CN109972850A - It is a kind of can be with the safe guarding shed of creeping formwork synchronization lifting - Google Patents
It is a kind of can be with the safe guarding shed of creeping formwork synchronization lifting Download PDFInfo
- Publication number
- CN109972850A CN109972850A CN201910339509.1A CN201910339509A CN109972850A CN 109972850 A CN109972850 A CN 109972850A CN 201910339509 A CN201910339509 A CN 201910339509A CN 109972850 A CN109972850 A CN 109972850A
- Authority
- CN
- China
- Prior art keywords
- creeping formwork
- safe guarding
- guarding shed
- creeping
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
- E04G11/20—Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
- E04G11/28—Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/32—Safety or protective measures for persons during the construction of buildings
- E04G21/3261—Safety-nets; Safety mattresses; Arrangements on buildings for connecting safety-lines
- E04G21/3266—Safety nets
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
, including the creeping formwork (2) being located on vertical structure (1) inner wall, protection canopy (4) can be equipped with below creeping formwork (2) with the safe guarding shed of creeping formwork synchronization lifting the invention discloses a kind of;Protection canopy (4) is connect through cable wire (3) with creeping formwork (2) bottom.The present invention is safe guarding shed to follow climbing formwork for construction to climb together, effectively raise security protection efficiency, reduce work progress risk, meet construction protection demand in time.It is safe guarding shed in entire work progress, need to only set up it is primary, and with climbing frame synchronize climb, be truly realized energy conservation, section material, environmental protection and safety construction.
Description
Technical field
The technology of the present invention, which is related to one kind, to belong to building construction technology neck with the safe guarding shed of creeping formwork synchronization lifting
Domain.
Background technique
Mould crawling technology Super High construction in using more and more extensive.It is that first only construction is vertical using climbing shuttering construction technology
Structure, rear construction level structure, 6-8 layers of vertical structure top standard's structure.Before horizontal structure construction, that has constructed is vertical
Inside configuration has biggish cavity, and there are the major hazard sources that eminence pendant object is hurted sb.'s feelings, and needs to pacify vertical structure inside
Full protection.
The way of the prior art is: in the cavity inside vertical structure every it is several layers of set up one layer it is safe guarding shed.It is existing
With the presence of technology scheme heavy workload, materials demand amount is big the disadvantages of, be unsatisfactory for energy conservation now, section material, green construction are wanted
It asks.
Summary of the invention
The object of the present invention is to provide one kind can be with the safe guarding shed of creeping formwork synchronization lifting, to solve existing skill
Art needs to set up one layer of safe guarding shed trouble every several layers of, to reduce workload and save material loss and overcome existing
The deficiency of technology.
To achieve the above object, the present invention adopts the following technical scheme:
One kind of the invention can be with the safe guarding shed of creeping formwork synchronization lifting, including the creeping formwork being located on vertical structure inner wall;
Protection canopy is equipped with below creeping formwork;Protection canopy is connect through cable wire with creeping formwork bottom;The vertical structure is rectangle empty structure, rectangle
At least provided with two creeping formworks, two creeping formworks are located on the opposite inner wall in rectangle cavity four walls in cavity.
It is aforementioned can with creeping formwork synchronization lifting it is safe guarding shed in, the protection canopy includes rectangular frame, rectangular frame
Frame size be slightly less than the rectangle pore size of vertical structure;Steel wire is welded on rectangular frame.
It is aforementioned can with creeping formwork synchronization lifting it is safe guarding shed in, be welded with and hang on the rectangular frame of the protection canopy
Ear, lifting lug are connect through cable wire with creeping formwork bottom.
It is aforementioned can with creeping formwork synchronization lifting it is safe guarding shed in, the creeping formwork bottom is welded with lifting lug, and lifting lug is through steel
Rope is connect with the lifting lug at the top of protection canopy.
It is aforementioned can with creeping formwork synchronization lifting it is safe guarding shed in, the creeping formwork and vertical structure inner wall lifting connect.
Climbing formwork for construction can be followed to climb together compared with prior art, the present invention the present invention is safe guarding shed, effectively mentioned
High security protection efficiency, reduces work progress risk, meets construction protection demand in time.It is safe guarding shed entirely to apply
During work, need to only set up it is primary, and with climbing frame synchronize climb, be truly realized energy conservation, section material, environmental protection and safety construction.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention.
The label in accompanying drawing is: 1- vertical structure;2- creeping formwork;3- cable wire;4- protection canopy;5- steel wire;6- lifting lug;7- square
Shape frame.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.
One kind of the invention can be with the safe guarding shed of creeping formwork synchronization lifting, as shown in Figure 1, including being located at vertical structure
Creeping formwork 2 on 1 inner wall;Protection canopy 4 is equipped with below creeping formwork 2;Protection canopy 4 is connect through cable wire 3 with 2 bottom of creeping formwork.Vertical structure 1 is
Rectangle empty structure, for four walls in rectangle cavity at least provided with two creeping formworks 2, two creeping formworks 2 are located at opposite interior in rectangle cavity
On wall.Protection canopy 4 includes rectangular frame 7, and the frame size of rectangular frame 7 is slightly less than the rectangle pore size of vertical structure 1;Square
Steel wire 5 is welded on shape frame 7.Lifting lug 6 is welded on the rectangular frame 7 of protection canopy 4, lifting lug 6 is through cable wire 3 and 2 bottom of creeping formwork
Portion's connection.2 bottom of creeping formwork is welded with lifting lug 6, and lifting lug 6 is connect through cable wire 3 with the lifting lug 6 at 4 top of protection canopy.Creeping formwork 2 and vertical
The lifting connection of 1 inner wall of structure.
Embodiment
This example is as shown in Figure 1.When using creeping formwork 2 construct shear wall vertical structure 1 when, inside vertical structure 1 in addition to
Outside the frame body of creeping formwork 2, there are also compared with macroscopic-void, need to set up protection canopy 4 for security consideration.Protection canopy 4 is suspended on by cable wire 3-
The frame body bottom of creeping formwork 2.The size of protection canopy 4 is determined according to cavity;More smaller than pore size, protection canopy 4 is rigid structure.Packet
Rectangular frame 7 is included, 7 four jiaos of 5. rectangular frame of steel wire is welded on rectangular frame 7 and is welded with for being hung with what cable wire 3 was connect
Ear 6.The application it is safe guarding shed can with hydraulic climbing formwork synchronize climb, protective action can be played in time.
Claims (5)
1. one kind can be with the safe guarding shed of creeping formwork synchronization lifting, including the creeping formwork (2) being located on vertical structure (1) inner wall;
It is characterized by: being equipped with protection canopy (4) below creeping formwork (2);Protection canopy (4) is connect through cable wire (3) with creeping formwork (2) bottom;Institute
Stating vertical structure (1) is rectangle empty structure, and four walls in rectangle cavity are at least provided with two creeping formworks (2), two creeping formwork (2) positions
In on the opposite inner wall in rectangle cavity.
2. according to claim 1 can be with the safe guarding shed of creeping formwork synchronization lifting, it is characterised in that: the protection canopy
It (4) include rectangular frame (7), the frame size of rectangular frame (7) is slightly less than the rectangle pore size of vertical structure (1);Rectangle
Steel wire (5) are welded on frame (7).
3. according to claim 1 can be with the safe guarding shed of creeping formwork synchronization lifting, it is characterised in that: the protection canopy
(4) it is welded with lifting lug (6) on rectangular frame (7), lifting lug (6) is connect through cable wire (3) with creeping formwork (2) bottom.
4. according to claim 1 can be with the safe guarding shed of creeping formwork synchronization lifting, it is characterised in that: the creeping formwork (2)
Bottom is welded with lifting lug (6), and lifting lug (6) is connect through cable wire (3) with the lifting lug (6) at the top of protection canopy (4).
5. according to claim 1 can be with the safe guarding shed of creeping formwork synchronization lifting, it is characterised in that: the creeping formwork (2)
It goes up and down and connects with vertical structure (1) inner wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910339509.1A CN109972850A (en) | 2019-04-25 | 2019-04-25 | It is a kind of can be with the safe guarding shed of creeping formwork synchronization lifting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910339509.1A CN109972850A (en) | 2019-04-25 | 2019-04-25 | It is a kind of can be with the safe guarding shed of creeping formwork synchronization lifting |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109972850A true CN109972850A (en) | 2019-07-05 |
Family
ID=67086258
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910339509.1A Pending CN109972850A (en) | 2019-04-25 | 2019-04-25 | It is a kind of can be with the safe guarding shed of creeping formwork synchronization lifting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109972850A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111706099A (en) * | 2020-06-24 | 2020-09-25 | 汪晨 | Climbing protection device for building |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB0823559D0 (en) * | 2008-12-24 | 2009-01-28 | Shire Precast Erection Ltd | Lifting device |
CN203626278U (en) * | 2013-12-21 | 2014-06-04 | 中国建筑第四工程局有限公司 | Protective structure for construction of internal core tube of high-rise building |
CN204040506U (en) * | 2014-05-30 | 2014-12-24 | 中国建筑第八工程局有限公司 | Hydraulic lifting protector |
CN204782031U (en) * | 2015-06-11 | 2015-11-18 | 北京六建集团有限责任公司 | Interior climbing tower hangs entrance to a cave from promoting safety protection platform |
CN205063331U (en) * | 2015-10-17 | 2016-03-02 | 神华大雁工程建设有限公司建筑安装分公司 | Slipform architecture |
CN205077885U (en) * | 2015-09-08 | 2016-03-09 | 中国建筑第二工程局有限公司 | Hydraulic intelligent climbing protection platform for core tube of building |
CN105649351A (en) * | 2016-01-13 | 2016-06-08 | 江苏揽月工程科技发展股份有限公司 | Self-climbing protection device |
CN205476449U (en) * | 2016-03-04 | 2016-08-17 | 中建三局第一建设工程有限责任公司 | A automatic lifting device for surmounting protection of layer core section of thick bamboo construction creeping formwork bottom level |
KR20170035733A (en) * | 2015-09-23 | 2017-03-31 | 주식회사 에스지이엔지 | Lifting safety cage for the core of building materials |
CN207296386U (en) * | 2017-07-28 | 2018-05-01 | 中建四局第一建筑工程有限公司 | A kind of combining structure of construction elevator and creeping formwork frame body |
CN108166767A (en) * | 2018-01-18 | 2018-06-15 | 北京崇建工程有限公司 | A kind of construction method and outer climbing frame protective device |
EP3339535A1 (en) * | 2016-12-23 | 2018-06-27 | Tries GmbH & CO. KG | Climbing device with a climbing rail |
CN208456100U (en) * | 2018-06-01 | 2019-02-01 | 广东奇正科技有限公司 | A kind of connection structure of the protective net of climbing frame |
CN109537867A (en) * | 2018-12-27 | 2019-03-29 | 上海绿地建设(集团)有限公司 | Protective platform in a kind of Super High Core Walls Structure based on climbing apparatus |
CN210002935U (en) * | 2019-04-25 | 2020-01-31 | 中建四局第一建筑工程有限公司 | safety protection shed capable of synchronously lifting along with creeping formwork |
-
2019
- 2019-04-25 CN CN201910339509.1A patent/CN109972850A/en active Pending
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB0823559D0 (en) * | 2008-12-24 | 2009-01-28 | Shire Precast Erection Ltd | Lifting device |
CN203626278U (en) * | 2013-12-21 | 2014-06-04 | 中国建筑第四工程局有限公司 | Protective structure for construction of internal core tube of high-rise building |
CN204040506U (en) * | 2014-05-30 | 2014-12-24 | 中国建筑第八工程局有限公司 | Hydraulic lifting protector |
CN204782031U (en) * | 2015-06-11 | 2015-11-18 | 北京六建集团有限责任公司 | Interior climbing tower hangs entrance to a cave from promoting safety protection platform |
CN205077885U (en) * | 2015-09-08 | 2016-03-09 | 中国建筑第二工程局有限公司 | Hydraulic intelligent climbing protection platform for core tube of building |
KR20170035733A (en) * | 2015-09-23 | 2017-03-31 | 주식회사 에스지이엔지 | Lifting safety cage for the core of building materials |
CN205063331U (en) * | 2015-10-17 | 2016-03-02 | 神华大雁工程建设有限公司建筑安装分公司 | Slipform architecture |
CN105649351A (en) * | 2016-01-13 | 2016-06-08 | 江苏揽月工程科技发展股份有限公司 | Self-climbing protection device |
CN205476449U (en) * | 2016-03-04 | 2016-08-17 | 中建三局第一建设工程有限责任公司 | A automatic lifting device for surmounting protection of layer core section of thick bamboo construction creeping formwork bottom level |
EP3339535A1 (en) * | 2016-12-23 | 2018-06-27 | Tries GmbH & CO. KG | Climbing device with a climbing rail |
CN207296386U (en) * | 2017-07-28 | 2018-05-01 | 中建四局第一建筑工程有限公司 | A kind of combining structure of construction elevator and creeping formwork frame body |
CN108166767A (en) * | 2018-01-18 | 2018-06-15 | 北京崇建工程有限公司 | A kind of construction method and outer climbing frame protective device |
CN208456100U (en) * | 2018-06-01 | 2019-02-01 | 广东奇正科技有限公司 | A kind of connection structure of the protective net of climbing frame |
CN109537867A (en) * | 2018-12-27 | 2019-03-29 | 上海绿地建设(集团)有限公司 | Protective platform in a kind of Super High Core Walls Structure based on climbing apparatus |
CN210002935U (en) * | 2019-04-25 | 2020-01-31 | 中建四局第一建筑工程有限公司 | safety protection shed capable of synchronously lifting along with creeping formwork |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111706099A (en) * | 2020-06-24 | 2020-09-25 | 汪晨 | Climbing protection device for building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209482679U (en) | Tub brace type integral steel platform suitable for sloping core construction | |
CN103982040B (en) | A kind of construction of super highrise building vertical multi-transportation device | |
CN204126230U (en) | Assembly scaffold unit | |
CN109505408B (en) | Outer wall hole plugging umbrella and construction method | |
CN109457931A (en) | Tub brace type integral steel platform and its construction method suitable for sloping core construction | |
CN108331336A (en) | The integrated lifting steel plateform system and its construction method of floor synchronous construction | |
CN102912996B (en) | Steel tube concrete column high-altitude construction safety protection system | |
CN203640249U (en) | External lifting scaffold with an opening | |
WO2023240812A1 (en) | Overall construction platform structure and method for adding core tube wall body in air | |
CN109972850A (en) | It is a kind of can be with the safe guarding shed of creeping formwork synchronization lifting | |
CN202954552U (en) | Steel tube concrete column high-altitude construction safety protection system | |
CN209620571U (en) | Contracture shear wall form frame system | |
CN206903256U (en) | Assembled integral concrete shear wall structure regularization safety net | |
CN105776092B (en) | A kind of extended position nacelle device | |
CN202731276U (en) | Independent discharge platform capable of synchronously lifting with external lifting scaffold | |
CN208734045U (en) | Monoblock type mould bases for Super High fission conjoined composite structure | |
CN210002935U (en) | safety protection shed capable of synchronously lifting along with creeping formwork | |
CN205134921U (en) | Building outer wall concrete constructional column hangs construction platform | |
CN207110035U (en) | Assembled steel tendon concrete frame structure based on steel plate connection joint | |
CN210177994U (en) | Protection stores pylon of outer wall construction | |
CN107829553A (en) | A kind of elevator hoistways construction platform system | |
CN210798251U (en) | But scaffold of automatically regulated height | |
CN211037760U (en) | Novel instrument formula elevartor shaft construction operation platform | |
CN208870379U (en) | The integrated lifting steel plateform system of floor synchronous construction | |
CN104563345B (en) | Construction method of laminated curtain wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |