JP2016217060A - Work room formation device for coating balustrade, sheet used therewith, and preservative coating method for balustrade using the same - Google Patents

Work room formation device for coating balustrade, sheet used therewith, and preservative coating method for balustrade using the same Download PDF

Info

Publication number
JP2016217060A
JP2016217060A JP2015105307A JP2015105307A JP2016217060A JP 2016217060 A JP2016217060 A JP 2016217060A JP 2015105307 A JP2015105307 A JP 2015105307A JP 2015105307 A JP2015105307 A JP 2015105307A JP 2016217060 A JP2016217060 A JP 2016217060A
Authority
JP
Japan
Prior art keywords
balustrade
frame
work
painting
working
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2015105307A
Other languages
Japanese (ja)
Inventor
山田 博文
Hirobumi Yamada
博文 山田
翔平 山田
Shohei Yamada
翔平 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yamada Infratechnos Co Ltd
Original Assignee
Yamada Infratechnos Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yamada Infratechnos Co Ltd filed Critical Yamada Infratechnos Co Ltd
Priority to JP2015105307A priority Critical patent/JP2016217060A/en
Publication of JP2016217060A publication Critical patent/JP2016217060A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a work room formation device for coating a balustrade that prevents scattering of dusts and powdery dusts, mitigates burdens for work preparation, and enables preservative coating work without restricting traffic on a pedestrian bridge, etc.SOLUTION: A work room formation device includes a main frame 2 comprising a first frame 4 mounted on a bridge walkway 55 and a second frame 5 installed outside of a balustrade 52, and a sheet 3 for forming a work room 6 fitted on the main frame 2. Since a slit is formed on both right and left sides of the sheet 3 for letting the balustrade 52 pass through, the work room may be formed to be relatively compact in size and light-weight. As a result, burdens on work preparation are mitigated. Furthermore, the balustrade 52 may be coated for preservation without restricting traffic on a pedestrian bridge 51.SELECTED DRAWING: Figure 3

Description

本発明は、橋の通路の側縁に沿って立設された欄干を保全塗装する作業に用いられる欄干塗装用の作業室形成装置、該作業室形成装置に用いられるシート、及び該作業室形成装置を用いて該欄干を保全塗装する欄干保全塗装方法に関する。   The present invention relates to a work chamber forming apparatus for balustrade painting used for maintenance painting of a balustrade erected along a side edge of a bridge passage, a sheet used for the work chamber forming apparatus, and the work chamber formation The present invention relates to a balustrade maintenance painting method for painting the balustrade using an apparatus.

従来から、歩道橋等の欄干には、サビ等の発生を防ぐ目的や、経年劣化によって変色してしまった塗装の塗り替えのために、定期的に再塗装(保全塗装)が実施される。具体的に保全塗装作業は、先ず古い塗装やサビ等を取り除き、その後に新しく塗装する。   Conventionally, railings such as pedestrian bridges are regularly repainted (maintenance coating) for the purpose of preventing the occurrence of rust and the like, and for repainting paint that has been discolored due to deterioration over time. Specifically, the maintenance painting work first removes old paint and rust, and then paints it again.

この保全塗装の作業の際には、古い塗装やサビ等の粉塵や新しい塗料の噴霧塵が周囲に飛び散る。そのため、こうした粉塵や噴霧塵が歩道橋を通行する人や周囲に影響を及ぼすことが無いように、該歩道橋の欄干を塗装する場合には、該歩道橋を通行止めにして、該歩道橋全体をシートなどで覆って作業を実施することが一般的である。   During this maintenance painting work, dust such as old paint and rust and spray dust of new paint are scattered around. Therefore, when painting the railings of the pedestrian bridge so that such dust and spray dust do not affect people and the surroundings passing through the pedestrian bridge, the pedestrian bridge is closed and the entire pedestrian bridge is covered with a sheet, etc. It is common to carry out the work.

ところで、自動車が通行する橋梁の欄干を保全塗装する作業には、例えば特許文献1,2のように、欄干の外側に足場を設けて、欄干と該足場とをシート等で覆う構成の作業ブースを形成し、該作業ブースの内部で保全塗装するものが利用される。かかる作業ブースの構造は、自動車を通行止めにせずに、足場とシートとを支持する骨組みを、欄干の外側で固定するものであることから、該欄干の外側で比較的しっかりした骨組み構造が必要である。   By the way, for the work of maintaining and painting the railings of the bridges through which automobiles pass, for example, as disclosed in Patent Documents 1 and 2, a work booth having a structure in which a scaffold is provided outside the railings and the railings and the scaffolds are covered with a sheet or the like. Is used, and maintenance painting is performed inside the work booth. Since the structure of such a work booth is to fix the framework that supports the scaffold and the seat outside the balustrade without blocking the automobile, a relatively solid framework structure is necessary outside the balustrade. is there.

特開2004−232366号公報JP 2004-232366 A 特開2008−231905号公報JP 2008-231905 A

しかしながら、例えば歩道橋は、通路の幅が狭いことから、従来構成を用いる場合に歩道橋の欄干の外側にしっかりとした足場を組むべく該足場を支持する骨組みを歩道橋の全体に設ける必要がある。さらに、作業者が乗る足場は、強固である必要があることから、該足場を支える骨組みが大がかりとならざるを得ない。このため、足場を組む等の作業準備に要する時間と負担とが大きく、これに伴って作業工期も長くなってしまう。   However, for example, a footbridge has a narrow passage, and therefore, when the conventional structure is used, it is necessary to provide a framework for supporting the scaffold over the entire footbridge in order to form a firm scaffold outside the railing of the footbridge. Furthermore, since the scaffold on which the operator rides needs to be strong, the framework that supports the scaffold must be a large scale. For this reason, the time and burden required for work preparation such as assembling a scaffold are large, and the work work period is also increased accordingly.

そこで、本発明は、粉塵や噴霧塵の飛散を防ぐことができると共に、作業準備にかかる負担を抑制し、さらに歩道橋等を通行止めにすること無く保全塗装作業を行うことが可能な欄干塗装用の作業室形成装置、該作業室形成装置に用いられるシート、及び該作業室形成装置を用いた欄干保全塗装方法を提供することを目的とする。   Therefore, the present invention is for a balustrade painting that can prevent dust and spray dust from being scattered, suppress a burden on work preparation, and can perform maintenance painting work without blocking a pedestrian bridge or the like. It is an object of the present invention to provide a working chamber forming apparatus, a sheet used in the working chamber forming apparatus, and a balustrade maintenance coating method using the working chamber forming apparatus.

本発明の欄干塗装用の作業室形成装置は、橋の通路の側縁に沿って立設された欄干を保全塗装する作業に用いられ、該欄干の長手方向の一部分を覆って外部から隔たれた作業用ルームを形成するものであって、前記通路上に載置される第一フレームと、該第一フレームの片側に設けられ、該欄干の外側に配される第二フレームとを備えた本体フレームと、該本体フレームに取り付けられ、該第一フレーム内に生ずる通路上の第一作業空域と第二フレーム内に生ずる欄干の外側の第二作業空域とが連続する前記作業用ルームを形成するシートとを備え、さらに、前記シートには、前記欄干を通すための左右一対のスリットが各々設けられ、また、前記第一フレームの下端部にはキャスターが配設されていることを特徴とする。   INDUSTRIAL APPLICABILITY The working chamber forming apparatus for balustrade painting according to the present invention is used for the maintenance painting of the balustrade erected along the side edge of the bridge passage, and covers a part in the longitudinal direction of the balustrade and is separated from the outside. A main body that forms a working room and includes a first frame placed on the passage and a second frame provided on one side of the first frame and disposed outside the balustrade. The working room is formed by a frame and a first working air space on the passage formed in the first frame and a second working air space outside the balustrade formed in the second frame. A pair of left and right slits for passing the balustrade, and a caster is disposed at the lower end of the first frame. .

かかる構成にあっては、通路上に載置された第一フレームが主に当該装置全体(本体フレーム及びシート)を支え、かつ該通路上の第一作業空域内で作業者が欄干の保全塗装を行うことができるから、比較的コンパクトなサイズでかつ比較的軽量なものとすることができる。そして、装置全体の左右方向の長さを比較的短くし、欄干の長手方向に順次移動させることにより、該欄干を、その長手方向で複数箇所に分けて順次保全塗装することができる。かかる構成によれば、上述した従来構成のように通路の外側に足場を組む必要がなく、かつ前記のようにコンパクトで軽量なことから、設置作業(作業準備)に要する時間と負担とを可及的に軽減でき、総じて作業工期も短縮することができる。   In such a configuration, the first frame placed on the passage mainly supports the entire apparatus (main body frame and seat), and the worker paints the balustrade in the first working airspace on the passage. Therefore, it can be made relatively compact in size and relatively lightweight. Then, by making the length of the entire apparatus in the left-right direction relatively short and sequentially moving in the longitudinal direction of the balustrade, the balustrade can be sequentially subjected to maintenance coating in a plurality of locations in the longitudinal direction. According to such a configuration, there is no need to assemble a scaffold outside the passage as in the conventional configuration described above, and since it is compact and lightweight as described above, the time and burden required for installation work (work preparation) can be saved. As a result, the work period can be shortened.

さらに、コンパクトなサイズであることから、歩道橋のように通路幅が狭い場所であっても、一側の欄干を保全塗装する場合に反対側の通路部分を開けて設置することが可能である。そのため、歩道橋を通行止めにすること無く作業を実施することができ、歩道橋の利便性と安全性とを保ちつつ、欄干の保全塗装作業を実施できる。   Furthermore, since it is a compact size, it is possible to open and install the opposite passage portion in the case of painting a balustrade on one side even when the passage width is narrow such as a footbridge. Therefore, it is possible to carry out the work without blocking the pedestrian bridge, and it is possible to carry out maintenance painting work for the balustrade while maintaining the convenience and safety of the pedestrian bridge.

また、上記装置は、キャスターにより容易に移動させることができる。これにより、上述のように、欄干の長手方向に順次移動させて、該欄干の保全塗装を実施する場合に、その移動作業を容易に行うことができ、作業者の負担を一層軽減できる。なお、キャスターが作業中に動いてしまうことも考えられることから、本体フレームは、一時的に移動不能とできる停止手段を備えた構成が好適である。なお、この停止手段は、移動不能な状態と移動可能な状態とに容易に変換できるものが好適であり、例えば、キャスターを転動不能なロック状態と転動可能な非ロック状態とに変換できるものが適用できる。   Moreover, the said apparatus can be easily moved with a caster. Thus, as described above, when the balustrade is moved sequentially in the longitudinal direction and the balustrade is subjected to maintenance coating, the moving operation can be easily performed, and the burden on the operator can be further reduced. Since the caster may move during work, it is preferable that the main body frame has a stopping means that can be temporarily disabled. The stopping means is preferably one that can be easily converted into a non-movable state and a movable state. For example, the caster can be converted into a non-rollable locked state and a non-lockable non-lockable state. Things can be applied.

上述した本発明の欄干塗装用の作業室形成装置にあって、前記シートは、作業用ルームの天井を構成する天井形成部と、該作業用ルームの周囲の壁を構成する側壁形成部と、該側壁形成部の下端から延成され、第二作業空域を下方から覆うための第二作業空域用延成部と、作業用ルーム内で該第二作業空域用延成部に並ぶように該天井形成部から下方へ垂下され、その下部が欄干の外側から通路上に差し入れられる第二作業空域用の内側垂下部とを備え、さらに、前記第二作業空域用延成部を、第二作業空域を下方から覆う状態で保持する保持手段を備えている構成が提案される。   In the work room forming apparatus for balustrade painting of the present invention described above, the sheet includes a ceiling forming part that constitutes a ceiling of the work room, and a side wall forming part that constitutes a wall around the work room, A second working air space extending portion extending from the lower end of the side wall forming portion to cover the second working air space from below; and the second working air space extending portion in the work room so as to be aligned with the second working air space extending portion. A second working air space extending portion that is suspended downward from the ceiling forming portion and whose lower portion is inserted into the passage from the outside of the balustrade; A configuration is proposed that includes holding means for holding the airspace in a state of covering the airspace from below.

かかる構成にあっては、シートの天井形成部と側壁形成部とにより、保全塗装作業中に粉塵や噴霧塵が周囲に飛散することを防止できることに加え、第二作業空域用延成部と内側垂下部の下部とによって第二作業空域を下方から二重に覆うことができるため、欄干の外側の下方へ粉塵や噴霧塵が落下してしまうことを防止する効果が高い。   In such a configuration, the ceiling forming portion and the side wall forming portion of the sheet can prevent dust and spray dust from being scattered around during the maintenance coating operation, and the second working air space extending portion and the inner side Since the second working air space can be double covered from below by the lower part of the drooping portion, the effect of preventing dust and spray dust from falling down outside the balustrade is high.

そして、第二作業空域用延成部が、保持手段により第二作業空域を下方から覆った状態で保持されることから、該延成部や内側垂下部上に粉塵や噴霧塵が多く溜まっても、その重量を安定して支えることができ、該粉塵や噴霧塵の落下を安定して防止できる。   And since the extension part for 2nd work airspace is held in the state which covered the 2nd work airspace from the lower part by the holding means, a lot of dust and spray dust collected on this extension part or inner hanging part However, the weight can be stably supported, and the fall of the dust and spray dust can be stably prevented.

上述した本発明の欄干塗装用の作業室形成装置にあって、第一フレームは、四隅に各々設けられた四本の支柱を備えた略直方体状の骨組み構造からなり、第二フレームは、該第一フレームの外側で、前記第一フレームにおける隣合う二本の支柱と各々略平行に配される二本の縦杆を備えた骨組み構造からなり、さらに、前記第二フレームの二本の縦杆に差し渡される上下動自在な横干と、該横干から通路側へ突出するように設けられ、欄干又は該欄干が立設された橋の台座部に係脱可能に係合される複数の係合片とを備えている構成が提案される。   In the above-described working room forming apparatus for balustrade painting according to the present invention, the first frame is composed of a substantially rectangular parallelepiped frame structure having four columns provided at four corners, and the second frame is The frame comprises a frame structure having two vertical rods arranged substantially in parallel with the two adjacent struts in the first frame outside the first frame, and further, the two vertical frames of the second frame. A plurality of horizontal halves that are freely movable up and down passed to the fence, and are provided so as to protrude from the horizontal halves to the passage side, and are detachably engaged with a railing or a pedestal portion of a bridge on which the railings are erected. The structure provided with the engagement piece is proposed.

かかる構成にあっては、コンパクトサイズの本体フレームの形成に適しており、上述した本発明の作用効果が適切に発揮される。また、複数の係合片を係合することにより本体フレームを位置決めできることから、該位置決めすることで、保全塗装する欄干の部位を安定して定めることができ、該保全塗装作業を安定して実施できる。また、係合片が横干を介して第二フレームに取り付けられていることから、欄干の外側に位置する該第二フレームが安定する。そのため、風などにより第二フレームや装置全体が傾いたり動いてしまったりすることを可及的に抑制でき、作業用ルーム内での保全作業を安定して実施できる。   Such a configuration is suitable for forming a compact-sized main body frame, and the above-described effects of the present invention are appropriately exhibited. In addition, since the main body frame can be positioned by engaging a plurality of engagement pieces, the position of the balustrade to be subjected to maintenance coating can be stably determined by the positioning, and the maintenance coating operation can be performed stably. it can. Moreover, since the engaging piece is attached to the second frame via the horizontal cross, the second frame located outside the balustrade is stabilized. Therefore, it is possible to suppress as much as possible that the second frame or the entire apparatus is tilted or moved due to wind or the like, and maintenance work in the work room can be stably performed.

さらに、複数の係合片は横干に設けられていることから、該横干を上下に動すことで該複数の係合片を一緒に係脱させることができる。このため、この係脱作業を迅速かつ容易に実行でき、作業室形成装置を移動させる際に極めて便利である。   Further, since the plurality of engagement pieces are provided on the horizontal lay, the plurality of engagement pieces can be engaged and disengaged together by moving the horizontal hang up and down. For this reason, this engagement / disengagement operation can be performed quickly and easily, which is extremely convenient when moving the working chamber forming apparatus.

上述した本発明の欄干塗装用の作業室形成装置にあって、少なくとも第一フレームの各支柱が、その高さを変更可能な高さ調整機構を備えている構成が提案される。   In the work room forming apparatus for balustrade painting of the present invention described above, a configuration is proposed in which at least each column of the first frame is provided with a height adjusting mechanism capable of changing its height.

ここで、歩道橋には、欄干の一部分で高さが異なるものもある。かかる構成によれば、こうした欄干を保全塗装する場合に、第一フレームの各支柱の高さを、欄干の高さに合わせて変えることにより、作業ルーム内に十分な作業スペースを確保できることから、保全塗装作業の作業性を安定して保つことができる。すなわち、本発明の構成は、上述したように、欄干の保全塗装する際に、欄干の長手方向に移動させることを前提としていることから、前記のように欄干の高さが変わっている場合にも容易に対応できるようになっている。   Here, some pedestrian bridges have different heights in part of the balustrade. According to such a configuration, when such a balustrade is maintenance-painted, it is possible to secure a sufficient work space in the work room by changing the height of each support of the first frame according to the height of the balustrade, Workability of maintenance painting work can be kept stable. That is, the configuration of the present invention is based on the premise that the railing is moved in the longitudinal direction when the balustrade is preserved as described above. Can be easily handled.

一方、本発明のシートは、上述した欄干塗装用の作業室形成装置に用いられるシートであって、前記天井形成部と、前記側壁形成部と、前記第二作業空域用延成部と、前記第二作業空域用の内側垂下部とを備え、本体フレームに取り付けられて作業用ルームを形成するものであることを特徴とするものである。   On the other hand, the sheet of the present invention is a sheet used in the above-described work chamber forming apparatus for balustrade painting, the ceiling forming part, the side wall forming part, the second working air space extending part, And an inner hanging portion for the second working air space, and is attached to the main body frame to form a working room.

かかる構成のシートによれば、上述したように、保全塗装作業中に粉塵や噴霧塵が周囲に飛散することを防止できる。   According to the sheet having such a configuration, as described above, dust and spray dust can be prevented from being scattered around during the maintenance painting operation.

一方、本発明の欄干保全塗装方法は、上述した欄干塗装用の作業室形成装置を用いて橋の欄干を保全塗装する欄干保全塗装方法であって、該作業室形成装置で該欄干の長手方向の一部分を覆って、その作業用ルーム内で該欄干の一部分を保全塗装する作業工程と、
該作業工程で保全塗装した後、保全塗装前の欄干の一部分を覆うように、作業室形成装置を欄干の長手方向に沿って移動させる移動工程とを含むことを特徴とする方法である。
On the other hand, the balustrade maintenance painting method of the present invention is a balustrade maintenance coating method for maintenance painting of a railing of a bridge using the above-described work chamber forming device for balustrade painting, and the longitudinal direction of the balustrade in the work chamber forming device A work process for covering a part of the balustrade, and painting a part of the balustrade in the work room,
And a moving step of moving the working chamber forming device along the longitudinal direction of the balustrade so as to cover a part of the balustrade before the maintenance coating after the maintenance coating in the operation step.

かかる方法にあっては、作業工程と移動工程とを交互に繰り返すことにより、欄干全体を保全塗装することができる。ここで、作業室形成装置は、上述したように、コンパクトサイズに形成されることから、作業工程と移動工程とを迅速に切り替えることができ、欄干の保全塗装作業を安定かつ容易に実行できる。   In such a method, the entire balustrade can be maintenance-painted by alternately repeating the work process and the moving process. Here, since the working chamber forming apparatus is formed in a compact size as described above, the working process and the moving process can be quickly switched, and the maintenance painting work for the balustrade can be executed stably and easily.

本発明の欄干塗装用の作業室形成装置によれば、比較的コンパクトなサイズで且つ軽量なものとできるから、作業準備に要する時間と負担とを軽減でき、作業工期を短縮可能である。さらに、歩道橋の欄杆を保全塗装する作業に使用した場合に、該歩道橋を通行止めせずに該保全塗装を行うことができるため、歩道橋の利便性と安全性とを保ちつつ、該保全塗装を実施可能である。   According to the balustrade painting apparatus for forming a balustrade according to the present invention, since it can be made relatively compact and lightweight, the time and burden required for work preparation can be reduced, and the work period can be shortened. In addition, when used for maintenance painting on the railroad of a pedestrian bridge, the maintenance painting can be performed without blocking the pedestrian bridge, so the maintenance painting is performed while maintaining the convenience and safety of the pedestrian bridge. Is possible.

実施例にかかる欄干塗装用の作業室形成装置1を歩道橋51に設置した状態を外側から示す正面図である。It is a front view which shows the state which installed the working room formation apparatus 1 for balustrade painting concerning an Example in the footbridge 51 from the outer side. 欄干塗装用の作業室形成装置1を歩道橋51に設置した状態を示す側面図である。FIG. 2 is a side view showing a state in which a work room forming apparatus 1 for balustrade painting is installed on a pedestrian bridge 51. 図1のL−L断面図である。It is LL sectional drawing of FIG. 本体フレーム2の平面図である。4 is a plan view of the main body frame 2. FIG. 本体フレーム2の正面図である。3 is a front view of a main body frame 2. FIG. 本体フレーム2の側面図である。4 is a side view of the main body frame 2. FIG. (a)シート3を内壁形成部32側から視た斜視図と、(b)シート3を外壁形成部34側から視た斜視図である。(A) The perspective view which looked at the sheet | seat 3 from the inner wall formation part 32 side, (b) The perspective view which looked at the sheet | seat 3 from the outer wall formation part 34 side.

本発明にかかる欄干塗装用の作業室形成装置1の実施例を、添付図面を用いて以下に説明する。なお、本発明は、下記に示す実施例に限定されることはなく、適宜、設計変更が可能である。また、本実施例では、歩道橋51の長手方向(橋の長さ方向)を作業室形成装置1の左右方向とし、該歩道橋51の幅方向を作業室形成装置1の内外方向とし、さらに該作業室形成装置1の内外方向において通路55側を内側、反対側を外側として説明する。なお、歩道橋51の通路55が、本発明にかかる橋の通路である。また、後述するシート3の肉厚は、装置全体において微少な寸法となるため、図面においては肉厚を省略して示すこととする。   An embodiment of a work chamber forming apparatus 1 for balustrade painting according to the present invention will be described below with reference to the accompanying drawings. In addition, this invention is not limited to the Example shown below, A design change is possible suitably. In the present embodiment, the longitudinal direction of the pedestrian bridge 51 (the length direction of the bridge) is the left-right direction of the work chamber forming apparatus 1, the width direction of the pedestrian bridge 51 is the inner and outer directions of the work chamber forming apparatus 1, and the work In the inside-outside direction of the chamber forming apparatus 1, the passage 55 side will be described as the inside and the opposite side as the outside. The passage 55 of the pedestrian bridge 51 is a bridge passage according to the present invention. Further, since the thickness of the sheet 3 to be described later is a minute dimension in the entire apparatus, the thickness is not shown in the drawings.

まず、作業室形成装置1の設置態様を概説する。
図1〜3に示すように、塗装ブースとなる作業室形成装置1は、歩道橋51に設けられた欄干52を保全塗装する作業に使用することができ、片側の欄干52の一部分を覆ってその内部に形成された作業用ルーム6内で該保全塗装を実施できる。なお、ここで歩道橋51にあっては、その通路55の両側縁に、該通路55の幅を規定する台座部56が該通路55の長手方向に亘って設けられ、該台座部56上に欄干52が設けられている。
First, the installation mode of the working chamber forming apparatus 1 will be outlined.
As shown in FIGS. 1 to 3, the work room forming apparatus 1 serving as a painting booth can be used for the maintenance painting of the balustrade 52 provided on the pedestrian bridge 51, covering a part of the balustrade 52 on one side and The maintenance coating can be performed in the work room 6 formed inside. Here, in the pedestrian bridge 51, pedestal portions 56 that define the width of the passage 55 are provided on both side edges of the passage 55 in the longitudinal direction of the passage 55. 52 is provided.

作業室形成装置1は、歩道橋51の通路55上に位置する部分と欄干52の外側に位置する部分とからなり、図3に示すように、作業用ルーム6が、欄干52の内側で歩道橋51の通路55上に形成される第一作業空域7と、該欄干52の外側に形成される第二作業空域8とから構成される。   The work room forming apparatus 1 includes a part located on the passage 55 of the pedestrian bridge 51 and a part located outside the balustrade 52, and the work room 6 is located inside the balustrade 52 inside the pedestrian bridge 51, as shown in FIG. 3. The first work air space 7 formed on the passage 55 and the second work air space 8 formed outside the balustrade 52 are configured.

本実施例の作業室形成装置1は、略直方体形状を成し、左右方向の長さが約2mであり、歩道橋51の全長(欄干52の全長)に比して短い。また、内外方向となる奥行が約1.3mで、そのうち通路55上における奥行(第一作業空域7の奥行)が約0.8mである。   The working chamber forming apparatus 1 of the present embodiment has a substantially rectangular parallelepiped shape, the length in the left-right direction is about 2 m, and is shorter than the total length of the pedestrian bridge 51 (the total length of the balustrade 52). Further, the depth in the inner and outer direction is about 1.3 m, and the depth on the passage 55 (the depth of the first work air space 7) is about 0.8 m.

こうした作業室形成装置1は、その設置位置で欄干52の一部分のみを覆うものであることから、該設置位置を欄干52に沿って順次移動させることで、該欄干52を覆っている部分を移動させることができる。また、作業室形成装置1の奥行が該通路55の全幅よりも短いことから、設置した状態で、該通路55の、反対側の欄干52寄り部位を空けて通行可能とすることができる。   Since such a working chamber forming apparatus 1 covers only a part of the balustrade 52 at the installation position, the part covering the balustrade 52 is moved by sequentially moving the installation position along the balustrade 52. Can be made. In addition, since the depth of the work chamber forming apparatus 1 is shorter than the entire width of the passage 55, it is possible to allow the passage 55 to pass through a portion near the balustrade 52 on the opposite side of the passage 55.

次に、作業室形成装置1の基本構造について説明する。
作業室形成装置1は、本体フレーム2とシート3とを備える。本体フレーム2は、図4〜6に示すように、歩道橋51の通路55上に載置される第一フレーム4と、欄干52の外側に配される第二フレーム5とから構成される。
Next, the basic structure of the working chamber forming apparatus 1 will be described.
The work chamber forming apparatus 1 includes a main body frame 2 and a seat 3. As shown in FIGS. 4 to 6, the main body frame 2 includes a first frame 4 placed on the passage 55 of the pedestrian bridge 51 and a second frame 5 arranged outside the balustrade 52.

第一フレーム4は、略直方体状の骨格構造を成すものであり、四隅に各々配された上下方向の四本の支柱11と、各支柱11の上端部に連結された四個の上梁12a,12bと、各支柱11の下端部に連結された四個の下梁13a,13bとを備える。そして、これら支柱11と上梁12a,12bと下梁13a,13bとにより、第一フレーム4の骨組み構造が形成される。   The first frame 4 has a substantially rectangular parallelepiped skeleton structure, and includes four vertical pillars 11 respectively arranged at four corners and four upper beams 12a connected to upper ends of the respective pillars 11. , 12b and four lower beams 13a, 13b connected to the lower end of each column 11. Then, the frame structure of the first frame 4 is formed by the support columns 11, the upper beams 12a and 12b, and the lower beams 13a and 13b.

支柱11は、上下二本の金属製パイプ11a,11bから構成され、上パイプ11aが下パイプ11bの上端から該下パイプ11b内に嵌入されてなる。下パイプ11bの上端には、上パイプ11aを固定するための高さ調整部材28が配設されている。この高さ調整部材28は、下パイプ11bの上端に外嵌されて固定された筒部(図示せず)と該筒部のネジ孔に螺合される固定用ボルト(図示せず)とから構成されており、該固定用ボルトが上パイプ11aに形成された調整孔(図示せず)内に挿入され、かつ締め付けられることで上パイプ11aを固定する高さ固定状態が得られる。一方、該締め付けを解除することで上パイプ11aを上下動可能とする可動状態に変換可能である。こうした高さ調整部材28により、下パイプ11bに対する上パイプ11aの突出高さを変更することができ、支柱11の高さが随時変更可能となる。   The column 11 is composed of two upper and lower metal pipes 11a and 11b, and the upper pipe 11a is fitted into the lower pipe 11b from the upper end of the lower pipe 11b. A height adjusting member 28 for fixing the upper pipe 11a is disposed at the upper end of the lower pipe 11b. The height adjusting member 28 includes a cylindrical portion (not shown) that is externally fitted and fixed to the upper end of the lower pipe 11b, and a fixing bolt (not shown) that is screwed into a screw hole of the cylindrical portion. The fixing bolt is inserted into an adjustment hole (not shown) formed in the upper pipe 11a and tightened to obtain a fixed height state for fixing the upper pipe 11a. On the other hand, the upper pipe 11a can be converted into a movable state in which the upper pipe 11a can be moved up and down by releasing the tightening. By such a height adjusting member 28, the protruding height of the upper pipe 11a with respect to the lower pipe 11b can be changed, and the height of the column 11 can be changed at any time.

支柱11は、上記のように高さを変更可能であり、例えば1.8m〜2.6mの範囲で高さ変更することができる。なお、通常は、一般的な欄干52の保全塗装に適した2.2mの高さに設定しておくことが好ましい。また、作業室形成装置1の左右方向(欄干52の長手方向)に沿って配される上梁12aと下梁13aとは、長さが約2mの長尺状の金属製パイプからなり、作業室形成装置1の内外方向(通路55の幅方向)に沿って配される上梁12b,13bは、長さが約0.8mの短尺状の金属パイプからなる。そして、上梁12a,12bと下梁13a,13bとは、各々の両端部が下方へ約90度折れ曲がっており、折れ曲がった部位で連結端部20が構成される。なお、本実施例では、支柱11の下パイプ11bと上梁12a,12bと下梁13a,13bとが同じパイプ径のステンレス製パイプであり、該支柱11の上パイプ11aは、該下パイプ11bに嵌入可能なパイプ径のステンレス製パイプである。   The height of the support | pillar 11 can be changed as mentioned above, for example, can be changed in the range of 1.8m-2.6m. In general, it is preferable to set the height to 2.2 m which is suitable for general balustrade 52 maintenance coating. Further, the upper beam 12a and the lower beam 13a arranged along the left-right direction of the work chamber forming apparatus 1 (longitudinal direction of the balustrade 52) are long metal pipes having a length of about 2 m. The upper beams 12b and 13b arranged along the inner and outer directions (the width direction of the passage 55) of the chamber forming device 1 are made of short metal pipes having a length of about 0.8 m. The upper beams 12a and 12b and the lower beams 13a and 13b are bent at about 90 degrees downward at both ends, and the connecting end portion 20 is formed by the bent portions. In this embodiment, the lower pipe 11b, the upper beams 12a and 12b, and the lower beams 13a and 13b of the column 11 are stainless steel pipes having the same pipe diameter, and the upper pipe 11a of the column 11 is formed of the lower pipe 11b. It is a stainless steel pipe with a pipe diameter that can be fitted into the pipe.

そして、各支柱11と上梁12a,12b又は下梁13a,13bとは、各支柱11の上端部と下端部とに各々取り付けられた連結部材21,22を介して連結される。なお、通路55の内側に位置する左右二本の支柱11,11には、その上端部と下端部とに連結部材21が各々取り付けられる。   And each support | pillar 11 and upper beam 12a, 12b or lower beam 13a, 13b are connected via the connection members 21 and 22 attached to the upper end part and lower end part of each support | pillar 11, respectively. Note that the connecting members 21 are attached to the upper and lower ends of the two left and right columns 11, 11 located inside the passage 55.

具体的に連結部材21は、支柱11に外嵌される円筒形の主筒部24と、上梁12a,12b又は下梁13a,13bの連結端部20を嵌入可能な円筒形の二個の副筒部25とを備える。そして、二個の副筒部25は、主筒部24の外周面に、その外周方向で約90度離間して各々接合される。   Specifically, the connecting member 21 includes two cylindrical main tube portions 24 that are externally fitted to the support column 11 and two cylindrical shapes that can be fitted with the connecting ends 20 of the upper beams 12a and 12b or the lower beams 13a and 13b. A sub-cylinder portion 25. And the two sub cylinder parts 25 are each joined to the outer peripheral surface of the main cylinder part 24, spaced apart about 90 degree | times in the outer peripheral direction.

一方、欄干52寄りに位置する左右二本の支柱11,11には、その下端部に前記連結部材21が各々取り付けられ、かつ上端部に連結部材22が各々取り付けられる。この連結部材22は、前記主筒部24と、三個の前記副筒部25とを備え、該三個の副筒部25が、主筒部24の外周面に接合される。   On the other hand, the two left and right support columns 11, 11 positioned near the balustrade 52 are each attached with the connecting member 21 at the lower end and the connecting member 22 at the upper end. The connecting member 22 includes the main tube portion 24 and the three sub tube portions 25, and the three sub tube portions 25 are joined to the outer peripheral surface of the main tube portion 24.

ここで、二個の副筒部25が、主筒部24の外周方向で互いに約180度離間する位置に設けられ、一個の副筒部25が、前記二個の副筒部25と各々約90度づつ離れた位置に設けられる。こうした連結部材21,22は、前記支柱11の上端部と下端部とに、所定の固定手段(ボルトによる螺合や溶接など)によって各々固定される。   Here, the two sub-cylinder portions 25 are provided at positions spaced apart from each other by about 180 degrees in the outer circumferential direction of the main cylinder portion 24, and one sub-cylinder portion 25 is approximately the same as the two sub-cylinder portions 25, respectively. It is provided at a position 90 degrees apart. The connecting members 21 and 22 are fixed to the upper end portion and the lower end portion of the support column 11 by predetermined fixing means (such as screwing or welding with bolts), respectively.

そして、四本の支柱11の上端部と下端部とに各々取り付けられた連結部材21,22の各副筒部25に、上梁12a,12bの連結端部20と下梁13a,13bの連結端部20とが各々嵌入されることで、略直方体状の第一フレーム4が形成される。   Then, the connecting end portions 20 of the upper beams 12a and 12b and the lower beams 13a and 13b are connected to the sub-cylinder portions 25 of the connecting members 21 and 22 attached to the upper end portion and the lower end portion of the four columns 11, respectively. By inserting the end portions 20 into each other, the substantially rectangular parallelepiped first frame 4 is formed.

さらに、各支柱11の下端には、キャスター16が各々装着されており、第一フレーム4(本体フレーム2)を、その形態を維持したままで容易に移動できるようにしている。なお、該キャスター16の少なくともいずれかには、キャスター16の転動を停止可能とする停止手段(ブレーキ手段)を備えている。   Further, casters 16 are respectively attached to the lower ends of the columns 11 so that the first frame 4 (main body frame 2) can be easily moved while maintaining its form. Note that at least one of the casters 16 is provided with a stop means (brake means) that can stop the rolling of the casters 16.

また、第二フレーム5は、第一フレーム4における欄干52寄りに位置した左右二本の支柱11,11に略平行な二本の縦杆17,17と、該縦杆17の上端部を連結した三個の上梁18a,18bと、該縦杆17の中央部分を連結した一個の中梁19とを備える。これら縦杆17、上梁18a,18b、及び中梁19は、上述した第一フレーム4と同じ金属製パイプから構成されている。そして、これら縦杆17、上梁18a,18b、及び中梁19により、第二フレーム5の骨組み構造が形成される。   Further, the second frame 5 connects two vertical rods 17, 17 substantially parallel to the two left and right columns 11, 11 located near the balustrade 52 in the first frame 4 and the upper end portion of the vertical rod 17. The three upper beams 18a and 18b and one middle beam 19 connecting the central portions of the vertical rods 17 are provided. The vertical rod 17, the upper beams 18a and 18b, and the middle beam 19 are made of the same metal pipe as that of the first frame 4 described above. The vertical frame 17, the upper beams 18a and 18b, and the middle beam 19 form a frame structure of the second frame 5.

縦杆17は、長さが約2.4mであり、通常設定された第一フレーム4の支柱11(2.2m)よりも長い。長尺の上梁18aと中梁19とは、第一フレーム4の上梁12a(又は下梁13a)と同じ形状寸法をなし、短尺の上梁18bは、長さが約0.5mである。そして、これら上梁18a,18bと中梁19とは、第一フレーム4の上梁12aと同様に、両端に連結端部20,20を備える。   The downpipe 17 has a length of about 2.4 m and is longer than the support 11 (2.2 m) of the first frame 4 that is normally set. The long upper beam 18a and the middle beam 19 have the same shape and dimensions as the upper beam 12a (or the lower beam 13a) of the first frame 4, and the short upper beam 18b has a length of about 0.5 m. . The upper beams 18 a and 18 b and the middle beam 19 are provided with connecting end portions 20 and 20 at both ends, similarly to the upper beam 12 a of the first frame 4.

そして、第二フレーム5の縦杆17と上梁18a,18bとは、上述した連結部材21を介して連結され、縦杆17と中梁19とは、連結部材23を介して連結される。   The vertical rod 17 and the upper beams 18 a and 18 b of the second frame 5 are connected via the connecting member 21 described above, and the vertical rod 17 and the middle beam 19 are connected via the connecting member 23.

ここで、連結部材23は、前記主筒部24と一個の前記副筒部25とを備え、該主筒部24の外周面に該副筒部25が接合されてなる。連結部材21は、縦杆17の上端部に外嵌されて所定の固定手段(ネジによる螺合や溶接など)により固定され、連結部材23は、縦杆17の中央部分に外嵌されて該固定手段により固定される。そして、各連結部材21の副筒部25に上梁18a,18bの連結端部20を各々嵌入すると共に、各連結部材23の副筒部25に中梁19の連結端部20を各々嵌入する。これにより第二フレーム5が形成される。   Here, the connecting member 23 includes the main tube portion 24 and one sub tube portion 25, and the sub tube portion 25 is joined to the outer peripheral surface of the main tube portion 24. The connecting member 21 is externally fitted to the upper end portion of the vertical rod 17 and fixed by predetermined fixing means (screwing or welding with a screw), and the connecting member 23 is externally fitted to the central portion of the vertical rod 17 and It is fixed by fixing means. Then, the connecting end portions 20 of the upper beams 18 a and 18 b are respectively inserted into the sub-cylinder portions 25 of the connecting members 21, and the connecting end portions 20 of the intermediate beams 19 are respectively inserted into the sub-tube portions 25 of the connecting members 23. . Thereby, the second frame 5 is formed.

さらに、短尺の上梁18b,18bの他方の連結端部20は、第一フレーム4の、欄干52寄りの支柱11,11の上端部に取り付けられた連結部材22の副筒部25,25に各々内嵌される。   Further, the other connecting end 20 of the short upper beams 18b, 18b is connected to the sub-cylinder portions 25, 25 of the connecting member 22 attached to the upper ends of the columns 11, 11 near the balustrade 52 of the first frame 4. Each is fitted inside.

こうして、第二フレーム5と上記の第一フレーム4とが一体化され、本体フレーム2が形成される。本体フレーム2では、第二フレーム5の上梁18aと第一フレーム4の上梁12aとが平行に設けられ、第二フレーム5の上梁18bと第一フレーム4の上梁12bとが略一直線状に設けられる。   Thus, the second frame 5 and the first frame 4 are integrated to form the main body frame 2. In the main body frame 2, the upper beam 18 a of the second frame 5 and the upper beam 12 a of the first frame 4 are provided in parallel, and the upper beam 18 b of the second frame 5 and the upper beam 12 b of the first frame 4 are substantially in a straight line. It is provided in the shape.

さらに、本体フレーム2には、各支柱11と上梁12a,12とに差し渡された複数の補強杆15が配設されている。同様に、複数の補強杆15は、各支柱11と下梁13a,13bとに、欄杆寄りの支柱11と上梁18bとに、各縦杆17と上梁18aとに、各縦杆17と中梁19とに各々差し渡されて配設されている。これら補強杆15は、本体フレーム2を補強し、かつその骨格の変形を防止できる。なお、補強杆15には、前記差し渡された状態への取り付けと該状態の解除とを容易に実施可能な構成が適用される。   Further, the main body frame 2 is provided with a plurality of reinforcing rods 15 extending between the respective columns 11 and the upper beams 12a and 12. Similarly, the plurality of reinforcing rods 15 are provided on the columns 11 and the lower beams 13a and 13b, on the columns 11 and the upper beams 18b near the balustrade, on the vertical beams 17 and the upper beams 18a, and on the vertical beams 17 and 17b. Each of the intermediate beams 19 is provided so as to extend. These reinforcing rods 15 reinforce the main body frame 2 and can prevent deformation of the skeleton. The reinforcing rod 15 is applied with a configuration that can be easily attached to the handed over state and released from the state.

また、第二フレーム5には、中梁19の下側で、左右の縦杆17,17に差し渡された上下動自在な横杆45が設けられている。横杆45は、その左右両端部に各々配設された位置決め部材46,46を介して、左右の縦杆17,17に固定される。ここで、位置決め部材46は、縦杆17に固定されて横杆45を上下動不能とする位置決め状態と、該固定を解除して該横杆45を上下動可能とする解除状態とに変換可能である。なお、位置決め部材46としては、例えば、縦杆17を外嵌する筒部(図示せず)と該筒部のネジ孔に螺合される固定ボルト(図示せず)とにより構成され、該固定ボルトを締め付けることで前記位置決め状態とする一方、該締め付けを解除することで前記解除状態とする。   Further, the second frame 5 is provided with a horizontal bar 45 that can be moved up and down between the left and right vertical bars 17 and 17 below the middle beam 19. The horizontal bar 45 is fixed to the left and right vertical bars 17 and 17 through positioning members 46 and 46 respectively disposed at both left and right ends thereof. Here, the positioning member 46 can be converted into a positioning state in which the horizontal bar 45 is fixed to the vertical bar 17 so that the horizontal bar 45 cannot move up and down, and a released state in which the horizontal bar 45 can be moved up and down by releasing the fixing. It is. The positioning member 46 includes, for example, a cylindrical portion (not shown) that fits the vertical rod 17 and a fixing bolt (not shown) that is screwed into a screw hole of the cylindrical portion. While the bolt is tightened to the positioning state, the tightening is released to the release state.

前記横杆45には、所定間隔をおいて複数の係合片47が取り付けられている。該係合片47は、横杆45から内方へ突出された主杆部48aと該主杆部48aの内端から下方へ延成された係合端部48bとから構成される。係合片47は、その主杆部48aを歩道橋51の台座部56に載置することで、係合端部48bが該台座部56の内側縁に係合される。すなわち、係合片47の主杆部48aを台座部56に載置する高さ位置で、横杆45を縦杆17,17に固定して位置決めすることによって、全ての係合片47を該台座部56に係合した状態で保持できる。また、この係合解除する場合には、横杆45の固定を解除して該横杆45を上方移動することで、全ての係合片47を同時に係合解除できる。   A plurality of engagement pieces 47 are attached to the horizontal bar 45 at a predetermined interval. The engagement piece 47 includes a main collar portion 48a that protrudes inward from the horizontal flange 45 and an engagement end portion 48b that extends downward from the inner end of the main collar portion 48a. The engaging piece 47 is engaged with the inner edge of the pedestal portion 56 by placing the main collar portion 48 a on the pedestal portion 56 of the pedestrian bridge 51. That is, by fixing and positioning the horizontal hook 45 to the vertical hooks 17 and 17 at the height position where the main hook portion 48a of the engaging piece 47 is placed on the pedestal portion 56, all the engaging pieces 47 are attached. It can hold | maintain in the state engaged with the base part 56. FIG. Further, when the engagement is released, all the engagement pieces 47 can be simultaneously released by releasing the fixation of the horizontal hook 45 and moving the horizontal hook 45 upward.

なおここで、各係合片47は、その主杆部48aが固定部材49を介して横杆45にそれぞれ固定される。固定部材49は、横杆45に固定されており、主杆部48aを固定状態と解除状態とに変換可能とするものであり、該解除状態とすることで、係合片47を内外方向に移動可能とし、固定状態で係合片47を移動不能とする。この固定部材49により、係合片47の、横杆45から係合端部48bまでの長さを調整することができ、該係合端部48bが台座部56と係合する所望の長さに設定することが可能である。   Here, each engagement piece 47 has its main collar portion 48 a fixed to the horizontal collar 45 via a fixing member 49. The fixing member 49 is fixed to the horizontal rod 45, and the main rod portion 48a can be converted into a fixed state and a released state. By setting the released state, the engagement piece 47 is moved inward and outward. The engaging piece 47 cannot be moved in a fixed state. With this fixing member 49, the length of the engagement piece 47 from the horizontal flange 45 to the engagement end portion 48 b can be adjusted, and the desired length with which the engagement end portion 48 b engages with the pedestal portion 56. Can be set.

一方、シート3は、図7に示すように、略長方形状の天井形成部31を有している。そして、該天井形成部31の内側縁から略長方形状の内壁形成部32が延成されている。また、該天井形成部31の左右の側縁からは、略長方形状の壁形成部33,33が各々延成されている。また、該天井形成部31の外側縁からは、略長方形状の外壁形成部34が延成されている。加えて、該外壁形成部34の下縁からは、略長方形状の延成部(第二作業空域用延成部)35が延成されている。また、該内壁形成部32の下縁からは、略長方形状の延成部(第一作業空域用延成部)36が延成されている。   On the other hand, the sheet 3 has a substantially rectangular ceiling forming portion 31 as shown in FIG. A substantially rectangular inner wall forming portion 32 extends from the inner edge of the ceiling forming portion 31. Further, from the left and right side edges of the ceiling forming portion 31, substantially rectangular wall forming portions 33, 33 are respectively extended. A substantially rectangular outer wall forming portion 34 extends from the outer edge of the ceiling forming portion 31. In addition, a substantially rectangular extending portion (second working air region extending portion) 35 extends from the lower edge of the outer wall forming portion 34. A substantially rectangular extending portion (first working air region extending portion) 36 extends from the lower edge of the inner wall forming portion 32.

そして、内壁形成部32の左右の側縁と、左右の壁形成部33,33の内側縁とが縫製等により各々接合されていると共に、外壁形成部34の左右の側縁と、左右の壁形成部33,33の外側縁とが縫製等により各々接合されている。このようにシート3は、四方を囲まれた四角形の筒形でその天井が閉鎖された伏箱形状に形成されてなる。なお、前記のように接合された内壁形成部32と左右の壁形成部33,33と外壁形成部34とにより、本発明にかかる側壁形成部が構成される。   The left and right side edges of the inner wall forming portion 32 and the inner edges of the left and right wall forming portions 33 and 33 are joined together by sewing or the like, and the left and right side edges of the outer wall forming portion 34 and the left and right walls The outer edges of the forming portions 33 and 33 are joined together by sewing or the like. Thus, the sheet | seat 3 is formed in the lower box shape by which the ceiling was closed with the square cylinder shape enclosed on all sides. The inner wall forming portion 32, the left and right wall forming portions 33, 33, and the outer wall forming portion 34 joined as described above constitute a side wall forming portion according to the present invention.

さらに、シート3にあって、天井形成部31には、その外側縁の内側に、略長方形状の内側垂下部37の上縁が縫製等により接合されている。この内側垂下部37は、上記の伏箱形状で外壁形成部34と略並行に天井形成部31から垂下され、該外壁形成部34と共に二重の外壁構造を成す。なお、内側垂下部37は、外壁形成部34から延成された延成部35と略同じ左右方向幅で形成されている。   Further, in the seat 3, the upper edge of the substantially rectangular inner hanging portion 37 is joined to the ceiling forming portion 31 inside the outer edge by sewing or the like. The inner hanging portion 37 is suspended from the ceiling forming portion 31 in the shape of the above-mentioned box and substantially parallel to the outer wall forming portion 34, and forms a double outer wall structure together with the outer wall forming portion 34. The inner hanging portion 37 is formed with a width in the left-right direction that is substantially the same as the extending portion 35 that extends from the outer wall forming portion 34.

こうしたシート3にあって、天井形成部31は、本体フレーム2の、上梁12a,12bと上梁18a,18bとに囲まれた長方形状の上方開口部を覆うものであり、内壁形成部32は、通路55の内側に位置する左右二本の支柱11,11と上梁12aと下梁13aとに囲まれた長方形状の内方開口部を覆うものである。そして、延成部36は、内壁形成部32の下縁から引き込まれて第一フレーム4の下方を覆う。   In such a sheet 3, the ceiling forming part 31 covers the rectangular upper opening of the main body frame 2 surrounded by the upper beams 12 a and 12 b and the upper beams 18 a and 18 b, and the inner wall forming part 32. Covers the rectangular inner opening surrounded by the left and right support columns 11, 11, the upper beam 12 a and the lower beam 13 a located inside the passage 55. The extending portion 36 is drawn from the lower edge of the inner wall forming portion 32 and covers the lower portion of the first frame 4.

外壁形成部34は、第二フレーム5の、上梁18aから縦杆17,17の下端部に至るまでの外方開口部を覆うものであり、延成部35は、外壁形成部34の下縁から引き込まれることで、第二フレーム5の下方への開口部を覆うものである。そして、内側垂下部37は、外壁形成部34と共に二重の外壁構造を形成し、該内側垂下部37の下部37aを、第二フレーム5の係合片47に上載して内側に差し入れることで、第二フレーム5の下方開口部を覆う。このように第二フレーム5の下方開口部は、延成部35と内側垂下部37の下部37aとにより二重に覆われる。なお、内側垂下部37の下部37aは、通路55上まで引き込まれる一方、延成部35は、クランプ等の保持手段Kによって歩道橋51の側縁部に取り付けられる。この保持手段Kは、歩道橋51の側縁部に着脱可能であり、取り付けた状態で、延成部35が前記第二フレームの下方開口部を覆い、取り外すことで移動可能となる。   The outer wall forming portion 34 covers the outer opening of the second frame 5 from the upper beam 18 a to the lower ends of the vertical rods 17 and 17, and the extending portion 35 is provided below the outer wall forming portion 34. By pulling in from the edge, the downward opening of the second frame 5 is covered. The inner hanging portion 37 forms a double outer wall structure together with the outer wall forming portion 34, and the lower portion 37 a of the inner hanging portion 37 is placed on the engagement piece 47 of the second frame 5 and inserted inside. Thus, the lower opening of the second frame 5 is covered. As described above, the lower opening portion of the second frame 5 is double-covered by the extending portion 35 and the lower portion 37 a of the inner hanging portion 37. The lower portion 37a of the inner hanging portion 37 is drawn up to the passage 55, while the extending portion 35 is attached to the side edge portion of the pedestrian bridge 51 by holding means K such as a clamp. The holding means K can be attached to and detached from the side edge of the pedestrian bridge 51, and in the attached state, the extending part 35 covers the lower opening of the second frame and can be moved by being removed.

また、左右の壁形成部33は、一直線状に配された上梁12b,18bから支柱11及び縦杆17の下端に至るまでの左右の各開口部を各々覆うものである。さらに、特徴的なこととして、壁形成部33は、隣合う内外の支柱11間で内外に分割されると共に、外側の該支柱11と縦杆17との間で内外に分割されており、第一形成部33a、第二形成部33b、及び第三形成33cにより構成される。ここで、第一形成部33aと第二形成部33bとが欄干52の内側にあり、第三形成部33cが欄干52の外側にある。   The left and right wall forming portions 33 cover the left and right openings from the upper beams 12b and 18b arranged in a straight line to the lower ends of the support column 11 and the vertical rod 17, respectively. Further, as a characteristic feature, the wall forming portion 33 is divided into the inside and outside between the adjacent inner and outer columns 11, and is divided into the inside and the outside between the outer columns 11 and the vertical rods 17. It is comprised by the 1st formation part 33a, the 2nd formation part 33b, and the 3rd formation 33c. Here, the first forming portion 33 a and the second forming portion 33 b are inside the balustrade 52, and the third forming portion 33 c is outside the balustrade 52.

そして、第一形成部33aと第二形成部33bとには、互いに隣り合う側縁に、着脱可能な面ファスナー部(図示せず)が各々設けられており、該面ファスナー部を接着することにより、第一形成部33aと第二形成部33bとを一枚の長方形状とすることができる。さらに、この面ファスナー部の上部を接着し、下部を非接着とすることにより、第一形成部33aと第二形成部33bとの間にスリットS1が形成された状態とできる。同様に、第二形成部33bと第三形成部33cとにも、互いに隣合う側縁に着脱可能な面ファスナー部(図示せず)が各々設けられており、該面ファスナー部を接着することにより、第二形成部33bと第三形成部33cとを一枚の長方形状とすることができる。さらに、この面ファスナー部の上部を接着し、下部を非接着とすることにより、第二形成部33bと第三形成部33cとの間にスリットS2が形成された状態とできる。なお、これら内外二つの面ファスナー部を接着した状態で、一枚状の壁形成部33が構成される。   The first forming portion 33a and the second forming portion 33b are respectively provided with detachable hook-and-loop fastener portions (not shown) on the side edges adjacent to each other, and the hook-and-loop fastener portions are bonded together. Thereby, the 1st formation part 33a and the 2nd formation part 33b can be made into one rectangular shape. Further, by bonding the upper portion of the hook-and-loop fastener portion and not bonding the lower portion, a slit S1 can be formed between the first forming portion 33a and the second forming portion 33b. Similarly, the second forming portion 33b and the third forming portion 33c are each provided with a detachable hook-and-loop fastener portion (not shown) on the side edges adjacent to each other, and the hook-and-loop fastener portion is bonded. Thereby, the 2nd formation part 33b and the 3rd formation part 33c can be made into one rectangular shape. Furthermore, the upper part of this hook_and_loop | surface fastener part is adhere | attached, and the lower part is made non-adhesive, and it can be in the state by which the slit S2 was formed between the 2nd formation part 33b and the 3rd formation part 33c. In addition, the sheet-like wall formation part 33 is comprised in the state which adhere | attached these inner and outer two surface fastener parts.

さらに、シート3は、左右の壁形成部33,33の内側縁と外側縁とに、装着用ひも体(図示せず)が、所定間隔を置いて複数取り付けられている。なお、延成部35の側縁にも、壁形成部33に結びつけることが可能な保持用ひも体が取り付けられていてもよい。なお、この保持用ひも体が、延成部35を、第二作業空域8を下方から覆う状態で保持する保持手段である。同様に、延成部36も、壁形成部33に保持用ひも体を介して結着されてもよい。   Furthermore, the seat 3 has a plurality of attachment straps (not shown) attached to the inner and outer edges of the left and right wall forming portions 33, 33 at predetermined intervals. A holding string that can be tied to the wall forming portion 33 may also be attached to the side edge of the extending portion 35. This holding string body is a holding means that holds the extending portion 35 in a state of covering the second working airspace 8 from below. Similarly, the extending part 36 may be bound to the wall forming part 33 via a holding string.

そして、本体フレーム2とシート3とは、該本体フレーム2を覆うように該シート3が取り付けられ、上記の装着用ひもを支柱11及び縦杆17等に結びつけることにより一体化される。こうして、図3のように、シート3の内部に作業用ルーム6が画成される。   Then, the main body frame 2 and the seat 3 are integrated by attaching the seat 3 so as to cover the main body frame 2 and tying the above-described mounting straps to the column 11 and the vertical rod 17 and the like. Thus, the work room 6 is defined inside the seat 3 as shown in FIG.

ここで、作業用ルーム6は、図1〜3のように、シート3の天井形成部31、内壁形成部32、壁形成部33,33、及び外壁形成部34に囲まれて外部から隔てられる。さらに、内壁形成部32の延成部36は、支柱11下で引き込まれて通路55上に敷かれる。そして、内側垂下部37の下部37aは、第二フレーム5の係合片47に上載して内側に差し入れられ、さらに、通路55上に敷かれる。ここで、内壁形成部32の延成部36と内側垂下部37の下部37aとが通路55上で重なることで、作業用ルーム6内で、通路55上を覆う。また、外壁形成部34の延成部35は、上記の保持手段Kによって歩道橋51の側縁部に一時的に取り付けられる。これにより、延成部35により第二フレーム5の下方開口部を閉鎖できる(図3参照)。   Here, as shown in FIGS. 1 to 3, the work room 6 is surrounded by the ceiling forming portion 31, the inner wall forming portion 32, the wall forming portions 33 and 33, and the outer wall forming portion 34 of the seat 3 and separated from the outside. . Further, the extending portion 36 of the inner wall forming portion 32 is drawn under the column 11 and laid on the passage 55. The lower portion 37 a of the inner hanging portion 37 is placed on the engaging piece 47 of the second frame 5 and inserted inside, and further laid on the passage 55. Here, the extension part 36 of the inner wall forming part 32 and the lower part 37 a of the inner hanging part 37 overlap on the passage 55, thereby covering the passage 55 in the work room 6. Further, the extending portion 35 of the outer wall forming portion 34 is temporarily attached to the side edge portion of the pedestrian bridge 51 by the holding means K described above. Thereby, the downward opening part of the 2nd frame 5 can be closed by the extension part 35 (refer FIG. 3).

次に、本体フレーム2とシート3とからなる作業室形成装置1を用いて歩道橋51の欄干52を保全塗装する欄干保全塗装方法を概説する。   Next, an outline of the balustrade maintenance painting method for carrying out maintenance painting of the balustrade 52 of the pedestrian bridge 51 using the work chamber forming apparatus 1 including the main body frame 2 and the seat 3 will be described.

作業室形成装置1は、図1〜3に示すように、本体フレーム2の第一フレーム4を歩道橋51の通路55上に載置し、且つ第二フレーム5を欄干52の外側に配するようにする。   The working chamber forming apparatus 1 places the first frame 4 of the main body frame 2 on the passage 55 of the pedestrian bridge 51 and places the second frame 5 outside the balustrade 52 as shown in FIGS. To.

ここで、シート3にあって、左右の壁形成部33,33では、第二形成部33bと第三形成部33c間の面ファスナー部(図示せず)を、その下端から欄干52の高さ位置まで非接着状態として、第二形成部33bと第三形成部33cとを部分的に分割しておく(スリットS1を構成する)。そして、このスリットS1を介して欄干52を通す。これにより、シート3により画成された作業用ルーム6の形状を保ちつつ、該作業用ルーム6内に欄干52の一部分を通すことができる。このとき、第一形成部33aと第二形成部33b間の面ファスナー部(図示せず)を接着状態としている。   Here, in the sheet 3, in the left and right wall forming portions 33, 33, a hook-and-loop fastener portion (not shown) between the second forming portion 33 b and the third forming portion 33 c is disposed at the height of the balustrade 52 from the lower end thereof. The second forming portion 33b and the third forming portion 33c are partially divided so as to be in a non-bonded state up to the position (slit S1 is configured). Then, the balustrade 52 is passed through the slit S1. Thereby, a part of the balustrade 52 can be passed through the work room 6 while maintaining the shape of the work room 6 defined by the sheet 3. At this time, the hook-and-loop fastener part (not shown) between the 1st formation part 33a and the 2nd formation part 33b is made into the adhesion | attachment state.

また、シート3にあって、内壁形成部32の延成部36は、内側の左右の支柱11下で引き込まれて通路55上に敷かれる。これで、延成部36は、支柱11のキャスター16にそれぞれ踏まれた状態となる。そして、キャスター16の停止手段でキャスター16にブレーキをかけた状態とする。   Further, in the seat 3, the extending portion 36 of the inner wall forming portion 32 is drawn under the left and right struts 11 on the inner side and laid on the passage 55. Now, the extending part 36 will be in the state where it was stepped on to the caster 16 of the support | pillar 11, respectively. Then, the caster 16 is braked by the stop means of the caster 16.

さらに、シート3にあって、内側垂下部37の下部37aは、第二フレーム5の係合片47に上載して内側に差し入れられ、内壁形成部32の延成部36と部分的に重なるように通路55上に敷かれる。また、外壁形成部34の延成部35を通路55側へ引き込むように折り曲げて、上記の保持手段Kで歩道橋51の側縁部に取り付けることにより第二フレーム5の下方開口部を覆う。これにより、第二フレーム5の下方開口部は、外壁形成部34の延成部35と内側垂下部37の下部37aとにより二重に覆われる。このように、作業用ルーム6は、歩道橋51の通路55上に形成された第一作業空域7と、欄干52の外側に形成された第二作業空域8とから構成され、周囲から閉鎖された空域となる。なお、シート3と歩道橋51との間に隙間が生じた場合には、適宜、隙間を塞ぐ策が講じられることが好ましい。   Further, in the seat 3, the lower portion 37 a of the inner hanging portion 37 is placed on the engagement piece 47 of the second frame 5 and inserted inside, and partially overlaps the extending portion 36 of the inner wall forming portion 32. It is laid on the passage 55. Further, the extending portion 35 of the outer wall forming portion 34 is bent so as to be pulled toward the passage 55 and attached to the side edge portion of the pedestrian bridge 51 by the holding means K to cover the lower opening portion of the second frame 5. As a result, the lower opening of the second frame 5 is doubly covered by the extending portion 35 of the outer wall forming portion 34 and the lower portion 37 a of the inner hanging portion 37. Thus, the work room 6 is composed of the first work air space 7 formed on the passage 55 of the pedestrian bridge 51 and the second work air space 8 formed outside the balustrade 52 and is closed from the periphery. It becomes an airspace. In addition, when a clearance gap arises between the sheet | seat 3 and the pedestrian bridge 51, it is preferable to take the measure for closing a clearance gap suitably.

このように作業室形成装置1を歩道橋51に配置した状態で、この作業用ルーム6外に配した集塵機(図示せず)の吸引用ホースを、該作業用ルーム6内に入れる。そして、作業用ルーム6内に、欄干52の古い塗装やサビ等を取り除く装置や新たに塗装するための装置を入れる。そして、前記集塵機を駆動させつつ、作業用ルーム6内で欄干52の保全塗装を実行する。ここで、上記した壁形成部33の第一形成部33aと第二形成部33b間の面ファスナー部(図示せず)を取り外す(スリットS1を形成する)ことで、作業用ルーム6への前記装置の出し入れ、及び作業者が該作業用ルーム6へ出入りできる。また、第一形成部33aと第二形成部33b間の面ファスナー部(図示せず)の一部を非接着として、前記した吸引用ホースを作業用ルーム6内に引き入れることができる。これにより、作業用ルーム6の閉鎖状態を保つことができる。   With the work chamber forming apparatus 1 thus arranged on the pedestrian bridge 51, a suction hose of a dust collector (not shown) arranged outside the work room 6 is put into the work room 6. Then, a device for removing old paint, rust and the like on the balustrade 52 and a device for newly painting are placed in the work room 6. And the maintenance coating of the balustrade 52 is performed in the work room 6 while driving the dust collector. Here, by removing a hook-and-loop fastener portion (not shown) between the first forming portion 33a and the second forming portion 33b of the wall forming portion 33 described above (to form the slit S1), the above-mentioned to the work room 6 is performed. The apparatus can be taken in and out, and an operator can go in and out of the work room 6. In addition, the suction hose described above can be drawn into the working room 6 with a part of the hook-and-loop fastener portion (not shown) between the first forming portion 33a and the second forming portion 33b being not bonded. Thereby, the closed state of the work room 6 can be maintained.

この保全塗装の実行中では、粉塵や噴霧塵などが発生するが、作業用ルーム6内から外部に飛び散ることを防止できると共に、前記吸引用ホースを介して集塵機により吸引される。そのため、粉塵や噴霧塵の飛散を防止しつつ、歩道橋51の通路55が粉塵や噴霧塵で汚れてしまうことも抑制できる。このように作業室形成装置1を所定位置に配置して保全塗装を実行することが、本発明にかかる作業工程である。   During the execution of the maintenance coating, dust, spray dust, and the like are generated, but the dust can be prevented from scattering from the work room 6 to the outside and sucked by the dust collector through the suction hose. Therefore, it is possible to prevent the passage 55 of the pedestrian bridge 51 from being contaminated with dust or spray dust while preventing dust and spray dust from scattering. In this way, the work process according to the present invention is to place the work chamber forming apparatus 1 at a predetermined position and execute the maintenance coating.

作業室形成装置1は、その作業用ルーム6内で、欄干52の一部分を保全塗装終了すると、キャスター16の停止手段を解除して該キャスター16を転動可能とする。さらに、外壁形成部34の延成部35を歩道橋51の側縁部に取り付けた保持手段Kを解除する。この後、作業室形成装置1を、欄干52に沿って移動させ、欄干52の、次に保全塗装する部分を、作業用ルーム6内に位置させる。そして、上述したように、キャスター16の停止手段でブレーキをかけ、外壁形成部34の延成部35を保持手段で歩道橋51の側縁部に取り付ける。こうして作業室形成装置1を、次に保全塗装を実施する位置に配置する。このように作業室形成装置1を移動させることが、本発明にかかる移動工程である。   In the work room 6, the work chamber forming apparatus 1 releases the stop means of the caster 16 and enables the caster 16 to roll when the maintenance painting of a part of the balustrade 52 is completed in the work room 6. Furthermore, the holding means K which attached the extension part 35 of the outer wall formation part 34 to the side edge part of the footbridge 51 is cancelled | released. Thereafter, the work chamber forming apparatus 1 is moved along the balustrade 52, and the portion of the balustrade 52 to be subjected to maintenance coating next is positioned in the work room 6. And as above-mentioned, it brakes with the stop means of the caster 16, and the extension part 35 of the outer wall formation part 34 is attached to the side edge part of the footbridge 51 with a holding means. In this way, the work chamber forming apparatus 1 is disposed at a position where maintenance coating is performed next. Moving the working chamber forming apparatus 1 in this way is a moving process according to the present invention.

このように欄干52に沿って作業室形成装置1を順次移動させる移動工程と、移動した位置で保全塗装を実施する作業工程とを交互に繰り返すことによって、該欄干52全体を保全塗装できる。さらに、反対側の欄干52に作業室形成装置1を移すことによって、該欄干52を同様に保全塗装できる。   In this way, the entire balustrade 52 can be maintenance-painted by alternately repeating the movement process of sequentially moving the work chamber forming apparatus 1 along the balustrade 52 and the operation process of performing the maintenance coating at the moved position. Furthermore, the balustrade 52 can be similarly maintenance-painted by moving the working chamber forming apparatus 1 to the opposite balustrade 52.

ここで、作業室形成装置1を配置した状態で、歩道橋51の通路55は、該作業室形成装置1を配していない反対側の欄干52寄りが開いており、歩行者を通行させることが可能である(図2,3参照)。したがって、作業室形成装置1を用いることで、歩道橋51を通行止めせずに欄干52の保全塗装を実施できる。   Here, in the state where the work room forming apparatus 1 is arranged, the passage 55 of the pedestrian bridge 51 is open near the railing 52 on the opposite side where the work room forming apparatus 1 is not arranged, and a pedestrian can be allowed to pass. It is possible (see FIGS. 2 and 3). Therefore, by using the working chamber forming apparatus 1, it is possible to carry out maintenance painting of the balustrade 52 without blocking the pedestrian bridge 51.

上述した本実施例の作業室形成装置1は、本体フレーム2からシート3を取り外し、該本体フレーム2を、支柱11、上梁12a,12b、下梁13a,13b、縦杆17、上梁18a,18b、及び中梁19に分解可能である。そのため、これら各部材を歩道橋51上まで各々運搬し、該歩道橋51上で本体フレーム2を組み立ててシートを取り付けることによって、作業室形成装置1を該歩道橋51上に配置できる。さらに、欄杆52の保全塗装作業が終了すると、前記のように分解して運搬できるため、該作業の後片付けも容易に行い得る。そして、前記した分解した状態で保管でき、上述したように次の現場まで運搬して使用できる。   The working chamber forming apparatus 1 of the present embodiment described above removes the seat 3 from the main body frame 2, and the main body frame 2 is attached to the column 11, the upper beams 12a and 12b, the lower beams 13a and 13b, the vertical rod 17 and the upper beam 18a. , 18b and the middle beam 19 can be disassembled. Therefore, the work room forming apparatus 1 can be arranged on the pedestrian bridge 51 by transporting these members onto the pedestrian bridge 51, assembling the main body frame 2 on the pedestrian bridge 51, and attaching a seat. Furthermore, when the maintenance painting work for the balustrade 52 is completed, it can be disassembled and transported as described above, so that the work can be easily cleaned up. And it can be stored in the disassembled state described above, and can be transported to the next site and used as described above.

このように、作業室形成装置1は、通路55が比較的狭い歩道橋51上まで、容易に運搬でき且つ組み立てることができる。なお、本体フレーム2は、比較的コンパクトな形状であり且つ軽量であることから、前記のように分解しなくとも、容易に運搬することができる。そして、分解せずに運搬すれば、組み立て作業を要しない。このように、作業室形成装置1は、容易に運搬できることから、作業準備や後片付けに要する負担を軽減できる。これにより、本実施例の構成によれば、欄杆52の保全塗装に要する工期を短くすることができる。   Thus, the work chamber forming apparatus 1 can be easily transported and assembled to the pedestrian bridge 51 where the passage 55 is relatively narrow. Since the main body frame 2 has a relatively compact shape and is lightweight, it can be easily transported without being disassembled as described above. And if it is transported without being disassembled, no assembly work is required. Thus, since the work chamber forming apparatus 1 can be easily transported, it is possible to reduce the burden required for work preparation and post-cleaning. Thereby, according to the structure of a present Example, the construction period required for the maintenance painting of the balustrade 52 can be shortened.

さらに、本体フレーム2を構成する各支柱11は、上述したように高さを変えることが可能である。本実施例の作業室形成装置1は、欄干52に沿って移動させることで保全塗装するものであることから、高さの異なる部位を備えた欄干52を保全塗装する場合にあっても、各支柱11の高さを欄干52の高さに応じて変えることによって作業用ルーム6内の作業スペースを十分に確保することができる。これにより、欄干52の、高さの異なる部位を保全塗装する場合にも、安定して保全塗装作業を実施できる。   Further, the heights of the columns 11 constituting the main body frame 2 can be changed as described above. Since the working chamber forming apparatus 1 according to the present embodiment performs maintenance coating by moving along the balustrade 52, each of the work chamber forming apparatuses 1 can perform maintenance coating on the balustrade 52 having different heights. By changing the height of the column 11 according to the height of the balustrade 52, a sufficient work space in the work room 6 can be secured. Thus, even when the parts of the balustrade 52 having different heights are subjected to maintenance coating, the maintenance coating work can be stably performed.

本発明は、上述した実施例以外にも、適宜設計変更可能である。例えば、第二フレームにも、第一フレームと同じ下梁を設けるようにしても良い。また、シートは、本体フレームに被せるように覆うのではなく、本体フレームの内部に配するようにしてもよい。また、本体フレームやシートなどの形状寸法は、適宜変更できる。また、本実施例では、本体フレーム2を分解可能な構成としたが、分解不能な構成とすることもできる。例え分解不能な構成としても、コンパクトな形状であり且つ軽量であることから、運搬や設置が容易であり、作業準備に要する負担を軽減できる。また、本体フレームを折り畳み可能な構成とすることも可能であり、この構成によれば、前記した運搬や設置作業を軽減可能である。また、本発明の作業室形成装置は、歩道橋の欄干以外にも、公園の通路に設けられた手摺りやマンション等のバルコニーの手すり等にも利用可能である。   The design of the present invention can be changed as appropriate in addition to the embodiments described above. For example, the second frame may be provided with the same lower beam as the first frame. In addition, the seat may be disposed inside the main body frame instead of covering the main body frame. Further, the shape and dimensions of the main body frame and the seat can be changed as appropriate. Further, in the present embodiment, the main body frame 2 is configured to be disassembled, but may be configured to be incapable of disassembly. Even if it cannot be disassembled, it has a compact shape and is lightweight, so that it can be easily transported and installed, and the burden required for work preparation can be reduced. Moreover, it is also possible to make it the structure which can fold a main body frame, According to this structure, the above-mentioned conveyance and installation work can be reduced. Moreover, the working room forming apparatus of the present invention can be used not only for a railing of a pedestrian bridge but also for a handrail provided in a passage of a park, a handrail of a balcony of an apartment, or the like.

さらにまた、第一フレームが、四隅の支柱に加え、隣合う該支柱間にさらに支柱を配設することもできる。ここで、加える支柱は、全ての支柱間に配設してもよいし、一部の支柱間にのみ配設するようにしてもよい。同様に、第二フレームの左右の縦杆の間に、さらに縦杆を配設することもできる。このように支柱や縦杆を加えることによって、本体フレームの剛性を向上できることから、比較的強い風によりシートが煽られてしまうことを抑制したり、シートがばたつくことを抑制したりでき、作業用ルーム6を安定して保持する効果に優れる。   Furthermore, in addition to the four corner posts, the first frame can also be provided with further posts between the adjacent posts. Here, the added struts may be disposed between all the struts, or may be disposed only between some of the struts. Similarly, a vertical hook can be further arranged between the left and right vertical hooks of the second frame. By adding support posts and vertical rods in this way, the rigidity of the main body frame can be improved, so that the sheet can be prevented from being beaten by a relatively strong wind, or the sheet can be prevented from flapping. The effect of stably holding the room 6 is excellent.

1 作業室形成装置
2 本体フレーム
3 シート
4 第一フレーム
5 第二フレーム
6 作業用ルーム
7 第一作業空域
8 第二作業空域
11 支柱
16 キャスター
17 縦杆
31 天井形成部
35 延成部(第二作業空域用延成部)
37 内側垂下部
45 横杆
47 係合片
52 欄干
55 通路
DESCRIPTION OF SYMBOLS 1 Work chamber formation apparatus 2 Main body frame 3 Sheet | seat 4 1st frame 5 2nd frame 6 Work room 7 1st work airspace 8 2nd work airspace 11 Support | pillar 16 Caster 17 Shaft 31 Ceiling formation part 35 Extension part (2nd Working air space extension)
37 Inner drooping portion 45 Reeds 47 Engagement piece 52 Parapet 55 Passage

Claims (6)

橋の通路の側縁に沿って立設された欄干を保全塗装する作業に用いられ、該欄干の長手方向の一部分を覆って外部から隔たれた作業用ルームを形成するものであって、
前記通路上に載置される第一フレームと、該第一フレームの片側に設けられ、該欄干の外側に配される第二フレームとを備えた本体フレームと、
該本体フレームに取り付けられ、該第一フレーム内に生ずる通路上の第一作業空域と第二フレーム内に生ずる欄干の外側の第二作業空域とが連続する前記作業用ルームを形成するシートと
を備え、
さらに、前記シートには、前記欄干を通すための左右一対のスリットが各々設けられ、
また、前記第一フレームの下端部にはキャスターが配設されていることを特徴とする欄干塗装用の作業室形成装置。
It is used for maintenance painting of balustrades erected along the side edges of the bridge passage, and forms a working room that covers a part of the balustrade in the longitudinal direction and is separated from the outside,
A main body frame comprising: a first frame placed on the passage; and a second frame provided on one side of the first frame and disposed outside the balustrade;
A sheet which is attached to the main body frame and forms the working room in which a first working air space on a passage generated in the first frame and a second working air space outside the balustrade formed in the second frame are continuous; Prepared,
Further, the sheet is provided with a pair of left and right slits for passing the balustrade,
A work chamber forming apparatus for balustrade painting, wherein a caster is disposed at a lower end portion of the first frame.
前記シートは、
作業用ルームの天井を構成する天井形成部と、
該作業用ルームの周囲の壁を構成する側壁形成部と、
該側壁形成部の下端から延成され、第二作業空域を下方から覆うための第二作業空域用延成部と、
作業用ルーム内で該第二作業空域用延成部に並ぶように該天井形成部から下方へ垂下され、その下部が欄干の外側から通路上に差し入れられる第二作業空域用の内側垂下部と
を備え、
さらに、前記第二作業空域用延成部を、第二作業空域を下方から覆う状態で保持する保持手段を備えている請求項1に記載の欄干塗装用の作業室形成装置。
The sheet is
A ceiling forming part constituting the ceiling of the work room;
A side wall forming portion constituting a wall around the work room;
Extending from the lower end of the side wall forming portion, and a second working air region extending portion for covering the second working air region from below,
An inner hanging portion for the second working air space, which is suspended downward from the ceiling forming portion so as to line up with the second working air space extending portion in the working room, and the lower portion is inserted into the passage from the outside of the balustrade; With
The work chamber forming apparatus for balustrade painting according to claim 1, further comprising holding means for holding the extension part for the second work air region in a state of covering the second work air region from below.
第一フレームは、四隅に各々設けられた四本の支柱を備えた略直方体状の骨組み構造からなり、
第二フレームは、該第一フレームの外側で、前記第一フレームにおける隣合う二本の支柱と各々略平行に配される二本の縦杆を備えた骨組み構造からなり、
さらに、前記第二フレームの二本の縦杆に差し渡される上下動自在な横干と、該横干から通路側へ突出するように設けられ、欄干又は該欄干が立設された橋の台座部に係脱可能に係合される複数の係合片とを備えている請求項1又は請求項2に記載の欄干塗装用の作業室形成装置。
The first frame consists of a substantially rectangular parallelepiped frame structure with four struts provided at the four corners,
The second frame is composed of a skeleton structure having two vertical rods arranged substantially parallel to the two adjacent struts in the first frame outside the first frame,
Further, a horizontal slat that is vertically movable across the two vertical fences of the second frame, and a rail pedestal or a bridge pedestal on which the railing is erected The work chamber forming apparatus for balustrade painting according to claim 1 or 2, further comprising a plurality of engaging pieces detachably engaged with the part.
少なくとも第一フレームの各支柱が、その高さを変更可能な高さ調整機構を備えていることを特徴とする請求項3の記載に欄干塗装用の作業室形成装置。   4. A work chamber forming apparatus for balustrade painting according to claim 3, wherein at least each column of the first frame is provided with a height adjusting mechanism capable of changing the height thereof. 前記請求項2に記載の欄干塗装用の作業室形成装置に用いられるシートであって、
前記天井形成部と、前記側壁形成部と、前記第二作業空域用延成部と、前記第二作業空域用の内側垂下部とを備え、本体フレームに取り付けられて作業用ルームを形成するものであることを特徴とするシート。
A sheet used in the work chamber forming apparatus for balustrade painting according to claim 2,
The ceiling forming portion, the side wall forming portion, the second working air space extending portion, and the inner working hanging portion for the second working air space are attached to a main body frame to form a working room. A sheet characterized by being.
請求項1乃至請求項4のいずれか1項に記載の欄干塗装用の作業室形成装置を用いて橋の欄干を保全塗装する欄干保全塗装方法であって、
該作業室形成装置で該欄干の長手方向の一部分を覆って、その作業用ルーム内で該欄干の一部分を保全塗装する作業工程と、
該作業工程で保全塗装した後、保全塗装前の欄干の一部分を覆うように、作業室形成装置を欄干の長手方向に沿って移動させる移動工程と
を含むことを特徴とする欄干保全塗装方法。
A balustrade maintenance painting method for carrying out maintenance painting of a railing of a bridge using the work chamber forming device for balustrade painting according to any one of claims 1 to 4,
A work process of covering a part of the balustrade in the longitudinal direction with the working chamber forming device and maintaining and painting a part of the balustrade in the work room;
A balustrade maintenance coating method comprising: a moving step of moving the work chamber forming device along a longitudinal direction of the balustrade so as to cover a part of the balustrade before the maintenance coating after the maintenance coating is performed in the operation process.
JP2015105307A 2015-05-25 2015-05-25 Work room formation device for coating balustrade, sheet used therewith, and preservative coating method for balustrade using the same Pending JP2016217060A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015105307A JP2016217060A (en) 2015-05-25 2015-05-25 Work room formation device for coating balustrade, sheet used therewith, and preservative coating method for balustrade using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015105307A JP2016217060A (en) 2015-05-25 2015-05-25 Work room formation device for coating balustrade, sheet used therewith, and preservative coating method for balustrade using the same

Publications (1)

Publication Number Publication Date
JP2016217060A true JP2016217060A (en) 2016-12-22

Family

ID=57578135

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015105307A Pending JP2016217060A (en) 2015-05-25 2015-05-25 Work room formation device for coating balustrade, sheet used therewith, and preservative coating method for balustrade using the same

Country Status (1)

Country Link
JP (1) JP2016217060A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080117A (en) * 2019-06-03 2019-08-02 倡创(上海)咨询管理事务所 Portable simplified concrete barrier formwork vehicle and preparation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080117A (en) * 2019-06-03 2019-08-02 倡创(上海)咨询管理事务所 Portable simplified concrete barrier formwork vehicle and preparation method thereof

Similar Documents

Publication Publication Date Title
JP2015055131A (en) Cure method of concrete bridge girder
JP6786070B2 (en) Permanent scaffolding installation method for bridge inspection
CN110748139B (en) Hanging basket support system
JP2013019126A (en) Scaffolding/protective unit and connection device of the same
JP2013256770A (en) Suspension frame for suspended scaffolding
KR20200126688A (en) Safety device for inter-layer slab
JP2007046356A (en) Scaffold in bridge structure and its assembling method
JP2016217060A (en) Work room formation device for coating balustrade, sheet used therewith, and preservative coating method for balustrade using the same
CN211341686U (en) Hanging basket support system
JP5773469B1 (en) Suspended scaffolding
KR200467252Y1 (en) cage for exterior works of building
JP2015048634A (en) Apparatus and method for forming intermediate working floor
KR101272887B1 (en) mounting bracket for prevention-net and prevention-plate of falling object.
JP2004232366A (en) Suspended scaffolding
JP6659200B2 (en) Large tent
JPH11190131A (en) Spraying fire resistant covering construction method and device
KR101219633B1 (en) Fixture for stationary gondola
JPH0960290A (en) Mobile suspended scaffold
CN106382001A (en) Parapet wall mold supporting frame capable of being moved and revolved
JP7122080B2 (en) temporary scaffolding
JP2536802Y2 (en) Construction rain shelter
JP6793960B2 (en) Large tent
JP2009203739A (en) Building and its construction method
JP2000213175A (en) All weather type outdoor scaffolding and method for spreading sheet thereof
JPH0312909Y2 (en)