CN106759477A - A kind of sheltered reverse excavation steel pipe column positioning construction method - Google Patents

A kind of sheltered reverse excavation steel pipe column positioning construction method Download PDF

Info

Publication number
CN106759477A
CN106759477A CN201611217751.4A CN201611217751A CN106759477A CN 106759477 A CN106759477 A CN 106759477A CN 201611217751 A CN201611217751 A CN 201611217751A CN 106759477 A CN106759477 A CN 106759477A
Authority
CN
China
Prior art keywords
steel pipe
pipe column
positioning
locator
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611217751.4A
Other languages
Chinese (zh)
Inventor
李志宏
陈强
陈卓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
Original Assignee
China Railway No 2 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 2 Engineering Group Co Ltd filed Critical China Railway No 2 Engineering Group Co Ltd
Priority to CN201611217751.4A priority Critical patent/CN106759477A/en
Publication of CN106759477A publication Critical patent/CN106759477A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The present invention relates to underground engineering construction construction field, and in particular to a kind of sheltered reverse excavation steel pipe column positioning construction method.Including following steps:(1) steel pipe column pretreatment;(2) steel pipe column locator is installed;(3) locating platform is installed;(4) steel pipe column absolute altitude positioning;(5) steel pipe column positioning.The present invention is arranged on steel pipe column by by locator, when being positioned to steel pipe column, operate the locator and adjust steel pipe column center by being manually entered in steel pipe column, and taper locator is installed in uplift pile top of concrete without as conventional method, the method can omit embedded steel sleeve, pump drainage mud, broken pile head and installation taper locator operation, solve existing steel sleeve retaining wall positioning mode and there is tedious process, mud is difficult, manually enter hole operating risk problem high, the method constructing operation is simple, it is safe, shorten the steel pipe column construction period, reduce engineering cost, with good economy.

