CN109930603A - A kind of ultra-deep is inverse to make steel pipe column verticality control device and its application method - Google Patents
A kind of ultra-deep is inverse to make steel pipe column verticality control device and its application method Download PDFInfo
- Publication number
- CN109930603A CN109930603A CN201910237203.5A CN201910237203A CN109930603A CN 109930603 A CN109930603 A CN 109930603A CN 201910237203 A CN201910237203 A CN 201910237203A CN 109930603 A CN109930603 A CN 109930603A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- pipe column
- correcting
- correction device
- deep
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The present invention provides that a kind of ultra-deep is inverse to make steel pipe column verticality control device and its application method, the positioning of steel pipe column locating steel frame is set at the upper end of foundation pit, steel pipe column vertically passes through steel pipe column locating steel frame and extends in foundation pit, axial distribution setting of the top hydraulic correction device along steel pipe column, and the base end of top hydraulic correction device is fixed on steel pipe column locating steel frame, the hydraulically extensible end of top hydraulic correction device is held out against to the side wall of steel pipe column, the circumferentially distributed lower end for being fixed on steel pipe column of lower hydraulic means for correcting, the base end of lower hydraulic means for correcting is fixed on the side wall of steel pipe column, the hydraulically extensible end of lower hydraulic means for correcting is vertically and fixedly provided with proofreading board.It avoids steel pipe post holes to occur tilting in the construction process and other issues, guarantees construction quality.Belong to construction pile foundation technology field.
Description
Technical field
The present invention relates to a kind of ultra-deep against steel pipe column verticality control device and its application method is made, and belongs to construction stake
Base technical field.
Background technique
With the development of Urban Construction in China, city underground engineering is more and more using the project of reverse construction.It compares
In other construction method of deep foundation ditch, it is most common underground that contrary sequence method, which has, which to be protected environment, shortens the construction period etc. obviously a little,
Construction technology.Reverse construction is preferentially selected at Large Underground Emporium, underground parking, underground transportation junction station etc..
Frame column of the contrary sequence method steel pipe column as axial compression bears vertical load when basement construction, is also simultaneously
Guarantee horizontally-supported key structure when reverse construction, therefore, the control planning of steel pipe column verticality is to entire contrary sequence method
The construction quality of lower room is the project of emphasis control in construction.
Summary of the invention
It is an object of the invention to: it provides that a kind of ultra-deep is inverse to make steel pipe column verticality control device and its application method, keeps away
Exempt from steel pipe post holes to occur tilting in the construction process and other issues, guarantees construction quality.
To solve the above problems, such a ultra-deep of proposed adoption is inverse to make steel pipe column verticality control device, including steel pipe column
Locating steel frame, top hydraulic correction device and lower hydraulic means for correcting, the positioning of steel pipe column locating steel frame are set to the upper of foundation pit
At end, steel pipe column vertically passes through steel pipe column locating steel frame and extends in foundation pit, axis of the top hydraulic correction device along steel pipe column
It is arranged to distribution, and the base end of top hydraulic correction device is fixed on steel pipe column locating steel frame, top hydraulic correction device
Hydraulically extensible end hold out against to the side wall of steel pipe column, the lower hydraulic means for correcting is circumferentially distributed to be fixed on steel pipe column
The base end of lower end, lower hydraulic means for correcting is fixed on the side wall of steel pipe column, the hydraulically extensible of lower hydraulic means for correcting
End is vertically and fixedly provided with proofreading board.
In forenamed vertical degree control device, the top hydraulic correction device and lower hydraulic means for correcting are along level side
To setting;
In forenamed vertical degree control device, shared two groups up and down of the top hydraulic correction device, and upper and lower two groups of top
Hydraulic correction device is vertically arranged in a one-to-one correspondence;
Its application method is as follows:
During steel pipe column decentralization, top hydraulic correction device makes the center pair of steel pipe column by telescopic device adjustment
Quasi- foundation pit central point, standard cylinder barrel mold check center position and verticality, and external manual measurement ensures that rack contraposition is accurate
After take out mold;
After decentralization in place, promotion 20mm slightly keeps steel pipe column hanging, carries out measuring for verticality at this time, according to testing result
Telescopic device drilling depth in lower hydraulic means for correcting is adjusted, corrected to make steel pipe column bottom centre point and foundation pit center
Point is overlapped, and guarantees steel pipe column verticality.
Compared with prior art, the invention avoids steel pipe column run-off the straight in the construction process, cause subsequently to connect down
There are quality problems in continuous wall, influences contrary sequence method underground construction quality.This method is easy to operate, and materials are convenient, sound construction, safety
Property it is high, overcome the deficiencies in the prior art.
Detailed description of the invention
Fig. 1 is the structural schematic diagram under use state of the present invention.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, the present invention will be made below further detailed
Explanation.
Embodiment:
Referring to attached drawing 1, make steel pipe column verticality control device, including steel pipe column positioning the present embodiment provides a kind of ultra-deep is inverse
Steelframe 1, top hydraulic correction device 2 and lower hydraulic means for correcting 3, top hydraulic correction device 2 and lower hydraulic correction dress
Set 3 horizontally disposed, the positioning of steel pipe column locating steel frame 1 is set at the upper end of foundation pit 4, and steel pipe column 5 vertically passes through
Steel pipe column locating steel frame 1 simultaneously extends in foundation pit 4, and top hydraulic correction device 2 is arranged along the axial distribution of steel pipe column 5, and top
The base end of hydraulic correction device 2 is fixed on steel pipe column locating steel frame 1, the hydraulically extensible end top of top hydraulic correction device 2
Tightly on the side wall of steel pipe column 5, shared two groups up and down of top hydraulic correction device 2, and upper and lower two groups of top hydraulic correction devices 2
It is vertically arranged in a one-to-one correspondence, the circumferentially distributed lower end for being fixed on steel pipe column 5 of lower hydraulic means for correcting 3, lower part liquid
The base end of pressure means for correcting 3 is fixed on the side wall of steel pipe column 5, and the hydraulically extensible end of lower hydraulic means for correcting 3 is vertically solid
Surely there is proofreading board 6, proofreading board 6 is square plate.
Its construction method is as follows:
During steel pipe column 5 is transferred, top hydraulic correction device 2 is made in steel pipe column 5 by telescopic device adjustment
The heart is directed at 4 central point of foundation pit, and standard cylinder barrel mold checks center position and verticality, and external manual measurement ensures that rack aligns
Mold is taken out after accurate;
After decentralization in place, promotion 20mm slightly keeps steel pipe column 5 hanging, carries out measuring for verticality at this time, according to testing result
Telescopic device drilling depth in lower hydraulic means for correcting 3 is adjusted, corrected to make 5 bottom centre's point of steel pipe column and foundation pit 4
Central point is overlapped, and guarantees 5 verticality of steel pipe column.
The above embodiments are only used to illustrate and not limit the technical solutions of the present invention, although referring to above-described embodiment to this hair
It is bright to be described in detail, it will be apparent to an ordinarily skilled person in the art that: still the present invention can be modified or be waited
With replacement, without departing from the spirit or scope of the invention, or any substitutions, should all cover in power of the invention
In sharp claimed range.
Claims (4)
1. a kind of ultra-deep is inverse to make steel pipe column verticality control device, it is characterised in that: including steel pipe column locating steel frame (1), top
Hydraulic correction device (2) and lower hydraulic means for correcting (3), steel pipe column locating steel frame (1) position the upper end for being set to foundation pit (4)
Place, steel pipe column (5) vertically pass through steel pipe column locating steel frame (1) and extend in foundation pit (4), top hydraulic correction device (2) edge
The axial distribution setting of steel pipe column (5), and the base end of top hydraulic correction device (2) is fixed on steel pipe column locating steel frame (1)
On, the hydraulically extensible end of top hydraulic correction device (2) is held out against to the side wall of steel pipe column (5), the lower hydraulic correction dress
(3) circumferentially distributed lower end for being fixed on steel pipe column (5) is set, the base end of lower hydraulic means for correcting (3) is fixed on steel pipe column
(5) on side wall, the hydraulically extensible end of lower hydraulic means for correcting (3) is vertically and fixedly provided with proofreading board (6).
2. a kind of ultra-deep is inverse according to claim 1 makees steel pipe column verticality control device, it is characterised in that: the top liquid
Press apparatus for correcting (2) and lower hydraulic means for correcting (3) horizontally disposed.
3. a kind of ultra-deep is inverse according to claim 1 makees steel pipe column verticality control device, it is characterised in that: the top liquid
Shared two groups up and down of apparatus for correcting (2) are pressed, and upper and lower two groups of top hydraulic correction devices (2) are vertically arranged in a one-to-one correspondence.
4. the inverse application method for making steel pipe column verticality control device of the ultra-deep as described in claim 1,2 or 3, which is characterized in that
The specific method is as follows:
During steel pipe column (5) are transferred, top hydraulic correction device (2) makes steel pipe column (5) by telescopic device adjustment
Center is directed at foundation pit (4) central point, and standard cylinder barrel mold review center position and verticality, external manual measurement ensure rack
Mold is taken out after contraposition is accurate;
After decentralization in place, promotion 20mm slightly makes steel pipe column (5) vacantly, carries out measuring for verticality at this time, according under testing result
Telescopic device drilling depth in portion's hydraulic corrector (3) is adjusted, corrected to make steel pipe column (5) bottom centre's point and foundation pit
(4) central point is overlapped, and guarantees steel pipe column (5) verticality.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910237203.5A CN109930603A (en) | 2019-03-27 | 2019-03-27 | A kind of ultra-deep is inverse to make steel pipe column verticality control device and its application method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910237203.5A CN109930603A (en) | 2019-03-27 | 2019-03-27 | A kind of ultra-deep is inverse to make steel pipe column verticality control device and its application method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109930603A true CN109930603A (en) | 2019-06-25 |
Family
ID=66988366
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910237203.5A Pending CN109930603A (en) | 2019-03-27 | 2019-03-27 | A kind of ultra-deep is inverse to make steel pipe column verticality control device and its application method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109930603A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110409481A (en) * | 2019-08-08 | 2019-11-05 | 中冶天工集团天津有限公司 | A kind of rim of a cup formula concrete foundation pit column fixed device and its installation method |
CN114108630A (en) * | 2021-12-31 | 2022-03-01 | 张忠良 | Civil engineering building foundation pile construction equipment |
CN114855768A (en) * | 2022-05-07 | 2022-08-05 | 中铁二十局集团第四工程有限公司 | Steel pipe column positioning construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101824919A (en) * | 2010-03-26 | 2010-09-08 | 中铁隧道集团有限公司 | Deep hole underwater installation and locating method of steel pipe column in weak watery stratum |
CN103321212A (en) * | 2013-05-27 | 2013-09-25 | 上海市基础工程有限公司 | One-column-one-pile post inserting method construction process |
CN106759477A (en) * | 2016-12-26 | 2017-05-31 | 中铁二局集团有限公司 | A kind of sheltered reverse excavation steel pipe column positioning construction method |
CN209837032U (en) * | 2019-03-27 | 2019-12-24 | 中国建筑第四工程局有限公司 | Super-deep reverse-construction steel pipe column verticality control device |
-
2019
- 2019-03-27 CN CN201910237203.5A patent/CN109930603A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101824919A (en) * | 2010-03-26 | 2010-09-08 | 中铁隧道集团有限公司 | Deep hole underwater installation and locating method of steel pipe column in weak watery stratum |
CN103321212A (en) * | 2013-05-27 | 2013-09-25 | 上海市基础工程有限公司 | One-column-one-pile post inserting method construction process |
CN106759477A (en) * | 2016-12-26 | 2017-05-31 | 中铁二局集团有限公司 | A kind of sheltered reverse excavation steel pipe column positioning construction method |
CN209837032U (en) * | 2019-03-27 | 2019-12-24 | 中国建筑第四工程局有限公司 | Super-deep reverse-construction steel pipe column verticality control device |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110409481A (en) * | 2019-08-08 | 2019-11-05 | 中冶天工集团天津有限公司 | A kind of rim of a cup formula concrete foundation pit column fixed device and its installation method |
CN114108630A (en) * | 2021-12-31 | 2022-03-01 | 张忠良 | Civil engineering building foundation pile construction equipment |
CN114855768A (en) * | 2022-05-07 | 2022-08-05 | 中铁二十局集团第四工程有限公司 | Steel pipe column positioning construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109930603A (en) | A kind of ultra-deep is inverse to make steel pipe column verticality control device and its application method | |
CN202298628U (en) | Automatic steel pipe column perpendicularity adjusting device using reverse construction method | |
CN102493471B (en) | Suspending installation construction process method of structural foot margin anchor bolt | |
CN104120721A (en) | Method for constructing static pressure pile foundation | |
CN104389268A (en) | Steel tower column with positioning structure and hoisting construction method thereof | |
CN110016914A (en) | Contrary sequence method steel pipe column perpendicularity correction equipment and steel pipe column construction method | |
CN104111031A (en) | Surface deformation optical measurement sighting target protecting device and monitoring system and method | |
CN209837032U (en) | Super-deep reverse-construction steel pipe column verticality control device | |
CN210031813U (en) | Steel-pipe column straightness correcting unit that hangs down of reverse construction method | |
CN106025486A (en) | Geological radar antenna self-regulation strutting device | |
CN217811023U (en) | Guide frame for positioning construction of foundation pit support structure upright post pile and lattice post | |
CN105569351A (en) | Mounting construction technology of steel structure steel column | |
CN203238967U (en) | Large steel structure frame whole lifting device | |
CN206888545U (en) | A kind of interim stud location regulating system | |
CN206189607U (en) | Rag bolt location structure | |
CN207829002U (en) | A kind of tower crane lattice column auxiliary locator | |
CN204298736U (en) | A kind of steel tower column with location structure | |
CN209703544U (en) | A kind of native pile foundation of monitoring upright bar | |
CN206477353U (en) | Automatic-positioning type steel pipe column | |
CN205530263U (en) | A locator for construction of steel pipe retaining pile | |
CN105696596A (en) | Positioner for steel pipe guard post construction and construction method of steel pipe guard post | |
CN203821231U (en) | Leveling support | |
CN214738066U (en) | Guiding device for perpendicularity adjustment of steel pipe pile | |
CN205576923U (en) | A locating rack for construction of pre -buried lattice column of reverse construction method | |
CN218492501U (en) | Earth-wood pile foundation construction pile foundation hole fixed point device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |