CN109944170A - Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system and construction method - Google Patents

Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system and construction method Download PDF

Info

Publication number
CN109944170A
CN109944170A CN201910372541.XA CN201910372541A CN109944170A CN 109944170 A CN109944170 A CN 109944170A CN 201910372541 A CN201910372541 A CN 201910372541A CN 109944170 A CN109944170 A CN 109944170A
Authority
CN
China
Prior art keywords
construction
bay
hanging basket
closure
cast
Prior art date
Application number
CN201910372541.XA
Other languages
Chinese (zh)
Inventor
张志飞
杨翔
颜立
谢永辉
江真
张庆明
陶伟
向起来
李晓倩
Original Assignee
重庆建工市政交通工程有限责任公司
重庆建工集团股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 重庆建工市政交通工程有限责任公司, 重庆建工集团股份有限公司 filed Critical 重庆建工市政交通工程有限责任公司
Priority to CN201910372541.XA priority Critical patent/CN109944170A/en
Publication of CN109944170A publication Critical patent/CN109944170A/en

Links

Abstract

The present invention relates to technical field of building construction, more particularly to continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system and construction method, specific steps are as follows: preparation of construction → construction monitoring calculates analysis → cantilever construction to closure section and the transformation of access bridge construction → hanging basket advancing and platform hanging basket, precompressed → end bay cast-in-place section construction → end bay closure section construction → end bay closure section tensioning → and hangs platform system and remove.It is compared with the traditional method, effectively solves the problems, such as that high pier bracket is set up, avoid a large amount of bracket erection constructions, system stress is hung using Hanging Basket, construction technology is simple, reduces materials'use amount, reduces the use of Large-scale Hoisting equipment, simultaneously for work such as bracket that may be present processing, it with save the cost, saves the duration, Technical Economy preferably waits clear superiorities, and avoiding conventional construction bracket sets up, and the work such as a large amount of based process are avoided, the duration saves apparent.

Description

Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system and construction method
Technical field
The present invention relates to technical field of building construction, and in particular to continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integration The construction method of construction system is suitable for Hanging Basket cantilever construction end bay Cast-in-Situ Segment and closure section erection without scaffolding.
Background technique
As infrastructure construction in china constantly promotes rapidly, a large amount of sciences of bridge building emerge in large numbers, and big Span Continuous beam bridge is mesh One of preceding main type of bridge.Such bridge generallys use precast beam structure in non-main span, and main span uses continuous beam, utilizes extension Basket carries out cantilever casting construction.Cradle construction continuous beam end bay closure section and Cast-in-Situ Segment high pier construction are very common, generally use Construction method is support cast-in-place.But pier stud is higher, and it is larger that bracket sets up difficulty, and lifting is difficult, and bracket elongate stabilization is deteriorated, and needs Increase more material.Bracket sets up difficulty there are foundation treatment simultaneously, and increased costs and construction period are elongated.
Summary of the invention
In view of problems of the prior art, the present invention provides continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integration The construction method of construction system, it is easy for construction, it effectively solves the problems, such as that high pier bracket is set up, avoids a large amount of bracket erection constructions, System stress is hung using Hanging Basket, construction technology is simple.
To realize the above-mentioned technical purpose, The technical solution adopted by the invention is as follows:
Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system include end bay pier shaft, away from end bay pier shaft recently in Across on pier shaft and close to the continuous of construction beam side across pier shaft, the construction beam being erected on end bay pier shaft and in being erected at Beam, it is characterised in that: further include Hanging Basket, underframe longitudinal member and floor beam, the Hanging Basket effect is mounted on continuous beam, the bottom One end of plate stringer rides upon on end bay pier shaft, the other end rides upon on Hanging Basket, and the floor beam is erected at underframe longitudinal member Bottom, the Cast-in-Situ Segment and closure section are cast on underframe longitudinal member and in the spaces between construction beam and continuous beam.
It further limits, the underframe longitudinal member and floor beam are at the lower edge of construction beam and continuous beam, The wing plate nose girder being also provided at construction beam and continuous beam upper edge right above underframe longitudinal member.
Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated system, specific construction method the following steps are included:
1. preparation of construction: according to conventional stand-by mode, tentatively drafting construction technical schemes, carry out temporary supporting system arrangement, system Temporary load(ing) situation is counted, the technology branch of relevant departments is obtained according to stress of the calculating analysis beam body under hoisted load It holds, is analyzed by calculating, work out special construction plan, complete the construction of end bay Cast-in-Situ Segment access bridge, end bay Cast-in-Situ Segment and closure are provided Duan Zhidian, and procedure of submitting reports for approval is completed, carry out the work of confiding a technological secret before going into operation;
2. construction monitoring calculates analysis: according to end bay is cast-in-place and joint scheme designs, 1/2 company of will act on of Hanging Basket Cast-in-Situ Segment weight Continuous girder cantilever end, in the case where cantilever end increases loading condition, analysis influences bridge internal force, determines counterweight scheme,
According to end bay is cast-in-place and joint scheme design, Hanging Basket closure pours the 1/2 of the sum of section+Cast-in-Situ Segment weight and will act on continuous beam Cantilever end, in the case where cantilever end increases loading condition, analysis influences bridge internal force, determines counterweight scheme,
Access bridge hangs the impact analysis of end bay Cast-in-Situ Segment and end bay closure section load to bridge internal force;
3. cantilever construction to closure section and access bridge is constructed: after by the construction of main pier pier top 0# block, then the symmetrical cantilever pouring in two sides, The outstanding beam section that fills uses Hanging Basket cantilever construction, after the completion of one of them main pier cantilever construction, retreat in time in across Hanging Basket, be the other side Back boom construction hanging basket provides working space, in the last one cantilever segmental construction, needs each sunpender of Hanging Basket passing through box beam Hole suitably amplify, it is ensured that box beam deform when sunpender can in the hole of box beam front and back move freely, access bridge construct when in access bridge Sunpender hole is reserved on wing plate and top plate to support as stringer under stringer, wing plate inside Hanging Basket;
4. hanging basket advancing and platform hanging basket transformation, precompressed: boom segments end is moved forward to after the completion of Hanging Basket cantilever construction, by Hanging Basket Stringer be adjusted to it is consistent with abutment pier top surface absolute altitude locate, whether detection stringer length meets end bay Cast-in-Situ Segment and closure section pours length Degree, the spreading stringer in the ungratified situation of height;Lower beam before Hanging Basket is extended into bridge pier, then Hanging Basket stringer is ridden upon into bridge Front crossbeam is removed after on pier, and overlap joint is met by the mobile adjustment stringer position of Hanging Basket and is required, wherein end bay Cast-in-Situ Segment and closure Section wing plate outside-supporting beam and inside top plate supporting beam by finish rolling deformed bar are hung on access bridge wing plate and inner top panel;Remove cantilever When Hanging Basket, end bay closure section bracket and installation template are set up, construction material, equipment in removing case top, case are applied for closure section The material and facility of work is put in an orderly manner to pier top;
Hanging Basket is transformed after the completion of stage+module, carries out precompressed to whole system, end bay construction section uses steel and 1t/ bags of sandbag Common preloading carries out preloading according to the sequence of bottom plate, web, top plate and wing plate, wherein by 40% → 60% → 80% → 100% → The other end of 120% multistage loadings, T structure is balanced ballast by water tank;
5. end bay cast-in-place section construction: end bay cast-in-place section construction platform floor is supported on abutment pier by Hanging Basket stringer and Hanging Basket cantilever is applied Workshop section, wing plate are supported on longitudinal hanging beam, and when end bay cast-in-place section construction, installation bed die and side form first adjust template Position and absolute altitude carry out the installation at bottom, abdomen, top and diaphragm plate reinforcing bar, bellows after installation inner support, internal model and sealing end mould, most After-pouring concrete, according to embedded anchorage is designed, realizes one-end tension when constructing end bay Cast-in-Situ Segment;
In end bay cast-in-place section construction, need to end bay cantilever end carry out ballast, and according to design and monitoring requirement in across side into Row counterweight, when Cast-in-Situ Segment pours concrete, cantilever end, which synchronizes, to discharge water, to keep cantilever end elevation not change, end bay cantilever end with Midspan closing end counterweight is all made of water tank and the mode that end bay cantilever end carries out ballast is arranged in, and wherein the weight of water tank is existing for end bay Pour end and pour the 1/2 of weight, wherein water tank welds water tank using brick or irony, when end bay Cast-in-Situ Segment pours, in across water tank not Waterproof unloading, only end bay cantilever end discharges water unloading;
6. end bay closure section construction: being locked according to midspan closing hanger installation → reinforcing bar binding → prestress pipe installation → closure It is fixed, remove lateral opening bracket, remove central bearing point horizontal direction temporary constraint → selection on the day of minimum temperature time casting concrete → Removal water tank ballast → closure section prestressed stretch-draw, anchoring, grouting finish step by step while casting concrete sequence carries out Construction, closure pour cantilever end and should temporarily connect with end bay Cast-in-Situ Segment, and the section concrete that avoids joining the two sections of a bridge, etc is pouring and premature cure mistake Apparent volume change occurs in journey, locking time is executed by closure section locking design, and Construction Support stiff skeleton is using " pre-buried The bold property I-shaped steel skeleton+pre-embedded anchoring bolts of foundation bolt+connection ";
7. end bay closure section tensioning: according to Design of Construction Organization arrangement, adjusting prestressing force in advance is one-end tension technique, cast-in-place Embedded anchor plate tensioning position, installs both ends tension ground tackle for anchored end after lashing when section construction, passes through anchorage using steel strand wires, And pre-tightened in the other end using single tendon stretch jack, entire beam tension is finally carried out using the jack for adapting to specification;
8. hanging platform system dismounting: after end bay closure is constructed, according to the stress specific requirement of midspan closing, prestressed grouting Platform is hung in dismounting after reaching design requirement, is hung platform and is unclamped hangar system first when removing, is supported on the Hanging Basket stringer of abutment pier Lower reduction lowering device is disengaged end template, is gradually transferred Hanging Basket floor beam, stringer to ground, Hanging Basket master using hoist engine Truss is moved to the 0# sections of enough positions of Lifting Capacity by walking line mode, and is removed using loop wheel machine, wherein when removing, it then follows The principle of " first prop up and tear open afterwards, rear branch is first torn open ".
According to the Comprehensive Correlation of the prior art, this construction method had the advantage that above
1. it is easy for construction, it effectively solves the problems, such as that high pier bracket is set up, avoids a large amount of bracket erection constructions, body is hung using Hanging Basket It is stress, construction technology is simple.
2. Technical Economy is good: present approach reduces materials'use amounts, reduce the use of Large-scale Hoisting equipment, same to hour hands To work such as bracket that may be present processing, there is save the cost, save the duration, Technical Economy preferably waits clear superiorities.
3. the duration saves, efficiency is improved: continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integration non-stand construction method It avoids conventional construction bracket to set up, and avoids the work such as a large amount of based process, the duration saves apparent.
Detailed description of the invention
Fig. 1 is the schematic view of the front view of continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system;
Fig. 2 is the flow diagram of the construction method of continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system;
Corresponding mark is respectively as follows: 1- end bay pier shaft in figure, across pier shaft in 2-, 3- construction beam, and 4- continuous beam, 5- Hanging Basket, the bottom 6- Plate stringer, 7- floor beam, 8- wing plate nose girder.
Specific embodiment
In order to which those skilled in the art may be better understood, with reference to the accompanying drawings and examples to the technology of the present invention Scheme further illustrates.
Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system as shown in Figure 1, including end bay pier shaft 1, Away from end bay pier shaft 1 recently in across pier shaft 2, the construction beam 3 being erected on end bay pier shaft 1 and in being erected at across on pier shaft 2 and Continuous beam 4 close to 3 side of construction beam, it is characterised in that: further include Hanging Basket 5, underframe longitudinal member 6 and floor beam 7, the extension The effect of basket 5 is mounted on continuous beam 4, and one end of the underframe longitudinal member 6 rides upon on end bay pier shaft 2, the other end rides upon Hanging Basket 5 On, the floor beam 7 is erected at the bottom of underframe longitudinal member 6, and the Cast-in-Situ Segment and closure section are cast on underframe longitudinal member 6 and locate In the space between construction beam 3 and continuous beam 4.The underframe longitudinal member 6 and floor beam 7 are in construction beam 3 and continuously At the lower edge of beam 4, it is also provided with the wing plate right above underframe longitudinal member 6 at 4 upper edge of construction beam 3 and continuous beam and leads Beam 8.
Its specific construction method the following steps are included:
1. preparation of construction: according to conventional stand-by mode, tentatively drafting construction technical schemes, carry out temporary supporting system arrangement, system Temporary load(ing) situation is counted, the technology branch of relevant departments is obtained according to stress of the calculating analysis beam body under hoisted load It holds, is analyzed by calculating, work out special construction plan, complete the construction of end bay Cast-in-Situ Segment access bridge, end bay Cast-in-Situ Segment and closure are provided Duan Zhidian, and procedure of submitting reports for approval is completed, carry out the work of confiding a technological secret before going into operation;
2. construction monitoring calculates analysis: according to end bay is cast-in-place and joint scheme designs, 1/2 company of will act on of Hanging Basket Cast-in-Situ Segment weight Continuous girder cantilever end, in the case where cantilever end increases loading condition, analysis influences bridge internal force, determines counterweight scheme,
According to end bay is cast-in-place and joint scheme design, Hanging Basket closure pours the 1/2 of the sum of section+Cast-in-Situ Segment weight and will act on continuous beam Cantilever end, in the case where cantilever end increases loading condition, analysis influences bridge internal force, determines counterweight scheme,
Access bridge hangs the impact analysis of end bay Cast-in-Situ Segment and end bay closure section load to bridge internal force;
3. cantilever construction to closure section and access bridge is constructed: after by the construction of main pier pier top 0# block, then the symmetrical cantilever pouring in two sides, The outstanding beam section that fills uses Hanging Basket cantilever construction, after the completion of one of them main pier cantilever construction, retreat in time in across Hanging Basket, be the other side Back boom construction hanging basket provides working space, in the last one cantilever segmental construction, needs each sunpender of Hanging Basket passing through box beam Hole suitably amplify, it is ensured that box beam deform when sunpender can in the hole of box beam front and back move freely, access bridge construct when in access bridge Sunpender hole is reserved on wing plate and top plate to support as stringer under stringer, wing plate inside Hanging Basket;
4. hanging basket advancing and platform hanging basket transformation, precompressed: boom segments end is moved forward to after the completion of Hanging Basket cantilever construction, by Hanging Basket Stringer be adjusted to it is consistent with abutment pier top surface absolute altitude locate, whether detection stringer length meets end bay Cast-in-Situ Segment and closure section pours length Degree, the spreading stringer in the ungratified situation of height;Lower beam before Hanging Basket is extended into bridge pier, then Hanging Basket stringer is ridden upon into bridge Front crossbeam is removed after on pier, and overlap joint is met by the mobile adjustment stringer position of Hanging Basket and is required, wherein end bay Cast-in-Situ Segment and closure Section wing plate outside-supporting beam and inside top plate supporting beam by finish rolling deformed bar are hung on access bridge wing plate and inner top panel;Remove cantilever When Hanging Basket, end bay closure section bracket and installation template are set up, construction material, equipment in removing case top, case are applied for closure section The material and facility of work is put in an orderly manner to pier top;
Hanging Basket is transformed after the completion of stage+module, carries out precompressed to whole system, end bay construction section uses steel and 1t/ bags of sandbag Common preloading carries out preloading according to the sequence of bottom plate, web, top plate and wing plate, wherein by 40% → 60% → 80% → 100% → The other end of 120% multistage loadings, T structure is balanced ballast by water tank;
5. end bay cast-in-place section construction: end bay cast-in-place section construction platform floor is supported on abutment pier by Hanging Basket stringer and Hanging Basket cantilever is applied Workshop section, wing plate are supported on longitudinal hanging beam, and when end bay cast-in-place section construction, installation bed die and side form first adjust template Position and absolute altitude carry out the installation at bottom, abdomen, top and diaphragm plate reinforcing bar, bellows after installation inner support, internal model and sealing end mould, most After-pouring concrete, according to embedded anchorage is designed, realizes one-end tension when constructing end bay Cast-in-Situ Segment;
In end bay cast-in-place section construction, need to end bay cantilever end carry out ballast, and according to design and monitoring requirement in across side into Row counterweight, when Cast-in-Situ Segment pours concrete, cantilever end, which synchronizes, to discharge water, to keep cantilever end elevation not change, end bay cantilever end with Midspan closing end counterweight is all made of water tank and the mode that end bay cantilever end carries out ballast is arranged in, and wherein the weight of water tank is existing for end bay Pour end and pour the 1/2 of weight, wherein water tank welds water tank using brick or irony, when end bay Cast-in-Situ Segment pours, in across water tank not Waterproof unloading, only end bay cantilever end discharges water unloading;
6. end bay closure section construction: being locked according to midspan closing hanger installation → reinforcing bar binding → prestress pipe installation → closure It is fixed, remove lateral opening bracket, remove central bearing point horizontal direction temporary constraint → selection on the day of minimum temperature time casting concrete → Removal water tank ballast → closure section prestressed stretch-draw, anchoring, grouting finish step by step while casting concrete sequence carries out Construction, closure pour cantilever end and should temporarily connect with end bay Cast-in-Situ Segment, and the section concrete that avoids joining the two sections of a bridge, etc is pouring and premature cure mistake Apparent volume change occurs in journey, locking time is executed by closure section locking design, and Construction Support stiff skeleton is using " pre-buried The bold property I-shaped steel skeleton+pre-embedded anchoring bolts of foundation bolt+connection ";
7. end bay closure section tensioning: according to Design of Construction Organization arrangement, adjusting prestressing force in advance is one-end tension technique, cast-in-place Embedded anchor plate tensioning position, installs both ends tension ground tackle for anchored end after lashing when section construction, passes through anchorage using steel strand wires, And pre-tightened in the other end using single tendon stretch jack, entire beam tension is finally carried out using the jack for adapting to specification;
8. hanging platform system dismounting: after end bay closure is constructed, according to the stress specific requirement of midspan closing, prestressed grouting Platform is hung in dismounting after reaching design requirement, is hung platform and is unclamped hangar system first when removing, is supported on the Hanging Basket stringer of abutment pier Lower reduction lowering device is disengaged end template, is gradually transferred Hanging Basket floor beam, stringer to ground, Hanging Basket master using hoist engine Truss is moved to the 0# sections of enough positions of Lifting Capacity by walking line mode, and is removed using loop wheel machine, wherein when removing, it then follows The principle of " first prop up and tear open afterwards, rear branch is first torn open ".
Above to it is provided by the invention be suitable for continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system into It has gone and has been discussed in detail, the explanation of specific embodiment is merely used to help understand method and its core concept of the invention.It should refer to It out, for those skilled in the art, without departing from the principle of the present invention, can also be to the present invention Some improvement and modification can also be carried out, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

Claims (3)

1. continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system, including it is end bay pier shaft, nearest away from end bay pier shaft In across pier shaft, the construction beam being erected on end bay pier shaft and in being erected at across the company on pier shaft and close to construction beam side Continuous beam, it is characterised in that: further include Hanging Basket, underframe longitudinal member and floor beam, the Hanging Basket effect is mounted on continuous beam, described One end of underframe longitudinal member rides upon on end bay pier shaft, the other end rides upon on Hanging Basket, and the floor beam is erected at underframe longitudinal member Bottom, the Cast-in-Situ Segment and closure section are cast on underframe longitudinal member and in the spaces between construction beam and continuous beam.
2. continuous beam with high-pier end bay Cast-in-Situ Segment according to claim 1 and closure section integrated construction system, feature exist In: the underframe longitudinal member and floor beam are at the lower edge of construction beam and continuous beam, on construction beam and continuous beam Edge is also provided with the wing plate nose girder right above underframe longitudinal member.
3. the construction party of continuous beam with high-pier end bay Cast-in-Situ Segment according to claim 1 and closure section integrated construction system Method includes the following steps:
1. preparation of construction: according to conventional stand-by mode, tentatively drafting construction technical schemes, carry out temporary supporting system arrangement, system Temporary load(ing) situation is counted, the technology branch of relevant departments is obtained according to stress of the calculating analysis beam body under hoisted load It holds, is analyzed by calculating, work out special construction plan, complete the construction of end bay Cast-in-Situ Segment access bridge, end bay Cast-in-Situ Segment and closure are provided Duan Zhidian, and procedure of submitting reports for approval is completed, carry out the work of confiding a technological secret before going into operation;
2. construction monitoring calculates analysis: according to end bay is cast-in-place and joint scheme designs, 1/2 company of will act on of Hanging Basket Cast-in-Situ Segment weight Continuous girder cantilever end, in the case where cantilever end increases loading condition, analysis influences bridge internal force, determines counterweight scheme,
According to end bay is cast-in-place and joint scheme design, Hanging Basket closure pours the 1/2 of the sum of section+Cast-in-Situ Segment weight and will act on continuous beam Cantilever end, in the case where cantilever end increases loading condition, analysis influences bridge internal force, determines counterweight scheme,
Access bridge hangs the impact analysis of end bay Cast-in-Situ Segment and end bay closure section load to bridge internal force;
3. cantilever construction to closure section and access bridge is constructed: after by the construction of main pier pier top 0# block, then the symmetrical cantilever pouring in two sides, The outstanding beam section that fills uses Hanging Basket cantilever construction, after the completion of one of them main pier cantilever construction, retreat in time in across Hanging Basket, be the other side Back boom construction hanging basket provides working space, in the last one cantilever segmental construction, needs each sunpender of Hanging Basket passing through box beam Hole suitably amplify, it is ensured that box beam deform when sunpender can in the hole of box beam front and back move freely, access bridge construct when in access bridge Sunpender hole is reserved on wing plate and top plate to support as stringer under stringer, wing plate inside Hanging Basket;
4. hanging basket advancing and platform hanging basket transformation, precompressed: boom segments end is moved forward to after the completion of Hanging Basket cantilever construction, by Hanging Basket Stringer be adjusted to it is consistent with abutment pier top surface absolute altitude locate, whether detection stringer length meets end bay Cast-in-Situ Segment and closure section pours length Degree, the spreading stringer in the ungratified situation of height;Lower beam before Hanging Basket is extended into bridge pier, then Hanging Basket stringer is ridden upon into bridge Front crossbeam is removed after on pier, and overlap joint is met by the mobile adjustment stringer position of Hanging Basket and is required, wherein end bay Cast-in-Situ Segment and closure Section wing plate outside-supporting beam and inside top plate supporting beam by finish rolling deformed bar are hung on access bridge wing plate and inner top panel;Remove cantilever When Hanging Basket, end bay closure section bracket and installation template are set up, construction material, equipment in removing case top, case are applied for closure section The material and facility of work is put in an orderly manner to pier top;
Hanging Basket is transformed after the completion of stage+module, carries out precompressed to whole system, end bay construction section uses steel and 1t/ bags of sandbag Common preloading carries out preloading according to the sequence of bottom plate, web, top plate and wing plate, wherein by 40% → 60% → 80% → 100% → The other end of 120% multistage loadings, T structure is balanced ballast by water tank;
5. end bay cast-in-place section construction: end bay cast-in-place section construction platform floor is supported on abutment pier by Hanging Basket stringer and Hanging Basket cantilever is applied Workshop section, wing plate are supported on longitudinal hanging beam, and when end bay cast-in-place section construction, installation bed die and side form first adjust template Position and absolute altitude carry out the installation at bottom, abdomen, top and diaphragm plate reinforcing bar, bellows after installation inner support, internal model and sealing end mould, most After-pouring concrete, according to embedded anchorage is designed, realizes one-end tension when constructing end bay Cast-in-Situ Segment;
In end bay cast-in-place section construction, need to end bay cantilever end carry out ballast, and according to design and monitoring requirement in across side into Row counterweight, when Cast-in-Situ Segment pours concrete, cantilever end, which synchronizes, to discharge water, to keep cantilever end elevation not change, end bay cantilever end with Midspan closing end counterweight is all made of water tank and the mode that end bay cantilever end carries out ballast is arranged in, and wherein the weight of water tank is existing for end bay Pour end and pour the 1/2 of weight, wherein water tank welds water tank using brick or irony, when end bay Cast-in-Situ Segment pours, in across water tank not Waterproof unloading, only end bay cantilever end discharges water unloading;
6. end bay closure section construction: being locked according to midspan closing hanger installation → reinforcing bar binding → prestress pipe installation → closure It is fixed, remove lateral opening bracket, remove central bearing point horizontal direction temporary constraint → selection on the day of minimum temperature time casting concrete → Removal water tank ballast → closure section prestressed stretch-draw, anchoring, grouting finish step by step while casting concrete sequence carries out Construction, closure pour cantilever end and should temporarily connect with end bay Cast-in-Situ Segment, and the section concrete that avoids joining the two sections of a bridge, etc is pouring and premature cure mistake Apparent volume change occurs in journey, locking time is executed by closure section locking design, and Construction Support stiff skeleton is using " pre-buried The bold property I-shaped steel skeleton+pre-embedded anchoring bolts of foundation bolt+connection ";
7. end bay closure section tensioning: according to Design of Construction Organization arrangement, adjusting prestressing force in advance is one-end tension technique, cast-in-place Embedded anchor plate tensioning position, installs both ends tension ground tackle for anchored end after lashing when section construction, passes through anchorage using steel strand wires, And pre-tightened in the other end using single tendon stretch jack, entire beam tension is finally carried out using the jack for adapting to specification;
8. hanging platform system dismounting: after end bay closure is constructed, according to the stress specific requirement of midspan closing, prestressed grouting Platform is hung in dismounting after reaching design requirement, is hung platform and is unclamped hangar system first when removing, is supported on the Hanging Basket stringer of abutment pier Lower reduction lowering device is disengaged end template, is gradually transferred Hanging Basket floor beam, stringer to ground, Hanging Basket master using hoist engine Truss is moved to the 0# sections of enough positions of Lifting Capacity by walking line mode, and is removed using loop wheel machine, wherein when removing, it then follows The principle of " first prop up and tear open afterwards, rear branch is first torn open ".
CN201910372541.XA 2019-05-06 2019-05-06 Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system and construction method CN109944170A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910372541.XA CN109944170A (en) 2019-05-06 2019-05-06 Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910372541.XA CN109944170A (en) 2019-05-06 2019-05-06 Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system and construction method

Publications (1)

Publication Number Publication Date
CN109944170A true CN109944170A (en) 2019-06-28

Family

ID=67016966

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910372541.XA CN109944170A (en) 2019-05-06 2019-05-06 Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system and construction method

Country Status (1)

Country Link
CN (1) CN109944170A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110345915A (en) * 2019-07-11 2019-10-18 中交公路养护工程技术有限公司 A kind of highway Surveillance of Continuous Beam end bay Cast-in-Situ Segment precompressed detection device and method
CN110409306A (en) * 2019-07-23 2019-11-05 中国十七冶集团有限公司 A kind of construction method that continuous rigid frame bridge end bay closes up
CN110409316A (en) * 2019-08-15 2019-11-05 中交路桥华南工程有限公司 End bay closure construction method
CN110468714A (en) * 2019-08-09 2019-11-19 中铁七局集团有限公司 Overlength joins lateral closure construction method after unequal span asymmetric continuous bridge is first indulged
CN110629677A (en) * 2019-09-29 2019-12-31 中铁大桥局集团有限公司 Method for erecting section steel beam on pier top short slideway beam
CN111088759A (en) * 2019-12-24 2020-05-01 中交二航局第四工程有限公司 Construction method for steel strand of side span closure section of cast-in-place beam cast by cantilever

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110345915A (en) * 2019-07-11 2019-10-18 中交公路养护工程技术有限公司 A kind of highway Surveillance of Continuous Beam end bay Cast-in-Situ Segment precompressed detection device and method
CN110409306A (en) * 2019-07-23 2019-11-05 中国十七冶集团有限公司 A kind of construction method that continuous rigid frame bridge end bay closes up
CN110468714A (en) * 2019-08-09 2019-11-19 中铁七局集团有限公司 Overlength joins lateral closure construction method after unequal span asymmetric continuous bridge is first indulged
CN110409316A (en) * 2019-08-15 2019-11-05 中交路桥华南工程有限公司 End bay closure construction method
CN110629677A (en) * 2019-09-29 2019-12-31 中铁大桥局集团有限公司 Method for erecting section steel beam on pier top short slideway beam
CN111088759A (en) * 2019-12-24 2020-05-01 中交二航局第四工程有限公司 Construction method for steel strand of side span closure section of cast-in-place beam cast by cantilever

Similar Documents

Publication Publication Date Title
CN105926669B (en) A kind of Construction Method of Metro Station
CN101230785B (en) Construction method for large section and multiple sections tunnel lining
CN101586330B (en) Receding construction method of cradle of continuous girder bridge made of prestressing concrete
CN101914897B (en) Construction method of single main cable inclined-suspender earth anchored suspension bridge
CN102146799B (en) Construction equipment for inverted arch of two-track tunnel of high-speed railway
CN102146796B (en) Construction technology for inverted arch of two-track tunnel of high-speed railway
CN103967050A (en) Construction system of subway station
CN104878693B (en) Lateral girder erection structure for truss double-girder type bridge girder erection machine, construction method of erection structure, and lateral girder erection method based on erection structure
CN101457513B (en) Bridge erection method
CN104695337B (en) Self-lifting sliding and turnover construction system and construction method
CN106223360A (en) Use the open cut cast in place and precast construction subway station construction method of stake supporting system
CN101736697B (en) Construction method for pushing and furling complete bracket of steel box girders
CN101748681B (en) Pretensioning method construction technology of 50m broken line reinforced concrete T-shaped beam
CN103741601B (en) Tower, beam and cable synchronous bridge forming technology
CN101117791B (en) Abnormal shape steel case and orthotropic plate bottom formwork combined type moving die carrier framework and construction method thereof
CN201908664U (en) Movable trestle bridge invert form board trolley
CN101250856B (en) Echelon cradle as well as construction method thereof
CN201065511Y (en) Mobile die carrier bridge fabrication machine for thin wall high frusta
CN105201106A (en) Construction method of double-shear wall template formwork at deformation joint
CN103161126A (en) Road bridge variable section hollow high pier slip-form construction method
CN104480810B (en) Low circuit continuous frame formula support rail girder construction and the construction method thereof of putting of middle low speed magnetic suspension
CN103498425B (en) One completely knocks down multifunctional assembled bearing bracket structure and construction method thereof
CN104831632B (en) A kind of bridge cable tower entablature and sill construction method
CN202830776U (en) Bridge variable cross-section rectangular high pier cantilever creeping formwork construction device
CN101225638A (en) Method for mounting ground anchor type suspension bridge prestressed concrete stiffening box girder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zhang Zhifei

Inventor after: Li Bingyue

Inventor after: Jiang Bo

Inventor after: Wang Hai

Inventor after: Chen Zhenyu

Inventor after: Liu Zhongfu

Inventor after: Yang Zhonghu

Inventor after: Yi Sicong

Inventor after: Yu Fei

Inventor after: Li Hongling

Inventor after: Hu Jianbo

Inventor after: Yang Xiang

Inventor after: Ma Yingfu

Inventor after: Duan Jili

Inventor after: Xu Li

Inventor after: Yan Li

Inventor after: Xie Yonghui

Inventor after: Jiang Zhen

Inventor after: Zhang Qingming

Inventor after: Tao Wei

Inventor after: Xiang Qilai

Inventor after: Li Xiaoqian

Inventor before: Zhang Zhifei

Inventor before: Yang Xiang

Inventor before: Yan Li

Inventor before: Xie Yonghui

Inventor before: Jiang Zhen

Inventor before: Zhang Qingming

Inventor before: Tao Wei

Inventor before: Xiang Qilai

Inventor before: Li Xiaoqian

CB03 Change of inventor or designer information