CN110241993A - A kind of assembled ceramic tile concrete composite board metope mounting system and method - Google Patents

A kind of assembled ceramic tile concrete composite board metope mounting system and method Download PDF

Info

Publication number
CN110241993A
CN110241993A CN201910564273.1A CN201910564273A CN110241993A CN 110241993 A CN110241993 A CN 110241993A CN 201910564273 A CN201910564273 A CN 201910564273A CN 110241993 A CN110241993 A CN 110241993A
Authority
CN
China
Prior art keywords
ceramic tile
composite board
concrete composite
metal tube
tube body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910564273.1A
Other languages
Chinese (zh)
Inventor
钱炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Original Assignee
Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gold Mantis Fine Decoration Technology Suzhou Co Ltd filed Critical Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Priority to CN201910564273.1A priority Critical patent/CN110241993A/en
Publication of CN110241993A publication Critical patent/CN110241993A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • E04F13/0805Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and the wall
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • E04F13/081Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and covering elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • E04F13/081Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and covering elements
    • E04F13/0814Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and covering elements fixed by means of clamping action

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The present invention provides a kind of assembled ceramic tile concrete composite board metope installation systems comprising: ceramic tile concrete composite board, the back side are fixedly connected with multiple pipe clamps, and pipe clamp is curved opening pipe clamp, and there are the cavitys for being laid with hydroelectric line between ceramic tile concrete composite board and wall;Composite plate bindiny mechanism comprising ceramic tile concrete composite board is connected on vertical metal tube body by vertical metal tube body and pipe code, pipe clamp, and vertical metal tube body is round tube;Vertical metal tube body is fixed on the wall using multiple pipe codes.The present invention also provides a kind of assembled ceramic tile concrete composite board metope installation methods.Assembled finishing Product industrialization production may be implemented in the present invention compared to the prior art, the installation of assembler scene rapidly and efficiently, product is applicable in the lesser situation in house inner space, a large amount of generations of building waste are reduced during fitting-out work, and it is easy to maintenance, detachable to reuse installation, final realization reduces the purpose of integrated construction cost.

Description

A kind of assembled ceramic tile concrete composite board metope mounting system and method
Technical field
The present invention relates to a kind of ceramic tile concrete composite board metope mounting techniques, in particular to a kind of assembled ceramic tile concrete Composite plate metope mounting system and method.
Background technique
Assembled decoration is a kind of in recent years emerging decoration construction form.Assembled is decorated as its name suggests, is that will decorate Required each component component realizes that production is completed in factory, then transports decoration scene and is combined installation, Traditional decoration scene is eliminated to operations such as measurement, the cuttings of each component component, is constructed more simple and convenient, it can be greatly The construction efficiency at decoration scene is improved, and construction site is more clean and tidy and beautiful, will not generate excessive ornament materials rubbish, It is a kind of more environmentally protective decoration construction form.
In existing building decorative ceramics brick wall surface construction, Site binder 1.5cm or so is needed to carry out vertical wall paving Patch, site operation dust is more, and environment is poor, and 1-2 talent is needed to can be carried out subsequent processing operation;Meanwhile patch block bricklayer skilled worker The number of practitioner is reduced year by year, and labor wage increases year by year, and technical level level is uneven;Also, tile laying generates hollowing Or use process is broken, maintenance process building waste is more, and cost is big, and the period is long.
Summary of the invention
In consideration of it, the present invention provides a kind of assembled ceramic tile concrete composite board metope mounting system and method, compared to existing There is technology that installation rapidly and efficiently may be implemented, improves construction efficiency, and easy to maintenance, can be effectively reduced and be constructed into This.
Thus, on the one hand, the present invention provides a kind of assembled ceramic tile concrete composite board metope installation systems comprising:
Ceramic tile concrete composite board, the back side are fixedly connected with multiple pipe clamps, and pipe clamp is curved opening pipe clamp, ceramic tile concrete composite board There are the cavitys for being laid with hydroelectric line between wall;
Composite plate bindiny mechanism comprising ceramic tile concrete composite board is connected to vertically by vertical metal tube body and pipe code, pipe clamp On metal tube, vertical metal tube body is round tube;Vertical metal tube body is fixed on the wall using multiple pipe codes.
Further, the height of above-mentioned cavity is 15-25mm.
Further, pour integral composite plate by mold using concrete and ceramic tile, ceramic tile with a thickness of 10- 15mm, concrete groundwork thickness are 10-15mm, the pre-buried attaching nut for being used to connect pipe clamp in concrete base.
Further, there are multiple reinforcement convex ribs along arcuate directions at the above-mentioned pipe clamp back side.
Further, above-mentioned wall is cast-in-place or precast light concrete wall comprising an one-piece casting wall or multiple The precast wall body unit successively spliced.
Further, above-mentioned pipe code and wall are provided with gasket, are used to adjust the verticality of vertical metal tube body.
Further, the bottom of above-mentioned wall is fixedly connected with backing board, and backing board supports the bottom of vertical metal tube body, The cross section of backing board is in zigzag.
On the other hand, the present invention provides a kind of assembled ceramic tile concrete composite board metope installation methods comprising following peace Fill step:
1) it is fixed on metope by pipe code and gasket, and regulation pipe code is levelling on same plane, then through hanging down Straight metal tube body;
2) bottom of vertical metal tube body collet positioning support;
3) pipe clamp on ceramic tile concrete composite board back is installed, and injects bonded adhesives or bonding agent, then blocks pipe clamp Vertical metal tube body.
A kind of assembled ceramic tile concrete composite board metope mounting system and method provided by the present invention is compared to the prior art Mainly have the advantage that
1) prefabricated ceramic tile concrete composite board, the industrialization that composite plate may be implemented is highly integrated, extensive using industrialization Batch production, scene no longer needs to wet-felting ceramic tile, is mounted directly;
2) when composite plate is installed, using snap fit, the levelling of live large area can be fast implemented, scene may be implemented Installation rapidly and efficiently improves site operation efficiency;
3) quality is stablized, and more preferable control, flatness and verticality are more accurate;The artificial paving of conventional on-site, quality are unstable Fixed, quality can not control;
4) it can be installed after worker's simple training, without relying on worker's experience;Tradition needs the experience by worker, And experienced worker's aging, and there is the problem of gap between generations;
5) experienced worker is fewer and fewer, and artificial tradition paving cost is higher and higher, using after above-mentioned installation system just It can solve the problem.
Detailed description of the invention
By reading the following detailed description of the preferred embodiment, various other advantages and benefits are common for this field Technical staff will become clear.The drawings are only for the purpose of illustrating a preferred embodiment, and is not considered as to the present invention Limitation.And throughout the drawings, the same reference numbers will be used to refer to the same parts.In the accompanying drawings:
Fig. 1 is a kind of structure of the assembled ground spacing mounting structure of ceramic tile concrete composite board provided in an embodiment of the present invention Broken away view:
Fig. 2 is a kind of structure of the assembled ground spacing mounting structure of ceramic tile concrete composite board provided in an embodiment of the present invention Assembling figure;
Fig. 3 is the enlarged drawing in the portion A in Fig. 2:
Fig. 4 is pipe clamp in a kind of assembled ground spacing mounting structure of ceramic tile concrete composite board provided in an embodiment of the present invention Structural schematic diagram;
Fig. 5 is collet in a kind of assembled ground spacing mounting structure of ceramic tile concrete composite board provided in an embodiment of the present invention The structural schematic diagram of plate.
Specific embodiment
Exemplary embodiments of the present disclosure are described in more detail below with reference to accompanying drawings.Although showing the disclosure in attached drawing Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure without should be by embodiments set forth here It is limited.On the contrary, these embodiments are provided to facilitate a more thoroughly understanding of the present invention, and can be by the scope of the present disclosure It is fully disclosed to those skilled in the art.
Embodiment one:
Referring to Fig. 1 to Fig. 5, a kind of assembled ceramic tile concrete composite board metope of the offer of the embodiment of the present invention one is shown in figure Installation system, ceramic tile concrete composite board 1, the back side are fixedly connected with multiple pipe clamps 11, and pipe clamp 11 is curved opening pipe clamp, ceramic tile There are the cavitys for being laid with hydroelectric line between concrete composite board 1 and wall 2;It further include composite plate bindiny mechanism comprising vertical gold Belong to tube body and ceramic tile concrete composite board 1 is connected on vertical metal tube body 12 by pipe code 13, pipe clamp 11, vertical metal tube body 12 is circle Pipe;Vertical metal tube body 12 is fixed on wall 2 using multiple pipe codes 13.
Referring to Fig. 1 to Fig. 3, specifically, ceramic tile concrete composite board 1 includes concrete base 14 and the ceramic tile being fixed in concrete base 14 15, concrete base 14 with a thickness of 10-15mm, ceramic tile 15 with a thickness of 10-15mm, pre-buried pipe clamp attaching nut in concrete base 14.
Wherein, specifically, wall 2 is cast-in-place or precast light concrete wall comprising an one-piece casting wall or multiple The precast wall body unit successively spliced.
Again wherein, pipe code 13 and wall 2 are provided with gasket 131, are used to adjust the verticality of vertical metal tube body 12.
A kind of assembled ceramic tile concrete composite board metope installation system provided by the present embodiment is main compared to the prior art It has the advantage that
1) prefabricated ceramic tile concrete composite board, the industrialization that composite plate may be implemented is highly integrated, extensive using industrialization Batch production, scene no longer needs to wet-felting ceramic tile, is mounted directly;
2) when composite plate is installed, using snap fit, the levelling of live large area can be fast implemented, scene may be implemented Installation rapidly and efficiently improves site operation efficiency;
3) quality is stablized, and more preferable control, flatness and verticality are more accurate;The artificial paving of conventional on-site, quality are unstable Fixed, quality can not control;
4) it can be installed after worker's simple training, without relying on worker's experience;Tradition needs the experience by worker, And experienced worker's aging, and there is the problem of gap between generations;
5) experienced worker is fewer and fewer, and artificial tradition paving cost is higher and higher, using after above-mentioned installation system just It can solve the problem.
Embodiment two:
Referring to Fig. 1 to Fig. 5, a kind of assembled ceramic tile concrete composite board metope provided by Embodiment 2 of the present invention is shown in figure Installation system, the present embodiment are also further made that following as improved technical side on the basis of the various embodiments described above Case: the back side of arc snap-gauge is provided with the arc convex ribs 111 that multiple width directions along arc snap-gauge extend, when snap-gauge is arc When shape snap-gauge, which is arc convex ribs, plays the role of being the booster action on the one hand forming snap-gauge, prevents snap-gauge from occurring Problem on deformation influences the fastness of clamping;When being on the other hand then to remove ground decoration panel, using the convex ribs at back, so that When one end of the length direction of snap-gauge is first detached from pipe fitting, convex ribs can prevent the one end from producing fracture phenomenon when being pulled up, from And ground decoration panel can be removed in the case where proof strength.
Embodiment three:
Referring to Fig. 5, a kind of assembled ceramic tile concrete composite board metope installation of the offer of the embodiment of the present invention three is shown in figure System, the present embodiment be also further made that on the basis of the various embodiments described above it is following as an improved technical scheme: wall The bottom of body 2 is fixedly connected with backing board 22, and backing board 22 supports the bottom of vertical metal tube body 12, the cross section of backing board 22 In zigzag.By the setting of above structure, using the structure of the backing board of zigzag, can prevent bottom (backing board Top is caught in the inside of vertical metal bottom) it is deformed phenomenon, guarantee the stability of keel fitting structure.
Example IV:
Referring to Fig. 3, a kind of assembled ceramic tile concrete composite board metope installation of the offer of the embodiment of the present invention four is shown in figure System, the present embodiment be also further made that on the basis of the various embodiments described above it is following as an improved technical scheme: porcelain The height of cavity is 15-25mm between brick concrete composite board 1 and wall 2, can both guarantee the intensity of composite plate, it is also ensured that multiple The pipeline installation space of plywood bottom abundance.
A kind of assembled ground spacing mounting structure of ceramic tile concrete composite board described in above-described embodiment mainly passes through following Construction method is realized:
1, zinc-plated (the diameter 15mm, according to every piece of ceramic tile ruler of vertical metal tube body 12 is run through by pipe code 13 (high 16mm) Very little unidirectional 4 tube body fixing pieces of double setting) carry out that metope is levelling (can to carry out height difference tune with the zinc-plated gasket of multilayer (1mm thickness) Section), after the completion of wall surface keel (vertical metal tube body) laying, keel level situation need to be checked simultaneously, control errors as far as possible exist In 1mm;
2, using sucker, by the pipe clamp 11 of 1 back of the body bolt ABS alloy of ceramic tile concrete composite board, (interior injection is foamed in pipe clamp when construction Agent, convenient for adjusting height difference) vertical metal tube body 12 is blocked, to admittedly, next procedures be carried out after half an hour at the beginning of 10 points;
3, after after-sales service is directly sucked out with sucker, product ceramic tile concrete composite board is changed into.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art Mind and range.In this way, if these modifications and changes of the present invention belongs to the range of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to include these modifications and variations.

Claims (8)

1. a kind of assembled ceramic tile concrete composite board metope installation system characterized by comprising
Ceramic tile concrete composite board (1), the back side are fixedly connected with multiple pipe clamps (11), and the pipe clamp (11) is curved opening pipe clamp, There are the cavitys for being laid with hydroelectric line between the ceramic tile concrete composite board (1) and wall (2):
Composite plate bindiny mechanism comprising vertical metal tube body (12) and pipe code (13), the pipe clamp (11) are compound by ceramic tile concrete Plate (1) is connected on vertical metal tube body (12), and the vertical metal tube body (12) is round tube;The vertical metal tube body (12) It is fixed on the wall (2) using multiple pipe codes (13).
2. a kind of assembled ceramic tile concrete composite board metope installation system according to claim 1, which is characterized in that the sky The height of chamber is 15-25mm.
3. a kind of assembled ceramic tile concrete composite board metope installation system according to claim 1, which is characterized in that use concrete Pour integral composite plate by mold with ceramic tile, ceramic tile (15) with a thickness of 10-15mm, concrete base (14) with a thickness of 10-15mm, it is pre-buried for connecting the attaching nut of the pipe clamp (11) in the concrete base (14).
4. a kind of assembled ceramic tile concrete composite board metope installation system according to claim 1, which is characterized in that the pipe There are multiple reinforcement convex ribs (111) along arcuate directions at card (11) back side.
5. a kind of assembled ceramic tile concrete composite board metope installation system according to claim 1, which is characterized in that the wall Body (2) is cast-in-place or precast light concrete wall comprising an one-piece casting wall or multiple precast wall body lists successively spliced Member.
6. a kind of assembled ceramic tile concrete composite board metope installation system according to claim 1, which is characterized in that the pipe Code (13) and the wall (2) are provided with gasket, are used to adjust the verticality of vertical metal tube body (12).
7. a kind of assembled ceramic tile concrete composite board metope installation system according to claim 1, which is characterized in that the wall The bottom of body (2) is fixedly connected with backing board (22), and the backing board (22) supports the bottom of the vertical metal tube body (12), The cross section of the backing board (22) is in zigzag.
8. a kind of assembled ceramic tile concrete composite board metope installation method, which is characterized in that including following installation steps:
1) it is fixed on metope by pipe code (13) and gasket, and regulation pipe code (13) is levelling on same plane, then passes through Wear vertical metal tube body (12);
2) the bottom collet positioning support of the vertical metal tube body (12);
3) pipe clamp (11) on ceramic tile concrete composite board (1) back is installed, and injects bonded adhesives or bonding agent, then by the pipe Card (11) blocks the vertical metal tube body (12).
CN201910564273.1A 2019-06-26 2019-06-26 A kind of assembled ceramic tile concrete composite board metope mounting system and method Pending CN110241993A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910564273.1A CN110241993A (en) 2019-06-26 2019-06-26 A kind of assembled ceramic tile concrete composite board metope mounting system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910564273.1A CN110241993A (en) 2019-06-26 2019-06-26 A kind of assembled ceramic tile concrete composite board metope mounting system and method

Publications (1)

Publication Number Publication Date
CN110241993A true CN110241993A (en) 2019-09-17

Family

ID=67889727

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910564273.1A Pending CN110241993A (en) 2019-06-26 2019-06-26 A kind of assembled ceramic tile concrete composite board metope mounting system and method

Country Status (1)

Country Link
CN (1) CN110241993A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110607861A (en) * 2019-09-27 2019-12-24 金螳螂精装科技(苏州)有限公司 Prefabricated light partition wall for building
CN110607888A (en) * 2019-09-25 2019-12-24 金螳螂精装科技(苏州)有限公司 Wall keel wall surface connecting and leveling device for ceramic tile concrete integrated plate
CN110607858A (en) * 2019-09-27 2019-12-24 金螳螂精装科技(苏州)有限公司 Prefabricated formula health partition wall
CN111456361A (en) * 2020-04-01 2020-07-28 河北旭威建筑装饰工程有限公司 Assembled shingle nail structure
CN113775133A (en) * 2021-10-21 2021-12-10 湖南环境生物职业技术学院 Wall structure of mating formation for hotel design
CN115370097A (en) * 2022-09-28 2022-11-22 苏州美瑞德建筑装饰有限公司 Integrated design structure of composite ceramic tile decorative surface

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005016029A (en) * 2003-06-23 2005-01-20 Jfe Steel Kk Tile mounting panel, metal plate for tile mounting panel, and method of mounting tile to metal plate
CN104032925A (en) * 2014-06-30 2014-09-10 龙信建设集团有限公司 Construction method for CSI residential wall and ground empty space
CN105587097A (en) * 2015-12-17 2016-05-18 浙江亚厦装饰股份有限公司 Ground aerial structure capable of being leveled
CN207944593U (en) * 2018-03-06 2018-10-09 中国新兴建设开发有限责任公司 A kind of fixed system for electrical conduits in assembled cavity partition
CN207999011U (en) * 2017-12-30 2018-10-23 浙江亚厦装饰股份有限公司 Toilet metope
CN109235669A (en) * 2018-10-31 2019-01-18 中国三冶集团有限公司 A kind of architectural engineering aluminium alloy structure expansion joint decoration device
CN210288947U (en) * 2019-06-26 2020-04-10 金螳螂精装科技(苏州)有限公司 Wall surface installation system for assembled ceramic tile concrete composite board

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005016029A (en) * 2003-06-23 2005-01-20 Jfe Steel Kk Tile mounting panel, metal plate for tile mounting panel, and method of mounting tile to metal plate
CN104032925A (en) * 2014-06-30 2014-09-10 龙信建设集团有限公司 Construction method for CSI residential wall and ground empty space
CN105587097A (en) * 2015-12-17 2016-05-18 浙江亚厦装饰股份有限公司 Ground aerial structure capable of being leveled
CN207999011U (en) * 2017-12-30 2018-10-23 浙江亚厦装饰股份有限公司 Toilet metope
CN207944593U (en) * 2018-03-06 2018-10-09 中国新兴建设开发有限责任公司 A kind of fixed system for electrical conduits in assembled cavity partition
CN109235669A (en) * 2018-10-31 2019-01-18 中国三冶集团有限公司 A kind of architectural engineering aluminium alloy structure expansion joint decoration device
CN210288947U (en) * 2019-06-26 2020-04-10 金螳螂精装科技(苏州)有限公司 Wall surface installation system for assembled ceramic tile concrete composite board

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110607888A (en) * 2019-09-25 2019-12-24 金螳螂精装科技(苏州)有限公司 Wall keel wall surface connecting and leveling device for ceramic tile concrete integrated plate
CN110607861A (en) * 2019-09-27 2019-12-24 金螳螂精装科技(苏州)有限公司 Prefabricated light partition wall for building
CN110607858A (en) * 2019-09-27 2019-12-24 金螳螂精装科技(苏州)有限公司 Prefabricated formula health partition wall
CN111456361A (en) * 2020-04-01 2020-07-28 河北旭威建筑装饰工程有限公司 Assembled shingle nail structure
CN111456361B (en) * 2020-04-01 2021-09-28 河北旭威建筑装饰工程有限公司 Assembled shingle nail structure
CN113775133A (en) * 2021-10-21 2021-12-10 湖南环境生物职业技术学院 Wall structure of mating formation for hotel design
CN113775133B (en) * 2021-10-21 2022-12-09 湖南环境生物职业技术学院 Wall structure of mating formation for hotel design
CN115370097A (en) * 2022-09-28 2022-11-22 苏州美瑞德建筑装饰有限公司 Integrated design structure of composite ceramic tile decorative surface
CN115370097B (en) * 2022-09-28 2023-10-27 苏州美瑞德建筑装饰有限公司 Integrated design structure of composite ceramic tile decorative surface

Similar Documents

Publication Publication Date Title
CN110241993A (en) A kind of assembled ceramic tile concrete composite board metope mounting system and method
CN111206698B (en) Construction method of assembled wallboard
CN108343181B (en) Novel clay brick outer wall and construction method
CN103669788B (en) Polishing face brick metope laying method
CN111549995A (en) Environment-friendly wall ceramic tile dry hanging structure and construction method thereof
CN104499614A (en) Wall heat-preservation integration point hanging system and mounting method thereof
CN103899072A (en) Hanging member for wet hanging of stone or tiles and wet hanging method
CN105544895A (en) Concrete prefabricated stair
CN106381999A (en) Fair-faced concrete wall intaglio character die plate construction method
CN219690953U (en) Integrated integrated decorative external wall panel
CN210288947U (en) Wall surface installation system for assembled ceramic tile concrete composite board
CN205576959U (en) Light -duty pottery glass siding wall and basic assembly component
CN2856248Y (en) Dry hanging building decorative structure of movable fiber ceramic boards
CN210659110U (en) Assembly type overhead ground installation system of ceramic tile concrete composite board
CN110067361A (en) A kind of assembled facing horizontal splicing mounting structure and installation method
CN110242010A (en) A kind of assembled ground spacing mounting system and method for ceramic tile concrete composite board
CN217105917U (en) Assembled composite ceramic tile module
CN110259144A (en) A kind of novel energy-saving environment-friendly ash concrete lightweight wall plate construction method
CN110080491A (en) The lateral assembled paving structure and method for paving of a kind of ground finishing material
CN110331795A (en) Arch construction top-down construction method
KR101646527B1 (en) The construction and civil engineering and construction methods that integrally formed stone
CN206554360U (en) A kind of assembled porcelain earthenware brick for building and the house built using the porcelain earthenware brick
CN210917822U (en) Green brick wall masonry structure of volume
CN211164582U (en) Ceramic tile concrete intergral template thickness control device
CN205369756U (en) Precast concrete stair

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination