CN103488138A - Method and system for generating scheduling item operation order - Google Patents

Method and system for generating scheduling item operation order Download PDF

Info

Publication number
CN103488138A
CN103488138A CN201310393050.6A CN201310393050A CN103488138A CN 103488138 A CN103488138 A CN 103488138A CN 201310393050 A CN201310393050 A CN 201310393050A CN 103488138 A CN103488138 A CN 103488138A
Authority
CN
China
Prior art keywords
item
information
operation order
equipment
confirmation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310393050.6A
Other languages
Chinese (zh)
Other versions
CN103488138B (en
Inventor
骆国铭
吴海江
周俊宇
郝玉锋
何锡祺
陈晓彤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
INFORMATION COMMUNICATION TECHNOLOGY BRANCH, NANJING NARI GROUP CORPORATION
Foshan Power Supply Bureau of Guangdong Power Grid Corp
Original Assignee
Foshan Power Supply Bureau of Guangdong Power Grid Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Power Supply Bureau of Guangdong Power Grid Corp filed Critical Foshan Power Supply Bureau of Guangdong Power Grid Corp
Priority to CN201310393050.6A priority Critical patent/CN103488138B/en
Publication of CN103488138A publication Critical patent/CN103488138A/en
Application granted granted Critical
Publication of CN103488138B publication Critical patent/CN103488138B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P80/00Climate change mitigation technologies for sector-wide applications
    • Y02P80/10Efficient use of energy, e.g. using compressed air or pressurized fluid as energy carrier
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a method and system for generating a scheduling item operation order. The method includes the steps of reading EMS data, judging whether an equipment position state is consistent with an equipment real-time state, if yes, generating task selection according to the operation conducted by an order drafter on equipment to be operated, generating an operation item with the position state opposite to the position state of the equipment according to the operation conducted by the order drafter on equipment in a transformer substation, judging a power source point of a factory and a power source point of a station according to an active power grid power flow diagram, a positive power grid flow diagram and the equipment position state when the switching of the operation method of a power grid is related, and when the power source point of the factory and the power source point of the station are converted into new power source points after the judgment operation, generating a secondary operation item which needs to be changed, wherein the EMS data include the active power grid power flow diagram, the positive power grid power flow diagram and the equipment position state, and the secondary operation item includes a reclosing device and automatic bus transfer equipment. According to the method and system, the order drafting speed is improved, the operation risk of the power grid is lowered, and a large number of paper resources are saved.

Description

Generate the method and system that scheduling makes operation order item by item
Technical field
The present invention relates to field of power, particularly relate to and a kind ofly generate scheduling and make item by item the method for operation order and a kind ofly generate the system that scheduling makes operation order item by item.
Background technology
Along with economic develop rapidly, the urban electric power network is more and more huger, the value volume and range of product of generating plant, transformer station, electric line and the power equipment thereof of power scheduling monitor staff administration is more and more, power system operating mode is increasingly sophisticated, the every scheduling of formulating day by day of power scheduling monitor staff makes the quantity of operation order increasing item by item, has increased the weight of yardman's working strength.
Traditional generation scheduling makes the method for operation order mainly utilize area of computer aided to intend ticket item by item, not only intend the location status that the ticket people needs artificial checking apparatus, and the change of relevant secondary device (as reclosing, backup auto-activating device etc.) is also needed to manually add.Adopt aforesaid way to generate scheduling and make item by item operation order, it is long that one side is intended the ticket time, thereby extended operating personnel's stand-by period and line outage time, increased the power grid security risk; Make item by item on the other hand operation order intend the ticket process need and use a large amount of paper, do not meet the requirement of environmental protection and saving.Visible, traditional generation scheduling makes the mode of operation order can not meet power dispatch system operation and management by the empirical requirement to logical type, intelligent lifting item by item.
Summary of the invention
Based on this, be necessary problem long for the above-mentioned plan ticket time, that do not save, a kind of method and system that scheduling makes operation order item by item that generate are provided.
For achieving the above object, the present invention adopts following technical scheme:
A kind ofly generate the method that scheduling makes operation order item by item, comprise the following steps:
Read the EMS data, described EMS data comprise following information: electric network current diagram is meritorious, idle, the device location state;
Judge that whether described device location state is consistent with the equipment real-time status;
If according to intending the ticket people, the operation of wanting operating equipment is generated to task choosing;
According to intending, the operation of ticket people to the power transformation station equipment generates and the operation item of this device location opposite states location status, and when relating to the power system operating mode conversion, meritorious, idle according to described electric network current diagram, the device location state is differentiated factory, the power supply source points of standing, when the power supply point of differentiating the rear described factory of operation, stand is transformed to new power point, generate the secondary operation project that needs change; Described secondary operation project comprises: reclosing, backup auto-activating device.
A kind ofly generate the system that scheduling makes operation order item by item, comprising:
Data read module, for reading the EMS data, described EMS data comprise: electric network current diagram is meritorious, idle, the device location state;
Judge module, whether consistent with the equipment real-time status for judging described device location state;
The task choosing generation module, in the situation that judgment result is that of described judge module be, according to intending the ticket people to wanting the operation generation task choosing of operating equipment;
The operation item generation module, for according to intending, the operation of ticket people to the power transformation station equipment generates and the operation item of this device location opposite states location status, and when relating to the power system operating mode conversion, meritorious, idle according to described electric network current diagram, the device location state is differentiated factory, the power supply source points of standing, when the power supply point of differentiating the rear described factory of operation, stand is transformed to new power point, generate the secondary operation project that needs change; Described secondary operation project comprises: reclosing, backup auto-activating device.
By above scheme, can be found out, a kind of method and system that scheduling makes operation order item by item that generate of the present invention, realized that the self-verifying of device location is checked, the automatic generation of the intelligent selection of operation task, operation item and can automatically generate the secondary operation projects such as the reclosing that needs change, backup auto-activating device.With traditional generation scheduling, make item by item the method for operation order compare, after using this programme, the plan ticket that makes item by item operation order that ground is adjusted, audit time can foreshorten to average 7 minutes now in average 15 minutes by former, and the rate of drawing a bill and accuracy all can reach 100%, thereby greatly alleviated the dispatching and monitoring personnel the intensity of making out an invoice, improved plan ticket speed and quality, greatly improved dispatching and monitoring personnel's work efficiency; The circuit power off time has also shortened accordingly simultaneously, has greatly reduced the operation of power networks risk, has shortened the power off time of power consumer, has improved power supply reliability, for the better service-user of electric system, service society have been contributed scheduling people's a strength; In addition, the present invention has also realized with no paper operation, has saved a large amount of paper resources, active response the call that reduces discharging of national energy-saving.
The accompanying drawing explanation
Fig. 1 a kind ofly in the embodiment of the present invention generates the schematic flow sheet that scheduling makes the method for operation order item by item;
Fig. 2 a kind ofly in the embodiment of the present invention generates the structural representation that scheduling makes the system of operation order item by item.
Embodiment
Below in conjunction with accompanying drawing and specific embodiment, the solution of the present invention is further described.
Shown in Figure 1, a kind ofly generate the method that scheduling makes operation order item by item, comprise the following steps:
Step S101, read EMS(Energy Management System, energy management system) data, described EMS data comprise following information: electric network current diagram is meritorious, idle, device location state etc., then enters step S102.
Step S102, judge that whether described device location state is consistent with the equipment real-time status; If enter step S103.
As an embodiment preferably, after step S101 reads the EMS data, if can also comprise the steps:, described device location state and equipment real-time status are inconsistent, the inconsistent information of prompt facility location status (need to carry out the state renewal or state manually is set).
Step S103, if described device location state is consistent with the equipment real-time status, according to intending the ticket people, the operation (as: clicking operation) of wanting operating equipment is generated to task choosing, as " general * * circuit by * * state transfers to * * state ", " mode is changed " etc.Wherein * * circuit is electric pressure+device name, and the original state of equipment is defaulted as current state, and dbjective state can be selected all the other states except original state.Enter step S104 after completing.
Step S104, according to intending, the operation of ticket people to power transformation station equipment (switch, disconnecting link, grounding switch, neutral ground disconnecting link etc.) generates and the operation item of this device location opposite states location status, and when relating to the power system operating mode conversion, the power supply source points of differentiating factory, standing according to described electric network current diagram meritorious (P), idle (Q), device location state, when the power supply point of differentiating the rear described factory of operation, stand is transformed to new power point, generate the secondary operation project that needs change; Described secondary operation project comprises: reclosing, backup auto-activating device etc., and the action statement now automatically generated is as follows: " drop into * * line * * switch * * reclosing ", " drop into * * line * * switch with * * line * * switch prepared auto restart each other ".
The detailed process of above-mentioned generating run project can be as follows: after circuit transfers empty charging to, read circuit both sides device location state in the EMS data, differentiate circuit points out when empty charged state: " * * circuit is in empty charged state; generating run ticket whether automatically? " and, according to " deenergization side switch---pull open the load side disconnecting link---pulling open the mains side disconnecting link---the line side grounding switch that closes " order generating run ticket automatically, by the device location state memorization under this sky charged state, be normal condition before having a power failure simultaneously; When the circuit power transmission operates, prompting: " * * circuit is at inspecting state; the empty charging operations ticket of generation whether automatically? " and according to " pull open the line side grounding switch---power turn-on side tool lock---load side of closing disconnecting link---power turn-on side switch " the automatic generating run ticket of order is normal condition before having a power failure by the device location recovering state.
After intending ticket, can be increased, delete, insert, copy, move, close the editings such as order and fractionation to relevant operation item; After making item by item the operation order editor, after receiving " preservation " information of intending ticket people transmission, according to this " preservation " information, will make item by item operation order be kept at pending; In addition after receiving " turning guardian's audit " information of intending ticket people transmission, can turn msu message Auto-writing operator name and will make item by item operation order automatically go in audit according to this, can point out the guardian to examine in the mode of voice or page top scroll bar simultaneously and make item by item operation order.
As an embodiment preferably, can also comprise following information in described EMS data: equipment limit value, section limit value, stable operation condition, PAS trend computing function etc.
In addition, tradition generates in the method make item by item operation order only has five basic anti-verifications, and as an embodiment preferably, in order to ensure the security of electric grid operating, the present invention, after generating described operation item, can also comprise the step of being checked as follows:
According to default equipment standard term and grid switching operation term rules, spelt and syntax check; When the power supply point of receive factory, standing is transformed to new power point, result of calculation, equipment limit value, section limit value, stable operation condition according to described PAS, whether cause decompression, section overload, apparatus overload, stable action after checking operation, separated/prompting side by side (the anti-non-synchronization paralleling of locking system), open/cyclization of system are reminded; Receive and intend the associated PMS(production safety management of ticket people infosystem) in after interruption maintenance list information, overhauling single information according to this association transfers in the PMS system mode suggestion, system in the interruption maintenance list state of equipment is required to information, whether the state of checking power supply point conversion and the rear equipment of operation is consistent, and the prompting checked result; Receive and intend after the ticket people carries out operation order preview information, launch the station wiring diagram simulation and carry out each task that makes item by item operation order, and prompting operation normally reaching the specifying information that dangerous point is found in operation.
As an embodiment preferably, after generating described operation item, can also comprise the step of being examined as follows:
Receive guardian each operation item confirmation and msu message, complete first trial according to this confirmation and msu message Auto-writing guardian name, the operation order that makes item by item generated is retained in audit, and points out responsible official on duty to examine the described operation order that makes item by item in the mode of voice or page top scroll bar;
Receive responsible official on duty each operation item confirmation and msu message, according to this confirmation and msu message Auto-writing responsible official's name on duty automatic generating run ticket numbering, complete reexamination and will be described to make item by item operation order automatically go to pending, and point out the described operation order that makes item by item of plan ticket people to examine and pass through in the mode of voice or page top scroll bar;
When receive described guardian or responsible official on duty audit not by the time when rollback that sends and rollback suggestion information, according to this rollback and rollback suggestion information rollback give intend the ticket people and will describedly make item by item operation order go to pending, then with the mode of voice or page top scroll bar point out plan ticket people this make item by item operation order rollback;
When receiving personnel on duty, hand over to the next shift after confirmation, after succeeding according to this confirmation mechanical check, whether three careful personnel are all identical, will wait if not to issue with executory to make item by item operation order go to pending, and in the mode of voice or page top scroll bar, point out dispatching and monitoring person to have new to make item by item operation order pending.
Tradition audit makes operation order item by item to be complete manual examination and verification and to turn audit, intending the ticket people intends filling in operation order numbering and operator's name and delivering guardian's audit after ticket, fill in guardian's name after guardian's audit and deliver responsible official's audit on duty, responsible official on duty examines and fills in name and returns to intending the ticket people, as audit not by, again three examine after relieving, the problem of operation order double sign (two and above people (yardman or monitor), while intending ticket, double sign can occur simultaneously) and inefficiency easily occurs in review process; Realized the e-cooperative work in the audit twist process in the present invention, Auto-writing realized in operation order numbering in the operation order nominal value, operator, guardian, responsible official's name on duty, generate numbering after responsible official on duty (people) audit, avoided operation order double sign problem, guaranteed the uniqueness of numbering, improve review efficiency, and pointed out hommization more in the mode of voice or page top scroll bar.
In addition, as an embodiment preferably, after being examined, can also comprise the described step that makes item by item operation order of following execution:
After receiving the operator and carrying out the confirmation information that power transmission makes first operation item of operation order item by item, read in described EMS data according to this confirmation the nameplate information on operating equipment for the treatment of, if also have the nameplate of not removing, pointed out (dismounting nameplate);
After receiving the operator and carrying out the confirmation information of an operation item, read the device location status information in described EMS data and carry out this operation item preview according to this confirmation, if the preview result is the power supply point that receives factory, stand while being transformed to new power point, carry out trend calculating according to PAS trend computing function in this call by result EMS system, if calculation of tidal current shows while there will be apparatus overload, section overload dangerous point, points out and the interrupt operation project implementation;
After receiving the operator and carrying out first operation item confirmation, fill in the people's name of issuing an order (being operator's name), issue an order the time (real-time time that is system) according to this confirmation, the confession operator that made us who screens corresponding unit according to the plant stand title confirms and automatically goes in execution by the described operation order that makes item by item; And be finished after information receiving operation item, fill in the deadline (real-time time that is system), reporter's name (be defaulted as and made us name) and automatically calculate this action-item execution time according to this information, if this action-item time is overtime, carry out filling at remarks column the prompting of overtime reason;
After receiving power failure and making item by item the complete confirmation of the operation order all operations project implementation, read in described EMS data according to this confirmation the nameplate information on operating equipment for the treatment of, if do not hang nameplate, hung the prompting of nameplate;
When receiving the described complete confirmation of the equal executed of operation order all operations project that makes item by item, according to this confirmation, in the described operation order nominal value that makes item by item, automatically add a cover the executed seal; When receiving an operation item, this does not carry out confirmation, automatically adds a cover this according to this confirmation at this action-item and does not carry out seal and carry out filling at remarks column the prompting that this does not carry out reason; When receiving the pending operation order calcellation confirmation that makes item by item, according to this confirmation, at this, make item by item the operation order nominal value automatically add a cover the calcellation seal, and make item by item operation order go to filing by pending this;
When receive add a cover executed seal information make operation order item by item the time, read in the PMS system interruption maintenance list and fill in and stop electric power feeding time and the people that issues an order, made us personnel's name according to this information;
When receive add a cover executed seal information make item by item that operation order and generating run mode change, circuit is while stopping power transmission registration confirmed information, according to this information, reads the DMIS(scheduling management information system) in the method for operation change record, circuit and stop power transmission and record and fill in and stop electric power feeding time and the people that issues an order, the original state of being made us name and device name, equipment and dbjective state, make the information such as operation order numbering item by item.
