CN109911765A - The vertical lifting horizontal alignment hanging method of main chord - Google Patents

The vertical lifting horizontal alignment hanging method of main chord Download PDF

Info

Publication number
CN109911765A
CN109911765A CN201910281903.4A CN201910281903A CN109911765A CN 109911765 A CN109911765 A CN 109911765A CN 201910281903 A CN201910281903 A CN 201910281903A CN 109911765 A CN109911765 A CN 109911765A
Authority
CN
China
Prior art keywords
main chord
horizontal alignment
lifting
vertical
hoist cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201910281903.4A
Other languages
Chinese (zh)
Inventor
于长彬
董健刚
张敏
田波
李惠民
张喆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201910281903.4A priority Critical patent/CN109911765A/en
Publication of CN109911765A publication Critical patent/CN109911765A/en
Withdrawn legal-status Critical Current

Links

Abstract

The present invention relates to a kind of vertical lifting horizontal alignment hanging methods of main chord, are used for steel truss arched bridge erection.Include the following steps: that vertical lifting lifting lug is fixed using high-strength bolt in the preceding two sides in main chord one end of main chord lifting, vertically lifts and horizontal alignment conversion hanging piece is hinged with by pin shaft on lifting lug;The fixed horizontal alignment lifting lug of high-strength bolt is utilized in the two sides of the main chord other end;Vertical hanger is converted hanging piece by horizontal alignment and is connect with vertical lifting lifting lug;Vertical lifting: promoting vertical hanger makes main chord vertically encircle closure mouth small space by steel truss;It is secondary to fasten hook, horizontal alignment hoist cable is connect with horizontal alignment lifting lug;Horizontal alignment: winding level aligns hoist cable, rotates main chord with pin shaft axis horizontal to main chord;Contraposition installation main chord, after main chord is installed, hoist cable is unclamped.The present invention solves the problems, such as that small space lifting is difficult, the lifting of main chord when closing on closure section assembly suitable for steel truss arched bridge erection.

Description

The vertical lifting horizontal alignment hanging method of main chord
Technical field
The present invention relates to steel structure hoisting field, the vertical lifting horizontal alignment hanging method of specifically a kind of main chord, For steel truss arched bridge erection.
Background technique
Currently, more and more bridges use steel structure truss system, especially high mountain gorge area large-span steel braced arch Bridge is especially prominent.In such steel truss arched bridge erection, when due to closing on closure section assembly, closure section narrow space and steel are reserved Braced arch rod piece weight is big, flat is hung or integral hoisting has been unable to satisfy construction requirement using common.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of vertical lifting horizontal alignment hanging method of main chord, the party Main chord vertical lifting is first promoted rod piece to level, to complete by closure mouth to steel truss dome portions, then secondary hook of fastening by method Main chord installation.
In order to solve the above technical problems, the technical solution adopted by the present invention is that:
A kind of vertical lifting horizontal alignment hanging method of main chord carries out in the steps below:
Step 1 before main chord (1) lifting, is vertically hung in the two sides of main chord (1) one end using high-strength bolt (8) fixation Ear (2) vertically lifts on lifting lug (2) and is hinged with horizontal alignment conversion hanging piece (4) by pin shaft (3);In main chord (1) other end Two sides it is fixed horizontal alignment lifting lug (7) using high-strength bolt (8);
Step 2, hoist cable (5) are connect by horizontal alignment conversion hanging piece (4) with vertical lifting lifting lug (2);
Step 3, vertical to lift: raising sling (5) makes main chord (1) is vertical to encircle the mouth small space that joins the two sections of a bridge, etc by steel truss;
Step 4, it is secondary to fasten hook, hoist cable (6) is connect with horizontal alignment lifting lug (7);
Step 5, horizontal alignment: raising sling (6) rotates main chord (1) to main chord (1) for axis in level with pin shaft (3) Shape;
After main chord (1) is installed, hoist cable (5), hoist cable (6) are unclamped for step 6, contraposition installation main chord (1).
The present invention by adopting the above technical scheme, compared with prior art, the beneficial effect is that:
It solves the problems, such as that existing method is lifted in small space difficult, one kind is provided newly by small space for large-scale rod piece Hanging method is particularly suitable for the lifting of main chord when steel truss arched bridge erection closes on closure section assembly.
Detailed description of the invention
Fig. 1 is the vertical lifting schematic diagram of the embodiment of the present invention;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is the horizontal alignment schematic diagram of the embodiment of the present invention;
Fig. 4 is the top view of Fig. 3;
In figure: 1, main chord;2, lifting lug is vertically lifted;3, pin shaft;4, horizontal alignment converts hanging piece;5, hoist cable is vertically lifted;6, Horizontal alignment hoist cable;7, horizontal alignment lifting lug;8, high-strength bolt.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawings and embodiments.
Referring to Fig. 1 to Fig. 4, a kind of vertical lifting horizontal alignment hanging method of main chord relates generally to first vertical lifting Horizontal alignment again, the specific steps are as follows:
(1) before main chord 1 lifts, the fixed vertical lifting lifting lug 2 of high-strength bolt 8, vertical lifting are utilized in the two sides of 1 one end of main chord Horizontal alignment is hinged with by pin shaft 3 on dress lifting lug 2 and converts hanging piece 4;High-strength bolt 8 is utilized in the two sides of 1 other end of main chord Fixed horizontal alignment lifting lug 7;
(2) it will vertically lift hoist cable 5 and be connect by horizontal alignment conversion hanging piece 4 with vertical lifting lifting lug 2;
(3) vertical lifting: promoting vertical lifting hoist cable 5, makes the vertical small space for encircleing closure mouth by steel truss of main chord 1;
(4) secondary to fasten hook, horizontal alignment hoist cable 6 is connect with horizontal alignment lifting lug 7;
(5) horizontal alignment: winding level aligns hoist cable 6, rotates main chord 1 with 3 axis of pin shaft horizontal to main chord 1;
(6) contraposition installation main chord 1, after main chord 1 is installed, will vertically lift hoist cable 5 and horizontal alignment hoist cable 6 unclamps, So far the contraposition installation of main chord 1 is completed.
The above is only specific embodiments of the present invention, but protection of the invention is without being limited thereto, the skill of any the art Art personnel the thinkable variation or substitution being equal with the technical program technical characteristic, all cover in protection scope of the present invention Within.

Claims (1)

1. a kind of vertical lifting horizontal alignment hanging method of main chord, which is characterized in that carry out in the steps below:
Step 1 before main chord (1) lifting, is vertically hung in the two sides of main chord (1) one end using high-strength bolt (8) fixation Ear (2) vertically lifts on lifting lug (2) and is hinged with horizontal alignment conversion hanging piece (4) by pin shaft (3);In main chord (1) other end Two sides it is fixed horizontal alignment lifting lug (7) using high-strength bolt (8);
Step 2, hoist cable (5) are connect by horizontal alignment conversion hanging piece (4) with vertical lifting lifting lug (2);
Step 3, vertical to lift: raising sling (5) makes main chord (1) is vertical to encircle the mouth small space that joins the two sections of a bridge, etc by steel truss;
Step 4, it is secondary to fasten hook, hoist cable (6) is connect with horizontal alignment lifting lug (7);
Step 5, horizontal alignment: raising sling (6) rotates main chord (1) to main chord (1) for axis in level with pin shaft (3) Shape;
After main chord (1) is installed, hoist cable (5), hoist cable (6) are unclamped for step 6, contraposition installation main chord (1).
CN201910281903.4A 2019-04-09 2019-04-09 The vertical lifting horizontal alignment hanging method of main chord Withdrawn CN109911765A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910281903.4A CN109911765A (en) 2019-04-09 2019-04-09 The vertical lifting horizontal alignment hanging method of main chord

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910281903.4A CN109911765A (en) 2019-04-09 2019-04-09 The vertical lifting horizontal alignment hanging method of main chord

Publications (1)

Publication Number Publication Date
CN109911765A true CN109911765A (en) 2019-06-21

Family

ID=66969176

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910281903.4A Withdrawn CN109911765A (en) 2019-04-09 2019-04-09 The vertical lifting horizontal alignment hanging method of main chord

Country Status (1)

Country Link
CN (1) CN109911765A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202279623U (en) * 2011-08-29 2012-06-20 上海宝冶集团有限公司 Hoisting tool of bent concrete precast slab
CN203946776U (en) * 2014-02-26 2014-11-19 武船重型工程股份有限公司 Head tower bearing plate turnover hoisting fixture
CN204588449U (en) * 2015-04-24 2015-08-26 华能伊敏煤电有限责任公司 A kind of hanging apparatus of steel structure
CN205802754U (en) * 2016-07-08 2016-12-14 中建八局第三建设有限公司 A kind of steel structure hydraulic pressure lift construction auxiliary device
CN108516454A (en) * 2018-04-20 2018-09-11 上海市机械施工集团有限公司 A kind of hanging apparatus of prefabricated components

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202279623U (en) * 2011-08-29 2012-06-20 上海宝冶集团有限公司 Hoisting tool of bent concrete precast slab
CN203946776U (en) * 2014-02-26 2014-11-19 武船重型工程股份有限公司 Head tower bearing plate turnover hoisting fixture
CN204588449U (en) * 2015-04-24 2015-08-26 华能伊敏煤电有限责任公司 A kind of hanging apparatus of steel structure
CN205802754U (en) * 2016-07-08 2016-12-14 中建八局第三建设有限公司 A kind of steel structure hydraulic pressure lift construction auxiliary device
CN108516454A (en) * 2018-04-20 2018-09-11 上海市机械施工集团有限公司 A kind of hanging apparatus of prefabricated components

Similar Documents

Publication Publication Date Title
CN212772802U (en) Suspension structure system with weak correlation of each layer
CN205367454U (en) Large -size formwork hoisting machine constructs
CN109911765A (en) The vertical lifting horizontal alignment hanging method of main chord
CN201635390U (en) Automatic formwork supporting machine for high-rise building elevator shaft construction
CN203145425U (en) Binding type cable crane truss cantilever scaffold
CN202936737U (en) Continuous beam cradle hoisting structure for corrugated steel webs
CN201786012U (en) Chimney suspension bracket
CN104404923A (en) Arch dam bracket template device and construction method based on arch dam bracket template device
CN204252082U (en) Arch dam bracket plate device
CN208964367U (en) A kind of safe and simple vertical support hanging apparatus
CN202657877U (en) Circuit equipment construction lifting frame
CN207986526U (en) A kind of cladding panel hoisting structure
CN218969768U (en) Hoisting device for corrugated steel web section beam
CN206915560U (en) Steel column lifts detacher
CN206580444U (en) A kind of urban construction building prefabricated components hanging apparatus
CN206328045U (en) A kind of steel structure truss self adaptation hoisting structure
CN209635724U (en) Platform is lifted for the more rod piece closures in four purlins
CN207001999U (en) Large tank shape equipment hoisting shoulder pole girder
CN201236098Y (en) Combined pressure bar sling
CN205935718U (en) Hoist device of embedded integral side fascia
CN205855781U (en) The lower flange of guide
CN203806952U (en) Mechanical self-tripping clamping and lifting device
CN205772948U (en) Super High Core Walls Structure soil dead man
CN104860209B (en) Movable arm tower crane height space-variant arm method
CN207243242U (en) Suspender

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20190621