CN110004959A - Concrete cofferdam rapid constructing method and template under circumstance of flowing water - Google Patents

Concrete cofferdam rapid constructing method and template under circumstance of flowing water Download PDF

Info

Publication number
CN110004959A
CN110004959A CN201910344432.7A CN201910344432A CN110004959A CN 110004959 A CN110004959 A CN 110004959A CN 201910344432 A CN201910344432 A CN 201910344432A CN 110004959 A CN110004959 A CN 110004959A
Authority
CN
China
Prior art keywords
panel
template
circumstance
flowing water
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910344432.7A
Other languages
Chinese (zh)
Other versions
CN110004959B (en
Inventor
李远运
唐珂
童杰
杨小华
李红心
张旭
马俊
罗磊
李世凯
严波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guodian Daduhe Monkey Cancer Water Power Construction Co Ltd
China Gezhouba Group No 1 Engineering Co Ltd
Original Assignee
Guodian Daduhe Monkey Cancer Water Power Construction Co Ltd
China Gezhouba Group No 1 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guodian Daduhe Monkey Cancer Water Power Construction Co Ltd, China Gezhouba Group No 1 Engineering Co Ltd filed Critical Guodian Daduhe Monkey Cancer Water Power Construction Co Ltd
Priority to CN201910344432.7A priority Critical patent/CN110004959B/en
Publication of CN110004959A publication Critical patent/CN110004959A/en
Application granted granted Critical
Publication of CN110004959B publication Critical patent/CN110004959B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B8/00Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • E02B8/06Spillways; Devices for dissipation of energy, e.g. for reducing eddies also for lock or dry-dock gates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/02Water-ways
    • E02B9/06Pressure galleries or pressure conduits; Galleries specially adapted to house pressure conduits; Means specially adapted for use therewith, e.g. housings, valves, gates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Revetment (AREA)

Abstract

The present invention provides concrete cofferdam rapid constructing method and template under a kind of circumstance of flowing water, and template processing processes underwater construction template according to the cross-sectional shape of water conservancy diversion hole outlet open channel;Bailey bridge (1), which is laid, in the top side of open channel pouring construction is used as material feeding and auxiliary construction platform;It is in segmental hoisting template to open channel and fixed;The arrangement of hopper and conduit;Underwater concreting;Concrete cofferdam rapid construction under circumstance of flowing water is realized by above step.Template includes two pieces of panels positioned opposite, and truss structure is arranged between panel, and the both ends of panel and open channel side slope are equipped with gap, and flexible block pulp body is equipped between the end positions of panel, two pieces of panels;The equalizing pipe of connection upstream and downstream is additionally provided in template.It is difficult to lift the technical problem of corresponding construction equipment the present invention overcomes diversion tunnel exit.

Description

Concrete cofferdam rapid constructing method and template under circumstance of flowing water
Technical field
The present invention relates to the cofferdam construction field of hydraulic and hydroelectric engineering, concrete cofferdam is fast under especially a kind of circumstance of flowing water Fast construction method and template.
Background technique
During the narrow valley superelevation face dam Hydropower Station Construction of certain deep & thick silt matter deep covering layer, need in diversion tunnel Outlet open channel arranges that annual water-retaining cofferdam is constructed to carry out reconstruction of diversion tunnel into very flood discharging tunnel.
According to previous similar engineering construction experience, when reconstruction of diversion tunnel is constructed at permanent hydraulic tunnel, water-retaining cofferdam one As using outside former water conservancy diversion hole outlet reconstruction construction area range fill earth rock cofferdam, and will be at earth rock cofferdam upstream face reinforcing Reason, wait reconstruct construction after earth rock cofferdam is removed again.In this project, power station power generation and reconstruction when reconstruction construction Very flood discharge hole outlet afterwards is located at exit of hydropower plant's tailwater opposite downstream side less than the deep hole flood discharge that 50m, abutting have come into operation Hole outlet chooses bank downstream, is had the following problems using earth rock cofferdam construction: (1) occupancy river area is big, be easy to cause river stifled Plug and river water harmony height influence tail water power output, reduce generating efficiency;(2) lower level outlet need to be let out for a long time very during flood discharging tunnel reconstruction Flood, the high water of wave is anxious, and earth rock cofferdam not can guarantee very flood discharging tunnel reconstruction construction safety there are larger security risk;(3) Cong Tushi Cofferdam is filled to cofferdam upstream face and is reinforced, to the end cofferdam demolition, long construction period, and construction cost is high.So conventional native stone Cofferdam is unfavorable for the construction of this engineering.
Concrete cofferdam construction is carried out using conventional method, but the cross dimensions of water conservancy diversion hole outlet open channel is big (wide × a height of 13 × 15m), outlet two sides diversion canal top concrete width only 1m, and since construction road is current inconvenient, difficulty of construction compared with Greatly, specifically: diversion tunnel exit is difficult to set up the bridge with enough bearing capacities, and the hanging device of large-tonnage is not easy to arrange, In addition water flow is surged larger, to construct in river channels, template pressure-bearing is larger, and template upstream and downstream lateral water pressure is different, It is influenced by water wave and water pressure unevenness, the easily damaged deformation of template.
Chinese patent literature CN102409688A describes a kind of construction method of steel sheet-pile cofferdam, construction method include with Lower step: (1) preparation of construction works;(2) surveying setting-out: according to the center of the design size in cofferdam and cushion cap, measurement is put Line determines four angle points in cofferdam, and sets the control point that guide pile is positioned as steel sheet-pile cofferdam in corner point;(3) to by leading The inner support system construction that beam, waling, inner support, linking beam and joist form;(4) after waling inner support first welds assembled whole decentralization Carry out inserting piling steel sheet pile construction;(5) mud is inhaled in cofferdam;(6) cofferdam back cover;(7) draw water clear base in cofferdam;(8) cofferdam demolition.But it should Scheme is difficult in the operating condition that road lifting is not easy the application.
Summary of the invention
Technical problem to be solved by the invention is to provide concrete cofferdam rapid constructing method under a kind of circumstance of flowing water and Template, can overcome in the prior art earth rock cofferdam occupy that river area is big, steel sheet-pile cofferdam is because having inconvenient traffic, lift and be not easy Difficulty can overcome upstream and downstream lateral water pressure difference to the pressure change of template in the preferred scheme.
In order to solve the above technical problems, the technical scheme adopted by the invention is that: concrete cofferdam under a kind of circumstance of flowing water Rapid constructing method, comprising the following steps:
S1, template processing, process underwater construction template according to the cross-sectional shape of water conservancy diversion hole outlet open channel;
S2, open channel pouring construction top side lay Bailey bridge as material feeding and auxiliary construction platform;
It is in S3, segmental hoisting template to open channel and fixed;
The arrangement of S4, hopper and conduit;
S5, underwater concreting;
Concrete cofferdam rapid construction under circumstance of flowing water is realized by above step.
In preferred scheme, the block stone of open channel bottom plate is cleared up before construction;
Truck crane is arranged in Bailey bridge to clear up for block stone, when block stone is smaller, is removed block stone to placement in water by diver Hanging basket in, block stone in hanging basket is hung on the dump truck being parked on highway by truck crane;It, will by diver when block stone is larger Wirerope is bundled on block stone, and block stone is removed construction area by truck crane.
In preferred scheme, the structure of the underwater construction template are as follows:
It includes two pieces of panels positioned opposite, and truss structure, back side setting and the fixed company of panel of panel are arranged between panel The longitudinal waling and lateral waling connect;
The both ends of panel and open channel side slope are equipped with gap, and flexible block pulp body is equipped between the end positions of panel, two pieces of panels;
The truss structure includes the more bars perpendicular to panel, and the both ends of bar and panel, longitudinal waling or lateral waling are solid Fixed connection, is additionally provided with more inclined bars, the end of inclined bar is fixedly connected with the rod end head perpendicular to panel.
In preferred scheme, be equipped with clamping plate in the end positions of panel, bolt pass through clamping plate, panel and flexible block pulp body with Nut is fixedly connected;The flexible block pulp body is canvas or rubberized fabric;
It is additionally provided with the equalizing pipe of connection upstream and downstream in template, gate valve is equipped on equalizing pipe, equalizing pipe is as upstream and downstream Water stream channel.
In preferred scheme, eliminator plate flexible is additionally provided in the end positions of panel.
In preferred scheme, the template is divided into multistage from top to bottom, the segmental hoisting in hoisting process;
It is equipped with vertical guide pipe in the position that each section of template is in contact, positioned at the mutual fitting of different sections of guide pipes.
In preferred scheme, the open channel side slope in the upstream side of template is equipped with many places positioning wire rope, positioning wire rope with Template connection, realizes Template Location.
A kind of template for concrete cofferdam rapid constructing method under above-mentioned circumstance of flowing water, it includes positioned opposite Truss structure is arranged between panel for two pieces of panels, and the longitudinal waling and transverse direction that the back side setting of panel is fixedly connected with panel enclose Jail;
The both ends of panel and open channel side slope are equipped with gap, and flexible block pulp body is equipped between the end positions of panel, two pieces of panels;
The truss structure includes the more bars perpendicular to panel, and the both ends of bar and panel, longitudinal waling or lateral waling are solid Fixed connection, is additionally provided with more inclined bars, the end of inclined bar is fixedly connected with the rod end head perpendicular to panel;
It is additionally provided with the equalizing pipe of connection upstream and downstream in template, gate valve is equipped on equalizing pipe, equalizing pipe is as upstream and downstream Water stream channel.
In preferred scheme, eliminator plate flexible is additionally provided in the end positions of panel;
In preferred scheme, the template is divided into multistage from top to bottom, the segmental hoisting in hoisting process;
It is equipped with vertical guide pipe in the position that each section of template is in contact, positioned at the mutual fitting of different sections of guide pipes.
Concrete cofferdam rapid constructing method and template under a kind of circumstance of flowing water provided by the invention, by using in water conservancy diversion Bailey bridge is set above the open channel of hole, and the scheme of the underwater steel truss template of segmental hoisting overcomes diversion tunnel exit and is difficult to lift Corresponding construction equipment, it is also difficult to lift the technical problem of integral mold plate.In the preferred scheme, overcome by the equalizing pipe of setting The upstream and downstream lateral water pressure different influence to template.The flexible block pulp body of setting can ensure that concrete cofferdam is being constructed Sealing characteristics in the process.The eliminator plate of setting can further increase block-water effect.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples:
Fig. 1 is the elevational view of water conservancy diversion hole outlet open channel construction site of the present invention.
Fig. 2 is the construction site top view of water conservancy diversion hole outlet open channel in the present invention.
Fig. 3 is the top view of template in the present invention.
Fig. 4 is the viewgraph of cross-section of template in the present invention.
Fig. 5 is the partial enlargement diagram in Fig. 3 at A.
Fig. 6 is the partial enlargement diagram of form stop in the present invention.
In figure: Bailey bridge 1, diversion tunnel 2, upper former 3, panel 31, truss structure 32, longitudinal waling 33, lateral waling 34, flexible block pulp body 35, eliminator plate 36, clamping plate 37, lower template 4, open channel side slope 5, open channel bottom plate 6, boom hoisting 7 above leads To pipe 8, lower guide pipe 9, positioning wire rope 10, equalizing pipe 11, gate valve 12.
Specific embodiment
Embodiment 1:
As shown in fig. 1, the cross dimensions of diversion tunnel 2 is 13 × 15m, wide × high, gateway opening type.Water conservancy diversion hole outlet is trapezoidal opens Open form open channel, due to landform, cofferdam construction difficulty is larger.Earth rock cofferdam is big in the presence of river area is occupied, and easily causes river Blocking and water level harmony are high, and construction cost investment is big, the problems such as long in time limit.And concrete cofferdam is used then to set in the presence of construction It applies, lifting is difficult, such as road is inconvenient, and large automobile crane is difficult to reach construction site, and design discharge is at this 1960m3/ s, water pressure difference is larger between upstream and downstream, and difficulty of construction is higher.
To overcome above-mentioned difficulties such as Fig. 1, in 2, concrete cofferdam rapid constructing method under a kind of circumstance of flowing water, including it is following Step:
S1, template processing, process underwater construction template according to the cross-sectional shape of water conservancy diversion hole outlet open channel;
In preferred scheme such as Fig. 3 ~ 6, the structure of the underwater construction template are as follows:
It includes two pieces of panels 31 positioned opposite, and truss structure 32, the back side setting of panel 31 and face are arranged between panel 31 The longitudinal waling 33 and lateral waling 34 that plate 31 is fixedly connected;
In Fig. 3,4, the truss structure 32 includes the more bars perpendicular to panel, the both ends of bar and panel 31, Zong Xiangwei Jail 33 or lateral waling 34 are fixedly connected, and are additionally provided with more inclined bars, the end of inclined bar and the rod end perpendicular to panel Head is fixedly connected.Template periphery angle steel is additionally provided in the bottom of panel 31.
The both ends of panel 31 and open channel side slope 5 are equipped with gap, are equipped between the end positions of panel 31, two pieces of panels 31 Flexible block pulp body 35;
Preferred scheme is as shown in Figure 6, is equipped with clamping plate 37 in the end positions of panel 31, bolt passes through clamping plate 37, panel 31 It is fixedly connected with flexible block pulp body 35 with nut;The flexible block pulp body 35 is canvas or rubberized fabric;
It is additionally provided with the equalizing pipe 11 of connection upstream and downstream in template, gate valve 12,11 conduct of equalizing pipe are equipped on equalizing pipe 11 The water stream channel of upstream and downstream.
In preferred scheme, eliminator plate 36 flexible is additionally provided in the end positions of panel 31.Eliminator plate 36 uses rubber Plate, for compensating the gap between template and open channel side slope 5.
In preferred scheme, the template is divided into multistage from top to bottom, the segmental hoisting in hoisting process;It will in this example Template is divided into upper former 3 and 4 two sections of lower template.It is equipped with vertically in the position that upper former 3 is in contact with lower template 4 Guide pipe, positioned at different sections of guide pipes in construction mutual fitting.
S2, top side laying Bailey bridge 1 conduct material feeding and auxiliary construction platform in open channel pouring construction;
According to diversion tunnel outlet stream form, there are a certain amount of block of stones for the open channel bottom plate 6 of water conservancy diversion hole outlet.In cofferdam construction Before, professional diving personnel need to be arranged to feel.Bailey bridge 1 be arranged 1 25t truck crane for block stone cleaning, when block stone compared with Hour, block stone is removed to the hanging basket placed in water by diver, block stone in hanging basket is hung to and is parked on highway by truck crane On dump truck;When block stone is larger, wirerope is bundled on block stone by diver, block stone is removed into construction area by truck crane Domain.
It is in S3, segmental hoisting template to open channel and fixed;
Upper former 3 and lower template 4 are completed the process at assembled scene, with 1 25t truck crane cooperation 10t flat car transhipment Boom hoisting 7 to bank is first to be lifted lower template 4 extremely by 200t truck crane in 200t truck crane R=26m working range Cofferdam construction predetermined position, it should be noted that since construction location is undesirable, and road is narrow, the arm of force of 200t truck crane compared with Long, the stress in cofferdam construction predetermined position, 200t truck crane is bad, it is difficult to lift by crane integral mold plate.
After the completion of lifting, by positioning wire rope 10 lower template 4 is fixed on by wirerope using bottle gouard moved by hands pre- Positioning is set.Specific steps are as follows: multiple 20t bottle gouards moved by hands are fixed on the upstream side of open channel side slope 5 by anchor pile, preferably also wrap It includes on the downstream side and Bailey bridge 1 of open channel side slope 5, bottle gouard moved by hands is connect with one end of positioning wire rope 10, positioning wire rope 10 The other end connect with lower template 4, by tightening and loosen each bottle gouard moved by hands, adjust lower template 4 to predetermined position simultaneously It is fixed.It recycles 200t truck crane to lift upper former 3, in hoisting process, makes the upper guide pipe 8 and lower layer's mould of upper former 3 The mutual fitting of lower guide pipe 9 of plate 4.To ensure being reliably connected for upper former 3 and lower template 4, pass through positioning wire rope 10 Upper former 3 is adjusted to predetermined position and fixation.It surges to prevent water flow when concreting under water and template is caused to shift.It is flat Pressure pipe 11 is arranged in upper former 3, and the gate valve 12 on equalizing pipe 11 is opened in hoisting process, balance upstream and downstream side Water pressure.
The arrangement of S4, hopper and conduit;Underwater concrete pouring is poured using tremie method, and conduit bottom is located at lower layer's mould Close to the position of open channel bottom plate 6 between two pieces of panels 31 of plate 4, conduit diameter is φ 250mm, is arranged along template length direction More, be preferably 6 in this example, and hopper is located at the lower section of 1 side of Bailey bridge, is convenient for dumper fast pouring.
S5, underwater concreting;
When pouring, conduit blanking wheel stream is carried out, and concrete face rises in parallel, must not stay construction joint, disposable continuous placing finishes.Under water When pouring concrete, the first batch of concrete into conduit is no less than 1.5m3, conduit is constantly promoted in casting process, it is ensured that conduit is embedded to concrete Depth is not less than 60cm.In casting process, concrete struts flexible block pulp body 35, makes flexible block pulp body 35 and open channel side slope 5 fit closely, and realization blocks water.
Concrete cofferdam rapid construction under circumstance of flowing water is realized by above step.
Embodiment 2:
In Fig. 1 ~ 6, a kind of template for concrete cofferdam rapid constructing method under above-mentioned circumstance of flowing water, it includes opposite Two pieces of panels 31 of arrangement, panel use 2.5mm steel plate, and truss structure 32, the back side setting of panel 31 are arranged between panel 31 The longitudinal waling 33 and lateral waling 34 being fixedly connected with panel 31;Longitudinal waling 33 uses channel steel, and lateral waling 34 uses angle Steel.
In preferred scheme, the template is divided into multistage from top to bottom, the segmental hoisting in hoisting process;As shown in figure 1, It is divided into upper former 3 and lower template 4.
The both ends of panel 31 and open channel side slope 5 are equipped with gap, gap width 5-20cm, preferably 15cm, in panel 31 End positions, flexible block pulp body 35 is equipped between two pieces of panels 31;
Preferred scheme is as shown in Figure 6, is equipped with two clamping plates 37 in the end positions of panel 31, and clamping plate 37 uses 8mm steel plate, Bolt passes through clamping plate 37, panel 31 and flexible block pulp body 35 and is fixedly connected with nut;The flexible block pulp body 35 be canvas or Rubberized fabric;The flexible block pulp body 35 is canvas or rubberized fabric;In casting process, concrete supports flexible block pulp body 35 It opens, fits closely flexible block pulp body 35 with open channel side slope 5, realization blocks water.
The truss structure 32 includes the more bars perpendicular to panel, the both ends of bar and panel 31, longitudinal waling 33 or Lateral waling 34 is fixedly connected, and is additionally provided with more inclined bars, and the end of inclined bar is fixed with the rod end head perpendicular to panel Connection;The horizon bar and brace of truss structure 32 in this example use angle steel.Slot is used in the hoisting point position of truss structure 32 Steel substitutes angle steel.Template periphery angle steel is additionally provided in the bottom of panel 31.
It is additionally provided with the equalizing pipe 11 of connection upstream and downstream in template, gate valve 12 is equipped on equalizing pipe 11, equalizing pipe 11 is made For the water stream channel of upstream and downstream.Equalizing pipe 11 in this example uses DN300 equalizing pipe, and the equalizing pipe 11 in this example stretches out template Upstream side and downstream side be respectively 0.5m, and 1, mating gate valve is respectively installed in downstream side, in the construction process opens gate valve 12 It opens, underwater cofferdam carries out gate valve closing after the completion of pouring, to balance template upstream and downstream side water flow pressure to the impact force of template.
In preferred scheme, eliminator plate 36 flexible is additionally provided in the end positions of panel 31;Eliminator plate 36 uses rubber Material, the end length of extending panel 31 are 10 ~ 25cm, preferably 15 ~ 30cm, eliminator plate 36 by deformation under water pressure with Open channel side slope 5 fits closely, and further increases block-water effect.
It is equipped with vertical guide pipe in the position that each section of template is in contact, guide pipe is arranged as along template length direction 3, the guide pipe of upper former 3 and lower template 4 in this example is mounted on the middle position of truss structure 32, upper guide pipe 8 Using DN150 steel pipe, lower guide pipe 9 uses DN100 steel pipe.Positioned at the upper guide pipe 8 of upper former 3 and lower template 4 under The mutual fitting during the installation process of guide pipe 9.
The above embodiments are only the preferred technical solution of the present invention, and are not construed as limitation of the invention, this hair The technical characteristic of bright middle record can be combined with each other use under the premise of not conflicting, and protection scope of the present invention should be with right It is required that record technical solution, including claim record technical solution in technical characteristic equivalents be protection model It encloses.Equivalent replacement i.e. within this range is improved, also within protection scope of the present invention.

Claims (10)

1. concrete cofferdam rapid constructing method under a kind of circumstance of flowing water, it is characterized in that the following steps are included:
S1, template processing, process underwater steel truss template according to the cross-sectional shape of water conservancy diversion hole outlet open channel;
S2, open channel pouring construction top side lay Bailey bridge (1) be used as material feeding and auxiliary construction platform;
It is in S3, segmental hoisting template to open channel and fixed;
The arrangement of S4, hopper and conduit;
S5, underwater concreting;
Concrete cofferdam rapid construction under circumstance of flowing water is realized by above step.
2. concrete cofferdam rapid constructing method under a kind of circumstance of flowing water according to claim 1, it is characterized in that: constructing The block stone of preceding cleaning open channel bottom plate (6);
In Bailey bridge (1) setting truck crane for the cleaning of block stone, when block stone is smaller, block stone is removed to being placed on water by diver In hanging basket in, block stone in hanging basket is hung on the dump truck being parked on highway by truck crane;When block stone is larger, by diver Wirerope is bundled on block stone, block stone is removed into construction area by truck crane.
3. concrete cofferdam rapid constructing method under a kind of circumstance of flowing water according to claim 1, it is characterized in that: described The structure of underwater construction template are as follows:
It includes two pieces of panels (31) positioned opposite, truss structure (32) is arranged between panel (31), the back side of panel (31) The longitudinal waling (33) being fixedly connected with panel (31) and lateral waling (34) are set;
The both ends and open channel side slope (5) of panel (31) are equipped with gap, the end positions in panel (31), between two pieces of panels (31) Equipped with flexible block pulp body (35);
The truss structure (32) includes the more bars perpendicular to panel, the both ends and panel (31) of bar, longitudinal waling (33) Or lateral waling (34) is fixedly connected, and is additionally provided with more inclined bars, the end of inclined bar and the rod end head perpendicular to panel It is fixedly connected.
4. concrete cofferdam rapid constructing method under a kind of circumstance of flowing water according to claim 3, it is characterized in that: in panel (31) end positions are equipped with clamping plate (37), and bolt passes through clamping plate (37), panel (31) and flexible block pulp body (35) and nut and consolidates Fixed connection;The flexible block pulp body (35) is canvas or rubberized fabric;
It is additionally provided with the equalizing pipe (11) of connection upstream and downstream in template, is equipped with gate valve (12) on equalizing pipe (11), equalizing pipe (11) water stream channel as upstream and downstream.
5. concrete cofferdam rapid constructing method under a kind of circumstance of flowing water according to claim 4, it is characterized in that: in panel (31) end positions are additionally provided with eliminator plate flexible (36).
6. concrete cofferdam rapid constructing method under a kind of described in any item circumstance of flowing water according to claim 1 ~ 5, feature Be: the template is divided into multistage from top to bottom, the segmental hoisting in hoisting process;
It is equipped with vertical guide pipe in the position that each section of template is in contact, positioned at the mutual fitting of different sections of guide pipes.
7. concrete cofferdam rapid constructing method under a kind of circumstance of flowing water according to claim 6, it is characterized in that: in mould The open channel side slope (5) of the upstream side of plate is equipped with many places positioning wire rope (10), and positioning wire rope (10) is connect with template, realizes mould Plate positioning.
8. template of the one kind for concrete cofferdam rapid constructing method under the described in any item circumstance of flowing water of claim 1 ~ 7, It is characterized in that: it includes two pieces of panels (31) positioned opposite, truss structure (32) are set between panel (31), panel (31) The longitudinal waling (33) and lateral waling (34) that back side setting is fixedly connected with panel (31);
The both ends and open channel side slope (5) of panel (31) are equipped with gap, the end positions in panel (31), between two pieces of panels (31) Equipped with flexible block pulp body (35);
The truss structure (32) includes the more bars perpendicular to panel, the both ends and panel (31) of bar, longitudinal waling (33) Or lateral waling (34) is fixedly connected, and is additionally provided with more inclined bars, the end of inclined bar and the rod end head perpendicular to panel It is fixedly connected;
It is additionally provided with the equalizing pipe (11) of connection upstream and downstream in template, is equipped with gate valve (12) on equalizing pipe (11), equalizing pipe (11) water stream channel as upstream and downstream.
9. the template of concrete cofferdam rapid constructing method under a kind of circumstance of flowing water according to claim 8, it is characterized in that: Eliminator plate flexible (36) are additionally provided in the end positions of panel (31).
10. the template of concrete cofferdam rapid constructing method, feature under a kind of circumstance of flowing water according to claim 8 Be: the template is divided into multistage from top to bottom, the segmental hoisting in hoisting process;
It is equipped with vertical guide pipe in the position that each section of template is in contact, positioned at the mutual fitting of different sections of guide pipes.
CN201910344432.7A 2019-04-26 2019-04-26 Quick construction method and template for concrete cofferdam in flowing water environment Active CN110004959B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910344432.7A CN110004959B (en) 2019-04-26 2019-04-26 Quick construction method and template for concrete cofferdam in flowing water environment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910344432.7A CN110004959B (en) 2019-04-26 2019-04-26 Quick construction method and template for concrete cofferdam in flowing water environment

Publications (2)

Publication Number Publication Date
CN110004959A true CN110004959A (en) 2019-07-12
CN110004959B CN110004959B (en) 2021-04-27

Family

ID=67174434

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910344432.7A Active CN110004959B (en) 2019-04-26 2019-04-26 Quick construction method and template for concrete cofferdam in flowing water environment

Country Status (1)

Country Link
CN (1) CN110004959B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110725320A (en) * 2019-10-16 2020-01-24 北京翔鲲水务建设有限公司 Sand prevention sill pouring method
CN114991091A (en) * 2022-05-10 2022-09-02 中国葛洲坝集团第二工程有限公司 Anti-impact wear-resistant concrete pouring method for hyperbolic twisted surface flow surface bottom plate

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070033097A (en) * 2005-09-20 2007-03-26 민병이 Outflow device connected to drain pipe of river bank
CN101824814A (en) * 2010-05-19 2010-09-08 葛洲坝集团第一工程有限公司 Method for plugging diversion tunnel without cutoff by using cast-in-place reinforced concrete gate and gate
CN105586858A (en) * 2016-03-10 2016-05-18 中国电建集团成都勘测设计研究院有限公司 Blocking structure of diversion tunnel
CN106522406A (en) * 2016-11-18 2017-03-22 哈尔滨鸿盛房屋节能体系研发中心 Assembly type cast-in-place concrete exterior thermal insulation wall steel skeleton framework system and connecting piece
CN106939581A (en) * 2017-05-11 2017-07-11 合肥学院 A kind of the interception net and its construction method of the mouth that inrushed for dykes and dams
CN208472743U (en) * 2018-05-24 2019-02-05 上海勘测设计研究院有限公司 Assembled cofferdam structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070033097A (en) * 2005-09-20 2007-03-26 민병이 Outflow device connected to drain pipe of river bank
CN101824814A (en) * 2010-05-19 2010-09-08 葛洲坝集团第一工程有限公司 Method for plugging diversion tunnel without cutoff by using cast-in-place reinforced concrete gate and gate
CN105586858A (en) * 2016-03-10 2016-05-18 中国电建集团成都勘测设计研究院有限公司 Blocking structure of diversion tunnel
CN106522406A (en) * 2016-11-18 2017-03-22 哈尔滨鸿盛房屋节能体系研发中心 Assembly type cast-in-place concrete exterior thermal insulation wall steel skeleton framework system and connecting piece
CN106939581A (en) * 2017-05-11 2017-07-11 合肥学院 A kind of the interception net and its construction method of the mouth that inrushed for dykes and dams
CN208472743U (en) * 2018-05-24 2019-02-05 上海勘测设计研究院有限公司 Assembled cofferdam structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨海新: "《建筑物下大采深坚硬顶板煤层安全高效开采技术研究》", 30 June 2018, 北京:煤炭工业出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110725320A (en) * 2019-10-16 2020-01-24 北京翔鲲水务建设有限公司 Sand prevention sill pouring method
CN114991091A (en) * 2022-05-10 2022-09-02 中国葛洲坝集团第二工程有限公司 Anti-impact wear-resistant concrete pouring method for hyperbolic twisted surface flow surface bottom plate
CN114991091B (en) * 2022-05-10 2024-03-22 中国葛洲坝集团第二工程有限公司 Anti-impact and wear-resistant concrete pouring method for bottom plate of double-twist-surface overflow surface

Also Published As

Publication number Publication date
CN110004959B (en) 2021-04-27

Similar Documents

Publication Publication Date Title
CN109339065B (en) Method for deep water exposed bedrock close-packed pile supporting construction bearing platform
CN105544575B (en) A kind of bottom concrete construction method under water of use steel truss reinforcement
CN101538833B (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN210529712U (en) Construction structure for foundation pit crossing underground pipeline area
CN105350526B (en) Method for setting up steel platform
CN112343003A (en) Reinforcing and seepage-proofing treatment method for ultra-shallow soil covering of river bed in tunnel underpass river construction
CN111676892A (en) Assembly type high-pile wharf node and construction method thereof
CN107034842A (en) A kind of modular assembly formula pile foundation wharfs structural system and its construction method
CN110004959A (en) Concrete cofferdam rapid constructing method and template under circumstance of flowing water
CN105332382B (en) Adjacent river foundation ditch builds island cofferdam clay water stop construction method
CN113502828B (en) Processing method for early warning of deep foundation pit
CN113931135A (en) Column cage stone pile supporting cage type flashboard for blocking breach and burst and rapid emergency rescue method
CN210315607U (en) Concrete cofferdam construction template
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN101476298B (en) Bridge integral descending construction method and construction equipment
CN107940102B (en) Underground raw water pipeline protection construction method
CN115478495A (en) Plate culvert reinforcing device capable of exerting flexibility of corrugated steel and construction method of plate culvert reinforcing device
CN213448506U (en) Plugging structure arranged between foundation pit fender posts
CN112144425B (en) Box culvert drainage ditch pouring method located at high water level and in sandy soil environment
CN211171994U (en) Occlusive pile and diaphragm wall combined foundation pit supporting structure
CN210151762U (en) Steel sheet pile cofferdam layered bottom sealing structure under silt geological condition
CN208455615U (en) A kind of prefabricated guide groove structure of concrete cut
KR0164646B1 (en) Concrete reinforcement method in the water
CN112575777A (en) Frame reinforcing system and method for high-speed railway pier foundation penetrating through under channel
CN110374676A (en) Freeway tunnel Central Drainage construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant