CN107034842A - A kind of modular assembly formula pile foundation wharfs structural system and its construction method - Google Patents

A kind of modular assembly formula pile foundation wharfs structural system and its construction method Download PDF

Info

Publication number
CN107034842A
CN107034842A CN201710434127.8A CN201710434127A CN107034842A CN 107034842 A CN107034842 A CN 107034842A CN 201710434127 A CN201710434127 A CN 201710434127A CN 107034842 A CN107034842 A CN 107034842A
Authority
CN
China
Prior art keywords
pile foundation
modularization
superstructure portion
modular assembly
modularization superstructure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710434127.8A
Other languages
Chinese (zh)
Inventor
江义
程泽坤
吴志良
金晓博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Third Harbor Consultants
Original Assignee
CCCC Third Harbor Consultants
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Third Harbor Consultants filed Critical CCCC Third Harbor Consultants
Priority to CN201710434127.8A priority Critical patent/CN107034842A/en
Publication of CN107034842A publication Critical patent/CN107034842A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/068Landing stages for vessels
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/20Equipment for shipping on coasts, in harbours or on other fixed marine structures, e.g. bollards
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/20Equipment for shipping on coasts, in harbours or on other fixed marine structures, e.g. bollards
    • E02B3/24Mooring posts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/20Equipment for shipping on coasts, in harbours or on other fixed marine structures, e.g. bollards
    • E02B3/26Fenders
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Ocean & Marine Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of modular assembly formula pile foundation wharfs structural system, including:Pile foundation(1), modularization superstructure portion(2), pile foundation and modularization superstructure portion connecting node(3);The technical scheme considers that by harbour general layout yardstick be N * L(It is long)* B(It is wide)M, is directly divided into N number of superstructure portion(2), be prefabricated in the factory the N number of superstructure portion of processing first(2), install in place by water-borne transport to scene, then overall assembling.The invention discloses a kind of construction method of modular assembly formula pile foundation wharfs structural system.The present invention can avoid a large amount of extraordinary dangerous construction operation processes waterborne, reduce field personnel's quantity, also shorten the duration, significantly improve construction work efficiency.

Description

A kind of modular assembly formula pile foundation wharfs structural system and its construction method
Technical field
The present invention relates to port and pier field, and in particular to a kind of modular assembly formula pile foundation wharfs structural system and its applies Work method.
Background technology
High-piled slab & girder wharf is a kind of wharf structure for being primarily suitable for soft soil foundation, and conventional foundation pile pattern includes Concrete square pile, concrete tubular pile, steel-pipe pile etc., superstructure are concrete beam and plate, mostly partial precast structure.In recent years Come, also have the large-scale pile foundation wharfs in part be built in that coating is shallower in addition exposed bedrock face on, such as ton ore code of Baosteel 30 The large-scale foreign experts engineerings, high-pile beam formula pile foundation such as head engineering, the ton ore terminal engineering of Zhoushan Shu Lang lakes 40 The scope of application of wharf structure is more and more wider.
In the construction of offshore type port and pier, pile foundation wharfs structure is a kind of very common structural shape, and China passes Uniting pile foundation wharfs upper structure owner will be with the structural system based on cast-in-place crossbeam, prefabricated longeron.Traditional pile foundation dock structure Work progress is built to generally comprise:1. pile sinking, 2. erect waling, 3. crossbeam end templates and side template, 4. assembling reinforcements, and 5. pour Concrete beam is noted, 6. install prefabricated longeron(Track girder), 7. install prefabricated panel, and the 8. cast-in-place beams in length and breadth of completion and surface layer are poured Note.In traditional pile foundation Wharf Construction, component standardization degree, batch production making, efficiency of construction, construction period, assembling degree Deng still needing to be further improved.
Traditional long piled wharf superstructure system typically largely uses cast-in-place concrete, and concrete amount is larger, from heavy burden Carry larger, and then bottom piling strtucture is not economical enough.In addition, cast-in-place crossbeam cast often further relates to the formwork support arrangement compared with low water level With removing work operations, effective construction operation time is shorter, and the construction period is longer, and it is relatively low to build work efficiency.It is a large amount of waterborne artificial Construction operation, the quantity such as field worker, technology, administrative staff is more, and normative operation manages very difficult, site safety, engineering The more difficult control of quality.
The content of the invention
In view of above-mentioned existing traditional high stake(Beam and slab type)The shortcoming of harbour superstructure system, it is an object of the invention to carry For a kind of modular assembly formula pile foundation wharfs structural system and its construction method, for overcoming traditional pile foundation terminal designs and construction Shortcoming.
A kind of technical scheme of the present invention is as follows:
A kind of modular assembly formula pile foundation wharfs structural system includes:Pile foundation(1), modularization superstructure portion(2), stake Base and modularization superstructure portion connecting node(3);The modularization superstructure portion(2)Including case section longitudinal beam(201), case Type or I-shaped gooseneck(202), composite faceplate structure portion(203)With berthing member portion(204);Case section longitudinal beam(201), box Or I-shaped gooseneck(202)With composite faceplate structure portion(203)It is connected, berthing member portion(204)Positioned at wharf apron case Type or I-shaped gooseneck(202)Cantilever part, both are connected by bolt;The pile foundation connects with modularization superstructure portion Connect node(3)By being fixed on case section longitudinal beam(201)On bottom protuberance(301)Directly and pile foundation(1)Connection, pressure Power slip casting portion(303)Located at bottom protuberance(301)With plugging plate at the top of pile foundation(302)Between cavity in;The pressure note Slurry portion(303)Slurries are injected, by the pile foundation(1), modularization superstructure portion(2), pile foundation and modularization superstructure Portion's connecting node(3)It is connected as a single entity.
Further, the pile foundation(1)Using straight stake steel-pipe pile, it is easy to modularization superstructure portion(2)Overall peace Dress construction in place.
Further, the modularization superstructure portion(2)It is additionally provided with wharf anchors facility(251), pier mooring facility (252), technique auxiliary equipment(253)And safety aid facility;The wharf anchors facility(251)For rubber fender, pass through spiral shell Bolt and berthing member portion(204)It is connected;The pier mooring facility(252)Take off for cast steel, cast iron bollard or quickly Cable hook, passes through bolt and box or I-shaped gooseneck(202)It is connected as a single entity;The technique auxiliary equipment(253)For rail and its Anchoring piece, passes through rail anchoring piece and case section longitudinal beam(201)It is connected as a single entity;The safety aid facility includes shield wheel bank (254), rubber ladder.
Further, the modularization superstructure portion(2)By the first modularization superstructure portion (2A) and second Modularization superstructure portion (2B) is constituted.
