CN110056722A - A kind of drainage pipeline and its construction method - Google Patents

A kind of drainage pipeline and its construction method Download PDF

Info

Publication number
CN110056722A
CN110056722A CN201910345100.0A CN201910345100A CN110056722A CN 110056722 A CN110056722 A CN 110056722A CN 201910345100 A CN201910345100 A CN 201910345100A CN 110056722 A CN110056722 A CN 110056722A
Authority
CN
China
Prior art keywords
annular groove
bellmouth
pipeline
socket
pipeline body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910345100.0A
Other languages
Chinese (zh)
Inventor
黄卫东
龚晓林
涂继红
吴方毅
张松涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN AEROSPACE CONSTRUCTION ENGINEERING Co Ltd
Original Assignee
SICHUAN AEROSPACE CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN AEROSPACE CONSTRUCTION ENGINEERING Co Ltd filed Critical SICHUAN AEROSPACE CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201910345100.0A priority Critical patent/CN110056722A/en
Publication of CN110056722A publication Critical patent/CN110056722A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • F16L1/036Laying or reclaiming pipes on land, e.g. above the ground in the ground the pipes being composed of sections of short length
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L13/00Non-disconnectible pipe-joints, e.g. soldered, adhesive or caulked joints
    • F16L13/10Adhesive or cemented joints
    • F16L13/103Adhesive joints
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L13/00Non-disconnectible pipe-joints, e.g. soldered, adhesive or caulked joints
    • F16L13/10Adhesive or cemented joints
    • F16L13/11Adhesive or cemented joints using materials which fill the space between parts of a joint before hardening
    • F16L13/116Adhesive or cemented joints using materials which fill the space between parts of a joint before hardening for socket pipes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Sewage (AREA)

Abstract

The present invention relates to a kind of drainage pipeline and its construction methods, including pipeline body, described pipeline body one end is provided with socket, the pipeline body other end is provided with bellmouth, the bellmouth can be mating with the socket on adjacent channel ontology, the receptacle wall is provided with the first annular groove around socket, the bellmouth inner wall surrounding bellmouth is provided with the second annular groove, it does not need worker and pierces inside pipeline to operate in sealing, the entrance outside pipeline body is only needed to inject adhesive, it is simple to operate.

Description

A kind of drainage pipeline and its construction method
Technical field
The present invention relates to the technical fields of urban architecture, more particularly, to a kind of drainage pipeline and its construction method.
Background technique
Urban underground water drainage pipe road is intricate, with the frequent draining use and aging of drainage pipeline, drainage pipeline Leakage problems are frequent occurrence.Various economic losses caused by either after valuable water resource waste or drainage pipeline leakage, So that drainage pipeline leakage problems must cause enough attention.
The Chinese patent of Publication No. CN104895174A discloses a kind of heavy caliber rain sewage conduct assembled component knot The construction method of structure.The construction method mainly includes the following steps: that preparation of construction, tube seat excavation, flat base, cement solidification layer are applied Work, the lifting of pipeline pedestal, Pipe installing, slip casting closing body construction, concrete backfill construction and gravel backfill construction.
Need to be tightly connected between adjacent channel in Pipe installing, existing way be usually connect two pipelines it Between filled by mortar so that being tightly connected between adjacent channel, still, sealed by mortar between adjacent channel When, it is very inconvenient when needing someone to pierce in pipeline and smoothed out to interface, therefore constructing.
Summary of the invention
The first object of the present invention is to provide a kind of drainage pipeline have easy for construction when being tightly connected adjacent channel Advantage.
Above-mentioned first technical purpose of the invention has the technical scheme that a kind of drainage pipeline, packet Pipeline body is included, described pipeline body one end is provided with socket, and the pipeline body other end is provided with bellmouth, and the bellmouth can be with phase Socket on adjacent pipeline body is mating, and the receptacle wall is provided with the first annular groove, the bellmouth inner wall ring around socket Bellmouth is provided with the second annular groove;
When in the bellmouth of the socket insertion adjacent channel ontology, first annular groove and the second annular groove are mutually butted simultaneously shape just At seal cavity;
The import that will be connected on the outside of the second annular groove and bellmouth is provided on the bellmouth.
Through the above technical solutions, in use, more pipeline bodies are docking together, when docking, it is inserted into bellmouth The socket end of adjacent channel ontology, the first annular groove will be mutually butted with the second annular groove at this time, pass through import later to the first annular groove With inject adhesive in the second annular groove, when injecting adhesive, the air in the first annular groove and the second annular groove will be from the first ring It is discharged at the splicing seams of slot and the second annular groove, finally makes adhesive full of in the first annular groove and the second annular groove, to be bonded dose solid Will be so that by excellent sealing between bellmouth and socket after change, therefore in sealing do not need worker and pierce inside pipeline to grasp Make, it is only necessary to which the entrance outside pipeline body injects adhesive, simple to operate.
Preferably, the import volume is multiple and being circumferentially distributed on bellmouth along bellmouth.
Through the above technical solutions, the case where avoiding adhesive from being cured when flowing the long period in seal cavity, So that adhesive can respectively enter in seal cavity from multiple imports, the adhesive that multiple imports enter at this time will be filled with seal chamber Body, the length that the adhesive that each import enters is flowed is smaller, therefore is less prone to adhesive flow and occurs in the process admittedly The case where change.
Preferably, the bellmouth is provided with close with the conjunction of the socket end face paste of adjacent channel ontology with pipeline body junction Cover is provided with sealing ring on the sealing surface.
Through the above technical solutions, adhesive is avoided to pass through the gap flow ipe between bellmouth and socket to a certain extent Body interior, when in socket end insertion bellmouth, socket end will be with sealing ring tight against pouring into the intracorporal bonding of seal chamber at this time Agent enters in the gap not easily passed through between sealing ring and bellmouth or sealing ring and socket inside pipeline body, so that pipeline body Inside keeps smooth, avoids impurity in pipeline body building up inside to a certain extent.
Preferably, the outlet that will be connected on the outside of the second annular groove and bellmouth is provided on the bellmouth.
Through the above technical solutions, may insure in seal cavity to be filled by adhesive it is full, when injecting adhesive from import When, adhesive will be gradually filled with seal cavity, and extra adhesive will be pushed to flow out after being completely filled with seal cavity from outlet, Intracorporal bubble of seal chamber etc. can be made to be extruded discharge when pushing extra adhesive from outlet outflow, so that holding Better tightness between mouth and socket.
Preferably, the opening of first annular groove and the second annular groove is provided with several baffles, multiple baffle edges The first annular groove or the second annular groove length direction it is uniformly distributed, between the baffle and the first annular groove bottom or with the second annular groove bottom Between there are channels.
Through the above technical solutions, baffle will be located inside cured adhesive, so that cured after adhesive curing Bonding strength between adhesive and bellmouth and socket is higher so that bellmouth connect with socket it is even closer.
Preferably, first annular groove or the second annular groove are gradually increased from outlet side to the cross-sectional area far from outlet side.
It is being sealed through the above technical solutions, adhesive is allowed to play increase adhesive when flowing into seal cavity The purpose of inside cavity pressure allows adhesive to be not likely to produce bubble in flowing, while being not easy bonding after adhesive curing Agent producing bubbles inside.
Preferably, first annular groove or the second annular groove inner wall are equipped with mesh plate, front and the back of the mesh plate Face is provided with several interconnecting pieces, and the interconnecting piece of the mesh back is embedded in the first annular groove or the second annular groove inner wall.
Through the above technical solutions, increasing adhesive and the first annular groove and the second annular groove bonding force.
The second object of the present invention is to provide a kind of construction method of drainage pipeline, when having sealed connection adjacent channel Advantage easy for construction.
Above-mentioned second technical purpose of the invention has the technical scheme that a kind of applying for drainage pipeline Work method, comprising the following steps:
Step 1: surveying setting-out, tissue surveying party carry out repetition measurement by the measurement control point that designing institute provides, and establish after review is errorless Engineering surveying control network carries out the measurement that a face combines to engineering and controls, and setting out survey, makes pipeline middle line and well location is set, And control point of the level datum points as entire engineering is made, measurement is intended to be closed every time, strict control closure error;
Step 2: channel excavation determines and excavates region soil property, and chooses the slope gradient according to soil property situation, and according to suitable The gradient is excavated;
Step 3: groove precipitation respectively excavates a gutter in the channel bottom two sides that step 2 is excavated out, and sets every one section Plash is set, the bright row that draws water is carried out using water pump;
Step 4: pipeline foundation is excavated according to bottom of the design requirement to basis, modifies trench bottom, removes mud and broken Soil is backfilled to pipe substrate absolute altitude with gravel sand, and compaction in layers makes reinforced concrete pipeline foundation by reinforced concrete floor, to After the hardening of reinforced concrete pipeline surface of base, pipe centerline is popped up in its end face;
Step 5: pipeline body lifting is entered in the groove excavated using truck crane, and makes pipeline body by Pipe installing Socket end insertion adjacent channel ontology bellmouth in, inject the rubber of molten condition into seal cavity from import later, directly Until when the rubber of molten condition is overflowed from outlet end;
Step 6: check that well construction, inspection shaft select concrete drainage inspection well or prefabricated assembling type reinforced concrete draining inspection Cha Jing;
Step 7: closed-water test carries out no pressure closed-water test to the pipeline body laid, and downward from upstream in test Trip carries out segmentation progress, and test port application brick wall is closed, and closing should be tight, and the leaching pipeline body time is small greater than 24 after filling water When;
Step 8: pipeline backfill: banketing and horizontal slice paving answered to fill out, compaction in layers, and should be layered filling's dry density after measurement compacting, After its compacting factor and compacting range meet design requirement on inspection, upper layer can be just filled.
Adjacent pipeline body sealing is docking together through the above technical solutions, can facilitate, in docking adjacent channel Worker is not needed when ontology to climb into inside pipeline, and it is more convenient to be laid with pipeline.
Preferably, if soil property is that silty clay belongs to three classes soil side slope by 1:0.67 slope, if soil property is to fill out in step 2 Penus is built in one, two class soil side slopes by 1:0.75 slope, if soil property is that mud side slope presses 1:1 slope.
Through the above technical solutions, the groove excavated is made to be not likely to produce collapsing, security performance is higher.
In conclusion the present invention having the beneficial effect that in contrast to the prior art
1, it does not need worker when sealing adjacent channel ontology and pierces inside pipeline to operate, it is only necessary to outside pipeline body Entrance injects adhesive, simple to operate;
2, the adhesive strength of adhesive and the first annular groove and the second annular groove is high, is not easy and the first annular groove or second using adhesive For annular groove there is a situation where being detached from, sealing effect is more preferable.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is the first structure diagram of embodiment one;
Fig. 2 is the cross-sectional view at bellmouth and socket cooperation, the position of main prominent seal cavity;
Fig. 3 is the second structural schematic diagram of embodiment one, the structure of main prominent first annular groove.
Appended drawing reference: 1, pipeline body;2, socket;3, bellmouth;4, the first annular groove;5, the second annular groove;6, seal cavity;7, Import;8, sealing surface;9, sealing ring;10, it exports;11, baffle;12, channel;13, mesh plate;14, interconnecting piece.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
Embodiment one:
As shown in Figure 1, 2, a kind of drainage pipeline, including pipeline body 1,1 one end of pipeline body are provided with socket 2, pipeline body 1 The other end is provided with bellmouth 3, and bellmouth 3 can be mating with the socket 2 on adjacent channel ontology 1, and 2 outer wall of socket is around socket 2 It is provided with the first annular groove 4,3 inner wall surrounding bellmouth 3 of bellmouth is provided with the second annular groove 5;When socket 2 is inserted into adjacent channel ontology 1 When in bellmouth 3, the first annular groove 4 and the second annular groove 5 are mutually butted just and form seal cavity 6;Import is provided on bellmouth 3 7, import 7 will be connected on the outside of second annular groove 5 and bellmouth 3.
Wherein, 7 quantity of import is multiple and being circumferentially distributed on bellmouth 3 along bellmouth 3, while being arranged on bellmouth 3 There is the outlet 10 that will be connected on the outside of the second annular groove 5 and bellmouth 3, when injecting adhesive from import 7, adhesive will be gradually filled with close Cavity 6 is sealed, extra adhesive will be pushed to flow out from outlet 10 after being completely filled with seal cavity 6, is pushing extra bonding Agent can make the bubble in seal cavity 6 etc. be extruded discharge when flowing out from outlet 10 so that bellmouth 3 and socket 2 it Between better tightness.
In order to avoid the adhesive in injection seal cavity 6 enters inside pipeline body 1, connect in bellmouth 3 and pipeline body 1 The place of connecing is provided with the sealing surface 8 being bonded with 2 end face of socket of adjacent channel ontology 1, meanwhile, sealing is provided on sealing surface 8 Circle 9, at this point, 2 end of socket will be with sealing ring 9 tight against being poured into seal cavity 6 at this time when in 2 end of socket insertion bellmouth 3 Adhesive the gap not easily passed through between sealing ring 9 and bellmouth 3 or sealing ring 9 and socket 2 is entered inside pipeline body 1, So that keeping smooth inside pipeline body 1, avoid impurity in 1 building up inside of pipeline body to a certain extent.
As shown in Figure 2,3, wherein the first annular groove 4 or the second annular groove 5 are from 10 sides of outlet to the cross section far from 10 sides of outlet Product is gradually increased, while being provided with several baffles 11, multiple 11 edges of baffle in the opening of the first annular groove 4 and the second annular groove 5 The first annular groove 4 or the second annular groove 5 length direction it is uniformly distributed, and between 4 bottom of baffle 11 and the first annular groove or with the second ring There are channels 12 between 5 bottom of slot, and after the adhesive curing injected in seal cavity 6, baffle 11 will be located at cured bonding Inside agent, so that the bonding strength between cured adhesive and bellmouth 3 and socket 2 is higher, so that bellmouth 3 and socket 2 connect It connects even closer.
For increase curing agent and the first annular groove 4 or second sliding slot inner wall adhesive strength, in the first annular groove 4 or the second annular groove 5 inner walls are equipped with mesh plate 13, and front and the back side of mesh plate 13 are provided with several interconnecting pieces 14,13 back side of mesh plate Interconnecting piece 14 is embedded in 5 inner wall of the first annular groove 4 or the second annular groove.
Adhesive is the rubber of molten condition in the present embodiment, also could alternatively be cement or asphalt sealant.
In use, more pipeline bodies 1 are mutually butted, 2 end of socket of pipeline body 1 will be inserted into adjacent channel when docking In the bellmouth 3 of ontology 1,2 end of socket will be abutted with sealing ring 9 at this time, and the first annular groove 4 docks formation sealing with the second annular groove 5 Then cavity 6 injects the rubber of molten condition by import 7 into seal cavity 6, seal cavity 6 will be gradually full of by rubber, When rubber will be discharged from the air from outlet 10 in outflow portion timesharing seal cavity 6, standing waits the rubber of molten condition later Connection is completed in adhesive curing after Cure of Rubber.
Embodiment two:
A kind of construction method of drainage pipeline, comprising the following steps:
Step 1: surveying setting-out, tissue surveying party carry out repetition measurement by the measurement control point that designing institute provides, and establish after review is errorless Engineering surveying control network carries out the measurement that a face combines to engineering and controls, and setting out survey, makes pipeline middle line and well location is set, And control point of the level datum points as entire engineering is made, measurement is intended to be closed every time, strict control closure error;
Step 2: channel excavation determines and excavates region soil property, and chooses the slope gradient according to soil property situation, and according to suitable The gradient is excavated;
Step 3: groove precipitation respectively excavates a gutter in the channel bottom two sides that step 2 is excavated out, and sets every one section Plash is set, the bright row that draws water is carried out using water pump;
Step 4: pipeline foundation is excavated according to bottom of the design requirement to basis, modifies trench bottom, removes mud and broken Soil is backfilled to pipe substrate absolute altitude with gravel sand, and compaction in layers makes reinforced concrete pipeline foundation by reinforced concrete floor, to After the hardening of reinforced concrete pipeline surface of base, pipe centerline is popped up in its end face;
Step 5: the lifting of pipeline body 1 is entered in the groove excavated using truck crane, and makes pipeline sheet by Pipe installing In the bellmouth 3 of 2 end of the socket insertion adjacent channel ontology 1 of body 1, molten condition is injected into seal cavity 6 from import 7 later Rubber, until when the rubber of molten condition is overflowed from 10 ends of outlet;
Step 6: check that well construction, inspection shaft select concrete drainage inspection well or prefabricated assembling type reinforced concrete draining inspection Cha Jing;
Step 7: closed-water test carries out no pressure closed-water test to the pipeline body 1 that lays, and in test from upstream to Downstream carries out segmentation progress, and the closing of test port application brick wall, closing should be tight, and leaching 1 time of pipeline body is greater than after filling water 24 hours;
Step 8: pipeline backfill: banketing and horizontal slice paving answered to fill out, compaction in layers, and should be layered filling's dry density after measurement compacting, After its compacting factor and compacting range meet design requirement on inspection, upper layer can be just filled.
Wherein, if soil property is that silty clay belongs to three classes soil side slope by 1:0.67 slope, if soil property is to fill in step 2 Penus presses 1:0.75 slope in one, two class soil side slopes, if soil property is that mud side slope presses 1:1 slope.
If meet longer rainy weather, side slope can be used 4cm solid cement mortar and carry out slope protection.When excavation such as geology, When situations such as hydrology differs larger with design, management, owner's unit are reported in time, redeploys excavation plan.Channel excavation is adopted It is cut the earth with machinery, hand fit Qing Po, clear bottom.Strict control absolute altitude is answered in excavator shoveling, prevents groove from backbreaking or disturbing substrate Native soil layer manually cooperates when digging to the above 20cm of slot bottom designed elevation or so, and trim slots bottom is repaired when digging, and immediately into Row basis, cushion construction.Loose ground, mud, the boulder of slot bottom will be removed and keep not soaking.Exist for no treatment of soft foundation section It finds there are the poor geology such as dark creek mud during earth excavation, takes to backbreak when foundation bearing capacity does not reach requirement and change arranging of filling out It applies to handle, replacing method is sandy gravel, changes and fills out range and depth according to the determination of laboratory's foundation bearing capacity test report.
When channel excavation, pay attention to having buried underground piping in construction area, carefully verify related data and carry out it is careful Scene confirmation, the underground piping having a major impact to scene with drawing data differentiated such as optical cable, cable more should be prudent right To which relevant road segments carry out trial trench and avoid the destruction to pipe laying road based on hand excavation.The interval of hand excavation's trial trench and Ditch depth etc. determines according to field condition.
Inspection shaft selects concrete drainage inspection well (06MS201-3) or prefabricated assembling type reinforced concrete draining to check Well (06MS201-5).Inspection shaft base thickness is not less than 20cm, using C15 concrete.Well week, 100cm range shaft bottom did 5% to Jing Ding Cement stabilized macadam reinforces and inspection shaft walling crib, well seat armored concrete are reinforced.
Cast-in-situ steel reinforced concrete inspection shaft construction technology: the surveying setting-out location of well, well location excavation, cushion construction, well room master Body is poured, detects, is backfilled.
1, well location the surveying setting-out location of well: is made on total station in the duct line according to design drawing and data.Part Excavating difficult location allows along the fine tuning within the scope of 1 meter of duct orientation plan-position.
2, well location size is excavated: well location excavates and channel excavation is formed on the same section, absolutely not being capable of first ditching Then slot excavates well location in ditch trough rim again, to guarantee groove stability of slope.
Form work engineering:
Cast-in-place inspection shaft uses punching block.
(1) when template construction, according to structure axis, template size line is popped up, is carried out by the sequence of first bottom plate, wall, cover board. It is required that accomplishing that size is accurate, piece is tight.
(2) combined steel formwork is spliced using U-shaped card, when yin, yang angle mould is respectively adopted at yin, yang angle connecting with punching block, such as It is not available U-shaped card or is bolted, the vertical direction in punching block end adds horizontally-supported;After steel form must go up release agent It reuses, to guarantee the presentation quality of concrete.
(3) strength of mould stripping is executed by job specfication: after concrete strength reaches the 50% of design strength, it is small to remove span In the template and support of 2m;After concrete strength reaches the 75% of design strength, template and support that span is less than 8m are removed.
(4) template, joist, wooden flute, supporting steel pipe, fastener for removing etc. carry out taxonomic revision, maintenance and stacking by specification, For use next time.
Reinforced bar engineering:
(1) the inventory specification for strictly going out steel bar meter by the authorizing standard of design working drawing and national regulation, is come by inventory Expect processing and fabricating.
(2) reinforcing bar processed is arranged, is classified, and is stacked neatly according to detail design division points, and is listed and is indicated kind Class and use position.
(3) supplied materials field fabrication can be used in reinforcing bar or processing factory is prefabricated transports two methods of building site, the quality of Rebars on Construction Site to All information.The raw material reinforcing bar marched into the arena has quality guarantee certificate, test report, and batch carries out raw material test, through site technology Department and supervisor come into operation again after approving.
(4) borehole wall reinforcing bar binding has following condition:
1. template acceptance(check)
2. axis cross-section size meets design working drawing.
3. when assembling reinforcement, pop-up reinforcing bar binds control line, to guarantee that spacing of reinforcement size, deviation should control In allowed band, reinforcing bar guarantees that quality meets code requirement.
4. after reinforcing bar binding, acceptance of concealed work is carried out immediately, carries out next procedure after qualified, in order to avoid cause to do over again, shadow Ring schedule requirement.
5. all built-in fittings have enough anchoring strengths, the lap of splice of reinforcing bar meets the specification regulation of design and country.
6. all reinforcing bars should be bound by design drawing and be completed before disturbing concrete, and be welded admittedly in suitable position It is fixed, prevent reinforcing bar when vibrated concrete from shifting.
7. various built-in fitting positions are accurate.
8. after the acceptance(check) for only passing through various aspects, then disturbing concrete.
Concreting:
(1) pour smash before to template, reinforcing bar, built-in fitting after the completion of, by supervisor press acceptance of concealed work, through qualification signature it is laggard Row casting and compacting of concrete.
(2) verification report code list after selecting the guaranteed mixing plant of quality, concrete to reach on commodity coagulation, and do at the scene Slump verification, allows 2cm error, and those of exceeding notifies mixing plant to adjust immediately, forbids arbitrarily to add water at the scene, and do by regulation Good resistance to compression and impervious test block.
(3) concreting pours thickness control in 300-500mm, in coagulation using layering tiling, every layer concrete It is poured in the native presetting period and finishes one layer.
(4) pour smash before check it is whether clean in mould.No problem pours smash again on inspection, pour smash control every layer of initial set when Between, every layer concrete, which pours, to be smash and should control in 0.5m, and should uniformly upwards.Forbid unilateral side to pour to smash, and there is special messenger to be responsible for commodity coagulation It improves quality, strictly constructs by operating instruction, to guarantee the casting pounding quality of concrete.
(5) within 12 hours after disturbing concrete, to concrete covering and water seasoning.
(6) after checking well construction to regulation elevation, pour and install in time walling crib, well lid.
(7) after inspection shaft completion, mud, mortar, rubbish and the other sundries accumulated in well is removed in time.
Reinforce to backfill when curing concrete and mortar, not up to design strength, if any particular/special requirement, by designer It determines the backfill time, and proposes corresponding technical guarantee measure.After inspection shaft builds or is poured into regulation elevation, well is installed in time Circle, covers well lid.
Check the main control measure of well construction:
This engineering supervision well is largely prefabricated installation, partially to be cast-in-place, be should be noted in construction:
(1) correctness of the inspection shaft in pipeline plan-position.It can be set with total station according to design drawing survey
Well location is set out.Local uniqueness range check well location sets the fine tuning that can be carried out on pipe-line within 1 meter.
(2) correctness of inspection shaft form and each portion's size.Compare design drawing, drainage construction specification.
Meet design, the inspection shaft form of specification according to different tube diameters, and different connection type selections.Before template construction It confides a technological secret to carpenter teams and groups.It is allowed to make each spot size of inspection shaft clear.After template construction, need to check and accept conjunction Concrete placings are carried out after lattice again.
(3) inspection shaft arrangement of reinforcement and concrete construction.It constructs according to design drawing setting-out.Referring in particular to associated construction specification.
Closed-water test and pipeline backfill:
Rain pipe and sewage pipe respectively independently carry out no pressure closed-water test, are closed after the completion of pipeline is laid with and well room pours Water experiment is closed water experiment and is carried out by design and code requirement, and it is 100% that storm sewer closed-water test, which detects frequency, and sewage conduct closes It is 100% that water test, which detects frequency,.It is segmented segmentation of the principle according to construction when, storm sewer is generally four inspection well section selective examination One section, sewage conduct is generally each inspection well section and needs to be tested, and rain sewage conduct test head is 2m.Closed-water test The whole reserving holes of preceding closure must not leak.Following requirement: pipeline and inspection shaft appearance should be met when high-line conduit closed-water test Quality acceptance(check);Without ponding in the non-backfill of pipeline and groove;Whole preformed holes should block, and must not have infiltration.
1) closed-water test program
Carry out closed-water test scheme → closed-water test preparation → blocking pipe → pour water dip tube → observation water percolating capacity → record → really Recognize qualification → end
2) test section preferably carries out segmentation progress from upstream toward downstream, and the closing of test port application brick wall, closing should be tight, fills The dip tube time is greater than 24 hours after water.
3) allow water percolating capacity calculation formula
Reinforced concrete pipeline water percolating capacity is calculated as follows:
Q=1.25D1/2, wherein q is to allow water percolating capacity (m3/24hkm), and D is pipe diameter.
4) the good data of charting are pressed, are calculated by above-mentioned formula, q is less than 1.84m3/24hkm as d400, works as d600 When q be less than 30.6m3/24hkm, as d800 q be less than 35.35m3/24hkm, as d1000 q be less than 43.3m3/24h Otherwise km, pass the test need to do over again, until reaching standard.
During closed-water test, by the relevant units personnel on site such as supervising engineer supervise, and when sample after sign Approve.
When the construction of rain, sewage brick wall inspection shaft and concrete inspection well side wall finishes, concrete reaches certain through maintenance Intensity, and when having certain backfill work surface, that is, start the backfill of foundation pit.Before backfill, rubbish, the ponding in pipe trench should be removed And various sundries.Filler has to comply with design requirement, bankets and horizontal slice paving is answered to fill out, compaction in layers, and should be layered measurement pressure Filling's dry density after reality can just fill upper layer after its compacting factor and compacting range meet design requirement on inspection.Backfill mistake Cheng Zhong should must not be backfilled without ponding with water in slot.The structures two sides such as trench backfill Ying Xiancong pipeline, catch-basin symmetrically backfill Ensure that pipeline and structures do not generate displacement.After pipeline laying, tube top 0.5m or more, should be by until in roadbase bottom range Design requirement uses respective material, and is layered flat layered compacting to reach design and code requirement.
During backfill, it should must not be backfilled with water without ponding in slot.The structures such as trench backfill Ying Xiancong pipeline, inspection shaft Building object two sides and symmetrically backfilling ensures that pipeline and structures do not generate displacement.After pipeline laying, pipeline two sides and the above 0.5m of tube top Using the backfill of artificial graded gravel (using medium coarse sand around HDPE pipe) backfill, artificial graded gravel match ratio is gravel for part (0.5~4cm of partial size): medium coarse sand=6:4(volume ratio).Because my segment pipe is predominantly located under road, returned according to design requirement groove Back-up sand cobble, and flat compaction in layers is layered to reach design and code requirement.Because porosity is larger between artificial graded gravel, to disappear Cause road surface to collapse except fine particle penetrates into hole, is laid with one layer of permeable geotextiles in artificial graded sand gravel bed top surface.Soil Work cloth specification is 200g/m2, is planar paved with and respectively takes in sloped sides paving 30cm, and geotextiles lap width is 30cm. Paving 30cm is taken upwards at inspection shaft position.
Trench backfill should follow following provisions:
A. pipeline is located at road lower groove range and all sandy gravel is used to backfill, in road outer channel using qualified earthen backfill.
B. backfill is first since tube bottom and basic binding site, and along lumen two sides, symmetrical layering is filled out and tamped, two sides simultaneously Height difference is no more than 0.3m, and the specific compacting equipment of compacted thickness root determines that constructing operation should be carried out strictly by operating instruction.
C. pipeline and inspection shaft foundation pit slot backfill compacting factor cannot be less than design and code requirement.
D. when rainy weather backfills, backfill will guarantee before leaving offices among two plash to plash back-filling in layers Centre is higher than plash, is conducive to rainwater exclusion, is before leaving offices compacted the loosened soil on the same day, and segmentation backfill prevents drift to manage.
E. the backfill for creating pipeline and other pipeline monitor positions should meet compactness requirement, and should make backfilling material and quilt Supporting pipeline is close to, or carries out consolidation process by pertinent regulations.When changing such as field condition, then determine specific measure warp Implement after crossing management owner confirmation.
F. pipeline groove backfill before, the former bypass pipeline clearly abolished in drawing is blocked, first using cotton-wool or its Pipe plugging is cast in pipeline using C15 plain concrete afterwards, it is not small in pipeline to guarantee that plain concrete is poured by its material In 1m.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection of the invention according to this Range, therefore: the equivalence changes that all structures under this invention, shape, principle are done, should all be covered by protection scope of the present invention it It is interior.

Claims (9)

1. a kind of drainage pipeline, including pipeline body (1), described pipeline body (1) one end is provided with socket (2), pipeline body (1) other end is provided with bellmouth (3), and the bellmouth (3) can be mating with the socket (2) on adjacent channel ontology (1), special Sign is: socket (2) outer wall is provided with the first annular groove (4) around socket (2), bellmouth (3) the inner wall surrounding bellmouth (3) It is provided with the second annular groove (5);
When the bellmouth (3) of socket (2) insertion adjacent channel ontology (1) is interior, first annular groove (4) and the second annular groove (5) Just it is mutually butted and forms seal cavity (6);
The import (7) that will be connected on the outside of the second annular groove (5) and bellmouth (3) is provided on the bellmouth (3).
2. a kind of drainage pipeline according to claim 1, it is characterised in that: import (7) quantity be it is multiple and along Bellmouth (3) is circumferentially distributed on bellmouth (3).
3. a kind of drainage pipeline according to claim 1, it is characterised in that: the bellmouth (3) connect with pipeline body (1) Place is provided with the sealing surface (8) being bonded with socket (2) end face of adjacent channel ontology (1), is provided on the sealing surface (8) close Seal (9).
4. a kind of drainage pipeline according to claim 3, it is characterised in that: be provided on the bellmouth (3) by the second ring The outlet (10) being connected on the outside of slot (5) and bellmouth (3).
5. a kind of drainage pipeline according to claim 1, it is characterised in that: first annular groove (4) and the second annular groove (5) Opening be provided with several baffles (11), multiple baffles (11) along the first annular groove (4) or the second annular groove (5) length It is uniformly distributed to spend direction, there are channels between the baffle (11) and the first annular groove (4) bottom or between the second annular groove (5) bottom (12)。
6. a kind of drainage pipeline according to claim 4, it is characterised in that: first annular groove (4) or the second annular groove (5) It is gradually increased from outlet (10) side to the cross-sectional area far from outlet (10) side.
7. a kind of drainage pipeline according to claim 1, it is characterised in that: first annular groove (4) or the second annular groove (5) Inner wall is equipped with mesh plate (13), and front and the back side of the mesh plate (13) are provided with several interconnecting pieces (14), described The interconnecting piece (14) at mesh plate (13) back side is embedded in the first annular groove (4) or the second annular groove (5) inner wall.
8. a kind of construction method of drainage pipeline, it is characterised in that: the following steps are included:
Step 1: surveying setting-out, tissue surveying party carry out repetition measurement by the measurement control point that designing institute provides, and establish after review is errorless Engineering surveying control network carries out the measurement that a face combines to engineering and controls, and setting out survey, makes pipeline middle line and well location is set, And control point of the level datum points as entire engineering is made, measurement is intended to be closed every time, strict control closure error;
Step 2: channel excavation determines and excavates region soil property, and chooses the slope gradient according to soil property situation, and according to suitable The gradient is excavated;
Step 3: groove precipitation respectively excavates a gutter in the channel bottom two sides that step 2 is excavated out, and sets every one section Plash is set, the bright row that draws water is carried out using water pump;
Step 4: pipeline foundation is excavated according to bottom of the design requirement to basis, modifies trench bottom, removes mud and broken Soil is backfilled to pipe substrate absolute altitude with gravel sand, and compaction in layers makes reinforced concrete pipeline foundation by reinforced concrete floor, to After the hardening of reinforced concrete pipeline surface of base, pipe centerline is popped up in its end face;
Step 5: pipeline body (1) lifting is entered in the groove excavated using truck crane, and makes pipeline by Pipe installing It is interior from import (7) to seal cavity (6) later in the bellmouth (3) of socket (2) end insertion adjacent channel ontology (1) of ontology (1) The rubber for injecting molten condition, until when the rubber of molten condition holds spilling from outlet (10);
Step 6: check that well construction, inspection shaft select concrete drainage inspection well or prefabricated assembling type reinforced concrete draining inspection Cha Jing;
Step 7: closed-water test carries out no pressure closed-water test to the pipeline body (1) laid, and in test from upstream Segmentation progress is downstream carried out, the closing of test port application brick wall, closing should be tight, soaks pipeline body (1) time after filling water Greater than 24 hours;
Step 8: pipeline backfill: banketing and horizontal slice paving answered to fill out, compaction in layers, and should be layered filling's dry density after measurement compacting, After its compacting factor and compacting range meet design requirement on inspection, upper layer can be just filled.
9. a kind of construction method of drainage pipeline according to claim 8, it is characterised in that: if soil property is powder in step 2 Matter clay belongs to three classes soil side slope by 1:0.67 slope, if soil property is that constructing soil belongs to one, two class soil side slopes by 1:0.75 slope, If soil property is that mud side slope presses 1:1 slope.
CN201910345100.0A 2019-04-26 2019-04-26 A kind of drainage pipeline and its construction method Pending CN110056722A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910345100.0A CN110056722A (en) 2019-04-26 2019-04-26 A kind of drainage pipeline and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910345100.0A CN110056722A (en) 2019-04-26 2019-04-26 A kind of drainage pipeline and its construction method

Publications (1)

Publication Number Publication Date
CN110056722A true CN110056722A (en) 2019-07-26

Family

ID=67321028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910345100.0A Pending CN110056722A (en) 2019-04-26 2019-04-26 A kind of drainage pipeline and its construction method

Country Status (1)

Country Link
CN (1) CN110056722A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110863540A (en) * 2019-11-27 2020-03-06 圣都家居装饰有限公司 S-shaped bent pipe drainage construction method capable of avoiding blockage
CN111075992A (en) * 2020-01-03 2020-04-28 青岛华德仪表工程有限公司 Water supply pipeline construction method
CN111265742A (en) * 2020-03-19 2020-06-12 山东威高普瑞医药包装有限公司 Injection device
CN111335445A (en) * 2020-03-18 2020-06-26 中国十七冶集团有限公司 Construction method of concrete catch basin by using steel pipe as inner mold
CN111525490A (en) * 2020-05-25 2020-08-11 广东电网有限责任公司 Cable joint protector
CN111677095A (en) * 2020-06-19 2020-09-18 中建富林集团有限公司 Construction method of drainage pipeline
CN111828746A (en) * 2020-07-24 2020-10-27 江苏凯翔建设集团有限公司 Municipal pipeline water leakage prevention structure and construction method
CN111851526A (en) * 2020-06-13 2020-10-30 宁波越兴建设工程有限公司 Pipeline groove excavation construction method
CN112195867A (en) * 2020-10-13 2021-01-08 山丹县湿地保护站 Water channel base structure for wetland protection recovery and construction method thereof
CN112628466A (en) * 2020-12-25 2021-04-09 安徽砼宇特构科技有限公司 Jacking pipe sealing device for jacking construction
CN112728210A (en) * 2020-12-30 2021-04-30 湖州友盛水泥制品有限公司 Concrete pipe jacking structure
CN113090826A (en) * 2021-03-24 2021-07-09 鹏图建设有限公司 Node and process for sewage treatment plant construction
CN113309912A (en) * 2021-03-24 2021-08-27 中铁一局集团铁路建设有限公司 Interface sealing structure and sealing method of concrete pipeline
CN114952060A (en) * 2022-06-15 2022-08-30 李天宏 Large-diameter pipeline butt-joint double-side welding one-time lofting and mouth repairing construction process
CN117249312A (en) * 2023-08-23 2023-12-19 保定市水泥制管有限公司 Permeation-proof concrete pipeline and production process thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB189804066A (en) * 1898-02-18 1898-05-07 Joseph William Brown An Improved Joint for Pipes Constructed on the Spigot and Socket Principle.
GB240317A (en) * 1924-11-05 1925-10-01 Moir Buchanan Centrifugal Proc Improved pipe joint particularly for concrete pipes
CN1920364A (en) * 2006-08-28 2007-02-28 阎金波 Thin wall stainless steel pipe glue injection type seamless socket connection method
NL2003773C2 (en) * 2009-11-09 2011-05-11 Plasticon Europ B V COMPOUND FOR FIBER-REINFORCED PLASTIC TUBES AND METHOD FOR MAKING THEM.
CN205424166U (en) * 2016-03-25 2016-08-03 淄博富源建材有限公司 Flexible interface inside lining glass tempering worker blowdown concrete pipe
CN106978843A (en) * 2017-04-25 2017-07-25 杭州之江市政建设有限公司 Municipal drainage pipeline construction technology
CN107761910A (en) * 2016-08-17 2018-03-06 彭建明 Based on the technique constructed to storm sewer
CN107761911A (en) * 2016-08-17 2018-03-06 彭建明 A kind of construction method for the blowdown pipe network for improving installation quality

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB189804066A (en) * 1898-02-18 1898-05-07 Joseph William Brown An Improved Joint for Pipes Constructed on the Spigot and Socket Principle.
GB240317A (en) * 1924-11-05 1925-10-01 Moir Buchanan Centrifugal Proc Improved pipe joint particularly for concrete pipes
CN1920364A (en) * 2006-08-28 2007-02-28 阎金波 Thin wall stainless steel pipe glue injection type seamless socket connection method
NL2003773C2 (en) * 2009-11-09 2011-05-11 Plasticon Europ B V COMPOUND FOR FIBER-REINFORCED PLASTIC TUBES AND METHOD FOR MAKING THEM.
CN205424166U (en) * 2016-03-25 2016-08-03 淄博富源建材有限公司 Flexible interface inside lining glass tempering worker blowdown concrete pipe
CN107761910A (en) * 2016-08-17 2018-03-06 彭建明 Based on the technique constructed to storm sewer
CN107761911A (en) * 2016-08-17 2018-03-06 彭建明 A kind of construction method for the blowdown pipe network for improving installation quality
CN106978843A (en) * 2017-04-25 2017-07-25 杭州之江市政建设有限公司 Municipal drainage pipeline construction technology

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110863540A (en) * 2019-11-27 2020-03-06 圣都家居装饰有限公司 S-shaped bent pipe drainage construction method capable of avoiding blockage
CN111075992A (en) * 2020-01-03 2020-04-28 青岛华德仪表工程有限公司 Water supply pipeline construction method
CN111075992B (en) * 2020-01-03 2021-12-17 青岛华德仪表工程有限公司 Water supply pipeline construction method
CN111335445B (en) * 2020-03-18 2021-11-02 中国十七冶集团有限公司 Construction method of concrete catch basin by using steel pipe as inner mold
CN111335445A (en) * 2020-03-18 2020-06-26 中国十七冶集团有限公司 Construction method of concrete catch basin by using steel pipe as inner mold
CN111265742A (en) * 2020-03-19 2020-06-12 山东威高普瑞医药包装有限公司 Injection device
CN111525490A (en) * 2020-05-25 2020-08-11 广东电网有限责任公司 Cable joint protector
CN111525490B (en) * 2020-05-25 2021-11-16 广东电网有限责任公司 Cable joint protector
CN111851526A (en) * 2020-06-13 2020-10-30 宁波越兴建设工程有限公司 Pipeline groove excavation construction method
CN111677095A (en) * 2020-06-19 2020-09-18 中建富林集团有限公司 Construction method of drainage pipeline
CN111828746A (en) * 2020-07-24 2020-10-27 江苏凯翔建设集团有限公司 Municipal pipeline water leakage prevention structure and construction method
CN111828746B (en) * 2020-07-24 2022-05-24 江苏凯翔建设集团有限公司 Municipal pipeline water leakage prevention structure and construction method
CN112195867A (en) * 2020-10-13 2021-01-08 山丹县湿地保护站 Water channel base structure for wetland protection recovery and construction method thereof
CN112628466A (en) * 2020-12-25 2021-04-09 安徽砼宇特构科技有限公司 Jacking pipe sealing device for jacking construction
CN112728210A (en) * 2020-12-30 2021-04-30 湖州友盛水泥制品有限公司 Concrete pipe jacking structure
CN113090826A (en) * 2021-03-24 2021-07-09 鹏图建设有限公司 Node and process for sewage treatment plant construction
CN113309912A (en) * 2021-03-24 2021-08-27 中铁一局集团铁路建设有限公司 Interface sealing structure and sealing method of concrete pipeline
CN114952060A (en) * 2022-06-15 2022-08-30 李天宏 Large-diameter pipeline butt-joint double-side welding one-time lofting and mouth repairing construction process
CN114952060B (en) * 2022-06-15 2024-07-09 李天宏 One-time lofting mouth repairing construction process for large-caliber pipeline butt joint double-sided welding
CN117249312A (en) * 2023-08-23 2023-12-19 保定市水泥制管有限公司 Permeation-proof concrete pipeline and production process thereof
CN117249312B (en) * 2023-08-23 2024-05-07 保定市水泥制管有限公司 Permeation-proof concrete pipeline and production process thereof

Similar Documents

Publication Publication Date Title
CN110056722A (en) A kind of drainage pipeline and its construction method
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN102433876B (en) Multi-compartment casing composite pile and construction method thereof
CN107938692B (en) Drainage and recharging construction method and structure
CN106978843A (en) Municipal drainage pipeline construction technology
CN110344423A (en) A kind of drop shaft sinking forms the construction method of water level for local deep foundation pit under high water level
CN111021509A (en) Municipal drainage pipeline construction method
CN109736847A (en) Primary concreting concrete inverted arch and its construction method
CN111677095A (en) Construction method of drainage pipeline
CN110761316B (en) Prefabricated foundation ring beam prefabricating method and storage tank construction method applying prefabricated foundation ring beam prefabricating method
CN107964976A (en) Steel pipe-conversion steel platform tower crane top-down construction method
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN111778941A (en) High-standard farmland channel construction method and structure
CN109838240A (en) Cross the river tunnel ledge cover and cut construction method
CN112144559A (en) Well construction method in high water-rich loess sandy gravel stratum transformer tube well
CN110230272A (en) A kind of pipe culvert construction method
CN110552371A (en) Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN107740355A (en) A kind of pipe culvert position roadbed construction method
CN206189430U (en) A escape canal for deep overburden ground
CN108104158A (en) A kind of assembled underground pipe gallery and assembled in situ method
KR100476839B1 (en) Construction method for installing concrete underground structures
CN212452584U (en) Foundation treatment system combining vacuum preloading of soft soil foundation with power consolidation drainage
CN113174904A (en) Construction method for ecological landscape open channel for downward seepage and stagnation storage in sponge city
CN110042859B (en) Retaining wall reverse filter body and construction method thereof
CN209891168U (en) Dredging engineering's floodgate case buried pipe formula outlet structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190726

RJ01 Rejection of invention patent application after publication