CN105696596A - Positioner for steel pipe guard post construction and construction method of steel pipe guard post - Google Patents
Positioner for steel pipe guard post construction and construction method of steel pipe guard post Download PDFInfo
- Publication number
- CN105696596A CN105696596A CN201610042895.4A CN201610042895A CN105696596A CN 105696596 A CN105696596 A CN 105696596A CN 201610042895 A CN201610042895 A CN 201610042895A CN 105696596 A CN105696596 A CN 105696596A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- auxiliary positioning
- construction
- localizer
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
- E02D13/04—Guide devices; Guide frames
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention provides a positioner which can improve guard post construction work so as to shorten the construction period and lower the cost and improve the positioning precision of a guard post as well as a construction method of the steel pipe guard post. The positioner comprises a positioner base and an auxiliary positioning pipe which is located above the positioner base, wherein a rectangular frame is arranged at the periphery of the auxiliary positioning pipe, and the auxiliary positioning pipe can be connected to the positioner base through four groups of adjustable jacks. The plane position and the perpendicularity of the steel pipe guard post are controlled by precisely lofting the position of the positioner through a total station, and the positioning precision of the guard post can be greatly improved by controlling the elevation of a post top through a level instrument; the used steel pipe guard post can be pulled out from a soil body by adopting a vibrating pipe pulling-out device after foundation pit engineering construction is finished, and the pulled-out steel pipe guard post further can be used again, so that the purpose of reusing the steel pipe guard post is achieved.
Description
Technical field
The present invention relates to fender post technical field of construction, be specifically related to a kind of localizer for the construction of steel pipe fender post and construction method thereof, be primarily adapted for use in subway station steel pipe fender post construction。
Background technology
Along with the quickening of Urbanization Process In China, urban population is added to the pressure that traffic brings and day by day substantially changes。Thus go up the corresponding underground traffic of traffic with us traditionally and just become the new channel alleviating urban traffic pressure。Here it is the subway transportation of development is being done one's utmost in current big or middle city。In subway station is built adopt fender posts to carry out foundation ditch protection more, and the cost at station shared by supporting pile structure about 15% ~ 20%。And in metno station design, supporting pile structure is generally temporary structure, namely discard after station has been built, and supporting pile structure can not have enough to meet the need and reuse, cause that station construction is relatively costly。
This traditional supporting pile structure construction is primarily present following deficiency:
1, supporting pile structure can not reuse, and construction cost is high;
2, supporting pile structure working procedure is many, and the construction period is longer;
3, fender post pile driving construction road occupying, take up an area more;
4, supporting pile structure is difficult to be accurately positioned, and pile body perpendicularity is difficult to control to。
Summary of the invention
For avoiding the weak point existing for above-mentioned prior art, the present invention provides one can improve fender post construction operation, with reduction of erection time and reduction cost, and improves the localizer of fender post positioning precision。
For solving above-mentioned technical problem, the present invention adopts the following technical scheme that
A kind of localizer for the construction of steel pipe fender post, including localizer pedestal and the auxiliary positioning pipe being positioned at this localizer pedestal, this auxiliary positioning pipe periphery has rectangular box, is connected by four groups of adjustable jack between described auxiliary positioning pipe with described localizer pedestal。
Preferably, described adjustable jack quadrangularly is arranged between localizer pedestal and auxiliary positioning pipe。
The present invention also provides for a kind of steel pipe fender post construction method adopting localizer described in the claims, comprises the steps:
1) smooth location, builds both sides concrete foundation, and in concrete foundation pre-buried angle steel;
2) the installation hole for placing steel tubes fender post, installation positioner pedestal are dug in rotation, and are welded and fixed with pre-buried angle steel;
3) adjustable jack and auxiliary positioning pipe are installed successively, and check auxiliary positioning pipe plane coordinates;
4) coordinate check errorless after, lift steel pipe fender post, steel pipe fender post is penetrated auxiliary positioning pipe successively;
5) by adjustable jack adjustment steel pipe fender post top to design altitude;
6), after the lifting of steel pipe fender post puts in place, uniformly backfilling about, fine sand is high to stake top mark;
7) step 1) is repeated to 6), until completing the construction of all fender posts of steel pipe。
Wherein in step 3), described in check auxiliary positioning pipe plane coordinates method particularly includes: adopt total powerstation and level gauge to remeasure plane coordinates and the elevation of auxiliary positioning pipe。
Compared with the prior art, the present invention has the beneficial effect that:
1, the present invention is by improving the location mode of fender post, it is possible to be greatly improved the positioning precision of fender post;
2, the present invention have selected reusable steel pipe fender post, has reached to economize on resources and reduce the purpose of cost;
3, present invention utilizes reusable steel pipe fender post localizer, improve steel pipe fender post construction speed, shorten the construction period;
4, each structure member form of the present invention is simple, can concentrate in factory and make, and in-site installation is easy to use。
Accompanying drawing explanation
Fig. 1 is the front view of localizer of the present invention;
Fig. 2 is the side view of localizer of the present invention;
Fig. 3 is the top view of localizer of the present invention;
Fig. 4 is the Construction State figure of construction method step one of the present invention;
Fig. 5 is the Construction State figure of construction method step two of the present invention;
Fig. 6 is the Construction State figure of construction method step three of the present invention;
Fig. 7 is the Construction State figure of construction method step four of the present invention。
In figure: 10, localizer pedestal, 20, auxiliary positioning pipe, 21, rectangular box, 30, adjustable jack。
Detailed description of the invention
Below in conjunction with accompanying drawing, a kind of preferred implementation of the present invention is described in detail。
As shown in Figure 1,2 and 3, described localizer includes localizer pedestal 10, auxiliary positioning pipe 20 and adjustable jack 30。Described localizer pedestal 10 is formed by two H profile steel longerons and two H profile steel beam weldings, is used for supporting auxiliary positioning pipe 20, and this auxiliary positioning pipe is through localizer pedestal and downwardly extends。Described auxiliary positioning pipe 20 is connected with described localizer pedestal 10 by adjustable jack 30, this auxiliary positioning pipe is used for plan-position and the control of gradient of assisting steel pipe fender post to construct, adopt steel plate and steel pipe in factory process molding, auxiliary positioning pipe periphery has rectangular box 21, for increasing and the contact area of adjustable jack, improve device stability。
Described adjustable jack 30 adopts DTC type accurate adjustment jack, and the present embodiment adopts four groups of adjustable jack pair auxiliary positioning pipes to be adjusted, and quadrangularly is arranged between localizer pedestal and auxiliary positioning pipe。
The present invention also provides for a kind of steel pipe fender post construction method adopting above-mentioned localizer, in conjunction with accompanying drawing 4-7, Specific construction step is described:
Step one, smooth location, build both sides concrete foundation 40, and in concrete foundation pre-buried angle steel 50, with reference to Fig. 4;
Step 2, rotation are dug the installation hole 60 for placing steel tubes fender post, installation positioner pedestal 10, and are welded and fixed with pre-buried angle steel 50, with reference to Fig. 5;
Step 3, successively adjustable jack 30 and auxiliary positioning pipe 20 it is installed, and checks auxiliary positioning pipe plane coordinates, total powerstation and level gauge can be adopted to remeasure plane coordinates and the elevation of auxiliary positioning pipe, with reference to Fig. 6;
Step 4, coordinate check errorless after, lift steel pipe fender post 70, steel pipe fender post penetrated auxiliary positioning pipe 20, with reference to Fig. 7;
Step 5, adjusted steel pipe fender post top by adjustable jack to design altitude;
After the lifting of step 6, steel pipe fender post puts in place, uniformly backfilling about, fine sand is high to stake top mark;
Repeat step one to six, until completing the construction of all fender posts of steel pipe。
The present invention controls steel pipe fender post plan-position and perpendicularity by the accurate lofting positioner position of total powerstation, controls height of pile top by level gauge, it is possible to be greatly improved the positioning precision of fender post;Steel pipe fender post used in the present invention, after Foundation Pit Construction completes, can adopt vibration pipe-drawing equipment to extract from the soil body, and the steel pipe fender post extracted can put back into again, to reach reusable purpose。Employing can have enough to meet the need reusable supporting pile structure, construction cost can be substantially reduced economize on resources the enhancing enterprise competitiveness in subway market, and working procedure can be reduced and save the duration, adopt when can have enough to meet the need reusable steel construction without assembling reinforcement simultaneously, municipal construction can reduce construction land tenure as much as possible。
The above embodiment is only that the preferred embodiment of the present invention is described; not the scope of the present invention is defined; under the premise designing spirit without departing from the present invention; various deformation that technical scheme is made by those of ordinary skill in the art and improvement, should fall in the protection domain that claims of the present invention are determined。
Claims (4)
1. the localizer for the construction of steel pipe fender post, it is characterized in that, including localizer pedestal (10) and the auxiliary positioning pipe (20) being positioned at this localizer pedestal, this auxiliary positioning pipe periphery has rectangular box (21), is connected by four groups of adjustable jack (30) between described auxiliary positioning pipe (20) with described localizer pedestal (10)。
2. localizer according to claim 1, it is characterised in that described adjustable jack (30) quadrangularly is arranged between localizer pedestal (10) and auxiliary positioning pipe (20)。
3. the steel pipe fender post construction method adopting localizer described in claim 1, it is characterised in that comprise the steps:
1) smooth location, builds both sides concrete foundation, and in concrete foundation pre-buried angle steel;
2) the installation hole for placing steel tubes fender post, installation positioner pedestal are dug in rotation, and are welded and fixed with pre-buried angle steel;
3) adjustable jack and auxiliary positioning pipe are installed successively, and check auxiliary positioning pipe plane coordinates;
4) coordinate check errorless after, lift steel pipe fender post, steel pipe fender post is penetrated auxiliary positioning pipe successively;
5) by adjustable jack adjustment steel pipe fender post top to design altitude;
6), after the lifting of steel pipe fender post puts in place, uniformly backfilling about, fine sand is high to stake top mark;
7) step 1) is repeated to 6), until completing the construction of all fender posts of steel pipe。
4. steel pipe fender post construction method according to claim 3, it is characterised in that in step 3), described in check auxiliary positioning pipe plane coordinates method particularly includes: adopt total powerstation and level gauge to remeasure plane coordinates and the elevation of auxiliary positioning pipe。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610042895.4A CN105696596A (en) | 2016-01-22 | 2016-01-22 | Positioner for steel pipe guard post construction and construction method of steel pipe guard post |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610042895.4A CN105696596A (en) | 2016-01-22 | 2016-01-22 | Positioner for steel pipe guard post construction and construction method of steel pipe guard post |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105696596A true CN105696596A (en) | 2016-06-22 |
Family
ID=56229142
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610042895.4A Pending CN105696596A (en) | 2016-01-22 | 2016-01-22 | Positioner for steel pipe guard post construction and construction method of steel pipe guard post |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105696596A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106480885A (en) * | 2016-11-07 | 2017-03-08 | 金陵科技学院 | Pile tube vertical piling positioning auxiliary device in a kind of cement soil wall |
CN106869123A (en) * | 2017-01-24 | 2017-06-20 | 青岛工学院 | The rotary steering pile frame and its construction method of a kind of Bidirectional pressure rotation uplift pile |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS58189423A (en) * | 1982-04-30 | 1983-11-05 | Hazama Gumi Ltd | Pile holder |
CN101824919A (en) * | 2010-03-26 | 2010-09-08 | 中铁隧道集团有限公司 | Deep hole underwater installation and locating method of steel pipe column in weak watery stratum |
CN102296600A (en) * | 2011-09-01 | 2011-12-28 | 北京交通大学 | Method for positioning middle pile of spread built subway station |
CN102767182A (en) * | 2012-07-18 | 2012-11-07 | 上海建工二建集团有限公司 | Verticality adjustment system for lattice column correcting mount and construction method thereof |
CN202865849U (en) * | 2012-09-10 | 2013-04-10 | 上海陆家嘴金融贸易区开发股份有限公司 | Counter-guiding control device for one-column-one-pile perpendicularity in frame reverse building method |
CN203546728U (en) * | 2013-10-28 | 2014-04-16 | 中国建筑第四工程局有限公司 | Improved installation fixing device of top-down steel pipe column |
CN205530263U (en) * | 2016-01-22 | 2016-08-31 | 中铁四局集团第一工程有限公司 | A locator for construction of steel pipe retaining pile |
-
2016
- 2016-01-22 CN CN201610042895.4A patent/CN105696596A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS58189423A (en) * | 1982-04-30 | 1983-11-05 | Hazama Gumi Ltd | Pile holder |
CN101824919A (en) * | 2010-03-26 | 2010-09-08 | 中铁隧道集团有限公司 | Deep hole underwater installation and locating method of steel pipe column in weak watery stratum |
CN102296600A (en) * | 2011-09-01 | 2011-12-28 | 北京交通大学 | Method for positioning middle pile of spread built subway station |
CN102767182A (en) * | 2012-07-18 | 2012-11-07 | 上海建工二建集团有限公司 | Verticality adjustment system for lattice column correcting mount and construction method thereof |
CN202865849U (en) * | 2012-09-10 | 2013-04-10 | 上海陆家嘴金融贸易区开发股份有限公司 | Counter-guiding control device for one-column-one-pile perpendicularity in frame reverse building method |
CN203546728U (en) * | 2013-10-28 | 2014-04-16 | 中国建筑第四工程局有限公司 | Improved installation fixing device of top-down steel pipe column |
CN205530263U (en) * | 2016-01-22 | 2016-08-31 | 中铁四局集团第一工程有限公司 | A locator for construction of steel pipe retaining pile |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106480885A (en) * | 2016-11-07 | 2017-03-08 | 金陵科技学院 | Pile tube vertical piling positioning auxiliary device in a kind of cement soil wall |
CN106869123A (en) * | 2017-01-24 | 2017-06-20 | 青岛工学院 | The rotary steering pile frame and its construction method of a kind of Bidirectional pressure rotation uplift pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209636847U (en) | Adjustable tower crane basis built-in fitting accurate positioning instrument | |
CN109487822B (en) | Method for installing and adjusting steel pipe column in reverse construction and control device | |
CN104264902B (en) | Steel pipe concrete column and pile foundation connection structure | |
CN105951747B (en) | A kind of construction method of the pre-buried lattice column of contrary sequence method | |
CN205530262U (en) | Adjust timing frame of steel tube column stake position among half reverse construction | |
CN104695557A (en) | Steel structure building construction method for one-step pre-burying of foundation bolts | |
CN202298628U (en) | Automatic steel pipe column perpendicularity adjusting device using reverse construction method | |
CN206503141U (en) | A kind of overlength casing in bridge pile foundation construction is accurately positioned mounting tool | |
CN107130592B (en) | construction method for long spiral drill and impact drill double-machine composite hole-forming cast-in-place pile | |
CN112900450A (en) | Rotary drilling and full-rotation combined back-inserting method positioning method for steel pipe structure pile by reverse construction method | |
CN110016938B (en) | Positioning and verticality adjusting device for rectangular lattice column of reverse construction method foundation pit | |
CN107558478A (en) | Foundation ditch and construction method of the support of Fei Shou roads with dynamic stress regulatory function | |
CN111335171A (en) | Construction method of steel trestle | |
CN110863495A (en) | Steel pipe column inserting accurate positioning structure and accurate positioning construction method | |
CN112240025A (en) | Station foundation pit engineering cover-excavation construction method | |
CN105696596A (en) | Positioner for steel pipe guard post construction and construction method of steel pipe guard post | |
CN202866304U (en) | Reverse-building-method steel pipe column bottom locating device | |
CN102296600B (en) | Method for positioning middle pile of spread built subway station | |
CN205530263U (en) | A locator for construction of steel pipe retaining pile | |
CN203323740U (en) | Building settlement nondestructive measurement leveling rod bracket | |
CN103061454A (en) | Locating method of installing concrete filled steel tubular column in underground deep hole | |
CN105625184A (en) | Subway station building method using bridge and station combined building mode | |
CN106403996A (en) | Production method of forced centering observation mark stake for precision engineering measurement | |
CN213572037U (en) | High prefabricated stand based on ecological barricade of grid | |
CN105756067B (en) | A kind of method of horizontal temporary support support replacement in deep basal pit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160622 |
|
RJ01 | Rejection of invention patent application after publication |