Tradition make item by item the execution of operation order want manual examination and verification fill in the nominal value content, manually arrange nameplate information, manually impress chapter, manually fill in PMS in interruption maintenance list content, DMIS the method for operation change record, circuit stops the power transmission record.And carry out in the present invention, make item by item operation order safer, quick, Auto-writing nominal value content, prompting arrange nameplate lock operation, automatic cover seal, intelligence and fill in that in PMS, in interruption maintenance list content, DMIS, the method for operation changes record, circuit stops the power transmission record, the present invention has added Real-time Power Flow to calculate locking in operation in addition, makes operation safe.
As an embodiment preferably, carry out described make operation order item by item after, can also comprise the step that following acceptance inquiry and data derive:
When receiving the combination condition Query Information, make item by item the quantity of operation order according to this Query Information statistical dependence; Described combination condition can comprise: time period constraint, equipment, numbering, type, task, executed, calcellation, personnel etc.;
When receive each monthly in, while making item by item operation order stop power transmission running time and average operating time Query Information in year, according to this Query Information, add up each running time that makes item by item operation order and average operating time and show overtime operation item and reason;
When receiving overtime operation item Query Information, according to this Query Information statistics, make item by item overtime operation item, the place of operation order make item by item operation order task, numbering, time and overtime reason, for the power equipments defect statistics provides the data foundation;
When receiving the statistical information derived information, automatically derive the statistical information of word or excel form according to this derived information; When receiving statistical information and export as chart-information, according to the tabular statistical information of this derived information derived graph.
Tradition makes the statistics of operation order want manual sorting, sequence, bookbinding item by item, and inquiry will be carried out page by page, and work efficiency is low; And in the present invention, query statistic makes operation order all realize e-cooperative work item by item, more quick and easy, accurate, and the supported data export function, be the data information collection work condition of providing convenience.Simultaneously the present invention has realized with no paper operation, has saved a large amount of paper resources, and the statistics that makes to make item by item operation order is environmental protection and saving more.
The present invention has called energy management system, production safety management infosystem and scheduling management information system data resource, and has realized direct access PMS Unit account of plant, EMS topological data, calls EMS trend computing function and is calculated, and has realized resource sharing.The present invention maximizes realization makes the intelligence of operation order generate item by item, reach the statistical study disaggregatedly of archive operation ticket by the automatic-prompting of the automatic generation of operation item, the secondary device of being correlated with, Auto-writing the automatic flow of the rear relevant nominal value content of audit, solved a traditional difficult problem that makes item by item the operation ticket system inefficiency.And increased associated maintenance request slip and lost the measures such as load is reminded, For Solutions of Systems/remind side by side (the anti-non-synchronization paralleling of locking system), open/cyclization of system prompting, trend verification on basic five anti-bases, increased the security of electric grid operating.
The solution of the present invention can adapt to the diversity of electric grid operating task, the complicacy of electric network composition and the dirigibility of the method for operation, by adopting this programme, can make the major network dispatcher concentrate more energy to be absorbed in the research power grid security, significant to the work efficiency that improves power network safety operation level and yardman.
A kind ofly generate scheduling and make item by item the method for operation order corresponding with above-mentioned, the present invention also provides a kind of system that scheduling makes operation order item by item that generates, and as shown in Figure 2, comprising:
Data read module 101, for reading the EMS data, described EMS data comprise: electric network current diagram is meritorious, idle, the device location state;
Judge module 102, whether consistent with the equipment real-time status for judging described device location state;
Task choosing generation module 103, in the situation that judgment result is that of described judge module be, according to intending the ticket people to wanting the operation generation task choosing of operating equipment;
Operation item generation module 104, for according to intending, the operation of ticket people to the power transformation station equipment generates and the operation item of this device location opposite states location status, and when relating to the power system operating mode conversion, meritorious, idle according to described electric network current diagram, the device location state is differentiated factory, the power supply source points of standing, when the power supply point of differentiating the rear described factory of operation, stand is transformed to new power point, generate the secondary operation project that needs change; Described secondary operation project comprises: reclosing, backup auto-activating device.
As an embodiment preferably, can also comprise following information in described EMS data: equipment limit value, section limit value, stable operation condition, PAS trend computing function.
As an embodiment preferably, generation scheduling of the present invention makes the system of operation order can also comprise the check module item by item, for after generating described operation item, carries out following check:
According to default equipment standard term and grid switching operation term rules, spelt and syntax check; When the power supply point of receive factory, standing is transformed to new power point, result of calculation, equipment limit value, section limit value, stable operation condition according to described PAS, whether cause decompression, section overload, apparatus overload, stable action after checking operation, separated/remind side by side, open/cyclization of system reminds; Receive and intend in the associated PMS system of ticket people after interruption maintenance list information, overhauling single information according to this association transfers in the PMS system mode suggestion, system in the interruption maintenance list state of equipment is required to information, whether the state of checking power supply point conversion and the rear equipment of operation is consistent, and the prompting checked result; Receive and intend after the ticket people carries out operation order preview information, launch the station wiring diagram simulation and carry out each task that makes item by item operation order, and prompting operation normally reaching the specifying information that dangerous point is found in operation.
Above-mentionedly a kind ofly generate scheduling and make item by item other technical characterictic of the system of operation order a kind ofly generate scheduling and make item by item the method for operation order identical with of the present invention, it will not go into details herein.
By above scheme, can find out, a kind of method and system that scheduling makes operation order item by item that generate of the present invention, realized that the self-verifying of device location is checked, the automatic generation of the intelligent selection of operation task, operation item and can automatically generate the secondary operation projects such as the reclosing that needs change, backup auto-activating device.With traditional generation scheduling, make item by item the method for operation order compare, after using this programme, the plan ticket that makes item by item operation order that ground is adjusted, audit time can foreshorten to average 7 minutes now in average 15 minutes by former, and the rate of drawing a bill and accuracy all can reach 100%, thereby greatly alleviated the dispatching and monitoring personnel the intensity of making out an invoice, improved plan ticket speed and quality, greatly improved dispatching and monitoring personnel's work efficiency; The circuit power off time has also shortened accordingly simultaneously, has greatly reduced the operation of power networks risk, has shortened the power off time of power consumer, has improved power supply reliability, for the better service-user of electric system, service society have been contributed scheduling people's a strength; In addition, the present invention has also realized with no paper operation, has saved a large amount of paper resources, active response the call that reduces discharging of national energy-saving.
The above embodiment has only expressed several embodiment of the present invention, and it describes comparatively concrete and detailed, but can not therefore be interpreted as the restriction to the scope of the claims of the present invention.It should be pointed out that for the person of ordinary skill of the art, without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.Therefore, the protection domain of patent of the present invention should be as the criterion with claims.

Claims (10)

1. one kind generates the method that scheduling makes operation order item by item, it is characterized in that, comprises the following steps:
Read the EMS data, described EMS data comprise following information: electric network current diagram is meritorious, idle, the device location state;
Judge that whether described device location state is consistent with the equipment real-time status;
If according to intending the ticket people, the operation of wanting operating equipment is generated to task choosing;
According to intending, the operation of ticket people to the power transformation station equipment generates and the operation item of this device location opposite states location status, and when relating to the power system operating mode conversion, meritorious, idle according to described electric network current diagram, the device location state is differentiated factory, the power supply source points of standing, when the power supply point of differentiating the rear described factory of operation, stand is transformed to new power point, generate the secondary operation project that needs change; Described secondary operation project comprises: reclosing, backup auto-activating device.
2. generation scheduling according to claim 1 makes the method for operation order item by item, it is characterized in that, also comprises following information in described EMS data: equipment limit value, section limit value, stable operation condition, PAS trend computing function.
3. generation scheduling according to claim 2 makes the method for operation order item by item, it is characterized in that, after generating described operation item, also comprises the step of being checked:
According to default equipment standard term and grid switching operation term rules, spelt and syntax check; When the power supply point of receive factory, standing is transformed to new power point, result of calculation, equipment limit value, section limit value, stable operation condition according to described PAS, whether cause decompression, section overload, apparatus overload, stable action after checking operation, separated/remind side by side, open/cyclization of system reminds; Receive and intend in the associated PMS system of ticket people after interruption maintenance list information, overhauling single information according to this association transfers in the PMS system mode suggestion, system in the interruption maintenance list state of equipment is required to information, whether the state of checking power supply point conversion and the rear equipment of operation is consistent, and the prompting checked result; Receive and intend after the ticket people carries out operation order preview information, launch the station wiring diagram simulation and carry out each task that makes item by item operation order, and prompting operation normally reaching the specifying information that dangerous point is found in operation.
4. generation scheduling according to claim 1 makes the method for operation order item by item, it is characterized in that, described read the EMS data after, also comprise step: if described device location state and equipment real-time status are inconsistent, the inconsistent information of prompt facility location status.
5. according to claim 1-4 any one, the method that makes item by item operation order is dispatched in described generation, it is characterized in that, after generating described operation item, also comprises the step of being examined:
Receive guardian each operation item confirmation and msu message, complete first trial according to this confirmation and msu message Auto-writing guardian name, the operation order that makes item by item generated is retained in audit, and points out responsible official on duty to examine the described operation order that makes item by item in the mode of voice or page top scroll bar;
Receive responsible official on duty each operation item confirmation and msu message, according to this confirmation and msu message Auto-writing responsible official's name on duty automatic generating run ticket numbering, complete reexamination and will be described to make item by item operation order automatically go to pending, and point out the described operation order that makes item by item of plan ticket people to examine and pass through in the mode of voice or page top scroll bar;
When receive described guardian or responsible official on duty audit not by the time when rollback that sends and rollback suggestion information, according to this rollback and rollback suggestion information rollback give intend the ticket people and will describedly make item by item operation order go to pending, then with the mode of voice or page top scroll bar point out plan ticket people this make item by item operation order rollback;
When receiving personnel on duty, hand over to the next shift after confirmation, after succeeding according to this confirmation mechanical check, whether three careful personnel are all identical, will wait if not to issue with executory to make item by item operation order go to pending, and in the mode of voice or page top scroll bar, point out dispatching and monitoring person to have new to make item by item operation order pending.
6. generation scheduling according to claim 5 makes the method for operation order item by item, it is characterized in that, after being examined, also comprises and carries out the described step that makes item by item operation order:
After receiving the operator and carrying out the confirmation information that power transmission makes first operation item of operation order item by item, read in described EMS data according to this confirmation the nameplate information on operating equipment for the treatment of, if also have the nameplate of not removing, pointed out;
After receiving the operator and carrying out the confirmation information of an operation item, read the device location status information in described EMS data and carry out this operation item preview according to this confirmation, if the preview result is the power supply point that receives factory, stand while being transformed to new power point, carry out trend calculating according to PAS trend computing function in this call by result EMS system, if calculation of tidal current shows while there will be apparatus overload, section overload dangerous point, points out and the interrupt operation project implementation;
After receiving the operator and carrying out first operation item confirmation, fill in the people's name of issuing an order, issue an order the time according to this confirmation, the confession operator that made us who screens corresponding unit according to the plant stand title confirms and automatically goes in execution by the described operation order that makes item by item; And be finished after information receiving operation item, fill in deadline, reporter's name and automatically calculate this action-item execution time according to this information, if this action-item time is overtime, carry out filling at remarks column the prompting of overtime reason;
After receiving power failure and making item by item the complete confirmation of the operation order all operations project implementation, read in described EMS data according to this confirmation the nameplate information on operating equipment for the treatment of, if do not hang nameplate, hung the prompting of nameplate;
When receiving the described complete confirmation of the equal executed of operation order all operations project that makes item by item, according to this confirmation, in the described operation order nominal value that makes item by item, automatically add a cover the executed seal; When receiving an operation item, this does not carry out confirmation, automatically adds a cover this according to this confirmation at this action-item and does not carry out seal and carry out filling at remarks column the prompting that this does not carry out reason; When receiving the pending operation order calcellation confirmation that makes item by item, according to this confirmation, at this, make item by item the operation order nominal value automatically add a cover the calcellation seal, and make item by item operation order go to filing by pending this;
When receive add a cover executed seal information make operation order item by item the time, read in the PMS system interruption maintenance list and fill in and stop electric power feeding time and the people that issues an order, made us personnel's name according to this information;
When receive add a cover executed seal information make item by item that operation order and generating run mode change, circuit is while stopping power transmission registration confirmed information, read the method for operation in the DMIS system according to this information and change record, circuit and stop power transmission and record and fill in and stop electric power feeding time and the people that issues an order, the original state of being made us name and device name, equipment and dbjective state, make the operation order number information item by item.
7. generation according to claim 6 scheduling makes the method for operation order item by item, it is characterized in that, carry out described make operation order item by item after, also comprise and accept the step that inquiry and data derive:
When receiving the combination condition Query Information, make item by item the quantity of operation order according to this Query Information statistical dependence; Described combination condition comprises: time period constraint, equipment, numbering, type, task, executed, calcellation, personnel;
When receive each monthly in, while making item by item operation order stop power transmission running time and average operating time Query Information in year, according to this Query Information, add up each running time that makes item by item operation order and average operating time and show overtime operation item and reason;
When receiving overtime operation item Query Information, according to this Query Information statistics, make item by item overtime operation item, the place of operation order make item by item operation order task, numbering, time and overtime reason;
When receiving the statistical information derived information, automatically derive the statistical information of word or excel form according to this derived information; When receiving statistical information and export as chart-information, according to the tabular statistical information of this derived information derived graph.
8. one kind generates the system that scheduling makes operation order item by item, it is characterized in that, comprising:
Data read module, for reading the EMS data, described EMS data comprise: electric network current diagram is meritorious, idle, the device location state;
Judge module, whether consistent with the equipment real-time status for judging described device location state;
The task choosing generation module, in the situation that judgment result is that of described judge module be, according to intending the ticket people to wanting the operation generation task choosing of operating equipment;
The operation item generation module, for according to intending, the operation of ticket people to the power transformation station equipment generates and the operation item of this device location opposite states location status, and when relating to the power system operating mode conversion, meritorious, idle according to described electric network current diagram, the device location state is differentiated factory, the power supply source points of standing, when the power supply point of differentiating the rear described factory of operation, stand is transformed to new power point, generate the secondary operation project that needs change; Described secondary operation project comprises: reclosing, backup auto-activating device.
9. generation scheduling according to claim 8 makes the system of operation order item by item, it is characterized in that, also comprises following information in described EMS data: equipment limit value, section limit value, stable operation condition, PAS trend computing function.
10. generation scheduling according to claim 9 makes the system of operation order item by item, it is characterized in that, also comprises the check module, for after generating described operation item, carries out following check:
According to default equipment standard term and grid switching operation term rules, spelt and syntax check; When the power supply point of receive factory, standing is transformed to new power point, result of calculation, equipment limit value, section limit value, stable operation condition according to described PAS, whether cause decompression, section overload, apparatus overload, stable action after checking operation, separated/remind side by side, open/cyclization of system reminds; Receive and intend in the associated PMS system of ticket people after interruption maintenance list information, overhauling single information according to this association transfers in the PMS system mode suggestion, system in the interruption maintenance list state of equipment is required to information, whether the state of checking power supply point conversion and the rear equipment of operation is consistent, and the prompting checked result; Receive and intend after the ticket people carries out operation order preview information, launch the station wiring diagram simulation and carry out each task that makes item by item operation order, and prompting operation normally reaching the specifying information that dangerous point is found in operation.
CN201310393050.6A 2013-09-02 2013-09-02 Generate the method and system that scheduling makes operation order item by item Active CN103488138B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310393050.6A CN103488138B (en) 2013-09-02 2013-09-02 Generate the method and system that scheduling makes operation order item by item

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310393050.6A CN103488138B (en) 2013-09-02 2013-09-02 Generate the method and system that scheduling makes operation order item by item

Publications (2)

Publication Number Publication Date
CN103488138A true CN103488138A (en) 2014-01-01
CN103488138B CN103488138B (en) 2016-06-08

Family

ID=49828450

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310393050.6A Active CN103488138B (en) 2013-09-02 2013-09-02 Generate the method and system that scheduling makes operation order item by item

Country Status (1)

Country Link
CN (1) CN103488138B (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104318491A (en) * 2014-10-27 2015-01-28 国家电网公司 Multi-source interconnected power distribution network overhaul anti-misoperation checking calculation method
CN104537452A (en) * 2014-11-04 2015-04-22 无锡鹰智科技有限公司 Electric power project computer management system
CN104571021A (en) * 2014-12-12 2015-04-29 国家电网公司 Equipment state operation executing method and device
CN106202541A (en) * 2016-07-26 2016-12-07 国网山东省电力公司东营供电公司 A kind of grid maintenance comprehensive inspection method of application ticket
CN108490894A (en) * 2018-02-27 2018-09-04 浙江浙能兰溪发电有限责任公司 The monitoring method of power plant valve and the monitoring device of power plant valve
CN108985468A (en) * 2018-06-27 2018-12-11 中国南方电网有限责任公司 A method of the single intelligence of association maintenance generates operation order
CN109193642A (en) * 2018-10-15 2019-01-11 深圳供电局有限公司 A kind of power scheduling network is issued an order method and system
CN109491355A (en) * 2017-09-13 2019-03-19 上海申通地铁集团有限公司 The monitoring method and its system of rail traffic grid switching operation
CN109613396A (en) * 2018-12-04 2019-04-12 国网浙江省电力有限公司衢州供电公司 A kind of reversed abnormal cause analysis method of user side trend
CN109636138A (en) * 2018-11-23 2019-04-16 北京南凯自动化系统工程有限公司 A kind of intelligent dispatching system for railway contact line power supply management
CN110782146A (en) * 2019-10-17 2020-02-11 广西电网有限责任公司贵港供电局 Scheduling operation task ticketing method and device based on power grid new equipment job scheduling
CN110829600A (en) * 2019-11-26 2020-02-21 广东电网有限责任公司 Anti-error control system and method based on automatic safety zone isolation interaction
CN110994796A (en) * 2019-12-06 2020-04-10 广东电网有限责任公司 Power dispatching operation panoramic visualization device and method
CN111048080A (en) * 2019-11-22 2020-04-21 广东电网有限责任公司 Intelligent dispatching command system based on voice recognition technology
CN111832972A (en) * 2020-07-27 2020-10-27 广东电网有限责任公司 Distribution network field electrical operation ticket machine generation method and computer storage medium
CN111967740A (en) * 2020-08-03 2020-11-20 国网天津市电力公司 Operation ticket safety checking system and method thereof
CN112365364A (en) * 2020-11-06 2021-02-12 云南电网有限责任公司昆明供电局 One-key ticket forming method and system for operation tickets of distribution network operation management system
CN113869871A (en) * 2021-10-11 2021-12-31 国网青海省电力公司信息通信公司 Method, device and equipment for auditing electric power ticket
CN114157020A (en) * 2021-10-27 2022-03-08 国家电网有限公司 System and method for realizing networked command issuing of scheduling instructions across security partitions

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004118684A (en) * 2002-09-27 2004-04-15 Hitachi Keiyo Engineerring & System Ltd Advance sale system of lunch
CN101183802A (en) * 2007-02-06 2008-05-21 深圳职业技术学院 Main-branch station mode based intelligent power system scheduling command ticket automatic generation system
JP2008269023A (en) * 2007-04-16 2008-11-06 Chugoku Electric Power Co Inc:The Operation target reporting system and operation target reporting server
CN102314643A (en) * 2011-08-15 2012-01-11 常州东瑞电力软件有限公司 Intelligent ticket proposing method of power network dispatch operation ticket system
CN102324788A (en) * 2011-09-19 2012-01-18 山西省电力公司大同供电分公司 Power dispatching integrated anti-misoperation simulation comprehensive management platform

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004118684A (en) * 2002-09-27 2004-04-15 Hitachi Keiyo Engineerring & System Ltd Advance sale system of lunch
CN101183802A (en) * 2007-02-06 2008-05-21 深圳职业技术学院 Main-branch station mode based intelligent power system scheduling command ticket automatic generation system
JP2008269023A (en) * 2007-04-16 2008-11-06 Chugoku Electric Power Co Inc:The Operation target reporting system and operation target reporting server
CN102314643A (en) * 2011-08-15 2012-01-11 常州东瑞电力软件有限公司 Intelligent ticket proposing method of power network dispatch operation ticket system
CN102324788A (en) * 2011-09-19 2012-01-18 山西省电力公司大同供电分公司 Power dispatching integrated anti-misoperation simulation comprehensive management platform

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张勇等: "基于EMS的智能调度操作票系统", 《现代电力》 *

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104318491B (en) * 2014-10-27 2017-05-10 国家电网公司 Multi-source interconnected power distribution network overhaul anti-misoperation checking calculation method
CN104318491A (en) * 2014-10-27 2015-01-28 国家电网公司 Multi-source interconnected power distribution network overhaul anti-misoperation checking calculation method
CN104537452A (en) * 2014-11-04 2015-04-22 无锡鹰智科技有限公司 Electric power project computer management system
CN104571021A (en) * 2014-12-12 2015-04-29 国家电网公司 Equipment state operation executing method and device
CN106202541A (en) * 2016-07-26 2016-12-07 国网山东省电力公司东营供电公司 A kind of grid maintenance comprehensive inspection method of application ticket
CN109491355A (en) * 2017-09-13 2019-03-19 上海申通地铁集团有限公司 The monitoring method and its system of rail traffic grid switching operation
CN108490894A (en) * 2018-02-27 2018-09-04 浙江浙能兰溪发电有限责任公司 The monitoring method of power plant valve and the monitoring device of power plant valve
CN108490894B (en) * 2018-02-27 2020-12-01 浙江浙能兰溪发电有限责任公司 Monitoring method and monitoring device for power plant valve
CN108985468A (en) * 2018-06-27 2018-12-11 中国南方电网有限责任公司 A method of the single intelligence of association maintenance generates operation order
CN109193642A (en) * 2018-10-15 2019-01-11 深圳供电局有限公司 A kind of power scheduling network is issued an order method and system
CN109636138A (en) * 2018-11-23 2019-04-16 北京南凯自动化系统工程有限公司 A kind of intelligent dispatching system for railway contact line power supply management
CN109613396B (en) * 2018-12-04 2020-10-30 国网浙江省电力有限公司衢州供电公司 Method for studying and judging reasons of reverse abnormal user-side power flow
CN109613396A (en) * 2018-12-04 2019-04-12 国网浙江省电力有限公司衢州供电公司 A kind of reversed abnormal cause analysis method of user side trend
CN110782146A (en) * 2019-10-17 2020-02-11 广西电网有限责任公司贵港供电局 Scheduling operation task ticketing method and device based on power grid new equipment job scheduling
CN111048080A (en) * 2019-11-22 2020-04-21 广东电网有限责任公司 Intelligent dispatching command system based on voice recognition technology
CN110829600A (en) * 2019-11-26 2020-02-21 广东电网有限责任公司 Anti-error control system and method based on automatic safety zone isolation interaction
CN110829600B (en) * 2019-11-26 2023-10-20 广东电网有限责任公司 Error control system and method based on automatic safety zone isolation interaction
CN110994796B (en) * 2019-12-06 2021-06-08 广东电网有限责任公司 Power dispatching operation panoramic visualization device and method
CN110994796A (en) * 2019-12-06 2020-04-10 广东电网有限责任公司 Power dispatching operation panoramic visualization device and method
CN111832972A (en) * 2020-07-27 2020-10-27 广东电网有限责任公司 Distribution network field electrical operation ticket machine generation method and computer storage medium
CN111967740A (en) * 2020-08-03 2020-11-20 国网天津市电力公司 Operation ticket safety checking system and method thereof
CN111967740B (en) * 2020-08-03 2024-02-20 国网天津市电力公司 Operation ticket safety checking system and method thereof
CN112365364A (en) * 2020-11-06 2021-02-12 云南电网有限责任公司昆明供电局 One-key ticket forming method and system for operation tickets of distribution network operation management system
CN113869871A (en) * 2021-10-11 2021-12-31 国网青海省电力公司信息通信公司 Method, device and equipment for auditing electric power ticket
CN113869871B (en) * 2021-10-11 2024-04-19 国网青海省电力公司信息通信公司 Method, device and equipment for checking power ticket
CN114157020A (en) * 2021-10-27 2022-03-08 国家电网有限公司 System and method for realizing networked command issuing of scheduling instructions across security partitions
CN114157020B (en) * 2021-10-27 2024-03-29 国家电网有限公司 System and method for realizing dispatching instruction networking order-issuing across secure partition

Also Published As

Publication number Publication date
CN103488138B (en) 2016-06-08

Similar Documents

Publication Publication Date Title
CN103488138A (en) Method and system for generating scheduling item operation order
CN107846011B (en) Power distribution network fault recovery method based on main and distribution network cooperative control
WO2017166735A1 (en) Power-grid self-healing system and self-healing logic thereof in 110kv chain power-supply mode
CN104678960B (en) It is a kind of based on scene it is anti-error and intend ticket training off-line type Dispatching system and method
CN103065215B (en) Power grid dispatching method
CN105427039A (en) Efficient processing method of distribution network repair work orders based on responsibility areas
CN101673965A (en) Automatic switching control method for wide-area emergency power source of electric power system
CN106651643A (en) Power security management and control method for whole process based on distribution and adjustment
CN104463696A (en) Power grid operating risk recognition and prevention method and system
CN108110893A (en) A kind of electric network fault grade automatic identifying method of transmission & distribution collaboration
CN103618297A (en) High-efficiency and high-reliability fault processing method aiming at complex power distribution network
CN103632311A (en) Fault examining system and method for power grid operation
CN104331777A (en) Error-preventing management system for county level power grid dispatching operation
CN106651198A (en) Power grid accident auxiliary processing method and system
CN107181321B (en) Method for realizing rapid load pulling based on power grid topological structure
CN101799897A (en) Intelligent figure error resistant operation ticket management system
CN109948897B (en) Automatic generation system and method for main transformer overload 10kV line-to-power supply scheme
CN105590164A (en) Power failure incident automatic integration-based analysis device for analyzing reliability of power transmission and transformation system
CN103065512B (en) Metro operation cooperation center (OCC) power dispatching simulating training system
CN105373893A (en) Scheduling automation system model definition assistant decision-making and risk assessment method
CN206211518U (en) A kind of photovoltaic case becomes uses comprehensive monitoring protection system
CN101847865A (en) Electric network relay protection and fault analysis system
CN103647279A (en) Plant wiring information based anticipatory fault set generation method
CN105224729A (en) Based on the information access method of inspection of substation secondary device panoramic information simulation
CN201773298U (en) Electric energy monitoring system for container loading and unloading machines

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: INFORMATION AND COMMUNICATION TECHNOLOGY BRANCH, N

Effective date: 20140508

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Luo Guoming

Inventor after: Wu Haijiang

Inventor after: Zhou Junyu

Inventor after: Hao Yufeng

Inventor after: He Xiqi

Inventor after: Chen Xiaotong

Inventor after: Hu Chao

Inventor after: Chen Zhangguo

Inventor after: Zhou Bo

Inventor before: Luo Guoming

Inventor before: Wu Haijiang

Inventor before: Zhou Junyu

Inventor before: Hao Yufeng

Inventor before: He Xiqi

Inventor before: Chen Xiaotong

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LUO GUOMING WU HAIJIANG ZHOU JUNYU HAO YUFENG HE XIQI CHEN XIAOTONG TO: LUO GUOMING WU HAIJIANG ZHOU JUNYU HAO YUFENG HE XIQI CHEN XIAOTONG HU CHAO CHEN ZHANGGUO ZHOU BO

TA01 Transfer of patent application right

Effective date of registration: 20140508

Address after: 528000 Fenjiang South Road, Chancheng District, Guangdong, No. 1, No.

Applicant after: Foshan Power Supply Bureau, Guangdong Power Grid Corporation

Applicant after: INFORMATION COMMUNICATION TECHNOLOGY BRANCH, NANJING NARI GROUP CORPORATION

Address before: 528000 Fenjiang South Road, Chancheng District, Guangdong, No. 1, No.

Applicant before: Foshan Power Supply Bureau, Guangdong Power Grid Corporation

C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 528011 No. 1 South Fenjiang Road, Chancheng District, Guangdong, Foshan

Co-patentee after: INFORMATION COMMUNICATION TECHNOLOGY BRANCH, NANJING NARI GROUP CORPORATION

Patentee after: FOSHAN POWER SUPPLY BUREAU OF GUANGDONG POWER GRID CORPORATION

Address before: 528000 Fenjiang South Road, Chancheng District, Guangdong, No. 1, No.

Co-patentee before: INFORMATION COMMUNICATION TECHNOLOGY BRANCH, NANJING NARI GROUP CORPORATION

Patentee before: Foshan Power Supply Bureau, Guangdong Power Grid Corporation