Description

A kind of sheltered reverse excavation steel pipe column positioning construction method
Technical field
The present invention relates to underground engineering construction construction field, and in particular to a kind of sheltered reverse excavation steel pipe column positions construction party Method.
Background technology
Sheltered reverse excavation is that after being excavated to certain depth downwards by ground, by top seal, remaining bottom engineering is in envelope Constructed under the top board for closing, i.e., successively excavated and built agent structure from top to bottom until base plate.Typically first in ground surface Do the building enclosure and middle pile of foundation ditch downwards, diaphram wall or curtain pile, intermediate supports are used more foundation pit enclosure structure It is agent structure middle standing pillar in itself is utilized to reduce construction costs more.The top layer soil body to agent structure top board can then be excavated Ground elevation, top board is poured by the use of the soil body not excavated as clay model.Top board can be as strong stull together, to prevent Building enclosure deforms in foundation ditch, after road is restored after backfill, resumes traffic.
With developing rapidly for city and urban track traffic, increasing subway station is built in heavy traffic, is built Build thing is intensive, underground utilities are crisscross city busy section of town and heavy traffic location.Because sheltered reverse excavation is handed over ground It is logical to disturb less, be conducive to environmental protection, it has also become the midtown of the external heavy traffic of Now Domestic is built subway station and taken A kind of effective ways.
In sheltered reverse excavation construction, construction stage and operational phase vertical load are mainly born with steel-pipe pile, to steel pipe The precision and degree control of post are proposed at a relatively high requirement, and steel pipe column construction positioning also turns into sheltered reverse excavation engineering One of heavy difficult point in construction.The construction of steel pipe column positioning in the prior art uses HPE engineering methods and steel sleeve retaining wall positioning mode, But both construction methods be present:
Positioning precision cannot ensure after HPE engineering methods exceed certain depth, and cost is high, cannot be inserted after pile foundation concrete initial set Enter positioning, engineering accident risk is high.
Steel sleeve retaining wall positioning mode is under the protection of steel sleeve, manually to enter in the cleaning hole of hole after slurry coat method, in resistance to plucking Taper locator is installed on pile concrete, then steel pipe column is hung to hole, by the automatic guiding function of taper locator, essence Really complete the bottom positioning of steel pipe column.But needed by following operation before taper locator is installed:Embedded steel sleeve (prevents from taking out Collapse hole after mud), pump drainage mud, manually enter hole broken pile head and manually enter hole taper locator is installed.The engineering method engineering time It is long, larger is influenceed on the duration;The mud extracted out from hole, its intractability is big, has a strong impact on the environment of job site;For super In the construction of deep foundation pit steel tube post, manually enter hole and abolish pile crown laitance, operating environment is poor, and the time is long, and risk is high.
The content of the invention
Present invention aim at:In being constructed in sheltered reverse excavation steel pipe column positioning, existing steel sleeve retaining wall positioning mode There is tedious process, mud is difficult, manually enter hole operating risk problem high, the present invention provides a kind of sheltered reverse excavation steel pipe Post positioning construction method, by using the construction method, when being positioned to steel pipe column, without using steel sleeve retaining wall, nothing Need pump drainage mud, taper locator is installed without manually entering hole broken pile head and without manually entering hole, efficiently solve existing skill In art there is tedious process in steel sleeve retaining wall positioning mode, and mud is difficult, manually enter hole operating risk problem high.
To achieve these goals, the technical solution adopted by the present invention is:
A kind of sheltered reverse excavation steel pipe column positioning construction method, including following steps:
A, steel pipe column is pre-processed;
B, circumferentially uniformly installed in steel pipe column bottom and can adjust the locator of steel pipe column center;
C, installation locating platform;
D, absolute altitude positioning is carried out to steel pipe column;
E, steel pipe column is positioned.
By the locator for being mounted with to can be used in adjusting steel pipe column center in steel pipe column bottom, enter to steel pipe column During row positioning, can operate the locator and adjust steel pipe column center by being manually entered in steel pipe column, make steel pipe column Perpendicularity meets construction requirement, and without as conventional method by uplift pile top of concrete installation taper locator come Positioning steel tube post, therefore the method can omit embedded steel sleeve, pump drainage mud, manually enter hole broken pile head and manually enter Kong An Dress taper locator operation, efficiently solves steel sleeve retaining wall positioning mode in the prior art and there is tedious process, and mud is difficult, Manually enter hole operating risk problem high, this steel pipe column localization method constructing operation is simple, safe, effectively shortens steel pipe The post construction period, engineering cost is greatly reduced, with good economy.
Used as preferred scheme of the invention, in stepb, the locator includes transmission device and support meanss;It is described Support meanss include the bearing of supporting plate and outer ring and support plate weld;The transmission device includes being fixedly linked with steel pipe column Thread bush, is equipped with screw rod in the thread bush, described screw rod one end is extended radially in steel pipe column along steel pipe column, the other end with The inner ring welding of bearing.
Because the thread bush of the locator is fixedly linked with steel pipe column, when steel pipe column positioning action is carried out, by artificial Screw rod is rotated in into steel pipe column, supporting plate will be driven to expand outwardly back brace offer level on uplift pile hole wall after screw rod movement Counter-force, makes the center of steel pipe column be moved, and the locator structure is simple, and easy to manufacture can quickly adjust steel pipe column Perpendicularity.
Used as preferred scheme of the invention, in step a, the steel pipe column pretreatment includes following steps:
A1, steel pipe column docking:It is integral that the steel pipe column that merogenesis is processed carries out docking at the scene;
A2, steel pipe column perforate and concrete precasting:The perforate and in steel pipe column on steel pipe column by buoyancy calculations result Pre-cast concrete;
A3, TOC chipping:By steel pipe column outer inclined-plane concrete chisel removal.
By docking pre-cast concrete in integral steel pipe column, the steel in pile foundation concreting process can be prevented Tubing string floats, while by pre-cast concrete upper flat, facilitates locating personnel into being adjusted hanging down for steel pipe column in steel pipe column Straight degree.
Used as preferred scheme of the invention, before step a1 is carried out, the steel pipe column need in advance use steel plate in processing Back cover.By to steel pipe column sealing, convenience pre-cast concrete in steel pipe column.
Used as preferred scheme of the invention, the locator is at least three, in 1.0~1.5m at the top of pre-cast concrete Position is along the circumferential direction uniformly installed on steel pipe column.It is easy to locating personnel to enter into steel pipe column using such design to pass through Rotational positioner screw rod is adjusted the perpendicularity of steel pipe column.
As preferred scheme of the invention, in step c, after locating platform hangs, should measure super flat, after the completion of will positioning Platform is fixed with ground.By to locating platform it is super it is flat after fixed with ground, so that it is guaranteed that accurately measurement and positioning platform top surface mark It is high and prevent the locating platform in steel pipe column position fixing process to be moved.
Used as preferred scheme of the invention, in step d, first measurement and positioning platform top surface absolute altitude is transferred according to steel pipe column After designed elevation and measurement result COMPREHENSIVE CALCULATING, two steel plate locator cards are welded on steel pipe column, steel pipe column is hung into uplift pile It is suspended on the crossbeam of locating platform both sides by locator card after in hole.Passing through the position of welded locator card ensures that steel pipe column is expired Foot puts designed elevation requirement, and steel pipe column top is suspended on locating platform, and due to Gravitative Loads, steel pipe column will be approximately at Vertical state, then entered into steel pipe column by locating personnel the vertical of steel pipe column is adjusted by rotational positioner screw rod Degree.
Used as preferred scheme of the invention, step e includes following steps:
E1, steel pipe column top plane positioning:After steel pipe column is lifted in locating platform centre bore, by total powerstation in locating rack Stake position central point is made at top, and hangs plumb bob, and it is suitable for reading to be placed on steel pipe column using the positioning cross frame for processing, and by positioning Level jack movement steel pipe column in platform, after plumb bob point is hung with positioning cross frame center superposition, enters to steel pipe column top Row is fixed.
E2, steel pipe column perpendicularity positioning:To pre-cast concrete face position in steel pipe column under locating personnel, survey crew is in steel By the way that plumb aligner cultellation is to pre-cast concrete face and transfers plumb bob, after plumb bob point overlaps with cultellation, locating personnel surveys on tubing string top Dimension tubing string wall adjusts the perpendicularity of steel pipe column by rotational positioner screw rod with a distance from plumb bob line.
By in stake position central point overhung plumb bob, making plumb bob point and being placed in steel pipe column positioning cross frame center suitable for reading Overlap, even if steel pipe column center suitable for reading and stake position center superposition, so as to complete steel pipe column top positioning, then by steel pipe column it is suitable for reading in The heart by the way that cultellation is to pre-cast concrete top surface and transfers plumb bob, by adjusting steel pipe post jamb with a distance from plumb bob line, so that steel Tubing string has preferable perpendicularity.
As preferred scheme of the invention, steel pipe column and locating platform are welded on one after the completion of the steel pipe column positioning Rise.It is to further prevent the steel pipe column in pile foundation concreting process from rising phenomenon occur using such method.
In sum, by adopting the above-described technical solution, the beneficial effects of the invention are as follows:
By the locator for being mounted with to can be used in adjusting steel pipe column center in steel pipe column bottom, enter to steel pipe column During row positioning, can operate the locator and adjust steel pipe column center by being manually entered in steel pipe column, make steel pipe column Perpendicularity meets construction requirement, and without as conventional method by uplift pile top of concrete installation taper locator come Positioning steel tube post, therefore the method can omit embedded steel sleeve, pump drainage mud, manually enter hole broken pile head and manually enter Kong An Dress taper locator operation, efficiently solves steel sleeve retaining wall positioning mode in the prior art and there is tedious process, and mud is difficult, Manually enter hole operating risk problem high, this steel pipe column localization method constructing operation is simple, safe, effectively shortens steel pipe The post construction period, engineering cost is greatly reduced, with good economy.
Brief description of the drawings
Fig. 1 is sheltered reverse excavation steel pipe column positioning construction method general structure schematic diagram of the invention.
Fig. 2 is the locator schematic diagram of sheltered reverse excavation steel pipe column positioning construction method of the invention.
Fig. 3 is that the locator of sheltered reverse excavation steel pipe column positioning construction method of the invention installs sectional view.
Fig. 4 is sheltered reverse excavation steel pipe column positioning construction method flow chart of the invention.
Marked in figure:1- locators, 11- thread bush, 12- sleeve pipes, 13- screw rods, 14- brake bars, 15- keep plates, 16- branch Fagging, 17- bearings, 2- locating platforms, 3- uplift pile hole walls, 4- steel pipe columns, 5- pre-cast concretes, 6- resistance to plucking pile concretes.
Specific embodiment
Below in conjunction with the accompanying drawings, the present invention is described in detail.
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that specific embodiment described herein is only used to explain the present invention, not For limiting the present invention.
Embodiment
The present invention provides a kind of sheltered reverse excavation steel pipe column positioning construction method;
As Figure 1-Figure 4, the sheltered reverse excavation steel pipe column positioning construction method in the present embodiment, including following step Suddenly:
A, steel pipe column is pre-processed;
B, circumferentially uniformly installed in steel pipe column bottom and can adjust the locator of steel pipe column center;
C, installation locating platform;
D, absolute altitude positioning is carried out to steel pipe column;
E, steel pipe column is positioned.
By the locator for being mounted with to can be used in adjusting steel pipe column center in steel pipe column bottom, enter to steel pipe column During row positioning, can operate the locator and adjust steel pipe column center by being manually entered in steel pipe column, make steel pipe column Perpendicularity meets construction requirement, and without as conventional method by uplift pile top of concrete installation taper locator come Positioning steel tube post, therefore the method can omit embedded steel sleeve, pump drainage mud, manually enter hole broken pile head and manually enter Kong An Dress taper locator operation, efficiently solves steel sleeve retaining wall positioning mode in the prior art and there is tedious process, and mud is difficult, Manually enter hole operating risk problem high, this steel pipe column localization method constructing operation is simple, safe, effectively shortens steel pipe The post construction period, engineering cost is greatly reduced, with good economy.
In the present embodiment, in stepb, the locator 1 includes transmission device, brake apparatus and support meanss;It is described Support meanss include supporting plate 16 and bearing 17, and the outer ring of the bearing 17 is welded with the plate face of supporting plate 16;The transmission device bag Two thread bush 11 are included, is arranged in coaxial spaced and the sleeve pipe 12 by being disposed in outside thread bush 11 is connected, the thread bush 11 Screw rod 13 is inside equipped with, the one end of the screw rod 13 is extended radially in steel pipe column 4 along steel pipe column 4, the other end and the inner ring of bearing 17 Welding;The brake apparatus includes two brake bars 14 and three pieces of keep plates 15, and it is outer simultaneously that the keep plate 15 is sheathed on sleeve pipe 12 Welded with sleeve pipe 12, the brake bar 14 is welded after passing through keep plate 15 with supporting plate 16.
Because the thread bush of the locator is fixedly linked with steel pipe column, when steel pipe column positioning action is carried out, by artificial Screw rod is rotated in into steel pipe column, supporting plate will be driven to expand outwardly back brace offer level on uplift pile hole wall after screw rod movement Counter-force, makes the center of steel pipe column be moved, and the locator structure is simple, and easy to manufacture can quickly adjust steel pipe column Perpendicularity.
In the present embodiment, in step a, the steel pipe column pretreatment includes following steps:
A1, steel pipe column docking:The merogenesis of steel pipe column 4 is machined to be transported to job site and be placed on docking platform and docked And installation tool post, wherein, steel pipe column processing need in advance use steel plate back cover, tool post flange to use M30 with steel pipe column flange Bolt connection, dismounting and tool post recycling after the completion of convenient positioning, tool post uses leak stopping king with steel pipe column seaming position Closure, mud is diffused in steel pipe column in stake when preventing decentralization.
A2, steel pipe column perforate and concrete precasting:After the docking of steel pipe column 4 and tool post installation, by buoyancy calculations Result perforate on steel pipe column carries out concrete precasting, using the steel plate closure aperture with bent anchor reinforcing bar after precoating.To ensure to apply Working medium amount, landform mating type steel of the selection with certain height difference is made teeming stage, it is ensured that steel pipe column angle of inclination is not less than 15 degree, during cast, strengthen concrete workability, the control of the slump, and strengthen concrete tamping, it is ensured that steel pipe column is precoated coagulation Native is closely knit.
A3, TOC chipping:After the initial set of pre-cast concrete 5, steel pipe column outer inclined-plane concrete chisel removal makes to precoat mixed Solidifying soil upper flat.
Concrete precasting is carried out after by being docked to steel pipe column, the steel pipe column in pile foundation concreting process can be prevented Float, while by the upper flat of pre-cast concrete 5, facilitate locating personnel into being adjusted the vertical of steel pipe column in steel pipe column Degree.
In the present embodiment, the locator is four, in 1.0~1.5m positions at the top of pre-cast concrete along the circumferential direction Uniformly it is installed on steel pipe column.It is easy to locating personnel to enter into using such design and passes through rotational positioner screw rod in steel pipe column It is adjusted the perpendicularity of steel pipe column.
In the present embodiment, in step c, treat after the completion of rotary digging drilled as holes, carrying out locating platform 2 and hanging, locating platform 2 hangs Discharge after finishing, should measure super flat, plan-position and level height are adjusted after finishing, and four spikes of platform are embedded in firmly with prior Built-in fitting welding or expansion bolt in terrace are fixed, to increase the stability of locating platform.By to locating platform it is super it is flat after Fixed with ground, so that it is guaranteed that accurate measurement and positioning platform top surface absolute altitude and preventing the locating platform in steel pipe column position fixing process from sending out Raw movement.
In the present embodiment, in step d, after locating platform is horizontally mounted to be adjusted, the top surface mark of measurement and positioning platform 2 Height, after transferring designed elevation and measurement result COMPREHENSIVE CALCULATING according to steel pipe column, welds two steel plate locator cards, steel on steel pipe column Tubing string is suspended on the crossbeam of locating platform both sides after hanging in stake by locator card, and locator card will ensure with the welding of steel pipe column The weight of steel pipe column and pre-cast concrete can be born, it is ensured that steel pipe column elevation location is accurate, ensures that steel pipe column is generally in again vertical Straight state.Passing through the position of welded locator card ensures that steel pipe column meets decentralization designed elevation requirement, and steel pipe column top is hanged Hang on locating platform, due to Gravitative Loads, steel pipe column will be approximately at vertical state, then enter into steel pipe by locating personnel The perpendicularity of steel pipe column is adjusted in post by rotational positioner screw rod.
In the present embodiment, step e includes following steps:
E1, steel pipe column top plane positioning:After steel pipe column 4 is lifted in the centre bore of locating platform 2, by total powerstation in positioning Top of the trellis makes stake position central point, and hangs plumb bob, and it is suitable for reading to be placed on steel pipe column using the positioning cross frame for processing, and by fixed Level jack movement steel pipe column in bit platform, after plumb bob point is hung with positioning cross frame center superposition, to steel pipe column top It is fixed, plan-position control deviation is 2mm.
E2, steel pipe column perpendicularity positioning:After the completion of the positioning of steel pipe column top, locating personnel is climbed by the good steel of pre-production Ladder needs to carry out gas detection by tool post mouthful is lower to steel pipe column pre-cast concrete face position, before lower opening, and sets up illumination and divulge information Equipment, locating personnel needs medical fitness and is equipped with a series of security implementations such as safety rope, kit, and survey crew is in steel pipe column top By the way that plumb aligner cultellation is to pre-cast concrete face and transfers plumb bob, after plumb bob point overlaps with cultellation, locating personnel utilizes tape measure at end Measurement steel pipe post jamb adjusts the perpendicularity of steel pipe column by rotational positioner screw rod with a distance from plumb bob line.
By in stake position central point overhung plumb bob, making plumb bob point and being placed in steel pipe column positioning cross frame center suitable for reading Overlap, even if steel pipe column center suitable for reading and stake position center superposition, so as to complete steel pipe column top positioning, then by steel pipe column it is suitable for reading in The heart by the way that cultellation is to pre-cast concrete top surface and transfers plumb bob, by adjusting steel pipe post jamb with a distance from plumb bob line, so that steel Tubing string has preferable perpendicularity.
In the present embodiment, steel pipe column and locating platform are welded using four A20 reinforcing bars after the completion of the steel pipe column positioning Together.It is to further prevent from emerging in steel pipe column appearance in pile foundation concreting process using such method As.
Specifically, steel pipe column 4 is carried out into steel plate back cover, the anti-floating of pre-cast concrete 5 and locating personnel is provided in steel pipe column Standpoint, 4 locators are installed on the outside of steel pipe column at post inner concrete top face 1.5m, locator screw rod stretches into steel pipe 300mm in post.By being manually entered rotary screw in steel pipe column so that supporting plate 16 is moved toward the direction of uplift pile hole wall 3, finally Support provides horizontal reacting force on uplift pile hole wall 3, to reach the purpose of steel pipe column bottom positioning.Steel pipe column is positioned at resistance to plucking for the first time Implement after pile cages decentralization, tremie placing resistance to plucking pile concrete 6 is transferred by steel pipe column outside after the completion of positioning, and be close to It is manually entered in steel pipe column before the uplift pile concrete initial set of steel pipe column bottom position and checks positioning, is carried out in steel pipe column after waiting by force Pouring for residual concrete, completes the construction of steel pipe column.
Presently preferred embodiments of the present invention is the foregoing is only, is not intended to limit the invention, it is all in original of the invention Any modification, equivalent and improvement for being made within reason etc., should be included within the scope of the present invention.

Claims (9)

1. a kind of sheltered reverse excavation steel pipe column positioning construction method, it is characterised in that including following steps:
A, steel pipe column is pre-processed;
B, circumferentially uniformly installed in steel pipe column bottom and can adjust the locator of steel pipe column center;
C, installation locating platform;
D, absolute altitude positioning is carried out to steel pipe column;
E, steel pipe column is positioned.
2. sheltered reverse excavation steel pipe column positioning construction method according to claim 1, it is characterised in that in stepb, institute Stating locator includes transmission device and support meanss;The support meanss include the axle of supporting plate and outer ring and support plate weld Hold;The transmission device includes the thread bush being fixedly linked with steel pipe column, and screw rod, the screw rod one are equipped in the thread bush End is extended radially in steel pipe column along steel pipe column, and the other end is welded with the inner ring of bearing.
3. sheltered reverse excavation steel pipe column positioning construction method according to claim 2, it is characterised in that in step a, institute Stating steel pipe column pretreatment includes following steps:
A1, steel pipe column docking:It is integral that the steel pipe column that merogenesis is processed carries out docking at the scene;
A2, steel pipe column perforate and concrete precasting:Perforate and precoated in steel pipe column on steel pipe column by buoyancy calculations result Concrete;
A3, TOC chipping:By steel pipe column outer inclined-plane concrete chisel removal.
4. sheltered reverse excavation steel pipe column positioning construction method according to claim 3, it is characterised in that carrying out step a1 Before, the steel pipe column need in advance use steel plate back cover in processing.
5. sheltered reverse excavation steel pipe column positioning construction method according to claim 4, it is characterised in that the locator is extremely It is less three, is along the circumferential direction uniformly installed on steel pipe column away from 1.0~1.5m positions at the top of pre-cast concrete.
6. sheltered reverse excavation steel pipe column positioning construction method according to claim 1, it is characterised in that in step c, it is fixed After bit platform hangs, should measure super flat, after the completion of locating platform is fixed with ground.
7. sheltered reverse excavation steel pipe column positioning construction method according to claim 6, it is characterised in that in step d, first Measurement and positioning platform top surface absolute altitude, after transferring designed elevation and measurement result COMPREHENSIVE CALCULATING according to steel pipe column, welds on steel pipe column Two steel plate locator cards are connect, steel pipe column is suspended on the crossbeam of locating platform both sides after hanging in tensile pile hole by locator card.
8. sheltered reverse excavation steel pipe column positioning construction method according to claim 7, it is characterised in that step e include with Under several steps:
E1, steel pipe column top plane positioning:After steel pipe column is lifted in locating platform centre bore, by total powerstation at the top of locating rack Stake position central point is made, and plumb bob is hung, it is suitable for reading to be placed on steel pipe column using the positioning cross frame for processing, and by locating platform Interior level jack moves steel pipe column, after plumb bob point is hung with positioning cross frame center superposition, steel pipe column top is consolidated It is fixed.
E2, steel pipe column perpendicularity positioning:To pre-cast concrete face position in steel pipe column under locating personnel, survey crew is in steel pipe column By the way that plumb aligner cultellation is to pre-cast concrete face and transfers plumb bob, after plumb bob point overlaps with cultellation, locating personnel measures steel on top Tubing string wall adjusts the perpendicularity of steel pipe column by rotational positioner screw rod with a distance from plumb bob line.
9. sheltered reverse excavation steel pipe column positioning construction method according to claim 8, it is characterised in that the steel pipe column is determined Steel pipe column is welded together with locating platform after the completion of position.
CN201611217751.4A 2016-12-26 2016-12-26 A kind of sheltered reverse excavation steel pipe column positioning construction method Pending CN106759477A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611217751.4A CN106759477A (en) 2016-12-26 2016-12-26 A kind of sheltered reverse excavation steel pipe column positioning construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611217751.4A CN106759477A (en) 2016-12-26 2016-12-26 A kind of sheltered reverse excavation steel pipe column positioning construction method

Publications (1)

Publication Number Publication Date
CN106759477A true CN106759477A (en) 2017-05-31

Family

ID=58925999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611217751.4A Pending CN106759477A (en) 2016-12-26 2016-12-26 A kind of sheltered reverse excavation steel pipe column positioning construction method

Country Status (1)

Country Link
CN (1) CN106759477A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107227738A (en) * 2017-08-03 2017-10-03 中铁十六局集团地铁工程有限公司 A kind of location structure and its localization method for small space steel pipe column
CN107675889A (en) * 2017-08-04 2018-02-09 上海建工建集团有限公司 Contrary sequence method steel pipe column vertical adjustment mould and vertical adjustment method
CN108265750A (en) * 2018-02-02 2018-07-10 北京市政建设集团有限责任公司 A kind of steel pipe column localization method
CN108532618A (en) * 2018-03-16 2018-09-14 无锡德林海环保科技股份有限公司 A kind of underwater installation method of heavy caliber back covers steel pipe well
CN108952007A (en) * 2018-08-15 2018-12-07 中电建南方建设投资有限公司 Construction is positioned manually in a kind of permanent steel column
CN109629555A (en) * 2018-06-21 2019-04-16 中铁十局集团第六工程有限公司 Improve the positioning device of empty stake interpolation steel pipe column and the method for pile integrated construction
CN109930603A (en) * 2019-03-27 2019-06-25 中国建筑第四工程局有限公司 A kind of ultra-deep is inverse to make steel pipe column verticality control device and its application method
CN110004988A (en) * 2019-02-11 2019-07-12 中国水电基础局有限公司 The protective device and method in a kind of extubation construction underground continuous wall connector hole
CN110485424A (en) * 2019-09-12 2019-11-22 深圳市工勘岩土集团有限公司 Deep basal pit underground structure contrary sequence method steel pipe column positioning device and positioning construction method
CN111676963A (en) * 2020-06-12 2020-09-18 中电建南方建设投资有限公司 Steel pipe upright post positioning device and positioning construction method thereof
CN112523227A (en) * 2020-12-14 2021-03-19 中国葛洲坝集团第一工程有限公司 Steel pipe column for underground space structure and construction method
CN112681294A (en) * 2021-01-18 2021-04-20 中国一冶集团有限公司 Concrete pipe pile
CN113718814A (en) * 2021-09-02 2021-11-30 中铁二十局集团第三工程有限公司 Pile foundation construction method and bridge pier construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101824919A (en) * 2010-03-26 2010-09-08 中铁隧道集团有限公司 Deep hole underwater installation and locating method of steel pipe column in weak watery stratum
JP2013108266A (en) * 2011-11-21 2013-06-06 Jfe Steel Corp Rotational driving device for spiral reinforcement steep pipe friction pile and screw-in penetration method
CN105297731A (en) * 2015-10-09 2016-02-03 中铁二局集团有限公司 Reverse construction method steel stand column positioning device and positioning method
CN105926672A (en) * 2016-05-06 2016-09-07 中铁十六局集团地铁工程有限公司 Mined metro station steel pipe column construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101824919A (en) * 2010-03-26 2010-09-08 中铁隧道集团有限公司 Deep hole underwater installation and locating method of steel pipe column in weak watery stratum
JP2013108266A (en) * 2011-11-21 2013-06-06 Jfe Steel Corp Rotational driving device for spiral reinforcement steep pipe friction pile and screw-in penetration method
CN105297731A (en) * 2015-10-09 2016-02-03 中铁二局集团有限公司 Reverse construction method steel stand column positioning device and positioning method
CN105926672A (en) * 2016-05-06 2016-09-07 中铁十六局集团地铁工程有限公司 Mined metro station steel pipe column construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李龙根: "《机械制造技术》", 31 August 2014 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107227738A (en) * 2017-08-03 2017-10-03 中铁十六局集团地铁工程有限公司 A kind of location structure and its localization method for small space steel pipe column
CN107675889A (en) * 2017-08-04 2018-02-09 上海建工建集团有限公司 Contrary sequence method steel pipe column vertical adjustment mould and vertical adjustment method
CN108265750A (en) * 2018-02-02 2018-07-10 北京市政建设集团有限责任公司 A kind of steel pipe column localization method
CN108532618A (en) * 2018-03-16 2018-09-14 无锡德林海环保科技股份有限公司 A kind of underwater installation method of heavy caliber back covers steel pipe well
CN109629555A (en) * 2018-06-21 2019-04-16 中铁十局集团第六工程有限公司 Improve the positioning device of empty stake interpolation steel pipe column and the method for pile integrated construction
CN108952007A (en) * 2018-08-15 2018-12-07 中电建南方建设投资有限公司 Construction is positioned manually in a kind of permanent steel column
CN110004988B (en) * 2019-02-11 2023-12-19 中国水电基础局有限公司 Protection device and method for joint hole of underground diaphragm wall constructed by tube drawing method
CN110004988A (en) * 2019-02-11 2019-07-12 中国水电基础局有限公司 The protective device and method in a kind of extubation construction underground continuous wall connector hole
CN109930603A (en) * 2019-03-27 2019-06-25 中国建筑第四工程局有限公司 A kind of ultra-deep is inverse to make steel pipe column verticality control device and its application method
CN110485424A (en) * 2019-09-12 2019-11-22 深圳市工勘岩土集团有限公司 Deep basal pit underground structure contrary sequence method steel pipe column positioning device and positioning construction method
CN111676963A (en) * 2020-06-12 2020-09-18 中电建南方建设投资有限公司 Steel pipe upright post positioning device and positioning construction method thereof
CN112523227A (en) * 2020-12-14 2021-03-19 中国葛洲坝集团第一工程有限公司 Steel pipe column for underground space structure and construction method
CN112681294A (en) * 2021-01-18 2021-04-20 中国一冶集团有限公司 Concrete pipe pile
CN112681294B (en) * 2021-01-18 2022-07-15 中国一冶集团有限公司 Concrete pipe pile
CN113718814A (en) * 2021-09-02 2021-11-30 中铁二十局集团第三工程有限公司 Pile foundation construction method and bridge pier construction method

Similar Documents

Publication Publication Date Title
CN106759477A (en) A kind of sheltered reverse excavation steel pipe column positioning construction method
CN106284313B (en) Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method
CN108086340B (en) Open caisson construction structure and construction method thereof
CN101824919B (en) Deep hole underwater installation and locating method of steel pipe column in weak watery stratum
CN105951747B (en) A kind of construction method of the pre-buried lattice column of contrary sequence method
CN110629744B (en) Construction process of steel pipe concrete pile of subway station
CN106930276B (en) The construction method of the deep hole blasting of rotary digging bored concrete pile and conduit rotary digging removing obstacles
CN111962504A (en) Construction method for covering and digging top-down permanent steel pipe column
CN110847177A (en) Fixed verticality adjusting and upward floating preventing device and method with steel pipe supporting column serving as structural column
CN106836206A (en) Casing rotary digging bore forming method
CN108149678A (en) A kind of loess retaining wall does the construction method of operation pore-creating filling pile
CN104747088A (en) Single-waist multi-leaf hose bit for bored pile and drilling construction method thereof
CN109778992A (en) A kind of ride well device and its construction method for pipeline construction
CN113638417B (en) Pile connection accurate positioning pouring system and construction method
CN110629747A (en) Full-casing full-rotation construction process for pile foundation under complex geological conditions
CN109853531A (en) A kind of pile foundation construction process of cast-in-situ bored pile
CN114673153A (en) Construction method of complex stratum overlength large-diameter pile foundation casing structure
CN107938658A (en) A kind of construction method of fender post
CN109024608A (en) The construction method that steel pipe column for contrary sequence method quickly positions
CN111945714A (en) Steel sleeve guiding method combined with steel upright column inserting construction method
CN106758759A (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN113417215A (en) Bridge construction method
CN115387328B (en) Beach cast-in-place pile construction method based on ultra-long spiral drilling machine
CN218148483U (en) Tower crane foundation structure
CN108035357B (en) Filling pile construction scheme and its funnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531