Summary of the invention
Based on this, be necessary problem long for the above-mentioned plan ticket time, that do not save, a kind of scheduling that generates is providedMake item by item the method and system of operation order.
For achieving the above object, the present invention adopts following technical scheme:
Generate the method that scheduling makes operation order item by item, comprise the following steps:
Read EMS data, described EMS data comprise following information: electric network current diagram is meritorious, idle,Device location state, equipment limit value, section limit value, stable operation condition, PAS trend computing function;
Judge that whether described device location state is consistent with equipment real-time status;
If so, according to intending ticket people, the operation of wanting operating equipment is generated to task choosing;
Operation generation according to plan ticket people to power transformation station equipment and this device location opposite states location statusOperation item, and in the time relating to power system operating mode conversion, meritorious, idle according to described electric network current diagram,The power supply source points that device location state is differentiated factory, stood, when the power supply point of differentiating described factory after operation, standingWhile being transformed to new power point, generate the secondary operation project that needs change; Described secondary operation project comprises:Reclosing, backup auto-activating device;
After generating described operation item, also comprise the step of checking:
Spell and syntax check according to default equipment standard term and grid switching operation term rules; ReceiveWhile being transformed to new power point to factory, the power supply point of standing, result, the equipment limit calculated according to described PAS trendWhether value, section limit value, stable operation condition, cause decompression, section overload, equipment mistake after inspection operationCarry, stable action, separate/remind side by side, open/cyclization of system reminds; Receive and intend the associated PMS of ticket peopleIn system, after interruption maintenance list information, transfer interruption maintenance list in PMS system according to this interruption maintenance list informationMiddle mode suggestion, system require information to the state of equipment, check the shape of power supply point conversion and the rear equipment of operationWhether state is consistent, and points out checked result; Receive plan ticket people and carry out after operation order preview information, launch factoryEach task that makes item by item operation order is carried out in the wiring diagram of standing simulation, and prompting operation is normal and danger is found in operationThe specifying information of danger point.
Generate the system that scheduling makes operation order item by item, comprising:
Data read module, for reading EMS data, described EMS data comprise: electric network current diagramMeritorious, idle, device location state, equipment limit value, section limit value, stable operation condition, PAS trendComputing function;
Judge module, whether consistent with equipment real-time status for judging described device location state;
Task choosing generation module, in the judged result of described judge module be, according toIntend ticket people the operation of wanting operating equipment is generated to task choosing;
Operation item generation module, for generating and this equipment the operation of power transformation station equipment according to intending ticket peopleThe operation item of location status opposite location state, and in the time relating to power system operating mode conversion, according to describedThe power supply source points that electric network current diagram is meritorious, idle, device location state is differentiated factory, stand, when differentiating behaviourWhen the power supply point of do rear described factory, standing is transformed to new power point, generate the secondary operation project that needs change;Described secondary operation project comprises: reclosing, backup auto-activating device;
Also comprise check module, for after generating described operation item, carry out following check:
Spell and syntax check according to default equipment standard term and grid switching operation term rules; ReceiveWhile being transformed to new power point to factory, the power supply point of standing, result, the equipment limit calculated according to described PAS trendWhether value, section limit value, stable operation condition, cause decompression, section overload, equipment mistake after inspection operationCarry, stable action, separate/remind side by side, open/cyclization of system reminds; Receive and intend the associated PMS of ticket peopleIn system, after interruption maintenance list information, transfer interruption maintenance list in PMS system according to this interruption maintenance list informationMiddle mode suggestion, system require information to the state of equipment, check the shape of power supply point conversion and the rear equipment of operationWhether state is consistent, and points out checked result; Receive plan ticket people and carry out after operation order preview information, launch factoryEach task that makes item by item operation order is carried out in the wiring diagram of standing simulation, and prompting operation is normal and danger is found in operationThe specifying information of danger point.
Can be found out by above scheme, a kind of method and system that generate scheduling and make item by item operation order of the present invention,The automatic inspection that has realized device location is checked, the automatic generation of the intelligent selection of operation task, operation itemAnd can automatically generate the secondary operation such as reclosing, the backup auto-activating device project that needs change. With traditionGeneration scheduling make item by item the method for operation order compare, use after this programme, what ground was adjusted makes operation order item by itemPlan ticket, audit time can be by within average 15 minutes, foreshortening in the past average 7 minutes now, and the rate and just of drawing a billReally rate all can reach 100%, thus greatly alleviated dispatching and monitoring personnel the intensity of making out an invoice, improved planTicket speed and quality, improved dispatching and monitoring personnel's operating efficiency greatly; Also phase of circuit power off time simultaneouslyThe shortening of answering, has reduced operation of power networks risk greatly, has shortened the power off time of power consumer, has improvedPower supply reliability, for the better service-user of power system, service society have been contributed scheduling people's a strength;In addition, the present invention has also realized with no paper operation, has saved a large amount of paper resources, active response national jointThe call that can reduce discharging.
Detailed description of the invention
Below in conjunction with accompanying drawing and specific embodiment, the solution of the present invention is further described.
Shown in Figure 1, a kind of method that generates scheduling and make item by item operation order, comprises the following steps:
Step S101, reads EMS (EnergyManagementSystem, EMS) data,Described EMS data comprise following information: electric network current diagram is meritorious, idle, device location state etc., soAfter enter step S102.
Step S102, judges that whether described device location state is consistent with equipment real-time status; If enterStep S103.
As a good embodiment, after step S101 reads EMS data, can also comprise asLower step: if described device location state and equipment real-time status are inconsistent, prompt facility location status is notConsistent information (need to carry out state renewal or state is manually set).
Step S103, if described device location state is consistent with equipment real-time status, according to intending ticket people to wantingThe operation (as: clicking operation) of operating equipment generates task choosing, as " general × × circuit is by × × stateTransfer to × × state ", " mode is changed " etc. Wherein × × circuit is electric pressure+device name, equipmentOriginal state is defaulted as current state, and dbjective state can be selected all the other states except original state. CompleteAfter enter step S104.
Step S104, according to intending ticket people, to power transformation station equipment, (switch, disconnecting link, grounding switch, neutral point connectGround disconnecting link etc.) operation generate and the operation item of this device location opposite states location status, and relating to electricityWhen network operation mode is changed, according to described electric network current diagram meritorious (P), idle (Q), device location stateThe power supply source points of differentiate factory, standing, when the power supply point of differentiating described factory after operation, stand is transformed to new powerWhen point, generate the secondary operation project that needs change; Described secondary operation project comprises: reclosing, certainly standbyThrow device etc., and the action statement now automatically generating is as follows: " input × × line × × switch × × overlapLock ", " input × × line × × switch with × × line × × switch prepared auto restart each other ".
The detailed process of above-mentioned generating run project can be as follows: transfer to after empty charging at circuit, read EMSCircuit both sides device location state in data, differentiate circuit and in the time of empty charged state, point out: " × × circuit isIn empty charged state, whether automatically generating run ticket? ", and according to " deenergization side switch---pull open loadSide tool lock---pulls open mains side disconnecting link---and closes line side grounding switch " order generating run ticket automatically, simultaneouslyBe normal condition before having a power failure by the device location state memorization under this sky charged state; In the time that circuit power transmission operates,Point out: " whether × × circuit, at inspecting state, generates empty charging operations ticket automatically? ", and according to " pulling openLine side grounding switch---power turn-on side tool lock---load side of closing disconnecting link---power turn-on side switch " sequentiallyAutomatically generating run ticket, reverts to by device location state the front normal condition that has a power failure.
Intend, after ticket, can relevant operation item being increased, delete, inserts, copies, moves, being closedThe editing such as order and fractionation; After making item by item operation order editor, intend when receiving " the guarantor that ticket people sendsDeposit " after information, will make item by item operation order be kept at according to this " preservation " information pending; In addition when receivingTo intending, after " turning guardian's examination & verification " information of ticket people transmission, can turning msu message Auto-writing behaviour according to thisMake people's name and will make item by item operation order automatically go in examination & verification, can roll with voice or page top simultaneouslyThe mode of bar is pointed out guardian to audit and is made item by item operation order.
As a good embodiment, in described EMS data, can also comprise following information: equipment limit value,Section limit value, stable operation condition, PAS trend computing function etc.
In addition, tradition generates in the method that makes item by item operation order only has five basic anti-verifications, as oneGood embodiment, in order to ensure the security of electric grid operating, the present invention after generating described operation item,Can also comprise the step of checking as follows:
Spell and syntax check according to default equipment standard term and grid switching operation term rules; ReceiveWhile being transformed to new power point to factory, the power supply point of standing, result, the equipment limit calculated according to described PAS trendWhether value, section limit value, stable operation condition, cause decompression, section overload, equipment mistake after inspection operationCarry, stable action, separate/remind side by side (the non-synchronization paralleling of anti-locking system), open/cyclization of system and remind;Receive and intend after the middle interruption maintenance list information of the associated PMS of ticket people (production safety management information system), according toThis interruption maintenance list information is transferred in PMS system mode suggestion, the state of system to equipment in interruption maintenance listRequirement information, whether the state of checking power supply point conversion and the rear equipment of operation is consistent, and points out checked result;Receive plan ticket people and carry out after operation order preview information, launch station wiring diagram simulation execution and make item by item operation orderEach task, and prompting operation is normal and the specifying information of dangerous spot is found in operation.
As a good embodiment, after generating described operation item, can also comprise as follows and carrying outThe step of examination & verification:
Receive guardian each operation item confirmation and msu message, according to this confirmation and examination & verificationInformation Auto-writing guardian name completes first trial, the operation order that makes item by item generating is retained in examination & verification, andPoint out director on duty to make item by item operation order described in auditing in the mode of voice or page top scroll bar;
Receive director on duty each operation item confirmation and msu message, according to this confirmation andMsu message Auto-writing director's name on duty automatically generating run ticket numbering, complete review and will described inMake item by item operation order automatically go to pending, and point out and intend ticket people in the mode of voice or page top scroll barThe described operation order that makes item by item is audited and is passed through;
When receive described guardian or director on duty examination & verification not by time the rollback that sends and rollback anticipateWhile seeing information, give plan ticket people and the described operation order that makes is item by item turned according to this rollback and rollback suggestion information rollbackTo pending, then point out and intend ticket people this has made operation order item by item in the mode of voice or page top scroll barRollback;
Hand over to the next shift after confirmation when receiving personnel on duty, after succeeding according to this confirmation automatic checking, three examineWhether personnel are all identical, will wait if not to issue with executory to make item by item operation order go to pending, andPointing out dispatching and monitoring person to have in the mode of voice or page top scroll bar new makes operation order pending item by item.
Tradition examination & verification makes operation order to be item by item complete manual examination and verification and to turn examination & verification, intends ticket people and intends filling in behaviour after ticketMake ticket numbering and operator's name and deliver guardian's examination & verification, after guardian's examination & verification, fill in guardian's name and sendHand over director's examination & verification on duty, director on duty audits and fills in name and returns to intending ticket people, pass through as do not audited,After relieving, again three examine, operation order double sign (two and above people (dispatcher easily occurs in review processOr monitor) while intending ticket, can there is double sign simultaneously) and the problem of inefficiency; Real in the present inventionShow the e-cooperative work in examination & verification twist process, the operation order numbering in operation order nominal value, operator, prisonProtect people, Auto-writing realized in director's name on duty, after director on duty (people) examination & verification, generate and compileNumber, avoid operation order double sign problem, ensure the uniqueness of numbering, improve review efficiency, and with languageThe mode of sound or page top scroll bar is pointed out hommization more.
In addition, as a good embodiment, after auditing, can also comprise following execution instituteState the step that makes item by item operation order:
Carry out after the confirmation that power transmission makes operation order Section 1 operation item item by item root when receiving operatorRead in described EMS data and treat the nameplate information on operating equipment according to this confirmation, do not remove if do not also haveNameplate, point out (dismounting nameplate);
Carry out after the confirmation of an operation item when receiving operator, read institute according to this confirmationState the device location status information in EMS data and carry out this operation item preview, if preview result is for connecingReceive when factory, the power supply point of standing are transformed to new power point, according to PAS trend in this call by result EMS systemComputing function is carried out trend calculating, there will be apparatus overload, the danger of section overload if calculation of tidal current showsWhen point, point out and the interrupt operation project implementation;
Carry out after Section 1 operation item confirmation when receiving operator, fill in and send out according to this confirmationMake us name (being operator's name), issue an order the time (real-time time that is system), sieve according to plant stand titleThe confession operator that made us of the phase selection unit of answering confirms and the described operation order that makes is item by item gone in execution automatically; AndBe finished after information receiving operation item, according to this information fill in the deadline (be system in real timeTime), reporter's name (be defaulted as and made us name) automatically calculating this operation item time of implementation, ifThis operation item time of implementation is overtime, carries out filling at remarks column the prompting of overtime reason;
Make item by item after the complete confirmation of the operation order all operations project implementation when receiving power failure, true according to thisRecognize information and read in described EMS data and treat the nameplate information on operating equipment, if do not hang nameplate,Hang the prompting of nameplate;
Described in receiving, make item by item the complete confirmation of the equal executed of operation order all operations project, according to thisConfirmation is added a cover executed seal automatically in the described operation order nominal value that makes item by item; When receiving an action-itemThis does not carry out confirmation order, automatically adds a cover this do not carry out according to this confirmation at this operation itemSeal also carries out filling in this and not carrying out at remarks column the prompting of reason; When receiving the pending behaviour of order item by itemMake ticket calcellation confirmation, make item by item operation order nominal value automatically add a cover calcellation seal according to this confirmation at this,And make item by item operation order go to filing by pending this;
When receive add a cover executed seal information make operation order item by item time, read PMS system according to this informationInterruption maintenance list fill in and stop electric power feeding time and the people that issues an order, made us personnel's name in system;
When receive add a cover executed seal information make item by item that operation order and generating run mode change, circuitWhile stopping power transmission registration confirmed information, read operation side in DMIS (scheduling management information system) according to this informationFormula changes record, circuit and stops power transmission and record and fill in and stop electric power feeding time and the people that issues an order, made us name and equipmentThe original state of title, equipment and dbjective state, make the information such as operation order numbering item by item.
Tradition make item by item the execution of operation order want manual examination and verification fill in nominal value content, manually arrange nameplate information,Manually impress chapter, manually fill in PMS in interruption maintenance list content, DMIS the method for operation change record,Circuit stops power transmission record. Make item by item operation order safer, quick and carry out in the present invention, Auto-writing ticketFace content, prompting arrange nameplate lock operation, automatic cover seal, intelligence is filled in interruption maintenance in PMSIn single content, DMIS, the method for operation changes record, circuit stops power transmission record, and the present invention adds in operation in additionEnter Real-time Power Flow and calculated locking, made operation safer.
As a good embodiment, after making operation order item by item described in carrying out, can also comprise as followsAccept the step that inquiry and data derive:
In the time receiving combination condition Query Information, make item by item operation order according to this Query Information statistical correlationQuantity; Described combination condition can comprise: time period constraint, equipment, numbering, type, task, holdRow, calcellation, personnel etc.;
When receive each monthly in, while making item by item operation order stop power transmission operating time and average operation in yearBetween when Query Information, according to each operating time and the average operation that makes item by item operation order of this Query Information statisticsTime also shows overtime operation item and reason;
In the time receiving overtime operation item Query Information, make item by item operation order according to this Query Information statisticsOvertime operation item, place make operation order task, numbering, time and overtime reason item by item, are power equipmentDefect statistics provides data foundation;
In the time receiving statistical information derived information, automatically derive word or excel lattice according to this derived informationThe statistical information of formula; In the time receiving statistical information and export as chart-information, according to this derived information derived graphTabular statistical information.
Tradition makes the statistics of operation order want manual sorting, sequence, bookbinding item by item, and inquiry will be carried out page by page, workMake inefficiency; And query statistic makes operation order all realize e-cooperative work item by item in the present invention, more acceleratePrompt, convenient, accurately, and supported data export function, be the data information collection work bar of providing conveniencePart. Simultaneously the present invention has realized with no paper operation, has saved a large amount of paper resources, makes to make item by item operation orderAdd up environmental protection and saving more.
The present invention has called EMS, production safety management information system and scheduling management information systemData resource, and realized direct access PMS Unit account of plant, EMS topological data, call EMS trendComputing function is calculated, and has realized resource-sharing. The present invention maximizes realization and makes item by item the intelligence of operation orderGenerate, by the rear relevant nominal value of automatic-prompting, examination & verification of the automatic generation of operation item, relevant secondary deviceThe Auto-writing of content automatic flow and to the statistical analysis disaggregatedly of archive operation ticket, solved traditionMake item by item a difficult problem for operation ticket system inefficiency. And increase associated maintenance Shen on basic five anti-basesPlease singly lose load prompting, For Solutions of Systems/remind side by side (the non-synchronization paralleling of anti-locking system), open/cyclization of system to carryWake up, the measure such as trend verification, increased the security of electric grid operating.
The solution of the present invention can adapt to the diversity of electric grid operating task, complexity and the operation of electric network compositionThe flexibility of mode, by adopting this programme, can make major network dispatcher concentrate more energy to be absorbed inResearch power grid security, has important meaning to the operating efficiency that improves power network safety operation level and dispatcherJustice.
A kind ofly generate scheduling and make item by item the method for operation order corresponding with above-mentioned, it is a kind of raw that the present invention also providesBecome scheduling to make item by item the system of operation order, as shown in Figure 2, comprising:
Data read module 101, for reading EMS data, described EMS data comprise: electric network swimScheme meritorious, idle, device location state;
Judge module 102, whether consistent with equipment real-time status for judging described device location state;
Task choosing generation module 103, in the judged result of described judge module be, rootAccording to intending ticket people, the operation of wanting operating equipment is generated to task choosing;
Operation item generation module 104, for generating and establish with this operation of power transformation station equipment according to intending ticket peopleThe operation item of standby location status opposite location state, and in the time relating to power system operating mode conversion, according to instituteState the power supply source points that electric network current diagram is meritorious, idle, device location state is differentiated factory, stand, work as differentiationWhen the rear described factory of operation, the power supply point of standing are transformed to new power point, generate the secondary operation project that needs change;Described secondary operation project comprises: reclosing, backup auto-activating device.
As a good embodiment, in described EMS data, can also comprise following information: equipment limit value,Section limit value, stable operation condition, PAS trend computing function.
As a good embodiment, generation scheduling of the present invention makes the system of operation order wrap item by itemDraw together check module, for after generating described operation item, carry out following check:
Spell and syntax check according to default equipment standard term and grid switching operation term rules; ReceiveWhile being transformed to new power point to factory, the power supply point of standing, result, the equipment limit calculated according to described PAS trendWhether value, section limit value, stable operation condition, cause decompression, section overload, equipment mistake after inspection operationCarry, stable action, separate/remind side by side, open/cyclization of system reminds; Receive and intend the associated PMS of ticket peopleIn system, after interruption maintenance list information, overhaul single information according to this association and transfer interruption maintenance list in PMS systemMiddle mode suggestion, system require information to the state of equipment, check the shape of power supply point conversion and the rear equipment of operationWhether state is consistent, and points out checked result; Receive plan ticket people and carry out after operation order preview information, launch factoryEach task that makes item by item operation order is carried out in the wiring diagram of standing simulation, and prompting operation is normal and danger is found in operationThe specifying information of danger point.
Above-mentionedly a kind ofly generate scheduling and make item by item other technical characterictic of system of operation order and of the present invention a kind of rawBecome scheduling to make item by item the method for operation order identical, it will not go into details herein.
Can find out by above scheme, of the present inventionly a kind ofly generate scheduling and make item by item the method for operation order and beSystem, the automatic inspection that has realized device location is checked, the intelligent selection of operation task, operation item automaticallyGenerate and can automatically generate the secondary operation such as reclosing, the backup auto-activating device project that need to change. WithTraditional generation scheduling makes the method for operation order compare item by item, uses after this programme, the behaviour of order item by item that ground is adjustedPlan ticket, the audit time of making ticket can foreshorten to average 7 minutes now for average 15 minutes by former, and the rate of drawing a billAll can reach 100% with accuracy, thereby greatly alleviate dispatching and monitoring personnel's the intensity of making out an invoice, raisingPlan ticket speed and quality, greatly improved dispatching and monitoring personnel's operating efficiency; Circuit power off time simultaneouslyAlso shortened accordingly, greatly reduced operation of power networks risk, shortened the power off time of power consumer, carriedHigh power supply reliability, for the better service-user of power system, service society have been contributed scheduling people's portionStrength; In addition, the present invention has also realized with no paper operation, has saved a large amount of paper resources, active responseThe call that national energy-saving reduces discharging.
The above embodiment has only expressed several embodiment of the present invention, and it describes comparatively concrete and detailed,But can not therefore be interpreted as the restriction to the scope of the claims of the present invention. It should be pointed out that for this areaThose of ordinary skill, without departing from the inventive concept of the premise, can also make some distortion andImprove, these all belong to protection scope of the present invention. Therefore, the protection domain of patent of the present invention should be with appendedClaim is as the criterion.