Further, the wharf anchors facility(251), pier mooring facility(252), technique auxiliary equipment(253)With Safety aid facility is arranged at intervals at the modularization superstructure portion(2)On, wherein wharf anchors facility(251), harbour system Moor facility(252)Positioned at wharf apron side.
Further, the first modularization superstructure portion (2A) and the second modularization superstructure portion (2B) are described Pile foundation(1)With the pile foundation and modularization superstructure portion connecting node(3)The position relationship of top is:Arranged on left and right sides The first modularization superstructure portion (2A), the second modularization superstructure portion (2B) of middle setting or the first modularization are set Superstructure portion (2A) and second modularization superstructure portion (2B) interlaced arrangement.
Further, the case section longitudinal beam(201)By box beam the week side of boss steel plate(201a), transverse stiffener(201b)、 Longitudinal stiffener(201c), bottom protuberance(301)Composition.
Further, the technique auxiliary equipment(253)With lower transverse direction, longitudinal stiffener(201b、201c)The storehouse of composition Embedded rail anchoring beam is formed every interior concrete of the filling containing swelling agent(253a)..
Further, the modularization superstructure portion(2)Modularized design is carried out using light-weight high-strength material, module is put down Face scale size mutually should determine that according to over-water construction lifting appliance ability.
It is as follows that the present invention separately provides a kind of construction method of modular assembly formula pile foundation wharfs structural system:
A. modularization superstructure portion is completed in prefabricated processing factory(2)Structure steel fabrication processing;Meanwhile, pile driving barge is dispatched to work Journey scene, carries out piling construction;
B. after pile driving barge reaches engineering site, pile foundation is carried out(1)Piling construction, and piling deviation, and shape are monitored in time Into modularization superstructure portion(2)Live piling foundation plan, and feed back to modularization superstructure portion in time(2)Prefabricated processing department Door;If necessary, it is considered as setting up pile foundation waling, it is ensured that pile foundation off normal is stable;
C. according to the piling deviation situation of scene feedback, modularization superstructure portion is completed in prefabricated processing factory(2)Bottom it is convex Go out portion(301), bottom projection ends(301a)Be welded and fixed, then will make the modularization superstructure portion that machines (2)Transport to scene;
D. while process (a) ~ (c) deploys, the device by ship for possessing corresponding crane capacity is dispatched to engineering site, module is treated Change superstructure portion(2)Work in place is installed in transport to scene progress;
E. wait that the device by ship for possessing corresponding crane capacity is reached the spot, modularization superstructure portion is carried out in time(2)Installation Work, and pile foundation and modularization superstructure portion connecting node are carried out in time(3)Mortar depositing construction, completes pier body structure and applies Work;
F. the installation and laying construction for carrying out harbour affiliated facility and rail etc. work, and carry out whole set equipment disembarkation and its tune Trial work is made, and completes Wharf Construction.
Beneficial effect:The construction overall process in the modular assembly formula pile foundation wharfs, can avoid a large amount of special types waterborne Dangerous construction operation process, significantly improves construction efficiency, and traditional High-piled Wharf Construction engineering method limitation, effectively save work are broken through completely Phase, the personnel amounts such as field worker, technology, management are reduced, reduce human cost.If it is considered that human cost in future also continues to increase Plus, scheme long term advantage also will become apparent from.
The agent structure system of the modular assembly formula high pile pier structure system mainly uses the steel of high-strength light, Superstructure gravity load is smaller, and then infrastructure piling strtucture is overall also relatively inexpensive.Meanwhile, complete straight stake steel pipe pile foundation Preferably, anti-seismic performance is more superior for dock structure deformability, is particularly suitable for use in macroseism area.
The superstructure of the modular assembly formula high pile pier structure system is all made using batch production and processed, and can be had Effect ensures that Superstructure Construction makes quality.In addition, superstructure is installed using live integral module, construction work is remarkably improved Effect.
The modular assembly formula high pile pier structure system longeron uses steel box-girder, can preferably adapt to harbour top weight Type operating procedure equipment load, including container bridge, door machine etc., wheel load are generally 30 ~ 80ton, wheelspan typically 0.6 ~ 1.2m, belongs to heavy load.
Brief description of the drawings
Fig. 1 is the top view of the present invention, module 2A, 2B combination one;
Fig. 2 is the top view of the present invention, module 2A, 2B combination two;
Fig. 3 is modularization superstructure portion, module 2A;
Fig. 4 is modularization superstructure portion, module 2B;
Fig. 5 is section of quay wall schematic diagram;
Fig. 6 is pile foundation and modularization superstructure portion connecting node figure.
Wherein, section of quay wall schematic diagram, pile foundation and modularization superstructure portion connecting node figure are described as follows:
1st, pile foundation
2nd, modularization superstructure portion
3rd, pile foundation and modularization superstructure portion connecting node
201st, case section longitudinal beam
201a, box beam the week side of boss steel plate
201b, transverse stiffener
201c, longitudinal stiffener
202nd, box or I-shaped gooseneck
203rd, composite faceplate structure portion
204th, berthing member portion
251st, wharf anchors facility
252nd, pier mooring facility
253rd, technique auxiliary equipment
253a, embedded rail anchoring beam
254th, shield wheel bank
301st, bottom protuberance
301a, bottom projection ends
302nd, plugging plate at the top of pile foundation
303rd, slip casing by pressure portion
Embodiment
Embodiments of the present invention are illustrated by particular specific embodiment below, thus those skilled in the art can illustrate Advantages of the present invention and effect is well understood in content disclosed by book.
For clear expression modular assembly formula pile foundation wharfs structural system and its construction method, embodiment one, two with The large-scale bulk cargo terminals of the long 1400m of water front(5 berths)Exemplified by, design vessel type is 100,000 tons of bulk freighters.The pile foundation of accompanying drawing, berthing, Mooring facilities type is to assume.
It is first in order to describe the present embodiment modular assembly formula pile foundation wharfs structural system and its construction method in detail First need to explain the structural system, specifically refer to brief description of the drawings.
Embodiment 1
As described in Fig. 1-6, a kind of modular assembly formula pile foundation wharfs structural system includes:
Pile foundation(1), modularization superstructure portion(2), pile foundation and modularization superstructure portion connecting node(3);
Bulk cargo terminals berth general layout yardstick is 1400(It is long)* 30(It is wide)M, by its top structural portion(2)It is divided into 28, first Make and process in factory, install in place by water-borne transport to scene, then overall assembling, wherein the first modularization superstructure portion (2A), the second modularization superstructure portion(2B)Each 14, each planar dimension 50(It is long)* 30(It is wide)m.
The pile foundation of the modular assembly formula pile foundation wharfs structural system(1)Using straight stake steel-pipe pile, it is easy to top Structural portion(2)Integral installation is constructed in place.The modularization superstructure portion (2A) of the present embodiment first and second,(2B)Relate separately to 18 Pile base, totally 432.
The modularization superstructure portion(2)Provided with case section longitudinal beam(201), box or I-shaped gooseneck(202), it is compound Panel construction portion(203)With berthing member portion(204);Modularization superstructure portion(2)Pass through case section longitudinal beam(201), box Or I-shaped gooseneck(202)With composite faceplate structure portion(203)It is connected, berthing member portion(204)Positioned at wharf apron case Type or I-shaped gooseneck(202)Cantilever part, is connected by bolt with it.
The pile foundation and modularization superstructure portion connecting node(3), by being fixed on case section longitudinal beam(201)Bottom Protuberance(301)Directly and pile foundation(1)Connection, slip casing by pressure portion(303)Located at case section longitudinal beam(201)Bottom protrusion Portion(301)With plugging plate at the top of pile foundation(302)Between cavity in, the slurries requirement typically used for high-strength cement slurry or other Macromolecule polymeric material, is properly added swelling agent, technological requirement slip casing by pressure in two times, it can be ensured that node connection is reliable.Pressure Slip casting portion(303)Height h1 be more than bottom protuberance(301)Height h2, slip casing by pressure portion(303)Width D be more than under Portion's protuberance(301)Width d.
The modularization superstructure portion(2)It is additionally provided with the facilities such as wharf anchors, mooring, technique auxiliary and safety auxiliary. Wharf anchors facility(251)Generally rubber fender, passes through bolt and berthing member portion(204)It is connected.Pier mooring is set Apply(252)Generally cast steel, cast iron bollard or quick releasing hook etc., pass through bolt and box or I-shaped gooseneck(202)Even It is integrated.Technique auxiliary equipment(253)Generally rail and its anchoring piece, pass through rail anchoring piece and case section longitudinal beam(201) It is connected as a single entity.Safety aid facility relates generally to shield wheel bank(254), rubber ladder.
Case section longitudinal beam(201)Provided with box beam the week side of boss steel plate(201a), transverse stiffener(201b), longitudinal stiffener (201c), bottom protuberance(301).Wherein, bottom projection ends(301a)With bottom protuberance(301)It is connected.
