CN110080117A - Portable simplified concrete barrier formwork vehicle and preparation method thereof - Google Patents
Portable simplified concrete barrier formwork vehicle and preparation method thereof Download PDFInfo
- Publication number
- CN110080117A CN110080117A CN201910477803.9A CN201910477803A CN110080117A CN 110080117 A CN110080117 A CN 110080117A CN 201910477803 A CN201910477803 A CN 201910477803A CN 110080117 A CN110080117 A CN 110080117A
- Authority
- CN
- China
- Prior art keywords
- steel
- vehicle
- outside
- hook bar
- weight vehicle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The present invention provides a kind of portable simplified concrete barrier formwork vehicle and preparation method thereof, including suspension system, jacking system, weight vehicle, track and trailer, jacking system is using pulley, steel wire, hoist engine composition and is arranged on weight vehicle, and suspension system passes through on the outside I-steel being stuck on weight vehicle, can control the adjustable height of suspension system using jacking system.Trailer is then connected on weight vehicle, after the completion of a construction section, template vehicle quickly can be moved to next construction section using trailer.
Description
Technical field
The present invention relates to concrete guardrail field, in particular to a kind of portable simplified concrete barrier formwork vehicle and its system
Make method.
Background technique
Bridge is as the critically important functional structure object in town road, to improvement urban traffic environment, thrust zone
Economic development plays very important effect.
In order to improve the degree of safety of pedestrian and traffic, generally guardrail can be set up in bridge two sides.When hanging bridge
That is when the vertical range of bridge floor and ground is larger, how quickly, safe guardrail outboard template of setting up becomes a difficult point.Due to
The lateral surface of guardrail and bridge side are in same straight line, thus the template of guardrail needs to ride upon bridge side, general at present
Template hard point can be built in bridge side using rigid material, such as squeeze into anchor pole toward bridge side, support is then set up on anchor pole
Platform.It when bridge height is higher, needs to carry out enough safety measures, avoids construction fault that the personal safety of personnel is caused to produce
It is raw to threaten.Safety rope is generally bound on construction personnel at present, then from bridge side transfer, suspension construction, this method without
Method provides supporting point to construction personnel, causes construction efficiency lower.
Therefore, quasi- at present to seek a kind of portable simplified concrete barrier formwork vehicle that can provide Construction Support point and its system
Making method just seems particularly significant.
Summary of the invention
The purpose of the present invention is to provide a kind of portable simplified concrete barrier formwork vehicle for overcoming disadvantages described above and its
Production method.
In order to realize that any of the above goal of the invention, the present invention provide a kind of portable simplified concrete barrier formwork vehicle,
It is characterized in that it is made of suspension system, jacking system, weight vehicle, track (1) and trailer (2);The suspention system
System is made of hook bar (3), hound (4), Hanging Basket (5), connecting plate (26), and hook bar (3) one end is connected to lifting system
On the I-steel (6) of system, hook bar (3) top is equipped with pull rod (7), and hook bar (3) lower part is set there are two hound (4), diagonal brace
On (4) two sections of the bar connecting plates (26) being fixed in hook bar (3), the hound (4) in outside is used for the stabilization of Hanging Basket (5), interior
The hound (4) of side and the pull rod (7) on top are for being connected to jacking system, hook bar (3) bottom end and Hanging Basket (5) corresponding positions
The place of setting is equipped with the bolt hole (25) of same apertures, and Hanging Basket (5) is placed on the bottom end of hook bar (3), and passes through nut (28)
It is connected with bolt (15) with hook bar (3);The jacking system is by I-steel (6), buckle systems, steel cable (8), slides
What wheel (9) and hoist engine (10) formed, jacking system is connect by buckle systems with weight vehicle, pulley (9) and hoist engine
(10) it is arranged in weight vehicle;Buckle systems are made of roller bearing (11) and a pair of channel steel (13) with circular hole (12), rolling
(11) two sections of axis are equipped with small perforation (14), and roller bearing (11) can pass through the circular hole (12) in channel steel (13), by roller bearing (11)
Buckle systems are fixed on outside I-shaped on the I-steel (6) and weight vehicle of jacking system by small perforation (14) setting perforation fixture
It between steel (16), move up and down jacking system can along outside I-steel (16) on weight vehicle together with suspension system;It is described
Perforation fixture by axis with holes (31) and perforation kelly (32) form;The weight vehicle is by two Pin I-shaped steel frames
Connecting system and middle and upper part by bottom, longitudinally firm lever system is connected and to be formed, and idler wheel (17) are arranged in I-steel lower frame,
The height of I-steel (16) is higher than inside I-steel (18) and is put into highly on the outside of I-shaped steel frame, outside I-steel (16) and inside
I-steel (18) is connected and fixed by two lateral braces (27) and a bottom bar (29), and it is the bottom of by that bottom, which connects system,
Portion's vertical pole (19) and brace (20) composition, longitudinally firm lever system is by middle part vertical pole (21), vertical bar (22) and oblique for middle and upper part
Bar (20) composition;Mass (23) are placed in I-steel (18) side on the inside of weight vehicle, and drawbar (30) are arranged in weight vehicle side,
And it walks on the track (1) on box bridge (24) under the traction of trailer (2) along setting.
A kind of portable simplified concrete barrier formwork vehicle above-mentioned, it is characterised in that including following construction procedure:
(1), suspension system is prefabricated.Hook bar (3) are connected on I-steel (6), hook bar (3) one end is connected to lifting system
On the I-steel (6) of system, hook bar (3) top is equipped with pull rod (7), and hook bar (3) lower part is set there are two hound (4), diagonal brace
On (4) two sections of the bar connecting plates (26) being fixed in hook bar (3), the hound (4) in outside is used for the stabilization of Hanging Basket (5), interior
The hound (4) of side and the pull rod (7) on top are for being connected to jacking system, hook bar (3) bottom end and Hanging Basket (5) corresponding positions
The place of setting is equipped with the bolt hole (25) of same apertures, and Hanging Basket (5) is placed on the bottom end of hook bar (3), and passes through nut (28)
It is connected with bolt (15) with hook bar (3).
(2), fixed Hanging Basket (5).Hanging Basket (5) is fixed on hook bar (3) by nut (28) and bolt (15).
(3), weight vehicle spelling.Counterweight car bottom plate is welded using bottom vertical pole (19) and brace (20), then the bottom of at
Outside I-steel (16) and inside I-steel (18) is set up on plate, wherein the height of outside I-steel (16) is higher than inside I-steel
(18), then the two is fixed together by two lateral braces (27) and a bottom bar (29);And it is two neighboring outer
Side I-steel (16) and adjacent inside I-steel (18) use middle part vertical pole (21), vertical bar (22) and brace (20) splicing one
It rises.Then mass (23) are placed on weight vehicle;In addition need to weight vehicle bottom install wheel.
(4), jacking system is installed.Two fixed pulleys (9) are installed on I-steel (16) on the outside, and are pacified in weight vehicle bottom
A fixed pulley (9) is filled, and three pulleys (9) are linked together with steel cable (8), steel cable (8) one end is connected to hoist engine
(10) on, the other end is used to connect suspension system.
(5), suspension system and weight vehicle combination.It will be on the I-steel (6) of suspension system and weight vehicle using buckle systems
Outside I-steel (16) is combined.
(6) track (1) is laid with.It is laid with track (1) on floorings, weight vehicle is then dragged into upper rail using trailer (2).
(7) template is installed.It controls hoist engine (10), Hanging Basket (5) is transferred into suitable position, then construction personnel binds peace
Quan Sheng, and enter in Hanging Basket (5), with Hanging Basket (5) for fulcrum, carry out the guardrail template installation of box beam side wall.Template is pacified at one
After the completion of dress, starts trailer (2), weight vehicle is moved to next construction section.
Compared with the prior art, the present invention has the following beneficial effects:
1, the present invention can provide Hanging Basket as operation platform on the outside of box beam, make the template on the outside of bridge concrete guardrail
It can smoothly install.
2, the template vehicle that the present invention designs can control the adjustable height of Hanging Basket by control hoist engine.
Detailed description of the invention
Fig. 1 is the front view of the portable simplified concrete barrier formwork vehicle of an embodiment according to the present invention.
Fig. 2 is the front view based on the suspension system in Fig. 1.
Fig. 3 is the front view based on the Hanging Basket in Fig. 1.
Fig. 4 is the front view based on the weight vehicle in Fig. 1.
Fig. 5 is the structure chart based on the two neighboring outside I-steel connection in Fig. 4.
Fig. 6 is the structure chart based on the two neighboring inside I-steel connection in Fig. 4.
Fig. 7 is the top view of Fig. 4.
Fig. 8 is buckle structure schematic diagram (a: band circular hole channel steel;B: roller bearing is inserted into channel steel circular hole;C: it is fixed with perforation fixture;
D: perforation fixture schematic diagram).
Fig. 9 is portable simplified concrete barrier formwork vehicle top view.
Wherein: 1-track;2-trailers;3-hook bars;4-hounds;5-Hanging Baskets;6-I-steel;7-pull rods;
8-steel cables;9-pulleys;10-hoist engines;11-roller bearings;12-circular holes;13-channel steels;14-small perforation;15-bolts;
16-outside I-steel;17-idler wheels;18-inside I-steel;19-bottom vertical poles;20- brace;Vertical pole in the middle part of 21-;22- is perpendicular
Bar;23-mass;24-box bridges;25-bolts hole;26-connecting plates;27-lateral braces;28-nuts;29-bottoms
Portion's cross bar;30-drawbars;31-axis with holes;32-perforation kellies;33-guardrail outboard templates;34-guardrail inner side templates.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art's every other embodiment obtained belong to what the present invention protected
Range.
It will be understood by those skilled in the art that in exposure of the invention, term " longitudinal direction ", " transverse direction ", "upper",
The orientation of the instructions such as "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside" or position are closed
System is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of description of the present invention and simplification of the description, without referring to
Show or imply that signified device or element must have a particular orientation, be constructed and operated in a specific orientation, therefore above-mentioned art
Language is not considered as limiting the invention.
It is understood that term " one " is interpreted as " at least one " or " one or more ", i.e., in one embodiment,
The quantity of one element can be one, and in a further embodiment, the quantity of the element can be it is multiple, term " one " is no
It can be interpreted as the limitation to quantity.
The present invention provide a portable simplified concrete barrier formwork vehicle, including suspension system, jacking system, weight vehicle,
Track (1) and trailer (2);Suspension system includes hook bar (3) and the Hanging Basket for being placed in hook bar (3) bottom end inner side
(5);Jacking system includes I-steel (6), and steel cable (8) buckle systems, pulley (9) and hoist engine (10), I-steel (6) pass through
Buckle systems are connect with weight vehicle, and setting outside I-steel (16) on weight vehicle, pulley (9) is placed on outside I-steel (16),
Steel cable (8) one end is connected to I-steel (6), is pulled around pulley (9) by hoist engine (10);Weight vehicle is placed on track (1), quilt
Trailer (2) is dilatory.
Wherein hook bar (3) is designed as hook shape, and hook bar (3) one end is connected on the I-steel (6) of jacking system, hook
Type bar (3) is arranged perpendicular to I-steel (6).
The top of hook bar (3) top side is equipped with pull rod (7), and the other end of pull rod (7) is connected on I-steel (6).
At least two connecting plates (26) are provided on the inside of hook bar (3), specifically, in the top side and side of hook bar (3)
Connecting plate (26) are provided on side, in addition, being also equipped with connecting plate in the position of I-steel (6) on the inside of hook bar (3)
(26)。
At least two hounds (4) are equipped on the inside of hook bar (3), hound (4) both ends are fixed on the company in hook bar (3)
On fishplate bar (26), and three-legged structure is formed with hook bar (3);The hound (4) in outside is used for the stabilization of Hanging Basket (5), inside
Hound (4) and the pull rod (7) on top are connected on the I-steel on jacking system (6).
The bolt hole (25) of same apertures, Hanging Basket (5) are equipped at hook bar (3) bottom end and Hanging Basket (5) opposite position
It is placed on the bottom end of hook bar (3), and is connected by nut (28) and bolt (15) with hook bar (3).
As shown in figure 8, what buckle systems were made of roller bearing (11) and a pair of channel steel (13) with circular hole (12), channel steel
(13) it is placed on roller bearing (11).
The both ends of roller bearing (11) are equipped with small perforation (14), and roller bearing (11) passes through the circular hole (12) in channel steel (13), and channel steel
(13) it is placed on the inside of small perforation (14), by small perforation (14) the setting perforation fixture in roller bearing (11), perforation fixture is blocked
Buckle systems, are fixed on the I-shaped of jacking system by the I-steel (6) and the outside I-steel (16) on weight vehicle of jacking system
Between outside I-steel (16) on steel (6) and weight vehicle, and then make jacking system can be along on weight vehicle together with suspension system
Outside I-steel (16) move up and down.
Perforation fixture is made of axis with holes (31) and perforation kelly (32), and perforation kelly (32) is set in axis with holes
(31) on.Specifically, axis (31) with holes passes through small perforation (14), perforation kelly (32) is set in the two of axis with holes (31)
Side.
Weight vehicle is to connect system by bottom by least two I-shaped steel frames to connect with the firm lever system in middle and upper part longitudinal direction
It is formed, idler wheel (17) are arranged in I-steel lower frame, and I-shaped steel frame includes outside I-steel (16) and inside I-steel
(18), wherein outside I-steel (16) is placed in the two sides of inside I-steel (18), and the outside I-steel on I-shaped steel frame
(16) height is higher than being put into highly for inside I-steel (18).
Outside I-steel (16) and inside I-steel (18) pass through two lateral braces (27) and a bottom bar (29)
It is connected and fixed.Specifically, outside I-steel (16) and inside I-steel (18) are placed on bottom bar (29), lateral brace
(27) connection outside I-steel (16) and inside I-steel (18).
The bottom connection system of weight vehicle is welded using bottom vertical pole (19) and brace (20), and wherein brace (20) inclines
Tiltedly it is arranged in bottom vertical pole (19), outside I-steel (16) and inside I-steel (18) are erected on bottom plate.
Two neighboring outside I-steel (16) and adjacent inside I-steel (18) are using the firm lever system in middle and upper part longitudinal direction
It is stitched together, longitudinally firm lever system is made of middle part vertical pole (21), vertical bar (22) and brace (20) for middle and upper part.
Mass (23) are placed in I-steel (18) side on the inside of weight vehicle, and drawbar (30) are arranged in weight vehicle side, counterweight
Vehicle is simultaneously walked on the track (1) on box bridge (24) under the traction of trailer (2) along setting.
The portable simplified concrete barrier formwork vehicle the production method is as follows:
(1) suspension system is prefabricated:
Hook bar (3) are connected on I-steel (6), hook bar (3) one end is connected on the I-steel (6) of jacking system,
Hook bar (3) top is equipped with pull rod (7), and hook bar (3) lower part is set there are two hound (4), and (4) two sections of hound are fixed on hook
On connecting plate (26) in type bar (3), the hound (4) in outside is used for the stabilization of Hanging Basket (5), the hound (4) of inside and upper
The pull rod (7) in portion is equipped with same holes for being connected to jacking system, hook bar (3) bottom end and Hanging Basket (5) corresponding position
The bolt hole (25) of diameter, Hanging Basket (5) are placed on the bottom end of hook bar (3), and pass through nut (28) and bolt (15) and hook
Bar (3) is connected, as shown in Figure 2.
(2) fixed Hanging Basket (5):
Hanging Basket (5) is fixed on hook bar (3) by nut (28) and bolt (15).
(3) weight vehicle spelling: counterweight car bottom plate is welded using bottom vertical pole (19) and brace (20), then in bottom plate
I-steel (16) and inside I-steel (18) on the outside of upper erection, wherein the height of outside I-steel (16) is higher than inside I-steel
(18), then the two is fixed together by two lateral braces (27) and a bottom bar (29);And it is two neighboring outer
Side I-steel (16) and adjacent inside I-steel (18) use middle part vertical pole (21), vertical bar (22) and brace (20) splicing one
It rises.Then mass (23) are placed on weight vehicle;In addition need to weight vehicle bottom install wheel, as shown in Figure 3.
(4) jacking system is installed: being installed two fixed pulleys (9) on I-steel (16) on the outside, and is pacified in weight vehicle bottom
A fixed pulley (9) is filled, and three pulleys (9) are linked together with steel cable (8), steel cable (8) one end is connected to hoist engine
(10) on, the other end is used to connect suspension system, as shown in Figure 3.
(5) suspension system and weight vehicle combination: will be outer on the I-steel (6) of suspension system and weight vehicle using buckle systems
Side I-steel (16) is combined, as shown in Figure 1.
(6) track (1) is laid with: it is laid with track (1) on floorings, weight vehicle is then dragged into upper rail using trailer (2),
As shown in Figure 7.
(7) template is installed: Hanging Basket (5) is transferred to suitable position, then construction personnel binds peace by control hoist engine (10)
Quan Sheng, and enter in Hanging Basket (5), with Hanging Basket (5) for fulcrum, carry out the guardrail template installation of box beam side wall.Template is pacified at one
After the completion of dress, starts trailer (2), weight vehicle is moved to next construction section.
The present invention is not limited to above-mentioned preferred forms, anyone can show that other are various under the inspiration of the present invention
The product of form, however, make any variation in its shape or structure, it is all that there is skill identical or similar to the present application
Art scheme, is within the scope of the present invention.
Claims (7)
1. a kind of production method of portable simplified concrete barrier formwork vehicle, which comprises the following steps:
(1) suspension system is prefabricated:
Hook bar (3) are connected on I-steel (6), hook bar (3) one end is connected on I-steel (6), and hook bar (3) top is set
Have pull rod (7), hook bar (3) lower part is equipped at least two hounds (4), and (4) two sections of hound are fixed in hook bar (3)
On connecting plate (26), the hound (4) in outside is used for the stabilization of Hanging Basket (5), the hound (4) of inside and the pull rod (7) on top
It is connected on I-steel (6), Hanging Basket (5) is placed and is fixed on the bottom end of hook bar (3);
(2) fixed Hanging Basket (5):
Hanging Basket (5) is fixed on hook bar (3) by nut (28) and bolt (15);
(3) weight vehicle spelling:
Counterweight car bottom plate is welded using bottom vertical pole (19) and brace (20), set up on bottom plate on the outside of I-steel (16) and
Inside I-steel (18), wherein the height of outside I-steel (16) is higher than inside I-steel (18), it is then oblique by two transverse directions
The two is fixed together by bar (27) and a bottom bar (29);Two neighboring outside I-steel (16) and adjacent inside work
Word steel (18) uses middle part vertical pole (21), vertical bar (22) and brace (20) to be stitched together.
(4) jacking system is installed:
At least two fixed pulleys (9) are installed on I-steel (16) on the outside, at least one fixed pulley is installed in weight vehicle bottom
(9), it and with steel cable (8) by pulley (9) links together, steel cable (8) one end is connected on hoist engine (10), and the other end is used to connect
Connect suspension system;
(5) suspension system and weight vehicle combination:
The I-steel (6) of suspension system and outside I-steel (16) on weight vehicle are combined using buckle systems;
(6) track (1) is laid with:
It is laid with track (1) on floorings, weight vehicle is then dragged into upper rail (1) using trailer (2);
(7) template is installed:
It controls hoist engine (10), Hanging Basket (5) is transferred into suitable position, construction personnel for fulcrum, carries out box beam side with Hanging Basket (5)
The installation of the guardrail template of wall after template is installed at one, starts trailer (2), weight vehicle is moved to next construction
Section.
2. the production method of portable simplified concrete barrier formwork vehicle according to claim 1, which is characterized in that buckle
System is made of roller bearing (11) and a pair of channel steel (13) with circular hole (12), and roller bearing (11) passes through the circle in channel steel (13)
Hole (12) is placed on roller bearing (11).
3. the production method of portable simplified concrete barrier formwork vehicle according to claim 2, which is characterized in that roller bearing
(11) both ends are equipped with small perforation (14), and small perforation (14) the setting perforation fixture in roller bearing (11), perforation fixture blocks liter
The I-steel (6) and the outside I-steel (16) on weight vehicle of drop system.
4. the production method of portable simplified concrete barrier formwork vehicle according to claim 3, which is characterized in that perforation
Fixture is made of axis with holes (31) and perforation kelly (32), and perforation kelly (32) is set on axis with holes (31).
5. the production method of portable simplified concrete barrier formwork vehicle according to claim 1, which is characterized in that in step
Suddenly in (3), idler wheel (17) are arranged in I-steel lower frame, and mass (23) are placed in I-steel (18) side on the inside of weight vehicle.
6. the production method of portable simplified concrete barrier formwork vehicle according to claim 5, which is characterized in that counterweight
Drawbar (30) are arranged in vehicle side, and weight vehicle is under the traction of trailer (2) along setting on the track (1) on box bridge (24)
Walking.
7. a kind of portable simplified concrete barrier formwork vehicle, which is characterized in that using the portable simplified of any description above
The production method of concrete barrier formwork vehicle makes to obtain.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910477803.9A CN110080117B (en) | 2019-06-03 | 2019-06-03 | Movable simple concrete guardrail template vehicle and manufacturing method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910477803.9A CN110080117B (en) | 2019-06-03 | 2019-06-03 | Movable simple concrete guardrail template vehicle and manufacturing method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110080117A true CN110080117A (en) | 2019-08-02 |
CN110080117B CN110080117B (en) | 2021-04-20 |
Family
ID=67423229
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910477803.9A Active CN110080117B (en) | 2019-06-03 | 2019-06-03 | Movable simple concrete guardrail template vehicle and manufacturing method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110080117B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110761191A (en) * | 2019-10-23 | 2020-02-07 | 四川路桥建设集团交通工程有限公司 | Concrete guardrail construction device and method thereof |
CN110777666A (en) * | 2019-11-12 | 2020-02-11 | 广州市第一市政工程有限公司 | Steel box girder construction platform and use method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11256521A (en) * | 1998-03-09 | 1999-09-21 | Sumitomo Constr Co Ltd | Bridge erection device |
CN103015325A (en) * | 2012-12-24 | 2013-04-03 | 中铁十七局集团第二工程有限公司 | Construction method of cast-in-place concrete crash barrier with eaves |
KR101580118B1 (en) * | 2015-06-12 | 2015-12-29 | (주)에이치엔피테크 | Aqueduct and installation methods thereof |
JP2016217060A (en) * | 2015-05-25 | 2016-12-22 | ヤマダインフラテクノス株式会社 | Work room formation device for coating balustrade, sheet used therewith, and preservative coating method for balustrade using the same |
CN107338727A (en) * | 2016-12-28 | 2017-11-10 | 广西路建工程集团有限公司 | A kind of overall demolition, installation anticollision wall form and its walking track crane move system |
CN108797339A (en) * | 2018-06-26 | 2018-11-13 | 中冶南方工程技术有限公司 | A kind of safe construction method of cast-in-situ steel reinforced concrete anticollision barrier |
-
2019
- 2019-06-03 CN CN201910477803.9A patent/CN110080117B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11256521A (en) * | 1998-03-09 | 1999-09-21 | Sumitomo Constr Co Ltd | Bridge erection device |
CN103015325A (en) * | 2012-12-24 | 2013-04-03 | 中铁十七局集团第二工程有限公司 | Construction method of cast-in-place concrete crash barrier with eaves |
JP2016217060A (en) * | 2015-05-25 | 2016-12-22 | ヤマダインフラテクノス株式会社 | Work room formation device for coating balustrade, sheet used therewith, and preservative coating method for balustrade using the same |
KR101580118B1 (en) * | 2015-06-12 | 2015-12-29 | (주)에이치엔피테크 | Aqueduct and installation methods thereof |
CN107338727A (en) * | 2016-12-28 | 2017-11-10 | 广西路建工程集团有限公司 | A kind of overall demolition, installation anticollision wall form and its walking track crane move system |
CN108797339A (en) * | 2018-06-26 | 2018-11-13 | 中冶南方工程技术有限公司 | A kind of safe construction method of cast-in-situ steel reinforced concrete anticollision barrier |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110761191A (en) * | 2019-10-23 | 2020-02-07 | 四川路桥建设集团交通工程有限公司 | Concrete guardrail construction device and method thereof |
CN110777666A (en) * | 2019-11-12 | 2020-02-11 | 广州市第一市政工程有限公司 | Steel box girder construction platform and use method |
Also Published As
Publication number | Publication date |
---|---|
CN110080117B (en) | 2021-04-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102979041B (en) | Soft overhead reinforcing jacking method for construction of span box bridge of jacking block of underpass turnout group of railway | |
CN103015325B (en) | Construction method of cast-in-place concrete crash barrier with eaves | |
CN101736703B (en) | 3000t special bridge girder erection machine for integrally erecting 120m-span double-layer four-line steel beam bridge for highway and railway | |
KR20140084107A (en) | Self-Launching Movable Scaffolding System | |
CN106522112A (en) | Cable-stayed bridge side span beam section erecting system and method thereof | |
CN103103925B (en) | Combined H-shaped steel column bracket | |
CN110080117A (en) | Portable simplified concrete barrier formwork vehicle and preparation method thereof | |
CN207498835U (en) | Needle beam combined steel plate beam bridge panel cast-in-place construction sliding form frame system | |
CN207987749U (en) | Ride cable-styled erection crane | |
CN106480825A (en) | Railway nonstandard Beams Erection Construction engineering method | |
JP2011202406A (en) | Method of assembling and disassembling movable working device for bridge | |
CN106758741B (en) | Modular box type plate beam structure and pontic erection method based on box type plate beam structure | |
CN108086168A (en) | Ride cable-styled erection crane | |
CN102225580B (en) | Method for longitudinally moving box girder internal mold | |
CN106906750A (en) | A kind of multi-functional across railway line swing bridge girder closing construction mould bases and its construction method | |
CN106320190A (en) | Platform of bridge maintenance, consolidation and suspension construction | |
CN107327307B (en) | A kind of internal model steel pipe support integral slipping method and structure | |
CN111455854B (en) | Semi-automatic protective shed frame used in construction of viaduct crossing railway and erection method | |
JPH06193017A (en) | Bridge laying device | |
CN212358040U (en) | Novel ultra-wide front fulcrum guyed hanging basket thrust device | |
CN211848997U (en) | Semi-span pier beam-lifting machine for bridge on high pier column prefabricated T beam in limited space | |
CN104278628A (en) | Light hanging basket applicable to bridge detection and maintenance operations | |
CN211368350U (en) | Protector for composite beam cable-stayed bridge | |
CN211200116U (en) | Protective frame for construction of mid-span closure section steel shell of continuous beam of cross highway | |
CN109205475B (en) | Device and method for assembling and disassembling girder type gantry crane in tunnel through connection of trusses |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |