CN110004988A - The protective device and method in a kind of extubation construction underground continuous wall connector hole - Google Patents

The protective device and method in a kind of extubation construction underground continuous wall connector hole Download PDF

Info

Publication number
CN110004988A
CN110004988A CN201910109604.2A CN201910109604A CN110004988A CN 110004988 A CN110004988 A CN 110004988A CN 201910109604 A CN201910109604 A CN 201910109604A CN 110004988 A CN110004988 A CN 110004988A
Authority
CN
China
Prior art keywords
wall
connector hole
bucket body
protective device
nipple orifice
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910109604.2A
Other languages
Chinese (zh)
Other versions
CN110004988B (en
Inventor
徐方才
沈增良
丁耀华
布浩然
潘文国
黄志雄
王丽华
刘宗强
宁隆
姚远
张成胜
杨卫杰
陈天增
周发友
张天翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Foundation Engineering Co Ltd
Original Assignee
Sinohydro Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Foundation Engineering Co Ltd filed Critical Sinohydro Foundation Engineering Co Ltd
Priority to CN201910109604.2A priority Critical patent/CN110004988B/en
Publication of CN110004988A publication Critical patent/CN110004988A/en
Application granted granted Critical
Publication of CN110004988B publication Critical patent/CN110004988B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures

Abstract

The invention discloses the protective devices and method in a kind of extubation construction underground continuous wall connector hole.The protective device in a kind of extubation construction underground continuous wall connector hole, comprising: be fixed on the fixing protector in nipple orifice internal upper part region, there is the semi arch cylinder being bonded with connector hole wall, for protecting nipple orifice upper area;It is mounted on grooving bucket body and with the mobile protective device that the grooving bucket body moves from top to bottom from nipple orifice top following region, there is the arc panel being bonded with connector hole wall, for protecting nipple orifice top following region;Wherein, the distance between the outermost of the arc panel and grooving bucket body center of gravity be equal to grooving bucket body free suspension when bucket tooth outermost to grooving bucket body center of gravity at a distance from adjunction head bore radius.The present invention can promote and improve the connector construction quality of diaphram wall.

Description

The protective device and method in a kind of extubation construction underground continuous wall connector hole
Technical field
The present invention relates to underground continuous wall construction technique field more particularly to a kind of extubation construction underground continuous wall connectors The protective device and method in hole.
Background technique
Diaphragm Wall is firstly introduced into domestic hydroelectric project field the fifties, has been widely used in domestic soil The underground space supporting of the engineering fields such as Wood construction, municipal traffic, the water conservancy energy and environmental protection, underground water antiseepage, which is cut, seeps work Journey.Diaphram wall is usually underground concealed engineering, and jointing is wall weak location, is to embody construction quality and antiseepage The key of performance, the quality of connector directly affect the total quality of entire underground engineering, engineering service life and operating cost.
Current tube pulling method construction underground continuous wall connector has become the main technique of domestic underground continuous wall connector connection.Greatly The diaphram wall engineering practice of amount shows that underground continuous wall connector defect is the common common fault of construction of diaphragm wall, mainly The reason is that when constructing the second stage of slot, since the grooving equipment of the operation under mud is gone up and down by suspension cable, thus grooving bucket body It will shake left and right when excavation, so that grooving bucket tooth easily damages not high half round splce of fist stage concrete of formed but intensity, shape At irregular concrete male and female face, so that the later period can not thoroughly scrub clean connector, when concreting, easily blends mudcake Sundries, it is likely that form fault in seam, and then form the security risk of concealed work, increase post-processing and maintenance cost.Thing In reality in the actual construction process, in order to avoid generation security risk, it will usually be backfilled again to the region of grooving bucket tooth damage New concrete extends construction period to increase concrete loss and waste.
Summary of the invention
The object of the invention is in order to overcome the above-mentioned problems of the prior art, provide under a kind of extubation construction ground The protective device in continuous wall connector hole can promote and improve the connector construction quality of diaphram wall.
It is a further object of the present invention to provide a kind of guard methods in extubation construction underground continuous wall connector hole.
In order to realize the first object of the present invention, the following technical schemes are provided:
The protective device in a kind of extubation construction underground continuous wall connector hole, comprising: be fixed on nipple orifice internal upper part region Fixing protector, there is the semi arch cylinder that is bonded with connector hole wall, for protecting nipple orifice upper area;It is mounted on On grooving bucket body and with the mobile protective device that the grooving bucket body moves from top to bottom from nipple orifice top following region, tool There is the arc panel being bonded with connector hole wall, for protecting nipple orifice top following region;Wherein, the outermost of the arc panel with The distance between grooving bucket body center of gravity be equal to grooving bucket body free suspension when bucket tooth outermost to grooving bucket body center of gravity distance The radius of adjunction head bore.
Preferably, the outer wall of the semi arch cylinder is bonded with the connector hole wall in nipple orifice internal upper part region, on inner wall End and lower end are equipped with cylinder reinforcing member.
Preferably, the semi arch cylinder across the crossbeam on guide wall of underground continuous wall by being suspended in nipple orifice; The top layout of the semi arch cylinder has two suspension hanging rings for wearing the crossbeam.
Preferably, described two suspension hanging rings are symmetrical arranged, and the line of two suspension hanging rings is than the semi arch cylinder Center of gravity will close to the semi arch cylinder the center of circle.
Preferably, the mobile protective device further include: for the arc panel to be mounted under the ladder of grooving bucket body The support frame in portion.
Preferably, the arc panel includes: that its shape matches with the connector hole wall of nipple orifice top following region Curved plate;It is fixed on the yielding rubber plate of the curved plate outer wall.
Preferably, support frame as described above includes: the vertical plate for being welded on the curved plate inner wall, upper level board and lower level Plate;Wherein, the vertical plate is arranged between the upper level board and lower horizontal board.
Preferably, the ladder lower part of the grooving bucket body is equipped with the connection frame of fixed support frame as described above, the connection frame packet It includes: for fixing the upper junction plate of the upper level board;For fixing the lower connecting plate of the vertical plate;
Wherein, the upper junction plate is vertically arranged with the lower connecting plate.
In order to realize the second object of the present invention, the following technical schemes are provided:
The guard method in a kind of extubation construction underground continuous wall connector hole, comprising: fixed in nipple orifice internal upper part region Fixing protector has the semi arch cylinder being bonded with connector hole wall, for protecting nipple orifice upper area;In grooving bucket The mobile protective device that moves from top to bottom with grooving bucket body from nipple orifice top following region is installed on body, is had and connector The arc panel of hole wall fitting, for protecting nipple orifice top following region;Wherein, the outermost of the arc panel and grooving bucket body The outermost of bucket tooth is to grooving bucket body center of gravity apart from adjunction head bore when the distance between center of gravity is equal to grooving bucket body free suspension Radius.
The beneficial effects of the present invention are embodied in following aspect: protective device processing of the present invention and easy to use and flexible, can week Turn to use, during the second phase grooving of underground diaphragm wall can be effectively reduced, damage to formed semicircle concrete joint hole, The joint geometry and seam length of wall are kept, concrete amount is saved, avoids the occurrence of underground continuous wall connector defect, it is ensured that ground Lower diaphragm wall construction quality, the diaphram wall engineering of the various depth suitable for extubation construction joint.
Detailed description of the invention
Fig. 1 is the top view of fixing protector use state of the invention;
Fig. 2 is the A-A cross-sectional view of fixing protector use state of the invention;
Fig. 3 is the scheme of installation of mobile protective device of the invention on grooving bucket body;
Fig. 4 is the top view of mobile protective device of the invention in use state;
Fig. 5 is E-E cross-sectional view shown in Fig. 4;
Fig. 6 is use block diagram of the invention.
Description of symbols: 1- fixing protector;11- semi arch cylinder;12- hangs hanging ring;13- hoisting ring;14- is horizontal Beam;15,16- cylinder reinforcing member;2- moves protective device;21- curved plate;22- yielding rubber plate;The upper level board of 23-;24- Lower horizontal board;25- vertical plate;26- upper junction plate;27- lower connecting plate;28- bolt;3- grooving bucket body;31- ladder;32- bucket Tooth;I- operation platform;II- leads wall;III- fist stage concrete wall section;IV- mono- phase nipple orifice;V- second phase slot section;VI- borehole cleaning changes slurry Slot;VII- second phase slot concrete;The complete connector seam of VIII-.
Specific embodiment
The present invention provides the protective device and method in a kind of extubation construction underground continuous wall connector hole, for connecting to underground The formed nipple orifice that continuous one phase of wall slot section pours end, junction block tube drawing is completed is protected.
The protective device and method in the extubation construction underground continuous wall connector hole provided through the invention, can improve biography Unite tube pulling method construction diaphram wall process flow so that the technical ability factor for being protected from grooving operating personnel of nipple orifice and Grooving equipment performance influences, and promotes and improve the connector construction quality of diaphram wall.
The present invention is described in detail with reference to the accompanying drawings and examples.
The present embodiment provides a kind of protective devices in extubation construction underground continuous wall connector hole, comprising: is fixed on connector The fixing protector 1 in hole internal upper part region, for protecting nipple orifice upper area, buffering dispersion grooving bucket body is issuable Dock the collision of head bore upper area;Be mounted on grooving bucket body and with grooving bucket body from nipple orifice top following region from upper and Grooving bucket body is limited in suitable position, kept away by the mobile protective device 2 of lower movement for protecting nipple orifice top following region Formed nipple orifice is grabbed or broken to the bucket tooth 32 for exempting from grooving bucket body.
At the second stage of slot grooving initial stage, due to the non-uniform influence of stratum compactness, top hangs skyborne grooving bucket body and exists Double swerve can be generated in operating process or even collides nipple orifice, and excessive shaking and collision can be applied to of the invention consolidate first Determine in protective device 1, fixing protector 1 avoids formed concrete joint hole by physics partition, dispersion and buffer function Damage, and play docking head bore protective effect.With the progress of excavation, after the ladder of grooving bucket body submerges high viscosity mud Double swerve will receive the constraint of itself center of gravity and mud, the energy and amplitude of shaking become smaller, therefore fixed protection dress It is laid special stress on protecting in the region for setting the 1 15 meters of depth in docking head bore top.
With the progress of excavation, the present invention passes through mobile protective device 2 and docks the region progress below of 15 meters of depth of head bore Protection, the bucket tooth that the position dimension of mobile protective device 2 can limit grooving bucket body, which touches, grabs formed semi-circular joint hole coagulation Soil structure, while buffering peptizaiton is also functioned to, and then dock head bore and protected from top to bottom.
It is used cooperatively by fixing protector 1 and mobile protective device 2, it can be to the diaphram wall of various depth Tube drawing connector realizes full depth protection.
Specifically, as illustrated in fig. 1 and 2, fixing protector 1 includes: the semi arch cylinder that its outer wall is bonded with connector hole wall Cylinder reinforcing member 15,16 is respectively welded in body 11, inner wall top and bottom, can become to avoid the collision by grooving bucket body Shape.In addition, 11 inside of semi arch cylinder is not provided with barrier up and down, in order to which grooving bucket body excavates the second stage of slot construction up and down, Without changing original operation mode.
When implementation, semi arch cylinder 11 is rolled using the steel plate of 1cm or more, semicircle cambered surface and nipple orifice arc shape phase It coincide, in order to which outer wall and the connector hole wall of semi arch cylinder 11 fit.
Wherein, two symmetrically arranged suspensions for being used to wear crossbeam 14 are welded in two sides at the top of the inner wall of semi arch cylinder 11 Hanging ring 12, and the arc center welding at the top of inner wall is for lifting by crane and fixing the hoisting ring 13 of insurance steel cable.Such as Fig. 2 institute Show, across on guide wall of underground continuous wall II, semi arch cylinder 11 is suspended in nipple orifice by crossbeam 14 at the both ends of crossbeam 14 Upper area.When implementation, the bar bending that 25mm diameter or more can be used in suspension hanging ring 12 is U-shaped, and internal diameter is greater than 50mm, with half Circular arc cylinder 11 welds.
In order to rely on the semi arch cylinder 11 of suspension from Beijing South Maxpower Technology Co. Ltd naturally close to connector hole wall, mobile protective device is not influenced 2 move up and down along connector hole wall, and when design will be such that the center of gravity of semi arch cylinder 11 is located on the outside of the line of two suspension hanging rings 12, I.e. two suspension hanging ring 12 line than semi arch cylinder 11 center of gravity close to the center of circle of semi arch cylinder 11.
As shown in Fig. 3 to 5, mobile protective device 2 includes: the arc panel being bonded with connector hole wall;For arc panel to be pacified Mounted in the support frame of grooving bucket body 3.Wherein, 31 lower part of ladder of grooving bucket body 3 is equipped with the connection frame of fixing support rack.
Wherein, as shown in figure 4, arc panel includes: the curved plate 21 coincideing with connector shape of hole wall;Rivet clasp is fitted in The yielding rubber plate 22 of 21 outer wall of curved plate.
As shown in Figures 4 and 5, support frame include: the vertical plate 25 for being welded on 21 inner wall of curved plate, upper level board 23 and under Level board 24;Wherein, vertical plate 25 is between upper level board 23 and lower horizontal board 24.
Connection frame includes: the upper junction plate 26 for fixed upper level board 23;For fixing the lower connecting plate of vertical plate 25 27;Wherein, upper junction plate 26 is vertically arranged with lower connecting plate 27.
When implementation, curved plate 21 is rolled using the steel plate of thickness 15mm or so, height 40cm or so, arc length about a quarter Nipple orifice perimeter.It is bonded yielding rubber plate 22 thickness 10mm or so of the rivet clasp on 21 outer wall of curved plate.It is welded on curved plate The thickness of the vertical plates 25 of 21 inner walls, upper level board 23 and lower horizontal board 24 is in 15mm or more, when it is implemented, such as Figure 4 and 5 institute Show, upper level board 23 opens up the bolt hole of two 40mm diameter above with the connecting portion of ladder;The company of vertical plate 25 and ladder Socket part position opens up the bolt hole of a 40mm diameter above, and makes three bolts hole on a vertical plane;It is welded on ladder The upper junction plate 26 of 31 lower parts and the thickness of lower connecting plate 27 are opened up in 15mm or more, and in the corresponding site of upper junction plate 26 The bolt hole of two 40mm diameter above opens up the bolt hole of a 40mm diameter above in the corresponding site of lower connecting plate 27, So that upper level board 23 is connect with upper junction plate 26 using two M35 or more bolts 28, vertical plate 25 and lower connecting plate 27 are used One M35 or more bolt 28 connects, and corresponding bolt 28 can be interchanged, and has biggish deformation adaptability.
Mobile protective device 2 is up and down with grooving bucket body 3 in the following range of nipple orifice upper area, only contacts a phase The intermediate intensity and globality of nipple orifice limit the bucket tooth 32 of grooving bucket body 3 in opening and closing and crawl process compared with high concrete part In position, avoid damaging molded concrete joint pore structure.Need to make when specifically, implementing the outermost of arc panel at The distance of outermost to the grooving bucket body center of gravity of bucket tooth adds when the distance between 3 center of gravity of slot bucket body is equal to grooving bucket body free suspension The radius of nipple orifice, limitation of the opening and closing and crawl position of bucket tooth 32 by arc panel, avoids when ensuring that grooving bucket body 3 excavates Damage nipple orifice.
As shown in fig. 6, being walked to the use of the protective device in extubation provided by the invention construction underground continuous wall connector hole It is rapid as follows:
A. extubation construction forming one phase of the diaphram wall nipple orifice IV of the prior art is used, and clears up a phase nipple orifice Sundries and wall II and operation platform I are nearby led at the top of IV;
B. fixing protector 1 and mobile guarantor are prepared according to the wall thickness of diaphram wall, the length of slot section and equipment feature Protection unit 2;
Fixing protector 1 is lifted to a phase nipple orifice IV internal upper part region by hoisting ring 13, and straight using 40mm The crossbeam 14 of diameter is fixed on by two symmetrical suspension hanging ring 12 suspensions and is led on wall II, guarantees the fixing protector fixed 1 semi arch cylinder 11 is bonded naturally with the hole wall of a phase nipple orifice IV, fastens safety rope by hoisting ring 12, avoids fixed guarantor In 1 accident collision falling hole of protection unit;
C. second phase slot section V close to a phase nipple orifice IV position excavate before, check again for fixing protector 1 whether position Correctly, whether safety rope is fastened;The top that hole position alignment carries out the second stage of slot section V is excavated, and fixing protector 1 is to a phase nipple orifice IV upper area shields;
D. when the second stage of slot section V cutting depth is close to 1 bottom of fixing protector, lift grooving bucket body, in ladder lower part Mobile protective device 2 is installed, it is ensured that be bolted normally, to protect to fixing protector 1 with the nipple orifice of lower portion Under the conditions of trenching construction;
E. second phase slot section V is excavated, until the excavation and clear bottom, bottom hole of completing entire slot are cleaned to after hole depth i.e. removable Fixing protector 1 and mobile protective device 2, and the flushing of protective device 1 and mobile protective device 2 is fixed immediately, with It is used when standby next nipple orifice construction;
F. after changing slurry by code requirement borehole cleaning, carry out second phase slot concrete VII and pour, due to a phase nipple orifice IV by Protection of the invention, forms complete connector seam VIII from top to bottom, and the probability for fault in seam occur will be greatly reduced.
Protective device and method of the present invention have the advantage that
It is processed using general steel plate, processing is relatively easy, and installing and dismounting uses building site existing equipment, and can have enough to meet the need for a long time makes With maintenance is relatively easy;Damage of the traditional handicraft to formed nipple orifice can be effectively reduced, underwater concrete construction damage is reduced Consumption;Most importantly can the biggish probability for reducing the rift defects such as connector clamp mud, promote the fining construction of diaphram wall It is horizontal;And then later period Anti-seeping technology and maintenance cost are reduced, largely prevent the security risk of diaphram wall concealed work; It is suitble to the engineering of the extubation construction diaphram wall of various depth, can satisfy most stringent of seam and antiseepage requirement.
Although above-mentioned elaborate the present invention, however, the present invention is not limited thereto, those skilled in the art can It is modified with principle according to the present invention, therefore, the various modifications that all principles according to the invention carry out all should be understood as Fall into protection scope of the present invention.

Claims (9)

1. a kind of protective device in extubation construction underground continuous wall connector hole characterized by comprising
It is fixed on the fixing protector in nipple orifice internal upper part region, there is the semi arch cylinder being bonded with connector hole wall, is used In protection nipple orifice upper area;
The mobile guarantor for being mounted on grooving bucket body and being moved from top to bottom with the grooving bucket body from nipple orifice top following region Protection unit has the arc panel being bonded with connector hole wall, for protecting nipple orifice top following region;
Wherein, bucket tooth when the distance between the outermost of the arc panel and grooving bucket body center of gravity are equal to grooving bucket body free suspension Outermost to grooving bucket body center of gravity the radius apart from adjunction head bore.
2. the protective device in extubation construction according to claim 1 underground continuous wall connector hole, which is characterized in that described The outer wall of semi arch cylinder is bonded with the connector hole wall in nipple orifice internal upper part region, and inner wall top and bottom are reinforced equipped with cylinder Part.
3. the protective device in extubation construction according to claim 2 underground continuous wall connector hole, which is characterized in that described Semi arch cylinder across the crossbeam on guide wall of underground continuous wall by being suspended in nipple orifice;The top of the semi arch cylinder It is disposed with two suspension hanging rings for wearing the crossbeam.
4. the protective device in extubation construction according to claim 3 underground continuous wall connector hole, which is characterized in that described Two suspension hanging rings are symmetrical arranged, and the line of two suspension hanging rings than the semi arch cylinder center of gravity close to the semicircle The center of circle of arc cylinder.
5. the protective device in extubation construction according to claim 4 underground continuous wall connector hole, which is characterized in that described Mobile protective device further include: for the arc panel to be mounted on to the support frame of the ladder lower part of grooving bucket body.
6. the protective device in extubation construction according to claim 5 underground continuous wall connector hole, which is characterized in that described Arc panel includes:
The curved plate that its shape matches with the connector hole wall of nipple orifice top following region;
It is fixed on the yielding rubber plate of the curved plate outer wall.
7. the protective device in extubation construction according to claim 6 underground continuous wall connector hole, which is characterized in that described Support frame includes: the vertical plate for being welded on the curved plate inner wall, upper level board and lower horizontal board;Wherein,
The vertical plate is arranged between the upper level board and lower horizontal board.
8. the protective device in extubation construction according to claim 7 underground continuous wall connector hole, which is characterized in that described The ladder lower part of grooving bucket body is equipped with the connection frame of fixed support frame as described above, and the connection frame includes:
For fixing the upper junction plate of the upper level board;
For fixing the lower connecting plate of the vertical plate;
Wherein, the upper junction plate is vertically arranged with the lower connecting plate.
9. a kind of guard method in extubation construction underground continuous wall connector hole characterized by comprising
In the fixed fixing protector in nipple orifice internal upper part region, there is the semi arch cylinder being bonded with connector hole wall, be used for Protect nipple orifice upper area;
The mobile protective device moved from top to bottom with grooving bucket body from nipple orifice top following region is installed on grooving bucket body, It has the arc panel being bonded with connector hole wall, for protecting nipple orifice top following region;
Wherein, bucket tooth when the distance between the outermost of the arc panel and grooving bucket body center of gravity are equal to grooving bucket body free suspension Outermost to grooving bucket body center of gravity the radius apart from adjunction head bore.
CN201910109604.2A 2019-02-11 2019-02-11 Protection device and method for joint hole of underground diaphragm wall constructed by tube drawing method Active CN110004988B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910109604.2A CN110004988B (en) 2019-02-11 2019-02-11 Protection device and method for joint hole of underground diaphragm wall constructed by tube drawing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910109604.2A CN110004988B (en) 2019-02-11 2019-02-11 Protection device and method for joint hole of underground diaphragm wall constructed by tube drawing method

Publications (2)

Publication Number Publication Date
CN110004988A true CN110004988A (en) 2019-07-12
CN110004988B CN110004988B (en) 2023-12-19

Family

ID=67165655

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910109604.2A Active CN110004988B (en) 2019-02-11 2019-02-11 Protection device and method for joint hole of underground diaphragm wall constructed by tube drawing method

Country Status (1)

Country Link
CN (1) CN110004988B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114351727A (en) * 2022-01-11 2022-04-15 上海市基础工程集团有限公司 Temporary supporting device for grooving section of underground diaphragm wall

Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2202851C (en) * 1997-04-16 2004-01-20 98492 Ontario Inc. Undercut excavation with protection against seismic events or excessive ground movement
US20050269104A1 (en) * 2004-06-07 2005-12-08 Folk Robert A Top drive systems
CN2906276Y (en) * 2005-10-27 2007-05-30 中国南车集团株洲电力机车研究所 Joint protective rest
JP2007138521A (en) * 2005-11-17 2007-06-07 Ohbayashi Corp Hole wall protecting device, hole excavating method using the hole wall protecting device, and hole wall protecting method using the hole wall protecting device
KR101035404B1 (en) * 2010-08-25 2011-05-20 (주)씨엠파트너스건축사사무소 Slurry wall and slab junction structure and its using top-down construction method
CN202194123U (en) * 2011-08-16 2012-04-18 中国十九冶集团有限公司 Protection system for pile hole excavated by manual work
CN102444144A (en) * 2011-09-28 2012-05-09 广东省基础工程公司 Device preventing concrete from streaming for I-shaped steel joint of diaphragm wall
JP2012177277A (en) * 2011-02-28 2012-09-13 Shimizu Corp Groundwater catchment structure and groundwater conduction structure
CN203080557U (en) * 2013-01-30 2013-07-24 烟台立丰市政工程有限公司 Portable inspection well protective device
KR101397527B1 (en) * 2012-12-18 2014-05-20 이승현 Construct for prevent water leaking to connecting part of concrete slab and concrete box
JP2015169067A (en) * 2014-03-05 2015-09-28 恭史 藤原 Flanged anchor bolt coated resin pipe
CN106759477A (en) * 2016-12-26 2017-05-31 中铁二局集团有限公司 A kind of sheltered reverse excavation steel pipe column positioning construction method
CN106836189A (en) * 2017-03-31 2017-06-13 中国水电基础局有限公司 Stream plastic state Muddy Bottoms burning into sand stratum construction method for diaphragm walls
CN107083771A (en) * 2017-06-15 2017-08-22 中铁六局集团天津铁路建设有限公司 A kind of drilling construction method of artificial digging pile
CN207176733U (en) * 2017-08-25 2018-04-03 重庆建工第七建筑工程有限责任公司 Control basis and the joint waterproofing construction of earthen fill zone open trench tunnel differential settlement
CN108824490A (en) * 2018-08-27 2018-11-16 安徽大来机械制造有限公司 A kind of highly-safe well head fall-preventing protection device
CN109098170A (en) * 2018-09-13 2018-12-28 深圳市工勘岩土集团有限公司 Diaphram wall enters the comprehensive construction method of hard rock grooving
CN209816928U (en) * 2019-02-11 2019-12-20 中国水电基础局有限公司 Protection device for joint hole of underground diaphragm wall constructed by pipe drawing method

Patent Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2202851C (en) * 1997-04-16 2004-01-20 98492 Ontario Inc. Undercut excavation with protection against seismic events or excessive ground movement
US20050269104A1 (en) * 2004-06-07 2005-12-08 Folk Robert A Top drive systems
CN2906276Y (en) * 2005-10-27 2007-05-30 中国南车集团株洲电力机车研究所 Joint protective rest
JP2007138521A (en) * 2005-11-17 2007-06-07 Ohbayashi Corp Hole wall protecting device, hole excavating method using the hole wall protecting device, and hole wall protecting method using the hole wall protecting device
KR101035404B1 (en) * 2010-08-25 2011-05-20 (주)씨엠파트너스건축사사무소 Slurry wall and slab junction structure and its using top-down construction method
JP2012177277A (en) * 2011-02-28 2012-09-13 Shimizu Corp Groundwater catchment structure and groundwater conduction structure
CN202194123U (en) * 2011-08-16 2012-04-18 中国十九冶集团有限公司 Protection system for pile hole excavated by manual work
CN102444144A (en) * 2011-09-28 2012-05-09 广东省基础工程公司 Device preventing concrete from streaming for I-shaped steel joint of diaphragm wall
KR101397527B1 (en) * 2012-12-18 2014-05-20 이승현 Construct for prevent water leaking to connecting part of concrete slab and concrete box
CN203080557U (en) * 2013-01-30 2013-07-24 烟台立丰市政工程有限公司 Portable inspection well protective device
JP2015169067A (en) * 2014-03-05 2015-09-28 恭史 藤原 Flanged anchor bolt coated resin pipe
CN106759477A (en) * 2016-12-26 2017-05-31 中铁二局集团有限公司 A kind of sheltered reverse excavation steel pipe column positioning construction method
CN106836189A (en) * 2017-03-31 2017-06-13 中国水电基础局有限公司 Stream plastic state Muddy Bottoms burning into sand stratum construction method for diaphragm walls
CN107083771A (en) * 2017-06-15 2017-08-22 中铁六局集团天津铁路建设有限公司 A kind of drilling construction method of artificial digging pile
CN207176733U (en) * 2017-08-25 2018-04-03 重庆建工第七建筑工程有限责任公司 Control basis and the joint waterproofing construction of earthen fill zone open trench tunnel differential settlement
CN108824490A (en) * 2018-08-27 2018-11-16 安徽大来机械制造有限公司 A kind of highly-safe well head fall-preventing protection device
CN109098170A (en) * 2018-09-13 2018-12-28 深圳市工勘岩土集团有限公司 Diaphram wall enters the comprehensive construction method of hard rock grooving
CN209816928U (en) * 2019-02-11 2019-12-20 中国水电基础局有限公司 Protection device for joint hole of underground diaphragm wall constructed by pipe drawing method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李晓东;王平;: "双塔水库坝体防渗墙施工及质量控制", 黑龙江水利科技, no. 02, pages 148 - 150 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114351727A (en) * 2022-01-11 2022-04-15 上海市基础工程集团有限公司 Temporary supporting device for grooving section of underground diaphragm wall

Also Published As

Publication number Publication date
CN110004988B (en) 2023-12-19

Similar Documents

Publication Publication Date Title
CN107090851B (en) The inverted side-wall construction method of downtown area open cut groove
CN111519637B (en) Grooving comprehensive construction method for pipeline underground diaphragm wall
CN110374349A (en) A kind of impaired armored concrete cylinder underpins processing unit and its application method
CN109706950A (en) The construction method of diaphram wall in a kind of tunnel
CN109654295B (en) Temporary thrust block for elbow access point, construction method and design method thereof
CN110004988A (en) The protective device and method in a kind of extubation construction underground continuous wall connector hole
CN212641468U (en) Pit-in-pit rapid construction structure
CN105973082A (en) Hole distribution method for blasting demolition of reinforced concrete support beam in foundation pit
CN209816928U (en) Protection device for joint hole of underground diaphragm wall constructed by pipe drawing method
CN212130145U (en) Pile hole enclosing device for manual hole digging pile
CN215926053U (en) In-situ water-supply-and-drainage pipe added connection well device without stopping water
CN211171994U (en) Occlusive pile and diaphragm wall combined foundation pit supporting structure
CN212336244U (en) Ductile cast iron pipe water-carrying connection device
CN108385820A (en) A kind of installation method of integrated pump station
CN110714438B (en) Long-distance concrete pouring construction method for high pile wharf
CN111877429B (en) Grooving device, grooving machine and grooving method suitable for construction of local diaphragm wall under cable trench
CN117266134B (en) Method and cleaner for treating continuous wall joint pipe accident
CN205742320U (en) A kind of chute forming machine auxiliary perching knife device
CN110512485A (en) A kind of ready-package road water collector and construction method
KR100402438B1 (en) An basement excavation apparatus of pier basis for a bridge
CN219034811U (en) Isolated drop shaft grid screen assembly
CN218816399U (en) Shield constructs quick-witted well-passing auxiliary guide structure
CN111155530A (en) A shovel mud ware for underground continuous wall connects processing
CN109751054A (en) Shape of a hoof large-section tunnel construction method
CN219034125U (en) Ultra-deep narrow space construction protection device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant