CN110056162A - The leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation - Google Patents

The leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation Download PDF

Info

Publication number
CN110056162A
CN110056162A CN201910461652.8A CN201910461652A CN110056162A CN 110056162 A CN110056162 A CN 110056162A CN 201910461652 A CN201910461652 A CN 201910461652A CN 110056162 A CN110056162 A CN 110056162A
Authority
CN
China
Prior art keywords
leveling
connecting rod
dry method
finishing material
mated formation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910461652.8A
Other languages
Chinese (zh)
Inventor
于利凯
周书棋
王杨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Original Assignee
Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gold Mantis Fine Decoration Technology Suzhou Co Ltd filed Critical Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Priority to CN201910461652.8A priority Critical patent/CN110056162A/en
Publication of CN110056162A publication Critical patent/CN110056162A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/024Sectional false floors, e.g. computer floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/024Sectional false floors, e.g. computer floors
    • E04F15/02447Supporting structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/024Sectional false floors, e.g. computer floors
    • E04F15/02447Supporting structures
    • E04F15/02464Height adjustable elements for supporting the panels or a panel-supporting framework
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F2290/00Specially adapted covering, lining or flooring elements not otherwise provided for
    • E04F2290/02Specially adapted covering, lining or flooring elements not otherwise provided for for accommodating service installations or utility lines, e.g. heating conduits, electrical lines, lighting devices or service outlets

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)
  • Floor Finish (AREA)

Abstract

The present invention provides the leveling bearing components that a kind of dry method of assembled ground finishing material is integrally mated formation, it includes the spaced component leveling of multiple groups, component leveling includes: multiple support bases, it includes pedestal, support frame and regulating part, it is provided with bottom plate and first connecting rod on pedestal, support plate and the second connecting rod are provided on support frame;First connecting rod is provided with connecting hole, and the second connecting rod and connecting hole are threadedly coupled;Regulating part is sheathed in the second connecting rod and the two is mutually threadedly coupled;Carrier, carrier are set on support frame.The present invention has the advantage that when being laid with ground that laying layer progress is levelling compared to the prior art, later ornament materials can be laid on leveling bearing component, the effect that i.e. dress is lived not only may be implemented, simultaneously have the advantages that environment protection health, efficiently it is convenient, shorten the construction period, in addition, due to passing through module assembled, convenient for disassembly and assembly, recoverable.

Description

The leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation
Technical field
The present invention relates to the leveling bearing component that a kind of dry method of ground finishing material is integrally mated formation, in particular to The leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation.
Background technique
Assembled decoration is a kind of in recent years emerging decoration construction form.Assembled is decorated as its name suggests, is that will decorate Required each component component realizes that production is completed in factory, then transports decoration scene and is combined installation, Traditional decoration scene is eliminated to operations such as measurement, the cuttings of each component component, is constructed more simple and convenient, it can be greatly The construction efficiency at decoration scene is improved, and construction site is more clean and tidy and beautiful, will not generate excessive ornament materials rubbish, It is a kind of more environmentally protective decoration construction form.
Traditional tile laying process flow are as follows: base's dabbing, floor leveling, be laid with the pipelines such as floor heating, be laid with filled layer, The positioning of floor tile snap the line is laid with floor tile, seam finishing.Traditional floor paving process flow are as follows: base's dabbing, floor leveling, paving If the pipelines such as floor heating, be laid with filled layer, unwrapping wire positioning, be laid with moisture-proof film, basal plate installation, skirting installation, floor walkthrough, Practical paving.
No matter which kind of above-mentioned paving mode is used, all had the disadvantage that:
One, process is more, long in time limit: the wet construction standard process flows complexity and scarce one on traditional ceramic tile or floor is not Can, it need to could complete through multinomial process, and process portion is related to naturally dry in wet construction engineering method, extends the duration more;
Two, seriously polluted: a large amount of cement mortar to be used during traditional wet construction engineering method, live dust pollution is serious and easy There is filthy situation;
Three, later period pipeline maintainance is difficult: the paving process on traditional ceramic tile and floor uses wet process paving, pipeline direct-burried cement Filled layer, later maintenance need to break ceramic tile or floor, cement filled layer, cumbersome.
Summary of the invention
In consideration of it, the present invention provides the leveling load-bearing groups that a kind of dry method of assembled ground finishing material is integrally mated formation Part, can be levelling by laying layer progress when being laid with ground, can be laid with ornament materials on leveling bearing component later, not only The effect that i.e. dress is lived may be implemented, at the same have the advantages that environment protection health, it is efficient it is convenient, shorten the construction period, in addition, due to passing through Module assembled, therefore convenient for disassembly and assembly, recoverable.
For this purpose, the present invention provides the leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation, It includes the spaced component leveling of multiple groups, and component leveling includes:
Multiple support bases comprising pedestal, support frame and regulating part are provided with bottom plate and first connecting rod on pedestal, Support plate and the second connecting rod are provided on support frame;First connecting rod is provided with connecting hole, the second connecting rod and connecting hole spiral shell Line connection;Regulating part is sheathed in the second connecting rod and the two is mutually threadedly coupled;
Carrier, carrier are set on support frame.
Further, above-mentioned regulating part is nut.
Further, above-mentioned bottom plate and the perpendicular setting of first connecting rod.
Further, above-mentioned support frame and the perpendicular setting of the second connecting rod.
Further, above-mentioned carrier includes loading plate and the connecting plate for being set to two side bottom of loading plate.
Further, the cross section of above-mentioned loading plate is inType.
Further, above-mentioned connecting plate is connect by screw with support plate.
Further, above-mentioned carrier is an integral structure.
Further, the length specification of above-mentioned loading plate is 3 meters/root.
The leveling bearing component that a kind of dry method of assembled ground finishing material provided by the present invention is integrally mated formation, mainly Including multiple support bases and carrier, carrier is set on support base, and support base includes pedestal, support frame and regulating part, Pedestal and support frame are threadedly coupled by first connecting rod and the second connecting rod, while adjusting height by regulating part.
When installation, support base is fixed on ground layer first, support base is placed according to cloth office point is pre-designed, if The out-of-flatness of original ground base needs the height of adjustment support base, then to guarantee the flatness on ground after mating formation;Secondly installation carrying Carrier is fixed on multiple support bases by frame, and the two is connected by fixing piece;The finally paving ground between adjacent carrier Decorative layer, while the pre- sunk screw of ground decoration layer being fixed with support base, carrier.
By above structure, so that a kind of dry method of assembled ground finishing material provided by the present invention was integrally mated formation Leveling bearing component mainly has the advantage that compared to the prior art
1) it, fills to live, environment protection health, is installed by leveling bearing component, overcome traditional wet process installation side Contamination phenomenon brought by method, each ornament materials are kept under strict control by factory, are all made of health environment-friendly material, are prevented formaldehyde pollution, Dry method assembling mode is used in fitment process, the noiseless pollution in scene, dust pollution really realize i.e. dress and live, pacify Loopful is protected;
2) it, efficiently convenient, the reduction duration: is installed by leveling bearing component, realizes that the dry method on ground is integrally mated formation Mode simplifies the program of original complexity, usual 30m2Ground only needs two workers, can complete within one day;
3), module assembled, dismounting convenience: the paving structure installed by leveling bearing component, by plant produced Component accessory carries out on-site assembly and is formed, and all pipelines in ground are cavity cabling, and the later period pipeline that needs repairing need to only dismantle porcelain Brick or floor or support base install recombination, without pounding drill after maintenance, destroy interior decoration structure;
4), recoverable, after being replaced in the component later period, the component being replaced will not still be removed by destructiveness, warp Recycling can be achieved to recycle, environmentally protective, sustainable use.
Detailed description of the invention
By reading the following detailed description of the preferred embodiment, various other advantages and benefits are common for this field Technical staff will become clear.The drawings are only for the purpose of illustrating a preferred embodiment, and is not considered as to the present invention Limitation.And throughout the drawings, the same reference numbers will be used to refer to the same parts.In the accompanying drawings:
Fig. 1 is the leveling load-bearing that a kind of dry method of assembled ground finishing material provided in an embodiment of the present invention is integrally mated formation The side view of component;
Fig. 2 is the leveling load-bearing that a kind of dry method of assembled ground finishing material provided in an embodiment of the present invention is integrally mated formation The main view of component;
Fig. 3 is the leveling load-bearing that a kind of dry method of assembled ground finishing material provided in an embodiment of the present invention is integrally mated formation The constitutional diagram of support base in component;
Fig. 4 is the leveling load-bearing that a kind of dry method of assembled ground finishing material provided in an embodiment of the present invention is integrally mated formation The broken away view of support base in component.
Wherein, 1, regulating part, 21, bottom plate, 22, first connecting rod, 23, connecting hole, 31, support plate, the 32, second connection Bar, 41, loading plate, 42, connecting plate, 5, screw.
Specific embodiment
Exemplary embodiments of the present disclosure are described in more detail below with reference to accompanying drawings.Although showing the disclosure in attached drawing Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure without should be by embodiments set forth here It is limited.On the contrary, these embodiments are provided to facilitate a more thoroughly understanding of the present invention, and can be by the scope of the present disclosure It is fully disclosed to those skilled in the art.
Embodiment one:
Referring to Fig. 1-4, a kind of dry method of assembled ground finishing material of the offer of the embodiment of the present invention one is shown in figure The leveling bearing component integrally mated formation comprising the spaced component leveling of multiple groups, component leveling include: multiple support bases, It includes pedestal, support frame and regulating part 1, and bottom plate 21 and first connecting rod 22 are provided on pedestal, is provided on support frame Support plate 31 and the second connecting rod 32;First connecting rod 22 is provided with connecting hole 23,23 screw thread of the second connecting rod 32 and connecting hole Connection;Regulating part 1 is sheathed in the second connecting rod 32 and the two is mutually threadedly coupled;Carrier, carrier are set to support frame On.Wherein, regulating part 1 is nut, is adjusted more convenient.
The leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation provided by the present embodiment, it is main It to include multiple support bases and carrier, carrier is set on support base, and support base includes pedestal, support frame and regulating part 1, pedestal and support frame are threadedly coupled by first connecting rod 22 and the second connecting rod 32, while being adjusted by regulating part 1 Highly.
When installation, support base is fixed on ground layer first, support base is placed according to cloth office point is pre-designed, if The out-of-flatness of original ground base needs the height of adjustment support base, then to guarantee the flatness on ground after mating formation;Secondly installation carrying Carrier is fixed on multiple support bases by frame, and the two is connected by fixing piece;The finally paving ground between adjacent carrier Decorative layer, while the pre- sunk screw of ground decoration layer being fixed with support base, carrier.
By above structure, so that a kind of dry method of assembled ground finishing material provided by the present invention was integrally mated formation Leveling bearing component mainly has the advantage that compared to the prior art
1) it, fills to live, environment protection health, is installed by leveling bearing component, overcome traditional wet process installation side Contamination phenomenon brought by method, each ornament materials are kept under strict control by factory, are all made of health environment-friendly material, are prevented formaldehyde pollution, Dry method assembling mode is used in fitment process, the noiseless pollution in scene, dust pollution really realize i.e. dress and live, pacify Loopful is protected;
2) it, efficiently convenient, the reduction duration: is installed by leveling bearing component, realizes that the dry method on ground is integrally mated formation Mode simplifies the program of original complexity, usual 30m2Ground only needs two workers, can complete within one day;
3), module assembled, dismounting convenience: the paving structure installed by leveling bearing component, by plant produced Component accessory carries out on-site assembly and is formed, and all pipelines in ground are cavity cabling, and the later period pipeline that needs repairing need to only dismantle porcelain Brick or floor or support base install recombination, without pounding drill after maintenance, destroy interior decoration structure;
4), recoverable, after being replaced in the component later period, the component being replaced will not still be removed by destructiveness, warp Recycling can be achieved to recycle, environmentally protective, sustainable use.
Embodiment two:
Referring to Fig. 1-4, a kind of dry method of assembled ground finishing material provided by Embodiment 2 of the present invention is shown in figure The leveling bearing component integrally mated formation, the present embodiment are also further made that following conduct on the basis of the various embodiments described above Improved technical solution: bottom plate 21 and the perpendicular setting of first connecting rod 22;Support plate 31 and the second connecting rod 32 is perpendicular sets It sets.By the setting of above structure, so that support effect is best.
Embodiment three:
Referring to Fig. 1-2, a kind of dry method of assembled ground finishing material of the offer of the embodiment of the present invention three is shown in figure The leveling bearing component integrally mated formation, the present embodiment are also further made that following conduct on the basis of the various embodiments described above Improved technical solution: carrier includes loading plate 41 and the connecting plate 42 for being set to 41 liang of side bottoms of loading plate.By above-mentioned The setting of structure, connection dynamics is best, and both sides are attached simultaneously, and stability and levelness are good.Wherein, carrier is integrated Formula structure, further increases rigidity.
Example IV
Referring to Fig. 1, the dry method that a kind of assembled ground finishing material of the offer of the embodiment of the present invention four is shown in figure is whole The leveling bearing component that body is mated formation, the present embodiment are also further made that following be used as changes on the basis of the various embodiments described above Into technical solution: the cross section of loading plate 41 is inType, specifically, the length specification of loading plate 41 is 3 meters/root.It is logical The setting of above structure is crossed, pipeline can be installed in the cavity of loading plate 41, avoid mixed and disorderly phenomenon, while improving safety Performance;
In addition, the length specification of loading plate 41 is 3 meters/root, the length of traditional loading plate is generally 0.6 meter/root, in this way Since loading plate 41 has length advantage, it is possible to reduce the installation number of loading plate 41 improves installation effectiveness;Meanwhile it is traditional During dry method is mated formation, need to be arranged the loading plate intersected anyhow, and in the present invention, it is only necessary to more parallel elongated carryings are set Plate, the lateral loading plate that no setting is required intersects with loading plate, the cost that can be effectively saved on material in this way, and mat formation It is more easy, it is only necessary to unidirectionally to mat formation along the length direction of loading plate, installation effectiveness is higher.
Embodiment five
Referring to Fig. 1-2, a kind of dry method of assembled ground finishing material of the offer of the embodiment of the present invention five is shown in figure The leveling bearing component integrally mated formation, the present embodiment are also further made that following conduct on the basis of the various embodiments described above Improved technical solution: connecting plate 42 is connect by screw 5 with support plate 31.By the setting of above structure, connection is more convenient, It is firm.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art Mind and range.In this way, if these modifications and changes of the present invention belongs to the range of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to include these modifications and variations.

Claims (9)

1. the leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation, which is characterized in that including multiple groups Spaced component leveling, the component leveling include:
Multiple support bases comprising pedestal, support frame and regulating part (1) are provided with bottom plate (21) and first on the pedestal Connecting rod (22) is provided with support plate (31) and the second connecting rod (32) on support frame as described above;The first connecting rod (22) sets It is equipped with connecting hole (23), second connecting rod (32) and the connecting hole (23) are threadedly coupled;The regulating part (1) is sheathed on On second connecting rod (32) and the two is mutually threadedly coupled;
Carrier, the carrier are set on support frame as described above.
2. the leveling bearing component that a kind of dry method of assembled ground finishing material according to claim 1 is integrally mated formation, It is characterized in that, the regulating part (1) is nut.
3. the leveling load-bearing group that a kind of dry method of assembled ground finishing material according to claim 1 or 2 is integrally mated formation Part, which is characterized in that the bottom plate (21) and the first connecting rod (22) perpendicular setting.
4. the leveling load-bearing group that a kind of dry method of assembled ground finishing material according to claim 1 or 2 is integrally mated formation Part, which is characterized in that the support plate (31) and second connecting rod (32) perpendicular setting.
5. the leveling bearing component that a kind of dry method of assembled ground finishing material according to claim 1 is integrally mated formation, It is characterized in that, the carrier includes loading plate (41) and the connecting plate for being set to (41) two side bottom of loading plate (42)。
6. the leveling bearing component that a kind of dry method of assembled ground finishing material according to claim 5 is integrally mated formation, It is characterized in that, the cross section of the loading plate (41) is inType.
7. the leveling bearing component that a kind of dry method of assembled ground finishing material according to claim 5 is integrally mated formation, It is characterized in that, the connecting plate (42) is connect by screw (5) with the support plate (31).
8. the leveling bearing component that a kind of dry method of assembled ground finishing material according to claim 7 is integrally mated formation, It is characterized in that, the carrier is an integral structure.
9. the leveling bearing component that a kind of dry method of assembled ground finishing material according to claim 5 is integrally mated formation, It is characterized in that, the length specification of the loading plate (41) is 3 meters/root.
CN201910461652.8A 2019-05-30 2019-05-30 The leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation Pending CN110056162A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910461652.8A CN110056162A (en) 2019-05-30 2019-05-30 The leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910461652.8A CN110056162A (en) 2019-05-30 2019-05-30 The leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation

Publications (1)

Publication Number Publication Date
CN110056162A true CN110056162A (en) 2019-07-26

Family

ID=67325107

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910461652.8A Pending CN110056162A (en) 2019-05-30 2019-05-30 The leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation

Country Status (1)

Country Link
CN (1) CN110056162A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924624A (en) * 2019-12-09 2020-03-27 北京北方车辆集团有限公司 Height adjusting device for rotary floor

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200179025Y1 (en) * 1999-11-18 2000-04-15 송영택 A leveling device for carrying out the ground
KR20020062391A (en) * 2001-01-20 2002-07-26 조영민 A floor system of access-floor type using a glass-ondol and the construction method of it
KR20050089434A (en) * 2004-03-05 2005-09-08 조흥기 Suspension type floor board
CN102425293A (en) * 2011-08-30 2012-04-25 中国建筑装饰集团有限公司 Novel composite surface layer fixation screw-concealed raised flooring and construction method thereof
CN108049592A (en) * 2017-12-30 2018-05-18 浙江亚厦装饰股份有限公司 Ground pavement pedestal, mat formation component and method for paving
CN208702087U (en) * 2018-08-20 2019-04-05 宁夏东睿建筑科技有限公司 A kind of raised flooring suitable for industrializing Shear Wall Residential
CN210127599U (en) * 2019-05-30 2020-03-06 金螳螂精装科技(苏州)有限公司 Leveling bearing assembly integrally paved by dry method of assembled ground facing material

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200179025Y1 (en) * 1999-11-18 2000-04-15 송영택 A leveling device for carrying out the ground
KR20020062391A (en) * 2001-01-20 2002-07-26 조영민 A floor system of access-floor type using a glass-ondol and the construction method of it
KR20050089434A (en) * 2004-03-05 2005-09-08 조흥기 Suspension type floor board
CN102425293A (en) * 2011-08-30 2012-04-25 中国建筑装饰集团有限公司 Novel composite surface layer fixation screw-concealed raised flooring and construction method thereof
CN108049592A (en) * 2017-12-30 2018-05-18 浙江亚厦装饰股份有限公司 Ground pavement pedestal, mat formation component and method for paving
CN208702087U (en) * 2018-08-20 2019-04-05 宁夏东睿建筑科技有限公司 A kind of raised flooring suitable for industrializing Shear Wall Residential
CN210127599U (en) * 2019-05-30 2020-03-06 金螳螂精装科技(苏州)有限公司 Leveling bearing assembly integrally paved by dry method of assembled ground facing material

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924624A (en) * 2019-12-09 2020-03-27 北京北方车辆集团有限公司 Height adjusting device for rotary floor

Similar Documents

Publication Publication Date Title
US9185748B2 (en) Electrical panel heating device and method and building materials for the protection thereof
CN206346443U (en) A kind of new adjustable floor heating paving structure
CN101568693A (en) Building block, building structure and the method of bricking wall using the same
CN111305410B (en) Anti-cracking wall and construction method thereof
CN108316606A (en) A kind of ground overhead system and its installation method
CN109267671A (en) A kind of decoration method of indoor wall system
CN110056161A (en) A kind of the dry method entirety paving structure and method for paving on assembled ground
CN110241993A (en) A kind of assembled ceramic tile concrete composite board metope mounting system and method
CN110056162A (en) The leveling bearing component that a kind of dry method of assembled ground finishing material is integrally mated formation
CN110067361A (en) A kind of assembled facing horizontal splicing mounting structure and installation method
CN104831926A (en) Paving method of joggle type block-shaped surface building floor
CN208023883U (en) Ground hybrid system
CN210947550U (en) Assembled resin leveling piece
CN102287039B (en) Integrated quickly-paved substrate system for electric heating floor heater
CN210127599U (en) Leveling bearing assembly integrally paved by dry method of assembled ground facing material
CN110080491A (en) The lateral assembled paving structure and method for paving of a kind of ground finishing material
CN210134616U (en) Dry-method overall paving structure of fabricated ground
CN110656752A (en) Mounting member and mounting structure of assembled threshold stone
CN210134614U (en) Horizontal assembled structure of mating formation of ground finish material
CN103362313B (en) The assemble method of modularized combination type heat insulating curtain wall panel
CN111946011A (en) Assembled ground/floor heating integrated plate structure
CN105401712B (en) Energy-saving ground tile paving mechanism
CN210659109U (en) Ground veneer leveling supporting device and ground veneer mounting structure
CN211341589U (en) Leveling strip
CN210659110U (en) Assembly type overhead ground installation system of ceramic tile concrete composite board

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination