak link appraisal procedure
CN109062993A (en) A kind of offline electric network fault Response project generation method and its device
CN112865316B (en) Big data-based power supply service analysis command system and method
Portante et al. Simulation of the september 8, 2011, san diego blackout
CN111667143A (en) Method for realizing fusion of real-time monitoring data and service management data in power grid dispatching
Fotuhi-Friuzabad et al. Upcoming challenges of future electric power systems: sustainability and resiliency
CN105207358A (en) Electrical energy quality online monitoring platform
CN112598257A (en) Power failure analysis method and system based on big data feature mining
CN103647279A (en) Plant wiring information based anticipatory fault set generation method
CN116227964A (en) Data asset management optimization method, system and equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510