When laying process auxiliary equipment(253)When, to ensure that the heavy types such as harbour face container bridge, gantry crane are set Standby normal even running, need to be in case section longitudinal beam(201)Transverse direction, longitudinal stiffener(201b、c)The storehouse of formation is set every interior Embedded rail anchoring beam(253a), fill the concrete containing swelling agent so that the connection of track anchoring piece is firm.
Due to above-mentioned modularization superstructure portion(2)Using modularized design, module flat yardstick is larger, its individual module It is related to the area of plane for 1500 square metres, using high-strength light steel construction, about 2250 ~ 3000 tons of deadweight, therefore, its construction is hung The lifting appliance elevating capacity waterborne that reload request is used is about 4500 ~ 6000 tons.The equipment of domestic corresponding elevating capacity waterborne is Through relatively conventional.
The present embodiment is according to wharf anchors facility(251), pier mooring facility(252)Security admission spacing and arrangement side Formula, by modularization superstructure portion(2)It is divided into 2 kinds of models(2A)、(2B), other structures construct completely the same.Then according to code Head rest moors facility(251), pier mooring facility(252)Arrangement requirement, give 2 kinds of rational combinations.
Embodiment 2
As shown in figures 1 to 6, the construction method of the structural system of modular assembly formula pile foundation wharfs described in embodiment 1:
A. modularization superstructure portion is completed in prefabricated processing factory(2)Structure steel fabrication processing.Meanwhile, pile driving barge is dispatched in time To engineering site, piling construction is carried out.
B. treat that pile driving barge reaches engineering site, carry out Pile Foundation of Wharf part piling construction, and monitor piling deviation in time, and Form modularization superstructure portion(2)Live piling foundation plan, and feed back to modularization superstructure portion in time(2)Prefabricated processing Department;If necessary, it is considered as setting up pile foundation waling, it is ensured that pile foundation off normal is stable.
C. according to the piling deviation situation of scene feedback, modularization superstructure portion is completed(2)Bottom protuberance (301), bottom projection ends(301a)Be welded and fixed, then will make the modularization superstructure portion that machines(2) In batches through water-borne transport to scene.
D. while working procedure (a) ~ (c) deploys, suitable time point is selected, dispatches possess corresponding lifting energy in time The device by ship of power treats modularization superstructure portion to engineering site(2)Work in place is installed in transport to scene progress.
E. wait that the device by ship for possessing corresponding crane capacity is reached the spot, modularization superstructure portion is carried out in time(2)'s Installment work, and pile foundation and modularization superstructure portion connecting node are carried out in time(3)Mortar depositing construction, completes pier body structure Construction.
F. the construction workings such as the installation and laying of harbour affiliated facility and rail etc. are carried out, and carry out complete machine disembarkation in time And its debugging efforts, complete Wharf Construction.
The present embodiment construction, which is related to, dispatches pile driving barge 1, modularization superstructure portion transport ship 1, plays Beijing South Maxpower Technology Co. Ltd Power is about 4500 ~ 6000 tons of lifting appliance barges waterborne only 1, and structure steel fabrication processing factory is located at transportation by land and water facility, and matches somebody with somebody Standby corresponding crane capacity.Meanwhile, the actual pile sinking in scene allows certain pile foundation off normal, and pile foundation off normal license limit value is(D-d)/2.
According to previous experiences, the long 1400m bulk cargo terminals of embodiment one, two water fronts use traditional pile foundation Wharf Structural Scheme, The construction cycle is about 2.5 ~ 3.0 years.And the long 1400m bulk cargo terminals of embodiment one, two water fronts use assembled pile foundation wharfs Structural system and its construction method, can be arranged in 1.0 ~ 1.5 years.The overall progress plan arrangement of embodiment construction period is considered Structure factory of portion has carried out flowing water work between making the processes such as processing, live pile sinking, the transport of superstructure portion, live integral installation Industry is arranged, and construction period substantially shortens, and construction efficiency can be significantly improved.
Embodiment scene operation at sea process greatly reduces, and is easy to operation at sea standardized administration, is easy to site safety and work Journey quality control.Operation at sea personnel amount also can obviously reduce, including workman, technology, administrative staff, and human cost substantially drops It is low.If it is considered that human cost at a specified future date will be sharply increased, the present embodiment future advantage also will become apparent from.
The process c requirements of the construction method of embodiment are tied according to the piling deviation situation determining module top of scene feedback The bottom protuberance of structure(301), bottom projection ends(301a)Making Working position, be easy to superstructure integral installation just Position.

Claims (9)

1. a kind of modular assembly formula pile foundation wharfs structural system includes:Pile foundation(1), modularization superstructure portion(2)、 Pile foundation and modularization superstructure portion connecting node(3);It is characterized in that:
The modularization superstructure portion(2)Including case section longitudinal beam(201), box or I-shaped gooseneck(202), composite panel Structural portion(203)With berthing member portion(204);Case section longitudinal beam(201), box or I-shaped gooseneck(202)And composite panel Structural portion(203)It is connected, berthing member portion(204)Positioned at wharf apron box or I-shaped gooseneck(202)Cantilever part, Both are connected by bolt,
The pile foundation and modularization superstructure portion connecting node(3)By being fixed on case section longitudinal beam(201)On bottom it is convex Go out portion(301)Directly and pile foundation(1)Connection, slip casing by pressure portion(303)Located at bottom protuberance(301)With being sealed at the top of pile foundation Closure plate(302)Between cavity in;The slip casing by pressure portion(303)Slurries are injected, by the pile foundation(1), in modularization Portion's structural portion(2), pile foundation and modularization superstructure portion connecting node(3)It is connected as a single entity.
2. modular assembly formula pile foundation wharfs structural system as claimed in claim 1, it is characterised in that:The modular assembly The pile foundation of formula pile foundation wharfs structural system(1)Using straight stake steel-pipe pile, it is easy to modularization superstructure portion(2)Integral installation Construction in place.
3. modular assembly formula pile foundation wharfs structural system as claimed in claim 1, it is characterised in that:The modularization top Structural portion(2)It is additionally provided with wharf anchors, mooring, technique auxiliary and safety aid facility;Wharf anchors facility(251)Protected for rubber The side of a ship, passes through bolt and berthing member portion(204)It is connected;Pier mooring facility(252)For cast steel, cast iron bollard or Quick releasing hook, passes through bolt and box or I-shaped gooseneck(202)It is connected as a single entity;Technique auxiliary equipment(253)For rail and Its anchoring piece, passes through rail anchoring piece and case section longitudinal beam(201)It is connected as a single entity;Safety aid facility includes shield wheel bank(254)、 Rubber ladder.
4. modular assembly formula pile foundation wharfs structural system as claimed in claim 1, it is characterised in that:The modularization top Structural portion(2)It is made up of the first modularization superstructure portion (2A) and the second modularization superstructure portion (2B).
5. modular assembly formula pile foundation wharfs structural system as claimed in claim 3, it is characterised in that:The wharf anchors are set Apply(251), pier mooring facility(252), technique auxiliary equipment(253)The modularization is arranged at intervals at safety aid facility Superstructure portion(2)On, wherein wharf anchors facility(251), pier mooring facility(252)Positioned at wharf apron side.
6. modular assembly formula pile foundation wharfs structural system as claimed in claim 4, it is characterised in that:First modularization Superstructure portion (2A) and the second modularization superstructure portion (2B) are in the pile foundation(1)In the pile foundation and modularization Portion's structural portion connecting node(3)The position relationship of top is:Arranged on left and right sides sets the first modularization superstructure portion In (2A), the second modularization superstructure portion (2B) of middle setting or the first modularization superstructure portion (2A) and the second modularization Portion's structural portion (2B) interlaced arrangement.
7. the modular assembly formula pile foundation wharfs structural system as described in claim 1 or 3, it is characterised in that:The box steel Longeron(201)By box beam the week side of boss steel plate(201a), transverse stiffener(201b), longitudinal stiffener(201c), bottom protuberance (301)Composition.
8. modular assembly formula pile foundation wharfs structural system as claimed in claim 3, it is characterised in that:Technique auxiliary equipment (253)With lower transverse direction, longitudinal stiffener(201b、201c)The storehouse of composition forms embedded steel every interior concrete of the filling containing swelling agent Rail anchors beam(253a).
9. the modular assembly formula pile foundation wharfs structural system as described in claim 1-8 any one, its construction method includes Following steps:
Modularization superstructure portion is completed in prefabricated processing factory(2)Structure steel fabrication processing;
Meanwhile, pile driving barge is dispatched in time to engineering site, carries out piling construction;
Treat that pile driving barge reaches engineering site, carry out Pile Foundation of Wharf part piling construction, and monitor piling deviation in time, and form mould Block superstructure portion(2)Live piling foundation plan, and feed back to modularization superstructure portion in time(2)Prefabricated machining sector; If necessary, it is considered as setting up pile foundation waling, it is ensured that pile foundation off normal is stable;
According to the piling deviation situation of scene feedback, modularization superstructure portion is completed(2)Bottom protuberance(301), bottom Projection ends(301a)Be welded and fixed, then will make the modularization superstructure portion that machines(2)Transport to scene;
While process (a) ~ (c) deploys, suitable time point is selected, the ship for possessing corresponding crane capacity is dispatched in time and is set Engineering site, treats modularization superstructure portion to the utmost(2)Work in place is installed in transport to scene progress;
Wait that the device by ship for possessing corresponding crane capacity is reached the spot, modularization superstructure portion is carried out in time(2)Erector Make, and carry out pile foundation and modularization superstructure portion connecting node in time(3)Mortar depositing construction, completes pier body structure construction;
Carry out harbour affiliated facility and rail etc. installation with laying etc. construction working, and in time carry out whole set equipment disembarkation and Its debugging efforts, completes Wharf Construction.
CN201710434127.8A 2017-06-09 2017-06-09 A kind of modular assembly formula pile foundation wharfs structural system and its construction method Pending CN107034842A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710434127.8A CN107034842A (en) 2017-06-09 2017-06-09 A kind of modular assembly formula pile foundation wharfs structural system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710434127.8A CN107034842A (en) 2017-06-09 2017-06-09 A kind of modular assembly formula pile foundation wharfs structural system and its construction method

Publications (1)

Publication Number Publication Date
CN107034842A true CN107034842A (en) 2017-08-11

Family

ID=59542123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710434127.8A Pending CN107034842A (en) 2017-06-09 2017-06-09 A kind of modular assembly formula pile foundation wharfs structural system and its construction method

Country Status (1)

Country Link
CN (1) CN107034842A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107975059A (en) * 2018-01-12 2018-05-01 中交第三航务工程勘察设计院有限公司 A kind of assembled pile foundation wharfs structure and its construction method
CN108797513A (en) * 2018-06-12 2018-11-13 中交第三航务工程勘察设计院有限公司 A kind of normalized assembled pile foundation wharfs structure and its method of construction
CN110331693A (en) * 2019-06-13 2019-10-15 中交第三航务工程勘察设计院有限公司 A kind of full assembled steel dock structure and its construction method
CN110485258A (en) * 2019-06-25 2019-11-22 中交第三航务工程勘察设计院有限公司 A kind of full assembling type steel structure access bridge and its construction method
CN110747805A (en) * 2019-10-25 2020-02-04 中交第三航务工程勘察设计院有限公司 Prefabricated high-pile wharf node structure and construction method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1861911A (en) * 2006-05-17 2006-11-15 大连理工大学土木建筑设计研究院有限公司 Integrated casing board type long piled wharf
US20070025816A1 (en) * 2005-08-01 2007-02-01 Roger Baber Marine pier system
CN201224878Y (en) * 2008-10-08 2009-04-22 中交第二航务工程勘察设计院有限公司 Large water head vertical type frame beam plate dock
CN103321241A (en) * 2013-06-26 2013-09-25 上海大学 Deepwater open type wharf with combined foundation and method for constructing deepwater open type wharf
CN203256681U (en) * 2013-05-23 2013-10-30 天津港航工程有限公司 Frame-wall pile type wharf
CN103741604A (en) * 2014-01-21 2014-04-23 张利铨 Fully prefabricated reinforced concrete bridge assembly structure and connecting method for same
CN104480922A (en) * 2014-11-05 2015-04-01 广州市恒盛建设工程有限公司 Space truss formwork supporting system and construction method thereof
CN104711983A (en) * 2015-01-28 2015-06-17 河海大学 Pier piling method based on crawler type engineering machine
CN105839589A (en) * 2016-05-27 2016-08-10 中交第航务工程局有限公司 Component assembly-type roll-on berth structure and assembly method
CN106012960A (en) * 2016-07-14 2016-10-12 中交第三航务工程勘察设计院有限公司 Assembly type long piled wharf upper structure system and construction method thereof
CN106759423A (en) * 2017-03-03 2017-05-31 中交第三航务工程勘察设计院有限公司 Super-large diameter pile foundation assembled dock structure and its construction method
CN207597341U (en) * 2017-06-09 2018-07-10 中交第三航务工程勘察设计院有限公司 A kind of modular assembly formula pile foundation wharfs structural system

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070025816A1 (en) * 2005-08-01 2007-02-01 Roger Baber Marine pier system
CN1861911A (en) * 2006-05-17 2006-11-15 大连理工大学土木建筑设计研究院有限公司 Integrated casing board type long piled wharf
CN201224878Y (en) * 2008-10-08 2009-04-22 中交第二航务工程勘察设计院有限公司 Large water head vertical type frame beam plate dock
CN203256681U (en) * 2013-05-23 2013-10-30 天津港航工程有限公司 Frame-wall pile type wharf
CN103321241A (en) * 2013-06-26 2013-09-25 上海大学 Deepwater open type wharf with combined foundation and method for constructing deepwater open type wharf
CN103741604A (en) * 2014-01-21 2014-04-23 张利铨 Fully prefabricated reinforced concrete bridge assembly structure and connecting method for same
CN104480922A (en) * 2014-11-05 2015-04-01 广州市恒盛建设工程有限公司 Space truss formwork supporting system and construction method thereof
CN104711983A (en) * 2015-01-28 2015-06-17 河海大学 Pier piling method based on crawler type engineering machine
CN105839589A (en) * 2016-05-27 2016-08-10 中交第航务工程局有限公司 Component assembly-type roll-on berth structure and assembly method
CN106012960A (en) * 2016-07-14 2016-10-12 中交第三航务工程勘察设计院有限公司 Assembly type long piled wharf upper structure system and construction method thereof
CN106759423A (en) * 2017-03-03 2017-05-31 中交第三航务工程勘察设计院有限公司 Super-large diameter pile foundation assembled dock structure and its construction method
CN207597341U (en) * 2017-06-09 2018-07-10 中交第三航务工程勘察设计院有限公司 A kind of modular assembly formula pile foundation wharfs structural system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107975059A (en) * 2018-01-12 2018-05-01 中交第三航务工程勘察设计院有限公司 A kind of assembled pile foundation wharfs structure and its construction method
CN108797513A (en) * 2018-06-12 2018-11-13 中交第三航务工程勘察设计院有限公司 A kind of normalized assembled pile foundation wharfs structure and its method of construction
CN110331693A (en) * 2019-06-13 2019-10-15 中交第三航务工程勘察设计院有限公司 A kind of full assembled steel dock structure and its construction method
CN110485258A (en) * 2019-06-25 2019-11-22 中交第三航务工程勘察设计院有限公司 A kind of full assembling type steel structure access bridge and its construction method
CN110747805A (en) * 2019-10-25 2020-02-04 中交第三航务工程勘察设计院有限公司 Prefabricated high-pile wharf node structure and construction method
CN110747805B (en) * 2019-10-25 2021-06-01 中交第三航务工程勘察设计院有限公司 Prefabricated high-pile wharf node structure and construction method

Similar Documents

Publication Publication Date Title
CN107034842A (en) A kind of modular assembly formula pile foundation wharfs structural system and its construction method
CN100587165C (en) Cast-in-situ beam-making construction method of assembled support
CN100591863C (en) Underwater no-bottom closing concrete boxed cofferdam and method of use thereof
CN102767189B (en) Set bearing platform foundations and construction method thereof
CN106012960B (en) A kind of assembled long piled wharf superstructure system and its construction method
CN105236275B (en) Soil lifting system and soil lifting method for building deep foundation pit construction in narrow zone
CN107975059A (en) A kind of assembled pile foundation wharfs structure and its construction method
CN101538833B (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN104746422A (en) Bridge prefabricated hollow pier column post-poured connecting structure and construction method
CN113481931B (en) Modular assembly type high-pile wharf structure and construction method thereof
CN105697021B (en) The prefabricated tunnel and construction method in the shallow earthing riverbed of shield crossing
CN108797513A (en) A kind of normalized assembled pile foundation wharfs structure and its method of construction
CN109653233A (en) Cushion cap single wall steel jacket box recoverable construction of bottom plates method
WO2023020356A1 (en) Caisson quay and construction method therefor
CN201943086U (en) Underground building wall body
CN204097864U (en) A kind of bridge prefabrication hollow pier stud delay-pour joint structure
CN207597341U (en) A kind of modular assembly formula pile foundation wharfs structural system
CN205822123U (en) 20 ton deep water sheet pile quay wall structure
CN101603315B (en) Method for constructing seepage prevention system of secondary cofferdam for immersed tube tunnel
CN206512730U (en) It is a kind of to realize the box that box wall body is used in turn
CN207919582U (en) A kind of assembled pile foundation wharfs structure
CN217325078U (en) Bearing platform cofferdam system suitable for bridge pier restoration of existing bridge
CN103882883A (en) Method for constructing foundation shared by tower crane and garage frame column
CN110004959A (en) Concrete cofferdam rapid constructing method and template under circumstance of flowing water
CN201485843U (en) Stream-guidance navigation pier structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No. 831 zhaojiaman Road, Xuhui District, Shanghai

Applicant after: CCCC Third Harbor Consultants Co., Ltd.

Address before: 200032 831 Zhaojia Bang Road, Xuhui District, Shanghai

Applicant before: CCCC Third Harbor Consultants Co., Ltd.

CB02 Change of applicant information